Portland International Airport North Runway Rehabilitation Project Manual
This is a Project Manual for a construction solicitation issued by The Port of Portland for the Portland International Airport North Runway Rehabilitation project (AIP No. 3-41-0048-106, Solicitation No. 2026-14659). The work encompasses comprehensive rehabilitation and reconstruction of the North Runway (Runway 10L-28R) and associated taxiways, including asphalt pavement mill and inlay operations, shoulder reconstruction, navigation aids upgrades to Category II/III, taxiway rehabilitation and construction, runway and taxiway lighting installation, signage, electrical infrastructure, storm drainage systems, pavement markings, grading, and seeding. The project includes extensive bid items organized into Schedule 1 (124 line items totaling over 479,000 square feet of pavement surface preparation and 152,640 square yards of sawcut grooving) and Schedule 2 (41 line items including ALSF-2 light lane installation and glide slope shelter replacement), plus Additive Alternate A for non-AIP-eligible items. A pre-bid meeting is scheduled for October 22, 2026, at 10:00 a.m. via Microsoft Teams, with RSVP required 24 hours prior. Bids are due electronically through the Port's online bidding system by 2:00 p.m. on November 12, 2026. Contract award is contingent upon Port Commission approval (anticipated December 9, 2026) and FAA grant funding receipt (anticipated early April 2027). The Notice to Proceed for onsite work is anticipated on or about May 3, 2027. The contractor must substantially complete Work Area 4 within 28 consecutive days from the agreed work start date, with all work (except pavement grooving) substantially complete by September 24, 2027, and final completion within 120 days thereafter.
Bid security of 10 percent of the total bid amount is required, submitted electronically as a certified check, irrevocable letter of credit, or bid bond. The contract price will be determined by the lowest responsive bid from a responsible bidder; the Port reserves the right to reject any or all bids. Liquidated damages are assessed at $10,000 per day for Work Area 4 delays beyond 28 days, $5,000 per hour for failure to open runways/taxiways by 5:00 a.m., and $30,000 per day for delays beyond the September 24, 2027, substantial completion date. The Port offers incentive payments ranging from $15,000 to $30,000 per day for early completion, up to a maximum of $235,000 if all work is completed before September 24, 2027. The project is partially funded by FAA Airport Improvement Program (AIP) grants, with the Port reserving the right to modify or terminate the contract if grant funding is suspended, canceled, or modified. Contractor performance must include at least 25 percent of total contract cost with the contractor's own organization, and mobilization costs cannot exceed 10 percent of the total bid. Prevailing wage requirements apply under both Oregon state law and the federal Davis-Bacon Act. The contractor must register with the Oregon Construction Contractors Board and comply with 49 CFR Part 26 Disadvantaged Business Enterprise requirements and FAA Buy American preferences for domestic materials and products.
View the file
Other files
Show 40 more
Latest 50 of 308 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P.O. Box 3529 Portland, Oregon 97208
P R O J E C T M A N U A L
Including Specifications for
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
Airport Improvement Program (AIP) Project No. 3-41-0048-106
Solicitation No. 2026-14659
EAN 2024D011
October 2026
9/28/26 APPROVALS
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 000107-1
DOCUMENT 000107
APPROVALS
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
Project Manager:
Project Engineer:
Electrical Engineer:
Stamp
Civil Consultant
HNTB
777 N.E. 108th Avenue, Suite 1000
Bellevue, WA 98004
(425) 455-3555
Civil Consultant
Century West Engineering
5500 Meadows Road, Suite 250
Lake Oswego, OR 97035
(503) 419-2130
Stamp Stamp nchowdhury Stamp
10/9/26 TABLE OF CONTENTS
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 000110-1
DOCUMENT 000110
TABLE OF CONTENTS
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
Document 000107 Approvals.................................................................................................000107-1
Document 001100 Invitation to Bid .......................................................................................001100-1
Document 002100 Instructions to Bidders .............................................................................002100-1
Document 002200 Supplementary Instructions to Bidders....................................................002200-1
Document 004100 Bid Form..................................................................................................004100-1
Document 004334 Bidders List Information������������������..004334-1
Document 004335 First Tier Subcontractor Disclosure Form ...............................................004335-1
Documents 004537 to 004548 Federal Certifications................................................................004537-1
Document 005200 Agreement................................................................................................005200-1
Document 006100 Performance Bond ...................................................................................006100-1
Document 006101 Labor and Material Payment Bond..........................................................006101-1
Document 007200 FAA General Contract Provisions ...........................................................007200-1
Document 007201 Supplementary Contract Provisions.........................................................007201-1
Document 007202 Port General Conditions...........................................................................007202-1
Document 007301 Supplementary Conditions for Federally Assisted Contracts ..................007301-1
Document 007346 Wage Rates ..............................................................................................007346-1
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
DIVISION 1 � GENERAL REQUIREMENTS
Section 011100 Summary of Work 012200 Unit Prices 013100 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 013513 Airport Security, Safety, and Operating Regulations 014500 Quality Control 015000 Temporary Facilities and Controls 015713 Temporary Erosion, Sediment, and Pollution Control 015719 Environmental Construction Controls 015720 Construction Equipment Idling, Engine, and Fuel Standards 017000 Execution Requirements
10/12/26 TABLE OF CONTENTS
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 000110-2
017419 Construction Waste Recycling
017700 Closeout Procedures
SITE WORK
FAA SPECIFICATIONS (MODIFIED FOR PORT USE)
Item C-100 Contractor Quality Control Program (CQCP) C-102 Temporary Air and Water Pollution, Soil Erosion, and Siltation Control C-105 Mobilization C-110 Methods of Estimating Percentage of Material Within Specifications Limits (PWL) P-101 Preparation/Removal of Existing Pavements P-152 Excavation, Subgrade, and Embankment P-153 Controlled Low-Strength Material (CLSM) P-209 Crushed Aggregate Base Course P-401 Asphalt Mix Pavement P-403 Asphalt Mix Pavement Base Course P-603 Emulsified Asphalt Tack Coat P-605 Joint Sealants for Pavements P-606 Adhesive Compounds, Two-Component for Sealing Wire and Lights in Pavement P-608 Emulsified Asphalt Seal Coat P-610 Concrete for Miscellaneous Structures P-620 Runway and Taxiway Marking P-621 Saw-Cut Grooves D-701 Pipe for Storm Drains and Culverts D-705 Pipe Underdrains for Airports D-751 Manholes, Catch Basins, Inlets, and Inspection Holes T-901 Seeding T-905 Topsoil
PORT SPECIFICATIONS
Section 026100 Removal and Disposal of Contaminated Soils 312300 Trenching, Backfilling, and Compacting 312319 Dewatering 331116 Site Water Utility Distribution Plumbing
ELECTRICAL
FAA SPECIFICATIONS (MODIFIED FOR PORT USE)
Item L-108 Underground Power Cable for Airports L-110 Airport Underground Electrical Duct Banks and Conduits
PORT SPECIFICATIONS
Section 260500 Common Work Results for Electrical 260526 Grounding and Bonding for Electrical Systems 260543 Manholes and Pull Boxes 260553 Identification for Electrical Systems 344300 Airfield Lighting 344301 Raising of Existing Lights and Base Cans 344302 Aircraft Guidance Signage
EXHIBITS
Exhibit A – Construction Safety and Phasing Plan (included as a separate attachment) Exhibit B – Environmental Management Plan (included as a separate attachment)
10/9/26 TABLE OF CONTENTS
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 000110-3
Exhibit C�- Establish Runway 10L ALSF-2, Replace Runway 10L Glide Slope Shelter, and Partial Reconstruction of Runway 28R MALSR (included as a separate attachment)
DRAWINGS
PDX 2026-501
10/12/26 INVITATION TO BID
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 001100-1
DOCUMENT 001100
INVITATION TO BID
THE PORT OF PORTLAND
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
AIP No. 3-41-0048-106
Solicitation No. 2026-14659
Bids for the Portland International Airport North Runway Rehabilitation project will be received electronically through the Port’s online bidding system until, but not after, 2 p.m. on November 12, 2026.
Bid results will be publicly available in the Port’s online bidding system immediately after the scheduled time for receipt of bids. See the Instructions to Bidders for more information on electronic submission.
The work includes but is not limited to:
1. Rehabilitation of Runway 10L-28R (North Runway) and shoulders in asphalt concrete pavement with mill and inlay.
2. Reconstruction of portions of the North Runway north shoulder pavement and sealing of the blast pad pavements.
3. Upgrade of Runway 10L navigation aids (NAVAIDs) to Category II/III.
4. Rehabilitation of pavement at Taxiways A1, A2, A3, A5, A6, K1, and T from the North Runway to the Runway 10L-28R hold bar, and widening of some existing shoulders.
5. Construction of Taxiway A4 in a new location and removal of the existing Taxiway A4 between the North Runway and Taxiway A.
6. Providing runway and taxiway edge and centerline lighting cans, conduit, and conductors.
7. Providing signage, electrical vaults, utility vault rehabilitation, storm drainage, pavement markings, grading, and seeding.
Prequalification is not required for this work.
The Contractor or a subcontractor need not be licensed for asbestos work under ORS 468A.720.
A pre-bid meeting will be held via Microsoft Teams at 10 a.m. on October 22, 2026, to discuss all phases of the work. To attend, bidders must RSVP through the Port’s online bidding system no later than 24 hours before the pre-bid meeting. A Microsoft Teams meeting invite will be sent to all bidders who RSVP, with instructions on attending the meeting remotely.
Contractors, subcontractors, consultants, and suppliers are strongly encouraged to register through the Port’s online bidding system, which can be accessed at https://www.planetbids.com/portal/portal.cfm?CompanyID=15598. All firms can view current business opportunities. Registered firms may receive electronic notification of Port solicitations, and have access to view or download solicitations, addenda, and solicitation-holders lists.
Questions must be submitted electronically using the “Q&A” feature in the Port’s online bidding system.
Hard copies of drawings and specifications are not available directly from the Port. Registered firms may download the project manual and drawings through the Port’s online bidding system.
https://www.planetbids.com/portal/portal.cfm?CompanyID=15598
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 001100-2
The Port may reject bids that do not comply with applicable public contracting procedures and requirements. The Port may reject for good cause any or all bids if the Port finds that doing so is in the public interest. Bidder compliance for this project includes the following:
A. Bids must be on the Port’s bid form and must be accompanied by bid security made payable to
The Port of Portland in an amount equal to at least 10 percent of the total amount bid.
B. In accordance with ORS 279C.370, bidders must submit the enclosed First-Tier Subcontractor
Disclosure Form within two working hours after bid opening.
C. The labor and civil rights requirements in the Bid, Bid Supplements, and Supplementary
Conditions apply to this work. The proposed contract is subject to 49 CFR Part 26, on
Participation By Disadvantaged Business Enterprises in United States Department of
Transportation Financial Assistance Programs, including any amendments thereto.
D. Title VI Solicitation Notice: The Port, in accordance with the provisions of Title VI of the Civil
Rights Act of 1964 (78 Stat. 252, 42 U.S.C. §§ 2000d to 2000d-4), 28 CFR § 50.3, and 49 CFR
Part 21, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, all contractors will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of the owner’s race, color, national origin, sex, creed, age, or disability in consideration for an award.
E. Bidders are required to comply with the provisions of Executive Order 14398 and
FAR 52.222-90, Addressing DEI Discrimination by Federal Contractors, as described in the
Supplementary Conditions.
F. Oregon law requires that the higher of either the state prevailing wage rates or federal Davis-
Bacon rates be paid to workers on projects in Oregon subject to both the state prevailing wage rate law and federal Davis-Bacon Act. This project is subject to both the state prevailing wage rate law and the federal Davis-Bacon Act.
G. The Port will not receive or consider a bid unless the bid contains a statement by the bidder that the bidder will comply with the provisions of ORS 279C.800 to 279C.870 (regarding payment of prevailing wage rates on public works projects over $50,000).
H. No bid will be considered unless the bidder is registered with the State of Oregon Construction
Contractors Board to the extent required by ORS Chapter 701, prior to submitting a bid.
I. Bidders are hereby alerted that public works contractors generally must file a public works bond with the Construction Contractors Board, as provided in ORS 279C.836.
Apprentice Opportunities on Port Projects over $500,000: The Port is committed to advancing access to quality jobs through investments in workforce development. This includes encouraging efforts that improve workplaces, create job opportunities, support skill-building, and build career pathways. The Port’s overall target for registered apprentice participation is 20 percent of total labor hours.
Bid Information Submitted as a Matter of Responsiveness: As a condition of responsiveness the bidder will be required to submit the information included on the Bidders List Information form.
DBE Program: The Port sets overall goals for Disadvantaged Business Enterprise (DBE) participation in DOT-assisted contracts pursuant to the requirements of 49 CFR § 26.45 and associated agency guidance.
There is no specific DBE participation goal for this project. See the Supplementary Conditions for Federally Assisted Contracts for more information related to DBE program requirements.
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 001100-3
THE PORT OF PORTLAND
Contracts and Procurement October 15, 2026
CPD/FAA
12/5/2023 INSTRUCTIONS TO BIDDERS
\\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX 002100-i
DOCUMENT 002100
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
ARTICLE 1 – DESCRIPTION
ARTICLE 2 – PRE-BID INTERPRETATION OF CONTRACT DOCUMENTS
ARTICLE 3 – RESIDENT BIDDER PREFERENCE
ARTICLE 4 – EQUIVALENT MATERIALS, PRODUCTS, OR SERVICES
ARTICLE 5 – ESTIMATED QUANTITIES
ARTICLE 6 – EXAMINATION OF SITE
ARTICLE 7 – OFFICIAL BID DOCUMENTS
ARTICLE 8 – BID SECURITY
ARTICLE 9 – EXECUTION OF BID
ARTICLE 10 – DISCLOSURE OF FIRST-TIER SUBCONTRACTORS
ARTICLE 11 – SUBMISSION OF BID
ARTICLE 12 – WITHDRAWAL OF BID
ARTICLE 13 – OPENING OF BIDS
ARTICLE 14 – ACCEPTANCE OR REJECTION OF BIDS
ARTICLE 15 – EXECUTION OF AGREEMENT AND BONDS
ARTICLE 16 – NOTICE TO PROCEED
ARTICLE 17 – PROTESTS
\\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX 002100-1
ARTICLE 1 – DESCRIPTION
1.1 Provide labor, materials, and other means required by the contract documents to complete the work.
ARTICLE 2 – PRE-BID INTERPRETATION OF CONTRACT DOCUMENTS
2.1 If the bidder finds discrepancies, omissions, or is in doubt as to the true meaning of any part of the contract documents, submit a request for a clarification or interpretation using the “Q&A” feature in the Port’s online bidding system no less than five business days prior to the bid submission deadline. The Port may not consider requests submitted outside of the Port’s online bidding system.
2.2 The Port will respond to bidder requests for clarification or interpretation using the “Q&A” feature in the Port’s online bidding system. Actual changes to the contract documents will be issued by addendum. Consider addenda in the bid.
ARTICLE 3 – RESIDENT BIDDER PREFERENCE
3.1 Each bid shall contain a statement as to whether the bidder is a resident bidder, as defined in
ORS 279A.120.
3.2 Under ORS 279A.120(1), a “resident bidder” is a bidder that has paid unemployment taxes or income taxes in this state during the 12 calendar months immediately preceding submission of the bid, has a business address in Oregon, and has stated in the bid whether the bidder is a “resident bidder” pursuant to ORS 279A.120(1).
3.3 Under ORS 279A.120(1), a “non-resident bidder” is a bidder who is not a “resident bidder” as defined in Item 3.2 above.
3.4 Failure to complete the “resident bidder” certification statement of residency or nonresidency contained in the bid form may result in rejection of the bid.
3.5 In determining the lowest responsive bidder, the Port will, for the purpose of awarding the contract, add a percent increase on the bid of a nonresident bidder equal to the percent, if any, of the preference given to that bidder in the state in which the bidder resides.
ARTICLE 4 – EQUIVALENT MATERIALS, PRODUCTS, OR SERVICES
4.1 Specified materials, products, or services are named for the purpose of establishing a standard of quality and characteristics desired. Unless the specification or description indicates that no substitution is permitted, other materials, products, or services of equal quality and characteristics for the purposes intended may be submitted at the appropriate time for approval. The Substitution Request Form is enclosed at the end of these Instructions to Bidders. Substitution requests must be submitted by a prospective bidder; substitution requests received from manufacturers, distributors, or companies that are not bidding the project will not be considered. The Port will be the judge of the equality and suitability of the proposed substitution.
4.2 The following definitions of the phrases stated after materials, products, or services in the Specifications determine the extent to which substitutions may be proposed.
A. “PRE-BID APPROVED EQUAL” materials, products, or services require approval by addendum prior to the bid submission deadline. Materials, products, or services which the bidder proposes to substitute, and which he/she considers equal to those specified, must be submitted by attaching the completed Substitution Request Form to the Q&A submission feature in the Port’s online bidding system no less than five business days prior to the bid submission deadline. Requests shall be accompanied by complete technical data and such pertinent
INSTRUCTIONS TO BIDDERS 12/5/2023
002100-2 \\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX
information and/or samples as necessary, or as specified, to fully identify and appraise the material, product, or service. Approval of materials, products, or services deemed equivalent will be issued by addendum prior to the bid submission deadline.
B. “EQUAL” materials, products, or services require approval after contract award. See the General Conditions for requirements.
C. “NO SUBSTITUTION” materials, products, or services are not eligible for substitution requests.
See the General Conditions for requirements.
ARTICLE 5 – ESTIMATED QUANTITIES
5.1 Estimated quantities shown in the bid form provide a basis for comparison of bids only. The bidder shall verify the quantity of each bid item prior to submission of its bid. Reference is made to Change of Contract Price in the General Conditions.
ARTICLE 6 – EXAMINATION OF SITE
6.1 Examine the site and conditions thereon. Bids shall take into consideration conditions which may affect the work. No additional compensation or extension of time will be allowed because of any condition of which the bidder could have informed itself either by examination, testing, sampling, review of records, or otherwise. The Port’s site study information, if any, will be made available to prospective bidders for review; however, the Port disclaims liability and responsibility for the completeness or accuracy thereof.
ARTICLE 7 – OFFICIAL BID DOCUMENTS
7.1 Bidders may view and download construction design and related documents electronically through the Port’s online bidding system. Bidders may only rely on the final construction design documents that the Port makes available through its online bidding system. Bidders are responsible for adjusting hardware and software settings as needed to view and print all bid document content. Guidance for optimal viewing and printing may be provided on the drawings. For the bidders’ convenience, the Port may occasionally post copies of studies, reports, permits, assessments, miscellaneous CAD files, reference drawings, manufacturer data, etc., as additional information that may pertain to this solicitation. However, the Port makes no warranties or representations regarding the integrity or completeness of such documents and bidders should use them only at their own risk.
7.2 Those using electronic documents provided by the Port do so at their own risk. The Port makes no warranties or representations regarding the ability to permanently access, or the presence or absence of computer viruses within, the electronic documents the Port provides.
All or parts of electronic documents provided by the Port may be copyrighted, and those using them are responsible for determining the existence of copyrights and for obtaining permission to copy copyrighted material.
ARTICLE 8 – BID SECURITY
8.1 The bid shall be accompanied by bid security. The security shall be a certified or cashier’s check, an irrevocable letter of credit, or a bid bond made payable to the Port of Portland.
Checks shall be drawn on a United States bank. Irrevocable letters of credit shall be issued by a bank as defined in ORS 706.008. Bid bonds shall be executed by a surety company licensed to do business in the State of Oregon. The amount of the check, letter of credit, or bond shall be equal to at least 10 percent of the total amount bid. The check, letter of credit, or bond will be held by the Port as security and a guaranty that the bidder will execute the Agreement, give satisfactory evidence of insurance, and furnish a 100 percent performance bond and a 100 percent labor and material payment bond. A scanned copy of the bid security shall be submitted electronically through the Port’s online bidding system along with the bid. The
\\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX 002100-3
bidder shall also provide hard copies of the original bid security documentation to the Port immediately if requested.
8.2 The Port may retain the bid security of the three lowest responsive bidders until:
A. all bids are rejected, B. the fully executed Agreement is delivered to the successful bidder, or
C. expiration of the bids, at which time the bid security of all bidders will be returned in accordance with Item 8.3 below.
8.3 Bid security in the form of a surety bond or letter of credit will be returned via an email to the bidder confirming release. All forms of bid security will only be physically returned upon request.
ARTICLE 9 – EXECUTION OF BID
9.1 Bids shall be on the bid form provided to prospective bidders.
9.2 When the bid form provides for writing the bid price in words and numerals, the price as written in words governs over the price written in numerals.
9.3 In the case of conflict between the amount bid and the product of the estimated quantity and the unit bid price, the unit bid price prevails and the corrected product will be used in computing the total amount bid. All arithmetic errors apparent on the face of a bid will be corrected in determining the total bid price.
9.4 Complete the bid form requirements, including acknowledgement of receipt of addenda, if applicable; statement of resident status; and any other requirements specifically called for in the bid.
9.5 Execute the bid in the name of the firm followed by the signature of the officer authorized to sign for the firm and the printed or typewritten designation of the officer’s name and office held.
9.6 Type or print the address and telephone number of the bidder on the bid form.
ARTICLE 10 – DISCLOSURE OF FIRST-TIER SUBCONTRACTORS
10.1 Within two working hours after the date and time of the bid submission deadline, the bidder shall disclose first-tier subcontractors on Document 004335, First-Tier Subcontractor Disclosure Form.
10.2 Disclosures of first-tier subcontractors shall be submitted by email (popcontracting@portofportland.com), and shall include one file with all the necessary attachments and be named “Bid XXXX-XXXX_Bidder Name_FT.” Hard copies will not be accepted.
ARTICLE 11 – SUBMISSION OF BID
11.1 Bids shall be submitted electronically through the Port’s online bidding system. Hard copies will not be accepted.
11.2 Bids will be received until the submission deadline stated in the Invitation to Bid.
mailto:popcontracting@portofportland.com
002100-4 \\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX
ARTICLE 12 – WITHDRAWAL OF BID
12.1 Prior to the bid submission deadline, a bidder may withdraw its bid. This will not preclude submission of another bid by such bidder prior to the bid submission deadline. Withdrawal of the bid is the sole responsibility of the bidder through the Port’s online bidding system.
Contact the service provider (PlanetBids) directly for any technical issues.
ARTICLE 13 – OPENING OF BIDS
13.1 The Port reserves the right to postpone the bid submission deadline.
13.2 At the time and place set for the opening and reading of bids, bids received prior to the bid submission deadline will be publicly opened and read aloud. When opening bids electronically, bids are deemed to be opened publicly when bidder and bid information is made available to the public in the Port’s online bidding system.
ARTICLE 14 – ACCEPTANCE OR REJECTION OF BIDS
14.1 The Port may reject any bid not in compliance with all prescribed public bidding procedures and requirements, and may, for good cause, reject any or all bids upon a finding it is in the public interest to do so. In any case where competitive bids are required and all bids are rejected, and the proposed contract is not abandoned, new bids may be called for as in the first instance. The Port may cancel a solicitation at any time before a contract is signed, if the Port determines cancellation is in the Port’s best interests. If a solicitation is canceled, the Port will not be liable for any costs incurred by prospective bidders or bidders. If a solicitation is canceled before the bid submission deadline, bids will not be returned electronically. If a solicitation is canceled after the bid submission deadline, the Port will retain the bids.
14.2 The Port may disqualify any bidder if, at any time, it finds:
A. The bidder has been convicted for the commission of a criminal offense as an incident in obtaining or attempting to obtain a public or private contract or subcontract, or in the performance of such contract or subcontract;
B. The bidder has been convicted under state or federal statutes of embezzlement, theft, forgery, bribery, falsification or destruction of records, receiving stolen property, or any other offense indicating a lack of business integrity or business honesty that currently, seriously, and directly affects the bidder’s responsibility as a contractor;
C. The bidder has been convicted under state or federal antitrust statutes; or
D. The bidder has violated a contract provision that is regarded by the Port to be so serious as to justify disqualification. A violation may include, but is not limited to, a failure to perform the terms of a contract or an unsatisfactory performance in accordance with the terms of the contract. However, a failure to perform or an unsatisfactory performance caused by acts beyond the control of the contractor may not be considered to be a basis for disqualification.
14.3 The Port may disqualify an apparent low bidder if, at any time, it finds that the bidder:
A. Does not have available the appropriate financial, material, equipment, facility and personnel resources and expertise, or the ability to obtain the resources and expertise, necessary to meet all contractual responsibilities;
B. Does not hold current licenses that businesses or service professionals operating in Oregon must hold in order to undertake or perform the work specified in the contract;
C. Is not covered by liability insurance and other insurance in amounts the Port requires in the solicitation documents;
\\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX 002100-5
D. Does not qualify as a carrier-insured employer or a self-insured employer under ORS 656.407 or, if applicable, has not elected coverage under ORS 656.128;
E. Has not made the first-tier subcontractor disclosure required under ORS 279C.370;
F. Has not completed previous contracts of a similar nature with a satisfactory record of performance;
G. Does not have a satisfactory record of integrity;
H. Is not legally qualified to contract with the Port; or
I. Is otherwise not responsible pursuant to ORS 279C.375 and, if applicable, ORS 200.045, or fails to supply all necessary information in connection with demonstrating such responsibility.
14.4 In determining the low responsive bid, the Port will not consider alternates called for in the bid form.
14.5 The Port reserves the right to reject any irregular bid if rejection is in the best interest of the Port. Irregular bids include, but are not limited to:
A. Bids that are incomplete or conditioned in any way;
B. Bids that contain erasures or alterations;
C. Bids that contain unit prices that are obviously unbalanced;
D. Bids that do not acknowledge receipt of previously issued addenda.
14.6 The Port may waive minor irregularities or technicalities in a bid if such waiver is in the best interest of the Port.
14.7 Acceptance of a bid by the Port and award of the Contract will be made by delivery of the fully executed Agreement to the successful bidder within 50 days after the bid submission deadline (or as modified by Document 004100, Bid Form). The bid may not be revoked by the bidder within this period. Failure by the Port to deliver the fully executed Agreement to the successful bidder within the 50-day period will permit the bidder to withdraw its bid. If withdrawn, the Port will return the bid security in accordance with Item 8.3 above. A bid remains effective until it is withdrawn by an affirmative act of the bidder or until the Port rejects the bid, either expressly or impliedly, by awarding the contract to another bidder.
ARTICLE 15 – EXECUTION OF AGREEMENT AND BONDS
15.1 Within 10 days after issuance of the Port’s written notice (or as otherwise requested), the apparent low bidder (Contractor) shall execute and deliver the Agreement, the Performance Bond, and the Labor and Material Payment Bond to the Port. The bonds shall each be for the total amount of the Contract. The company providing the bonds shall be authorized to do business in the State of Oregon. The Agreement and the bonds shall be on the forms provided by the Port.
15.2 The apparent low bidder, if a joint venture/partnership, shall provide a copy of the joint venture agreement or partnership agreement evidencing authority to offer and to enter into the resulting contract that may be awarded, together with corporate resolutions (if applicable) evidencing corporate authority to participate as a joint venture or partner. A contact person must also be designated for purposes of receiving all notices and communications under the contract. All partners and joint venturers will be required to sign the Agreement.
002100-6 \\POPFS\ENG-SPEC\MASTERS\FRONT\STANDARDCONTRACTDOCS\IBS.DOCX
15.3 If the bidder fails to execute the Agreement, give satisfactory evidence of insurance, and furnish the bonds within 10 days after the Port’s written notice, the bid security shall be forfeited in accordance with the applicable statute. The Port may extend the time for delivery of the executed contract documents. If the Port extends the time for delivery of the executed contract documents at the successful bidder’s request, the Port may:
A. Extend the time (see NOTICE TO PROCEED below) within which to issue a Notice to Proceed by an equivalent number of days, or
B. Reduce the contract duration period (see the Bid and the Agreement) by an equivalent number of days.
ARTICLE 16 – NOTICE TO PROCEED
16.1 Within 45 days after delivery of the fully executed Agreement to the successful bidder, the Port will issue Notice to Proceed. The Notice to Proceed will state the dates: (1) on which the Contractor may begin the work, (2) by which the Contractor is required to attain substantial completion of the work, and (3) by which the Contractor is required to attain final acceptance of the work.
ARTICLE 17 – PROTESTS
17.1 A bidder or prospective bidder who wishes to object to any aspect of this solicitation must deliver a written protest to the Port’s Manager of Contracts and Procurement, 7200 N.E.
Airport Way, 8th Floor, Portland, Oregon 97218; or P.O. Box 3529, Portland, Oregon 97208;
or fax to (503) 548-5812.
17.2 If the protest relates to matters that are apparent on the face of the solicitation documents or that otherwise are known or reasonably ought to be known to the protestor, the protest must be delivered no less than five business days before the deadline for the Port’s receipt of offers.
17.3 If the protest relates to other matters, including but not limited to the award of the Contract, it must be delivered as soon as possible, and in no event more than five business days after the protestor knows or reasonably ought to know of the award of the contract, the Port’s intent to award the Contract, or the other matters to which the protest is addressed.
17.4 A protest is delivered for the purposes of this article when it actually is received by the Port’s Contracts and Procurement staff.
17.5 The Port may decline to review a late protest.
17.6 The protest shall be deemed to include only the documents timely delivered pursuant to this article. It must clearly state all of the grounds for the protest and must include all arguments and evidence in support of the protest. Testimonial evidence may be submitted by affidavit.
The Port may investigate as it deems appropriate in reviewing the protest, and will issue a written response to the protest. The Port may proceed with contract award, execution, and performance while a protest is pending.
END OF DOCUMENT
SUBSTITUTION
REQUEST
Project: From:
To: Port of Portland Date:
Specification
Title:
Specification
Section No.:
Section
Page:
Article/
Paragraph:
Proposed Substitution:
Trade Name: Model No.:
Manufacturer: Address: Phone:
Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.
Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its proper installation.
The Undersigned certifies:
• Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.
Same warranty will be furnished for proposed substitution as for specified product.
• Same maintenance service and source of replacement parts, as applicable, is available.
• Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule. Proposed substitution does not affect dimensions and functional clearances.
• Undersigned will pay for changes to building design, including A/E design, detailing, and construction costs caused by the substitution.
Submitted By:
Signature:
Address:
Telephone:
PORT REVIEW AND ACTION
☐ Substitution approved – Make submittals in accordance with the General Conditions and Specification Section 013300.
☐ Substitution approved as noted – Make submittals in accordance with the General Conditions and Specification
Section 013300.
☐ Substitution rejected – Use specified materials.
☐ Substitution request received too late – Use specified materials.
Signed by: Date:
Supporting Data Attached: ☐ Drawings ☐ Product Data ☐ Samples ☐ Tests ☐ Reports ☐
CSI Form 1.5C Version January 2013
Port-revised March 2019
10/9/26 SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 002200-1
DOCUMENT 002200
SUPPLEMENTARY INSTRUCTIONS TO BIDDERS
1.2 GENERAL
A. These supplements modify, delete from, or add to the Instructions to Bidders.
B. Where an article, paragraph, or clause of the Instructions to Bidders is modified or deleted by these supplements, the unaltered provisions of that article, paragraph, or clause remain in effect.
1.3 RESIDENT BIDDER STATEMENT FOR FEDERALLY ASSISTED CONTRACTS
A. See the Instructions to Bidders, Article 3. Delete in its entirety.
1.4 DOCUMENT REFERENCES
A. See Instructions to Bidders Items 4.2 and 5.1. Change all references of �General Conditions� to �Port General Conditions.�
1.5 ESTIMATED QUANTITIES
A. See Instructions to Bidders Item 5.1. Delete and replace with, �An estimate of quantities of work to be done and materials to be furnished under these specifications is given in the bid. It is the result of careful calculations and is believed to be correct. It is given only as a basis for comparison of proposals and the award of the contract. The Port does not expressly, or by implication, agree that the actual quantities involved will correspond exactly therewith; nor shall the bidder plead misunderstanding or deception because of such estimates of quantities, or of the character, location, or other conditions pertaining to the work. Payment to the Contractor will be made only for the actual quantities of work performed or materials furnished in accordance with the plans and specifications. It is understood that the quantities may be increased or decreased as provided in the Section 40, paragraph 40-02, Alteration of Work and Quantities, without in any way invalidating the unit bid prices.�
Bidder: _____________________
10/9/26 BID FORM
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 004100-1
DOCUMENT 004100
BID FORM
To The Port of Portland P.O. Box 3529 Portland, Oregon 97208 AIP No. 3-41-0048-106 Solicitation No. 2026-14659
The bidder warrants that it has carefully examined the contract documents for the contract described as follows:
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
The bidder further warrants that it has examined, or did not avail itself of the opportunity to examine, the proposed work area independently of the indications in the contract documents and has made, or did not avail itself of the opportunity to make, such investigations as are necessary to determine: (1) the character of the materials to be handled, (2) the probable interferences due to Port operations, and (3) other conditions to be encountered.
The bidder further warrants that if this bid is accepted, it will contract with The Port of Portland in the form of Agreement hereto annexed and will to the extent of its bid provide all things necessary for the performance of the contract, including, but not limited to, bonds, labor, material, transportation, and equipment.
The Port anticipates the work under this Contract to be partially funded with the proceeds of a grant from the FAA. The bidder agrees to comply with the Contract provisions required by the grant and acknowledges that the grant conditions are subject to change at any time, before or after Contract award.
The bidder will be notified of and shall comply with any additional or changed grant conditions which may be imposed by the FAA or other applicable law at any time, beyond those provisions already stipulated in this Contract.
In the event that some or all of the grant funding is terminated, suspended, or modified by the FAA or other applicable law, the Port reserves the right to proceed with any elements of work paid for by the Port, and to delete or modify elements that were to be paid for using grant funds. The deleted or modified elements of work will be handled as a change in the work in accordance with the General Conditions.
The Port further reserves the right to terminate the Contract for convenience at any time in accordance with the General Conditions, in the event some or all of the grant funding is canceled or modified by the FAA or other applicable law.
The bidder acknowledges that the FAA does not permit escalation clauses for increases in fuel, asphalt, or other construction costs. Bids shall be adjusted accordingly to account for possible material and labor cost increases over the life of the project.
The bidder further acknowledges that the price for mobilization shall not exceed 10 percent of the total amount bid in accordance with Item C-105, Mobilization.
The bidder further acknowledges that it shall perform, with its organization, an amount of work equal to at least 25 percent of the total Contract cost in accordance with Section 80 of Document 007200, FAA General Contract Provisions.
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 004100-2
The bidder further acknowledges that award of this contract is contingent upon approval by the Port Commission and receipt of FAA grant funding. Commission approval is anticipated on December 9, 2026. Receipt of all grant funding is anticipated sometime in early April 2027. A Notice to Proceed for onsite work in certain areas is anticipated to occur on or about May 3, 2027, but will not be issued until the grant documents are executed and approved by the FAA. However, a limited Notice to Proceed for preliminary paperwork, draft schedule, submittals, and other administrative work may be granted by the Port after the contract is executed but prior to actual construction. This administrative work will not be paid for by the Port until FAA grant funding is received.
The bidder promises that all work in Work Area 4 shall be substantially complete within a period of 28 consecutive days from the work start date agreed upon in writing by the bidder and the Port. This includes, but may not be limited to, all paving, lighting, and pavement marking such that the work area can be returned to service for aircraft use. The Port will deem the work of Work Area 4 to be substantially complete when the Port determines that all the requirements of 14 CFR Part 139 are met and the work is completed in accordance with the contract documents. The bidder agrees to pay, as liquidated damages to the Port for any delay, the sum of $10,000 per day for each day of delay beyond the 28-day period so promised for substantial completion of Work Area 4.
The bidder further promises that before 5 a.m. each day following a night closure, the runway or taxiway shall be cleared of personnel and equipment and ready for use by aircraft. The bidder agrees to pay, as liquidated damages to the Port for any delay in opening the runway and or taxiway, the sum of $5,000 per hour or portion of each hour of delay beyond the 5 a.m. scheduled opening
The bidder further promises that all work under this contract, except pavement grooving, shall be substantially complete on or before September 24, 2027. The bidder agrees to pay, as liquidated damages to the Port for any delay, the sum of $30,000 per day for each day of delay beyond substantial completion date so promised. The Port will deem all work to be substantially complete when the Port determines that all the requirements of 14 CFR Part 139 are met and the work is completed in accordance with the contract documents.
If all work under this Contract is completed before September 24, 2027, the Port recognizes that it may benefit. The Port agrees to pay the bidder an incentive as identified in the Incentive Table below for each day that all work under this Contract (except final striping) is complete before the substantial completion date so promised, up to a maximum of $235,000. The Port�s obligation to pay the incentive is conditioned upon the Port�s acceptance of the work as substantially complete. If earned, the incentive will be paid with the final payment.
Incentive Table
Day Amount per Day Cumulative Incentive
1 $15,000 $15,000
2 $15,000 $30,000
3 $20,000 $50,000
4 $20,000 $70,000
5 $25,000 $95,000
6 $25,000 $120,000
7 $25,000 $145,000
8 $30,000 $175,000
9 $30,000 $205,000
10 $30,000 $235,000
\\POPFS\ENG-SPEC\PDX\24D\011\FTEND.DOCX 004100-3
After substantial completion and on or about October 1, 2027, one or more flight checks will be performed on Runway 10L-28R by the FAA. Remaining work to be performed by the bidder following the substantial completion date shall be performed during night closures, or as otherwise scheduled by the Port or the FAA, to accommodate aircraft operations. The bidder further promises that before 5 a.m. each day following a night closure, the runway shall be cleared of personnel and equipment and ready for use by aircraft.
The bidder further promises that pavement grooving shall be complete within 30 days after substantial completion.
The bidder further promises that all work under this contract shall be complete, having gained a successful final inspection and received final acceptance from the Port, within 120 days after substantial completion. Final payment will not be made until the work is judged complete by the Port.
The bidder also agrees to pay Other Damages described in the Port General Conditions.
The bidder is requested to provide prices for Schedules 1 and 2 (Base Bid) and Additive Alternate A. The Contract will be awarded to the responsible bidder with the lowest responsive Base Bid. Additive Alternate A may be awarded in its entirety at the option of the Port. It will not be used as a basis for determining the apparent low bidder.
The bidder submits and proposes the following unit bid prices, to wit:
SCHEDULE 1 BASE BID (AIP-ELIGIBLE ITEMS) Bidder: _________________________
Item
No. Item Description
Estimated
Quantity Units Unit Price Total Price
0001 Sweeper
(Section 012200)
1.00 LS
0002 Security Control Monitoring
(Section 012200)
1.00 LS
0003 Traffic Control
(Section 012200)
1.00 LS
0004 Escort
(Section 012200)
1.00 LS
0005 Inlet Protection
(Section 015713)
83.00 EA
0006 Jet Blast Control Material
(Section 015713)
6.00 AC
0007 Wattles
(Section 015713)
4,200.00 EA
0008 Mobilization
(Item C-105)
1.00 LS
0009 Asphalt Pavement Removal (3 to 5 Inch
Depth)
(Item P-101)
15,300.00 SY
0010 Asphalt Pavement Removal (10 to 11 Inch
Depth)
(Item P-101)
1,800.00 SY
0011 Asphalt Pavement Removal (12 to 13 Inch
Depth)
(Item P-101)
1,700.00 SY
0012 Asphalt Pavement Removal (15 to 16 Inch
Depth)
(Item P-101)
3,700.00 SY
0013 Cold Milling (2" to 4" Depth)
(Item P-101)
107,000.00 SY
0014 Cold Milling (9" Depth)
(Item P-101)
81,000.00 SY
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
\\POPFS\Eng-Spec\Pdx\24D\011\Bid Tab
BID
004100-4
No. Item Description
Estimated
Quantity Units Unit Price Total Price
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
0015 Cold Milling (16" Depth)
(Item P-101)
84,000.00 SY
0016 Removal of Pipe and Structures
(Item P-101)
1.00 LS
0017 Unclassified Excavation
(Item P-152)
20,000.00 CY
0018 Unsuitable Excavation
(Item P-152)
5,300.00 CY
0019 Mechanical Stabilization
(Item P-152)
15,400.00 CY
0020 Existing Subgrade Stabilization
(Item P-152)
700.00 CY
0021 Crushed Aggregate Base Course
(Item P-209)
5,900.00 CY
0022 Separation Geotextile
(Item P-209)
21,000.00 SY
0023 Asphalt Surface Course
(Item P-401)
64,000.00 TN
0024 Asphalt Mixture Base Course
(Item P-403)
112,000.00 TN
0025 Emulsified Asphalt Tack Coat
(Item P-603)
90,500.00 GL
0026 Joint Sealing Filler
(Item P-605)
204.00 GL
0027 Adhesive Compound
(Item P-606)
349.00 GL
0028 Asphalt Surface Treatment
(Item P-608)
19,000.00 SY
\\POPFS\Eng-Spec\Pdx\24D\011\Bid Tab
004100-5
No. Item Description
Estimated
Quantity Units Unit Price Total Price
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
0029 Structural Portland Cement Concrete
(Item P-610)
928.00 CY
0030 Surface Preparation
(Item P-620)
479,350.00 SF
0031 Temporary Pavement Marking
(Item P-620)
18,350.00 SF
0032 Marking
(Item P-620)
461,000.00 SF
0033 Reflective Media
(Item P-620)
26,550.00 LB
0034 Sawcut Grooving
(Item P-621)
152,640.00 SY
0035 12-Inch STS Pipe
(Item D-701)
414.00 LF
0036 15-Inch STS Pipe
(Item D-701)
238.00 LF
0037 18-Inch STS Pipe
(Item D-701)
652.00 LF
0038 6-Inch Perforated STS Pipe
(Item D-705)
2,332.00 LF
0039 6-Inch Non-perforated STS Pipe
(Item D-705)
225.00 LF
0040 48-Inch Manhole
(Item D-751)
4.00 EA
0041 Catch Basin
(Item D-751)
4.00 EA
0042 Underdrain Cleanout
(Item D-751)
15.00 EA
\\POPFS\Eng-Spec\Pdx\24D\011\Bid Tab
004100-6
No. Item Description
Estimated
Quantity Units Unit Price Total Price
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
0043 Connect to Existing Catch Basin/Manhole
(Item D-751)
1.00 EA
0044 Underdrain Cleanout Adjustment
(Item D-751)
5.00 EA
0045 Repair Communications Vault
(Item P-610)
1.00 LS
0046 Seeding
(Item T-901)
7.00 AC
0047 Topsoil
(Item T-905)
3,300.00 CY
0048 Contaminated Material Excavation and
Disposal
(Section 026100)
1,700.00 TN
0049 Flush Hydrant Assembly
(Section 331116)
1.00 LS
0050 Hydrant Water Valve Box Adjustment
(Section 331116)
6.00 EA
0051 Remove Flush Hydrant Assembly
(Section 331116)
1.00 LS
0052 No. 8 AWG, 5kV, L-124, Type C Cable, Installed in Trench, Duct Bank, or Conduit
(Item L-108)
100,775.00 LF
0053 No. 6 AWG, Solid, Bare Copper Counterpoise
Wire, Installed Above Duct Bank or Conduit, Including Connections/Terminations
(Item L-108)
25,755.00 LF
0054 Counterpoise Ground Rod
(Item L-108)
72.00 EA
0055 2-Inch PVC Encased in Concrete in New
Structural AC
(Item L-110)
19,795.00 LF
\\POPFS\Eng-Spec\Pdx\24D\011\Bid Tab
004100-7
No. Item Description
Estimated
Quantity Units Unit Price Total Price
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
0056 2-Inch PVC in Existing Structural AC
(Item L-110)
335.00 LF
0057 2-Inch PVC Direct Buried in Grass or under
New AC Shoulder
(Item L-110)
7,005.00 LF
0058 2-Inch PVC in Existing Shoulder AC
(Item L-110)
70.00 LF
0059 Five 4-Inch PVC Encased in Concrete in New
Structural AC
(Item L-110)
180.00 LF
0060 Five 4-inch PVC Direct Buried in Grass or under New AC Shoulder
(Item L-110)
200.00 LF
0061 2-Inch GRSC in Existing Structural AC
(Item L-110)
25.00 LF
0062 General Electrical Removal
(Section 260500)
1.00 LS
0063 Temporary Circuit Connection
(Section 260500)
1.00 LS
0064 444-LA Pull Boxes
(Section 260543)
2.00 EA
Install PF Runway Centerline Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
195.00 EA
0066 Install PF Runway Touchdown Zone Light on
PF Base Can, PF Extension, PF Flange Ring and CF Transformer
(Section 344300)
180.00 EA
0067 Install Elevated Runway Edge Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
74.00 EA
0068 Install In-Pavement Runway Edge Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
14.00 EA
\\POPFS\Eng-Spec\Pdx\24D\011\Bid Tab
004100-8
No. Item Description
Estimated
Quantity Units Unit Price Total Price
PORTLAND INTERNATIONAL AIRPORT
NORTH RUNWAY REHABILITATION
0069 Install In-Pavement Runway Threshold Light on PF Base Can, PF Extension, PF Flange
Ring and CF Transformer
(Section 344300)
16.00 EA
0070 Install PF Taxiway Centerline Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
58.00 EA
0071 Install PF Elevated Taxiway Edge Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
46.00 EA
0072 Install PF Runway Guard Light on PF Base
Can, PF Extension, PF Flange Ring and CF
Transformer
(Section 344300)
2.00 EA
0073 Install PF Elevated Red Stop Bar Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer
(Section 344300)
2.00 EA
0074 Install PF In-Pavement Runway Guard/Stop
Light on PF Base Can, PF Extension, PF
Flange Ring and CF Transformer
(Section 344300)
11.00 EA
0075 Install PF Microwave Sensor Assembly with
PF Base Can, PF Extension, PF Flange Ring, PF Cover Plate and CF Transformer
(Section 344300)
2.00 EA
0076 Install PF Base Can, PF Extension, PF
Flange Ring and PF Cover Plate
(Section 344300)
5.00 EA
0077 Install PF Elevated Taxiway Edge Light on PF
Base Can, PF Extension, PF Flange Ring and
CF Transformer in Existing AC
(Section 344300)
1.00 EA
0078 Reinstall Elevated Runway End Light on
Existing Base Can with CF Transformer
(Section 344300)
16.00 EA
0079 Reinstall Elevated Taxiway Edge Light on
Existing Base Can with CF Transformer
(Section 344300)
48.00 EA
\\POPF…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .