14.11_ED102.4.2 - PHASE 4 DEMOLITION TECH FIRE ALARM PLAN.pdf

PDF 423 KB Posted

Attached to
Z2DA--621-22-121 Renovate Bldg. 204 for Cath Lab II - Engineering
Solicitation number
36C24926R0057
Issued by

About this file

This is an architectural floor plan and fire alarm system design document for a medical facility renovation project. The document depicts two floor plans for what appears to be a healthcare facility, with the upper plan showing the fire alarm head end location and the lower plan showing the technology design layout. The facility includes specialized medical spaces such as an ultrasound room (L285), EP catheterization laboratory (L220), scrub area (L220B), sterile storage (L212), and various support spaces including staff and patient toilets, equipment rooms, and HAC (likely Hospital Acquired Condition) monitoring area.

Key technical requirements include: the electrical contractor must connect all fire alarm devices to the existing Simplex fire alarm control panel; wireless access points and dome antennas must be removed from existing ceiling tiles, temporarily stored, and reinstalled in the same location and orientation in new ceilings during the new work phase; and three CAT 6A cables must be installed per location throughout the facility. The document is marked as "100% BID DOCUMENTS" and is titled "Phase 4 Demolition Tech Fire Alarm Plan" for the Mt. Home, Virginia Medical Center located in Mt. Home, Tennessee. The document reference number is ED1024.2, and it is designated as fully sprinklered.

View the file

Other files

File Type Posted
00 01 10 - Table Of Contents 29072026.pdf PDF
07 42 13 - Insulated Metal Wall Panels.pdf PDF
07.314_AE301 - PENTHOUSE CONSTRUCTION.pdf PDF
01 45 35a - Schedule of SI.pdf PDF
28 05 00 - Common Work Results for Electronic Safety and Security.pdf PDF
07 41 13 - Insulated Metal Roof Panels.pdf PDF
14.26_EE102.5.2 - PHASE 5 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.08_ED102.3.2 - PHASE 3 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
13.12_MH103 - MECHANICAL ROOF HVAC PLAN.pdf PDF
07.730_AQ732 - OVERALL EQUIPMENT PLAN.pdf PDF
FINAL COORDINATION STUDY -- 12-17-19.pdf PDF
09 54 00 - Operating Room Modular Diffuser System.pdf PDF
23 82 00 - Convection Heating and Cooling Units.pdf PDF
14.38_E600 - PARTIAL SINGLE LINE DIAGRAM.pdf PDF
14.20_EE102.2.2 - PHASE 2 ENLARGED TECH FIRE ALARM PLAN.pdf PDF
14.13_ED102.5.2 - PHASE 5 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
07.704_AF702.4 - PHASE FOUR FINISH PLANS.pdf PDF
13.10_MH102.4 - MECHANICAL SECOND FLOOR HVAC PLAN - PHASE 4.pdf PDF
S-102824-291.pdf PDF
10 51 26 - Plastic Lockers and Bench.pdf PDF
09 05 16 - Subsurface Preparation For Floor Finishes.pdf PDF
01 45 35b - Statement of SI.pdf PDF
14.29_E501 - TECHNOLOGY DETAILS.pdf PDF
14.06_ED102.2.2 - PHASE 2 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.04_ED102.1.2 - PHASE 1 DEMOLITION TECH FIRE ALARM PLAN.pdf PDF
14.02_E102 - SECOND FLOOR OVERALL PLAN.pdf PDF
14.00_E001 - ELECTRICAL LEGENDS AND ABBREVIATIONS.pdf PDF
07.705_AF702.5 - PHASE FIVE FINISH PLANS.pdf PDF
07.734_AQ732.4 - EQUIPMENT PLANS - PHASE FOUR.pdf PDF
11.22_PL601 - PLUMBING SCHEDULES and DIAGRAMS.pdf PDF
Revised Cath Shielding 2024.pdf PDF
Project 621-22-121 RFI Log - Mt Home Cath Lab to VA 7-24-26.xlsx XLSX spreadsheet
36C24926R0057 0003.pdf PDF
28 23 00 - Video Surveillance.pdf PDF
01 45 35 - Special Inspections.pdf PDF
00 01 10 - Table Of Contents.pdf PDF
36C24926R0057 0002.pdf PDF
621-22-121 Site Visit Sign in sheet.pdf PDF
2026-0629 Cath Lab II - BID specs - Add 01.pdf PDF
36C24926R0057 0001.pdf PDF
2026-0629 Cath Lab II - BID Dwgs - Add 01.pdf PDF
Price Breakout Schedule.xlsx XLSX spreadsheet
Contractor EMR Certification Form.docx DOCX document
621-22-121 Renovate B204 for Cath Lab II - Bid Specifications.pdf PDF
36C24926R0057_1.pdf PDF
General Conditions Breakout.xlsx XLSX spreadsheet
621-22-121 Renovate B204 for Cath Lab II - Bid Drawings.pdf PDF
Calculation of Contractor Self Performed Work.xlsx XLSX spreadsheet
WD TN20260191 2 Jan 2026.pdf PDF
Past_Performance_Questionnaire.docx DOCX document
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F

F

F

F

S

SS

F

F

D

D105

D

D

AP

AP

S

PB

DL PB

S S S

CR

S

ML

ML

SK

AN

S

S

SK

SK

SK

SK

CLEAN

L281

SOILED

L282

PATIENT TOILET

L283

AMM

L284

ULTRASOUND

L285

ELECTRICAL

L226

MECH

STAFF TOILET

L219

STAFF TOILET

L217

EP CATH LAB

L220

SCRUB

L220B

CATH LAB

L222

EQUIPMENT

L228

SCRUB

L222B

STERILE STORAGE

L224

CONTROL ROOM

L222C

CONTROL ROOM

L220A STERILE STORAGE

L212

HAC

L215

PATIENT TOILET

L205

EQUIPMENT

L216

ELECTRICAL

L252

AMP

CB CB

KEY PLAN

ENTIRE FLOOR

AREA SHOWN ON SHEET

NORTH EXISTING BELOW

CEILING ONLY RELATED WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

VA FORM 08 - 6231

A

FULLY SPRINKLERED

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

Date:Revisions:No.

F

Au to de sk

D oc s:

//M t H om e

VA

C at h

La b/

FF

E_

R en ov at e C at h

La b

II_

B2

_M

EP

(2

4)

.rv t

7/

/2

2:

:0

PM

ED102.4.2

PHASE 4 DEMOLITION TECH FIRE

ALARM PLAN

06/12/2026 JB IA

RENOVATE BLDG 204 CATH LAB II 621-22-121

MT HOME, TENNESSEE

100% BID DOCUMENTS

MT HOME, VA

MEDICAL

CENTER Approved: Owner

3/16" = 1'-0"3 SECOND FLOOR - TECHNOLOGY DEMO PLAN

3/16" = 1'-0"2 SECOND FLOOR - FIRE ALARM DEMO PLAN

G E N E R A L N O T E S :

A.

B.

C.

ELECTRICAL CONTRACTOR SHALL CONNECT ALL FIRE ALARM DEVICES TO EXISTING SIMPLEX FIRE ALARM

CONTROL PANEL.

FOR ALL WIRELESS ACCESS POINTS AND DOME ANTENNAS, REMOVE FROM CEILING TILE AND SUPPORT ABOVE THE CEILING. REINSTALL IN SAME PLACE AND DIRECTION IN NEW CEILING DURING NEW WORK PHASE.

= (3) CAT 6A CABLES PER LOCATION

0 100% BID DOCUMENTS 06/12/2026

1 ADDENDUM 01 06/29/2026

2 ADDENDUM 02 07/24/2026

06/12/2026

D