This is a request for proposal for environmental remediation services. The contractor will conduct site restoration activities at four installations in South Carolina and North Carolina, including fifty-four Installation Restoration Program sites and eleven Military Munitions Response Program sites. The services include maintenance of established remedies, optimization efforts, and achievement of site-specific objectives over a ten-year period of performance. The solicitation is set aside for small businesses and will result in a firm fixed-price contract. Proposals are due by March 27, 2023 at 1:00pm Eastern through the Procurement Integrated Enterprise Environment solicitation module. Enclosures include performance standards, government-furnished information, and site visit details.
View the file
Other files
Show 40 more
Latest 50 of 70 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FOR
CAROLINA GROUP
OPTIMIZED REMEDIATION CONTRACT
AT
JOINT BASE CHARLESTON-AIR, SOUTH CAROLINA
JOINT BASE CHARLESTON-WEAPONS, SOUTH CAROLINA
NORTH AUXILIARY AIRFIELD, SOUTH CAROLINA
SEYMOUR JOHNSON AIR FORCE BASE, NORTH CAROLINA
30 MARCH 2023
FY23 Version 1.2
CONTENTS
1.0 SCOPE
1.1 INTRODUCTION
1.2 OVERVIEW OF ORC SCOPE AND REQUIREMENTS
1.2.1 Scope Discussion and Limits
1.2.2 Preliminary Assessment/Site Inspection, Remedial Investigation or Remedial Investigation/Feasibility
Study (including Supplemental Investigations), and Decision Document
1.2.3 Response Complete or Site Closeout
1.2.4 Remedial Action-Operation with Optimization
1.2.5 Remedial Action-Operation and Reduce Life Cycle Cost; Long Term Management and Reduce Life
Cycle Cost
1.2.6 Remedial Action-Operation or Long-Term Management (as appropriate)
1.2.7 Alternate Objectives
1.3 PERFORMANCE REQUIREMENTS
1.3.1 Table 1: Performance Table
1.3.2 Additional Scope Discussion and Limits
2.0 APPLICABLE DOCUMENTS
3.0 GOVERNMENT FURNISHED INFORMATION AND PROPERTY
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
4.1 PROJECT MANAGEMENT PLAN
4.2 SCHEDULE AND PLANNING REQUIREMENTS – INTEGRATED MASTER SCHEDULE
4.3 MILESTONE PAYMENT SCHEDULE
4.4 COST AND STATUS REPORTING
4.5 ORC DOCUMENT REPOSITORY – TO INCLUDE ALL DOCUMENT VERSIONS, AND REGULATORY CORRESPONDENCE.
4.6 MEETING AND CONFERENCE REQUIREMENTS
4.6.1 Meeting/Teleconference Support
4.6.2 Public Meetings and Hearings
4.7. SPATIAL DATA (MAP) REQUIREMENTS
4.8 INFORMATION SECURITY
4.8.1 Computer and Network Access Requirements:
4.8.2 Cybersecurity Reporting
4.9 NOTIFICATION REQUIREMENTS
4.10 PERMITS
4.10.1 Environmental Permits
4.10.2 Rights of Access to Non-AF Real Property
4.11 PHOTO DOCUMENTATION
4.12 REMOTE AND/OR AUSTERE SITES
4.13 SITE ACCESS
4.14 WORKSITE ACTIVITIES AND COORDINATION
4.14.1 Coordination of Activities
4.14.2 Hazardous Material, and Hazardous Waste Permitting and Reporting
5.0 CHEMISTRY REQUIREMENTS
5.1 QUALITY ASSURANCE
5.2 LABORATORY SELECTION
5.3 ANALYTICAL DATA MANAGEMENT
5.4 RECORD KEEPING
6.0 PLANS AND REPORTS
6.1 QUALITY PROGRAM PLANS
6.1.1 Work Plans
6.1.2 Health and Safety Plan
6.1.3 Construction Quality Plan
6.2 TECHNICAL PLANS AND REPORTS
7.0 SITE WORK
7.1 CONSERVATION
7.2 SITE CHARACTERIZATION AND FIELD INVESTIGATION
7.3 SITE PREPARATION
7.4 DEMOLITION
7.5 SITE RESTORATION
8.0 ENVIRONMENTAL REQUIREMENTS
8.1 ENVIRONMENTAL RESTORATION PROCESS APPLICATION
8.1.1 Conceptual Site Model Guidance
8.1.2 Exit Strategy
8.1.3 Performance and Optimization
8.2 TRANSITION OF WORK
8.3 ENVIRONMENTAL CONSTRUCTION
8.3.1 Design
8.3.2 Inspection
8.3.3 Delivery and Warranty
8.4 ENVIRONMENTAL RESOURCES PROGRAM INFORMATION MANAGEMENT SYSTEM
8.5 INNOVATIVE AND PROVEN TECHNOLOGIES
8.6 OPERATIONS AND MAINTENANCE
8.7 ORDNANCE REMOVAL AND SUPPORT
8.8 HAZARDOUS WASTE REMOVAL AND SUPPORT
8.9 STUDY EFFORT INCIDENTAL TO REMEDY OR CORRECTIVE ACTION
8.10 FIVE-YEAR REVIEW SUPPORT
9.0 QUALITY ASSURANCE SURVEILLANCE PLAN
10.0 POINTS OF CONTACT
11.0 KEY PERSONNEL
11.1 ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
11.2 AT LEVEL I TRAINING
11.3 GENERAL SECURITY REQUIREMENTS AND GUIDANCE
11.4 PHYSICAL SECURITY AND ACCESS CONTROL REQUIREMENTS
11.5 CONTRACT PERSONNEL REQUIRING A COMMON ACCESS CARD
11.6 TRAINING REQUIREMENTS FOR THE PROTECTION OF SENSITIVE INFORMATION
11.7 COUNTERINTELLIGENCE AWARENESS TRAINING
11.8 CONTRACTS REQUIRING A FORMAL OPSEC PROGRAM
Enclosure 1 – Acronyms and Definitions
Enclosure 2 – Government Furnished Information (GFI)
1.0 SCOPE
This requirement is for environmental remediation activities at Joint Base Charleston-Air
(JBCA), Joint Base Charleston-Weapons (JBCW), and North Auxiliary Airfield (NAAF), in
South Carolina (SC); and Seymour Johnson Air Force Base (SJAFB), in North Carolina (NC).
This Performance Work Statement (PWS) defines the scope of environmental services necessary to conduct site restoration under the Optimized Remediation Contract (ORC). The range of activities includes maintenance of established remedies, optimization at applicable sites, and achievement of site-specific objectives. The Contractor shall undertake Environmental
Remediation activities to achieve Performance Objectives (POs) at fifty-four (54) Installation
Restoration Program (IRP) sites and eleven (11) Military Munitions Response Program (MMRP) sites.
NOTE: For purposes of this ORC, the term “Government” includes the Air Force (AF) and
United States Army Corps of Engineers (USACE). While regulators are a governmental entity, they are also a third party over whom the Air Force has no control and, as such, will be referred to as “regulators.”
1.1 Introduction
Joint Base Charleston-Air (JBCA)
Joint Base Charleston-Air is located on the west bank of the Cooper River about ten miles north of Charleston, SC and is within North Charleston city limits. JBCA is home to the 437th Airlift
Wing (AW), 315th Airlift Wing (AW) (Reserves), and 628th Airbase Wing (ABW) and encompasses approximately 3,400 acres of land. The 315th AW operates the C-17 Globemaster
III strategic airlift aircraft and shares the same aircraft with 437th AW. The 437th AW provides airlift of troops and passengers, military equipment, cargo, and aeromedical equipment and supplies worldwide in support of tasking by Air Mobility Command and unified combatant commanders. The 628th ABW provides installation support to 53 Department of Defense
(DOD) and federal agencies as well as mission-ready expeditionary Airmen to combatant commanders in support of joint and combined operations.
Remediation activities at Joint Base Charleston-Air are being conducted pursuant to the National
Oil and Hazardous Substances Contingency Plan (NCP), and the Resource Conservation and
Recovery Act (RCRA) requirements. Regulatory oversight is provided by the South Carolina
Department of Health and Environmental Control (SCDHEC). Cleanup is performed under
RCRA, but the Air Force maintains its CERCLA authority. The Environmental Protection
Agency (EPA) may be consulted by SCDHEC for issues with Risk Assessments and Permit
Renewals.
JB Charleston-Air operates under RCRA Corrective Action Permit SC3 570 024 460 effective through 16 Aug 2029; issued 31 July 2019. The Compliance office plans on initiating the next permit renewal application in 2028. The ORC contractor will need to support, as needed, updates for the Environmental Restoration program sections of the RCRA Permit applications.
Tier I and Tier II partnering meetings are conducted with SCDHEC monthly via teleconference;
the Contractor will attend in-person and support Tier I meetings semiannually during each year of the contract. These meetings are held in either Columbia, SC. or Charleston, SC.
Joint Base Charleston-Weapons (JBCW)
Joint Base Charleston-Weapons is located in the town of Goose Creek, Berkeley County, and is approximately 10 miles from the Air Base and 14 miles from downtown Charleston. The Naval
Weapons Station was commissioned in 1941, with two distinct missions: home for two strategic submarine squadrons and a tender, and an ordnance station with capacity for more than 60 million pounds of conventional ordnance. The ordnance mission continues today. JBCW is the only military installation in the continental US with completely unencumbered explosive safety arcs. JBCW is also a training center for the Naval Nuclear Power Training Command, Nuclear
Power Training Unit, and other tenants.
Remediation activities at Joint Base Charleston-Weapons are being conducted pursuant to the
National Oil and Hazardous Substances Contingency Plan (NCP), and the Resource
Conservation and Recovery Act (RCRA) requirements. Regulatory oversight is provided by the
South Carolina Department of Health and Environmental Control (SCDHEC). Cleanup is performed under RCRA, but the Air Force maintains its CERCLA authority. The Environmental
Protection Agency (EPA) may be consulted by SCDHEC for issues with Risk Assessments and
Permit Renewals.
JB Charleston-Weapons operates under RCRA Corrective Action Permit SC8 170 022 620 effective through 2031; issued 2021. The Compliance office plans on initiating the next permit renewal application in 2030. The ORC contractor will need to support, as needed, updates for the
Environmental Restoration program sections of the RCRA Permit applications.
Tier I and Tier II partnering meetings are conducted with SCDHEC monthly via teleconference;
the Contractor will attend in-person and support Tier I meetings semiannually during each year of the contract. These meetings are held in either Columbia, SC. or Charleston, SC.
North Auxiliary Airfield (NAAF)
North Auxiliary Airfield is located 65 miles northwest of JBCA and 45 miles southeast of the state capital of Columbia. NAAF has 2,400 acres of land, of which 1,150 acres is undeveloped.
The original dirt runway was constructed in 1943 and used by Hughes Aircraft Company for testing. Today the base has a 12,000 ft runway and a 3,000 ft assault runway. The 628th Civil
Engineer Squadron operates the base. The base supports the 437th and 315th Airlift Wing’s C-17
Globemaster III aircrew training and proficiency training.
Remediation activities at North Auxiliary Airfield are being conducted pursuant to the
Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), as amended by the Superfund Amendments and Reauthorization Act (SARA) and the National Oil and Hazardous Substances Contingency Plan (NCP). Regulatory oversight is provided by the
South Carolina Department of Health and Environmental Control (SCDHEC). The
Environmental Protection Agency (EPA) may be consulted by SCDHEC for issues with Risk
Assessments and Permit Renewals.
Seymour Johnson Air Force Base (SJAFB)
Seymour Johnson Air Force Base is annexed to Goldsboro, North Carolina, and occupies 3,300 acres in the southeast section of Goldsboro. Seymour Johnson Field was opened in April 1942 as
Headquarters, Technical School, and Army Air Forces Technical Training Command. Seymour
Johnson Field was deactivated in May 1946. Seymour Johnson Air Force Base was reactivated as a Tactical Air Command base on April 1, 1956. Seymour Johnson has been an active Air
Force base since it reopened. The 4th Fighter Wing is the host unit at Seymour Johnson Air
Force Base and accomplishes its training and operational missions with 92 F-15E Strike Eagle aircraft. Two of the Wing’s four fighter squadrons are operational units capable of deploying world-wide on short notice and immediately generating combat power. The other two squadrons are responsible for training all F-15E aircrews for the Air Force.
Remediation activities at Seymour Johnson AFB are being conducted pursuant to the National
Oil and Hazardous Substances Contingency Plan (NCP), and the Resource Conservation and
Recovery Act (RCRA) requirements. Regulatory oversight is provided by the North Carolina
Department of Environment Quality (NCDEQ). Cleanup is performed under RCRA, but the Air
Force maintains its CERCLA authority.
Seymour Johnson AFB operates under RCRA Corrective Action Permit NC 7570024474R2 effective through 24 Sep 25. The Compliance office will submit the permit renewal application in FY24 (SJAFB RCRA permit will be due 24 Mar 25; the new permit will be effective for 10 years).
Tier I and Tier II partnering meetings are conducted with NCDEQ quarterly via teleconference
(or virtual meeting); the Contractor will attend in-person and support Tier I meetings once annually during each year of the contract. These meetings have been held previously at either
SJAFB or in Raleigh, North Carolina.
1.2 Overview of ORC Scope and Requirements
The Contractor shall perform all the necessary environmental remediation activities needed to achieve the performance requirement described in Section 1.3 of the PWS inclusive of the POs listed in Table 1, Performance Table, and additional scope in 1.3.2. This PWS and enclosures listed below detail the project requirements needed to meet the AF objectives:
• Enclosure 1 – Acronyms and Definitions
• Enclosure 2 – Government Furnished Information (GFI) o Enclosure 2A – Installation Administrative Record Spreadsheets o Enclosure 2B – Additional Site GFI Files and Spreadsheets o Enclosure 2C – Site Added Considerations Summaries
The intent of the ORC initiative is to advance site cleanup during the Period of Performance
(POP) in the most efficient and cost-effective manner as supported by a cost benefit analysis and exit strategy that achieves the greatest reduction in life-cycle cost (LCC). The AF is interested in http://www.globalsecurity.org/military/facility/seymour_johnson.htm http://www.globalsecurity.org/military/facility/seymour_johnson.htm substantial reduction of long-term environmental liabilities and total LCC. However, costs should be commensurate with the level of effort required to achieve each PO and all potential technical contingencies within reason. Technical approaches that are simply reduced to a minimal level of effort with no well-planned contingencies provide no insurance to the
Government that the POs will be achieved without work stoppages or change orders which is not in keeping with the intent of this performance based contracting effort. The AF is required to implement remedies as necessary to enable the mission, protect human health and the environment, and comply with laws and regulations. The goal of the ORC initiative is to ensure the AF continues to fulfill all facets of its Environmental Restoration Program (ERP) mission, by effectively and efficiently managing the program in a performance-based, results-oriented, and cost-conscious framework.
The AF desires that all sites be cleaned up to standards that allow for the current or reasonably anticipated future land use of the property. Accurate documentation and reporting of contaminant removal and cost savings are critical adjuncts to optimization success. In keeping with Defense Environmental Restoration Program (DERP) and Air Force Instruction (AFI) 32-
7020, the AF defines optimization under the ORC as: the reduction of contaminant mass and concentrations, reduction in LCC, or any combination of activities leading to acceleration of
Response Complete (RC)/Site Closeout (SC) as a result of remedial implementation the
Contractor undertakes, above and beyond what is required to maintain compliance in accordance with an approved Decision Document (DD).
The Contractor shall maintain compliance with all DDs/Records of Decision (RODs)/Proposed
Plans/RCRA Permits that are currently in place until no longer required, or an alternate approach is approved. The contractor shall conduct DD/ROD amendments or Explanation of Significant
Differences (ESD) as required to implement new approach(es).
The Contractor shall function as an integral team member in support of the Air Force Civil
Engineer Center (AFCEC) mission to include the sharing of information with USACE, other
AFCEC Contractors, and AF personnel, in cooperation with community stakeholders, regulators, and other Government entities.
Requirements for efficient management of this contract include, but are not limited to, the achievement of the POs in the Performance Period (PP) per Table 1 and work described in
Section 1.3.2 of this PWS, and timely identification and solution of impediments to successful project execution. The Contractor shall provide all personnel, equipment, supplies, tools, materials, and other items necessary to perform the tasks defined in this PWS. The Contractor is solely responsible for reviewing all available information and forming their independent, professional conclusions/interpretations of site conditions and requirements to achieve the POs of this contract within PP specified for each site. AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues during the execution of this contract. The
Contractor shall perform all work in accordance with federal, state, and local statutes and regulations. The Contractor shall also comply with installation regulations. Remedies shall conform to environmental permits, DD requirements, or other legal requirements. The
Contractor shall continue work throughout the entire duration of the POP. The Contractor’s local office presence will be relied upon to provide rapid-response actions for field activities and on-site meetings.
Site specific POs are identified in Section 1.3.1 Table 1: Performance Table and in Section 1.3.2.
POs that are in keeping with standard DERP milestones are defined in Enclosure 1. In addition, for certain categories of sites, the AF has set POs based on current site conditions and consistency with the POP of the contract and ORC goal.
1.2.1 Scope Discussion and Limits
The scope of this contract is to perform environmental restoration services for the sites listed in
Table 1 and Section 1.3.2. The ORC Contractor shall assume contractual liability and responsibility for achieving the POs. If the selected technical approach is not working, as demonstrated by the trends in the performance model, the Contractor shall develop and implement a revised technical approach to achieve the POs, including DD amendments, if required, to implement the remedial approach. This scope includes all known contaminants linked to the specific sites (includes contaminants on, under, or sourced at/migrating from the specific sites) without regard to quantity (e.g., plume size, concentrations). The AF remains statutorily responsible for all sites listed in Table 1 and work described in Section 1.3.2. The
Contractor shall perform all work in accordance with federal, state, and local statutes and regulations, as well as installation regulations, and is responsible for obtaining certifications and licenses required to complete all aspects of this project.
1.2.2 Preliminary Assessment/Site Inspection, Remedial Investigation or Remedial
Investigation/Feasibility Study (including Supplemental Investigations), and
Decision Document
Table 1 of the PWS identifies Preliminary Assessment/Site Inspection (PA/SI), Remedial
Investigation (RI) or RI/Feasibility Study (FS) (including Supplemental Investigations, and DDs as the PO for selected sites. The Contractor is responsible for achieving these POs as identified in Table 1 and work described in Section 1.3.2. See PO definitions in Enclosure 1, Acronyms and Definitions.
1.2.3 Response Complete or Site Closeout
Table 1 of the PWS identifies RC or SC as PO for selected sites. The Contractor is responsible for achieving these objectives as identified in Table 1 and work described in Section 1.3.2. See
PO definitions in Enclosure 1, Acronyms and Definitions. The performance components are described in Section 8.1.3.
1.2.4 Remedial Action-Operation with Optimization
Table 1 of the PWS identifies the following POs utilizing with optimization as follows: 1.
Remedy in Place (RIP) and Remedial Action-Operation (RA-O) with Optimization, 2. DD
Amendment (or Explanation of Significant Differences [ESD]) with Remedy Implementation and RA-O with Optimization, or 3. RA-O with Optimization as POs for selected sites in accordance with the optimization initiative. The Contractor is responsible for achieving these
POs as identified in Table 1 and work described in Section 1.3.2. See PO definitions in
Enclosure 1, Acronyms and Definitions. The optimization and performance components are described in Section 8.1.3.
1.2.5 Remedial Action-Operation and Reduce Life Cycle Cost; Long Term Management and Reduce Life Cycle Cost
Table 1 of the PWS identifies RA-O and Reduce LCC or Long-Term Management (LTM) and
Reduce LCC as the PO for selected sites. The goal of these POs is to minimize future AF liability and cost to the greatest degree feasible. Reduce LCC sites have achieved RIP or RC, have remedies that are effective (source control, risk mitigation, and plume stability), and have the potential for LCC reduction by optimizing some component of the existing remedy, by, for example:
• Reducing sampling frequency
• Reducing system operations
• Reducing number of wells sampled per event
• Reducing number of analytes per sampling event
The Contractor shall achieve the following objectives for each Reduce LCC site:
• Maintain compliance with all DDs and permits (currently in place or to be approved) throughout the POP.
• For RA-O sites, develop performance models addressing all Contaminants of Concern
(COCs) and breakdown products. Refer to Section 8.1.3.1, Performance Models.
• Deliver a Reduce LCC Plan, as a stand-alone plan or in the Project Management Plan
(PMP), that identifies opportunities to improve cost efficiency of RA-O or LTM activities, and the planned approach for implementation. The Reduce LCC Plan shall:
o Provide a basis for proposed reductions in LCC throughout the POP compared to the cost of status-quo RA-O activities (those required to maintain compliance).
The planned reduction can be illustrated using a line graph (current, planned, achieved) or verbiage describing the current and planned reductions.
o Document risk and mitigation strategies for implementing optimization activities to reduce LCC.
• Update or revise site-specific work plans, monitoring plans, and/or DDs, as appropriate.
• Deliver Reduce LCC Reports to document progress in achieving the planned reductions when those reductions are achieved. Reduce LCC Reports may be combined with monitoring reports. Reductions in required RA-O activities are contingent upon regulatory approval.
• Deliver an RA-O & Reduce LCC Summary and Forecasting Report two years prior to the
POP end date. The Reduce LCC Summary and Forecasting Report shall:
o Document optimization activities to date and forecast remaining activities and assumptions to further reduce LCC 10 years post-POP.
Provide a realistic projection to achieve SC or RC after the POP (the Contractor shall identify which PO is the optimal endpoint). See PO definitions in Enclosure 1, Acronyms and
Definitions.
1.2.6 Remedial Action-Operation or Long-Term Management (as appropriate)
Table 1 of the PWS identifies RA-O or LTM in accordance with the approved DD/ROD as the
PO for selected sites. The Contractor shall achieve the following objectives for each RA-O and
LTM site:
• Maintain compliance with all DDs and permits (currently in place or to be approved) throughout the PP. Update or revise site-specific work plans, monitoring plans, and/or
DDs, as appropriate.
• For RA-O sites, develop performance models addressing all COCs and breakdown products. Refer to Section 8.1.3.1, Performance Models.
• Provide a realistic projection to achieve SC or RC after the POP (the Contractor shall identify which PO is the optimal endpoint).
1.2.7 Alternate Objectives
This section and the subparagraphs below describe the Alternate Objective Sites and a general overview of the work associated with these sites. Please see Table 1 and work described in
Section 1.3.2 for specific elements of work required for each site with an Alternate Objective
PO. These sites have complex attributes that have, to date, inhibited progress towards the achievement of RC. For Alternate Objective sites, as for all sites in Table 1 of the PWS where applicable, the Contractor shall maintain compliance throughout the POP of the contract with all existing regulatory requirements including but not limited to regulations, FFAs, RCRA Permits, final or interim RODs, or other equivalent remedial DDs. The Contractor is responsible for implementing changes to the monitoring program based on activities conducted in the Advanced
Site Characterization (PWS Section 1.2.7.1) including the addition and decommissioning of wells in the monitoring well network as agreed by all parties and the addition of new delineation monitoring where new information indicates our understanding of the plumes is changed.
Based on technical review of existing site conditions/activities, the AF placed sites in the category of Alternate Objective if one or more of the following conditions exist:
1. Achieving RC is expected to require substantially longer than 30 years.
2. Achieving RC is unattainable with standard characterization and/or existing remediation technology due to technical or other limitations related to site conditions.
3. Achieving RC is anticipated to require advanced site characterization technologies to improve the Conceptual Site Model (CSM), determine appropriate remedial technology, and/or characterize recently regulated contaminants.
The AF will use data and information obtained during execution of this PWS to determine restoration potential and future investment strategies at Alternate Objective sites. Each Sub-
CLIN for the Alternate Objective sites will only be awarded if the activities are needed to determine the future investment strategy for the site. The decision to award each Sub-CLIN resides solely at the discretion of the AF.
For each Alternate Objective site, a summary of site-specific considerations is provided as GFI.
As with all GFI provided, this GFI is provided for informational purposes only; the Contractor remains responsible for developing their own independent, professional conclusions/interpretation of site conditions and requirements to achieve the PO. The Contractor shall conduct project scoping sessions before work plan development and throughout the planning and execution of the project to meet the PO including the Installation Point(s) of
Contact (POC[s]), the AFCEC Program Manager (PM) and Remedial Project Manager (RPM), the AF technical support team, and the USACE Contracting Officer’s Representative (COR).
Upon approval by the AF and the USACE COR, the Contractor shall participate in scoping sessions with the regulators, as appropriate.
1.2.7.1 Advanced Site Characterization
Based on existing data, the AF has determined that the existing remedial approaches at the
Alternative Objective sites are not achieving satisfactory remedial progress towards their intended goals. In order for the AF to determine the best path forward for these sites, the
Contractor shall conduct Advanced Site Characterization to collect data to update and refine the
CSM in order to achieve the following goals: (1) Fill data gaps; and (2) Collect data needed to:
(A) Determine why existing and previous remedial actions are not effective at achieving remedial progress; (B) Determine appropriate remedial technology(ies) based on site conditions;
C) Develop remediation design parameters for recommended technology(ies); and D) Determine extent and concentrations of recently regulated contaminants, if required.
Advanced Site Characterization includes one or more of the following three activities: (1)
Supplemental Site Investigation (SSI), (2) Revised CSM, and (3) Groundwater Monitoring
Program Update.
1.2.7.1.1 Supplemental Site Investigation
The Contractor shall conduct an SSI to collect data necessary to improve the CSM, determine appropriate remedial technology, support remediation design and construction, and/or characterize recently regulated contaminants. The Contractor shall implement advanced characterization methods, both established approaches and state-of-science techniques consistent with AF, regulatory, Interstate Technology and Regulatory Council (ITRC), and Strategic
Environmental Research and Development Program/Environmental Security Technology
Certification Program (SERDP/ESTCP) guidance to attain these objectives. Data collection includes better definition of the geology, hydrogeology, geochemistry, and/or source(s) and distribution of COCs, as required. The Contractor shall evaluate the need for, and collect the following data where appropriate: (1) Source Zone Delineation; (2) Source Mass/Extent1,2,3; (3)
Vertical and lateral extent of contamination, if not sufficiently defined; (4) Plume Stability4; (5)
Migration pathway, rates, and fluxes in 3-D; (6) Mass distribution; (7) Biogeochemical conditions and influences on contaminant degradation pathways; (8) Impact of recent and historical remedies on site conditions; and (9) Comprehensive Risk including the vapor intrusion pathway.
The SSI report shall document data collection efforts to include a risk evaluation, if appropriate.
The Contractor shall evaluate and provide recommendations regarding whether additional source
1 ITRC. (2015). Integrated DNAPL Site Characterization and Tool Selection.
2 SERDP/ESTCP. (2012). Matrix Diffusion Tool Kit.
3 USEPA. (2009). Evaluating Natural Source Zone Depletion at Sites with LNAPL.
4 USEPA. (2014). High Resolution Site Characterization for Groundwater Short Course, 23rd Annual NARPM
Training Program.
control is needed or whether the plume, or portions of the plume, are amenable to natural attenuation by conducting source strength and plume stability evaluations as needed.
1.2.7.1.2 Conceptual Site Model
The Contractor shall develop a revised CSM in 3-D to include establishing or updating existing fate and transport models based on existing data and data gathered during the SSI. The CSM should cover the source area and the distal plume, to include the lateral and vertical extent of the contaminants in the context of geologic/hydrogeological parameters and the remedial actions conducted to date.
1.2.7.1.3 Groundwater Monitoring Program Update
The Contractor shall evaluate the current horizontal and vertical well distribution to determine if the following can be properly evaluated:
Remedy performance in treatment areas
Hydrogeology, plume geometry, horizontal and vertical plume stability, and matrix diffusion across site
Plume migration through use of perimeter/boundary wells and sentinel wells
Based on the well network evaluation coordinated and approved by the Government and regulators (if required), the Contractor shall optimize the monitoring well network to include adjusting sample collection frequency and the addition of new wells as appropriate. The
Contractor shall update the Basewide or Site-Specific Monitoring Plan or other equivalent document, as appropriate.
1.2.7.2 Remedy Evaluation and Recommendation
Based on all existing data and data gathered during the Advanced Site Characterization, the
Contractor shall evaluate the existing active and/or passive remedy(ies)5,6,7. The Contractor shall provide recommendations to augment, modify, and/or replace the existing remedy8. The evaluation and recommendations will include a cost-benefit analysis and evaluation of the usability, expandability, and/or discontinued use of any existing infrastructure. All remedy recommendations must include a performance model addressing all COCs and breakdown products. Refer to Section 8.1.3.1, Performance Models.
Where necessary to evaluate the proposed technology, the Contractor shall conduct pilot scale technology demonstrations. The Contractor shall identify appropriate remedial technologies and target zones, design/plan, conduct, and evaluate the pilot and/or field scale technology consistent with AF, regulatory, and ITRC guidance. The Contractor shall determine performance monitoring criteria and identify a control sub-site (current state) for comparison and to evaluate results.
In some instances, achievement of RC may not be feasible with currently available technologies within a reasonable timeframe. If this is the case, Contractor shall develop and evaluate alternatives for site management that will be protective of human health and the environment. If
5 USEPA. (2010). Best Management Practices.
6 USEPA. (2014). Groundwater Remedy Completion Strategy.
7 ITRC. (2006). Performance-Based Management.
8 ITRC. (2010). Use and Measurement of Mass Flux and Mass Discharge.
this recommendation is made, it must include the rationale, recommended target when active remediation can cease, and a strategy for obtaining regulatory approval.
1.2.7.2.1 Cost/Benefit Analysis
The Contractor shall provide a cost/benefit analysis for proposed alternatives. Alternatives may include optimizing the remedy in the DD or other remedies with the potential for better performance. All alternatives identified should be evaluated against one another to determine which alternative can achieve RC in the shortest time and has the lowest overall LCC. The cost/benefit analysis should include:
• A focused analysis of alternative approaches, to include conceptual designs and engineering cost estimates. The analysis should identify the total cost of executing the optimized remedy (including the plan and reports).
• An estimate of the reduction of LCC of each alternative evaluated.
• Any risk inherent in implementing the alternative optimized remedy.
• A summary comparison of the LCC and risk of each alternative in a cost/benefit analysis that clearly states the recommended alternative.
1.2.7.3 Decision Document Amendment
Based on the results of the remedy evaluation and recommendation, it may be necessary to amend the Decision Document to augment, modify, and/or replace the existing remedy. If warranted, the Contractor shall update the Decision Document.
1.3 Performance Requirements
1.3.1 Table 1: Performance Table
Table 1 presents the POs, PPs, and Performance Standards associated with all installations/sites under this ORC. The PP specified in Table 1 starts from the Obligation Date of the first Sub-
Contract Line Item Number (CLIN) for the site unless otherwise specified. All approvals (both
Government and regulator) per the Performance Standard are required in writing. Additional scope discussion and limits can be found in Section 1.3.2.
Table 1: Performance Table Site Performance Objective Performance Period Performance Standard
N/A Project Management Plan (PMP):
1) Draft PMP
2) Final PMP
3) Updates as necessary
Draft PMP within 90 calendar days from contract award, Final
PMP within 21 calendar days of receipt of AF/ USACE comments on the draft. Update as necessary throughout the POP, AF/USACE will determine when whole document PMP updates are warranted
AF and USACE approval of
PMP.
The PMP should be maintained with accuracy and completeness based on the current technical approach for each site, management structure, etc.
N/A Integrated Master Schedule
(IMS)/Milestone Payment Schedule
(MPS)
Draft IMS/MPS within 90 calendar days from contract award, Final
IMS/MPS within 21 calendar days of receipt of AF and
USACE comments on the draft, and updates monthly throughout the POP
IMS/MPS.
N/A Basewide Quality Program Plans (QPP) for each Installation
Draft Basewide QPP within 60 calendar days from award and update as necessary throughout the POP
AF and USACE and
Regulatory approval of
Basewide QPP.
Joint Base Charleston-Air
All Open Sites
(IRP, MMRP,
PFAS, etc.)
Community Involvement Plan (CIP) for each Installation and associated
Geographically Separate Units (GSUs)*
One (1) year AF and USACE approval of
CIP.
DD540
(AOC P)
Underground
Fuel Line
Leak
RA-O with Optimization in accordance with the approved Statement of Basis and
RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of RA-O documentation (e.g., Quarterly/Annual
Groundwater and Surface
Water Monitoring Reports, Corrective Measures
Implementation Progress
Reports, etc.)
FT003
(SWMU 55)
Fire Training
Area No. 3
RA-O in accordance with the approved
Statement of Basis, RCRA Permit and
Reduce LCC
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
Through the duration of the POP
AF, USACE, and Regulatory approval of RA-O documentation (e.g., Annual
Groundwater and Surface
Water Monitoring Reports, Corrective Measures
Implementation Progress
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
Reports).
LF002
(SWMU 69)
Landfill No. 4
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual approval of Groundwater
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
Groundwater Monitoring
LF004
(SWMU 66)
Landfill No. 1
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF006
(SWMU 68)
Landfill No. 3
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF017
(SWMU 67)
Landfill No. 2
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual approval of Groundwater and
Surface Water Monitoring documentation (e.g., Annual
Corrective Measures
Implementation Progress
Reports, Annual Groundwater
Monitoring Reports, etc.)
OT011
(SWMU 60)
Hardfill Area
No. 3
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
OT012
(SWMU 58)
Hardfill Area
No. 1
LTM in accordance with the approved
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
OT016
(SWMU 137)
Zone 2
Entomology
Shop
Response Complete (RC)
Continue Long Term Management (LTM) in accordance with the Statement of Basis and RCRA Permit
Ten (10) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final
Remedial Action Completion
Report).
documentation (e.g., Land
Use Control Inspection
Reports, Annual Corrective
Measures Implementation
Progress Report).
RW532
(SWMU 118)
Bldg. 371
Wash rack and RCRA Permit
Five (5) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
Use Control Inspection
Reports and Groundwater
Monitoring documentation, e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
SS042
(SWMU 149)
Zone 4 TCE -
Bldg. 543 –
Bldg. 532
RA-O in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of Groundwater and
Surface Water Monitoring documentation (e.g., Corrective Measures
Implementation Progress
SS042
(SWMU 149)
Zone 4 TCE -
Bldg. 543 –
Bldg. 532
Alternate Objectives:
1) Advanced Site Characterization
(Supplemental Site Investigation
(SSI), Revised Conceptual Site
Model (CSM), and Recommended
Monitoring Program Update)
2) Remedy Evaluation and
Recommendation (including results of any pilot study)
3) Decision Document Amendment
Eight (8) years AF, USACE, and Regulatory approval of SSI Report, revised CSM and Basewide
Monitoring Plan.
the remedy evaluation and recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or field test) showing decreasing trends in COCs.
approval of Permit
Modifications or Stmt. Of
Basis Amendments (i.e., Air
Force, and Regulatory signatures on new Final
Permits or new Decision
Documents.)
ST027
(SWMU 145)
Bldg. 575
JP-4 Leak
Site Closeout (SC) Seven (7) years AF, USACE, and Regulatory approval of SC documentation (e.g., Site
Closeout Report and Well
Abandonment Confirmation
TS837
(AOC X)
Skeet Range 2 and RCRA Permit
Five (5) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
Use Control Inspection
TU542
(AOC V)
Shoppette
Site Closeout (SC) Ten (10) years AF, USACE, and Regulatory approval of SC documentation (e.g., Site
Closeout Report and Well
TU543
(SWMU 108)
Bldg. 58
Abandoned
Diesel Tank
Site Closeout (SC) Seven (7) years AF, USACE, and Regulatory approval of SC documentation (e.g., Site
Closeout Report and Well
Abandonment Confirmation
TU544
(AOC T)
Bldg. 129
UST
Site Closeout (SC) Seven (7) years AF, USACE, and Regulatory approval of SC documentation (e.g., Site
Closeout Report and Well
Joint Base Charleston-Weapons
PFAS, etc.)
Community Involvement Plan (CIP) for
Geographically Separate Units (GSUs)*
One (1) year AF and USACE approval of
AB062
(SWMU 62)
South Annex, Landfill 1st &
A-B Avenue
LTM in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
CG074
(SWMU 74)
South Annex
Boiler Slag
Pile
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
CS023
(SWMU 23)
Old South
Annex
Sanitary
Landfill
Injections to address concentration rebound (Option)
FY25 – FY33 AF, USACE, and Regulatory documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
DA017
(SWMU 17)
Old Southside
Missile &
Waste Oil
Disposal
RA-O in accordance with the approved
FY25 – FY33 AF, USACE, and Regulatory approval of RA-O documentation (e.g., Semi-
Annual Corrective Measures
Implementation Progress
Reports, Annual Groundwater
Monitoring Reports, Land
Use Control Inspection
DA017
(SWMU 17)
Missile &
Waste Oil
Disposal
Alternate Objectives:
1) Advanced Site Characterization
(Supplemental Site Investigation
(SSI), Revised Conceptual Site
Model (CSM), and Recommended
Monitoring Program Update)
2) Remedy Evaluation and
Recommendation (including results recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or
Modifications or Stmt. Of
Basis Amendments (i.e., Air
Force, and Regulatory signatures on new Final
DA951
(AOC Q)
Eastside
Ordnance
Area 1
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
ED17178B
(SWMU 81)
Southside
EOD Storage
Area
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
FL066
Bldg. 3221 –
Old
Entomology
FY25 – FY33 AF, USACE, and Regulatory approval of RA-O documentation (Corrective
Measures Implementation
Progress Reports, Annual
Groundwater Monitoring
FL066
Bldg. 3221 –
Old
Entomology
(Supplemental Site Investigation
(SSI), Revised Conceptual Site
Model (CSM), and Recommended
Monitoring Program Update)
2) Remedy Evaluation and
Recommendation (including results recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or
Modifications or Stmt. Of
Basis Amendments (i.e., Air
Force, and Regulatory signatures on new Final
FL073
(SWMU 73)
Bldg. 3440
Battery Shop and RCRA Permit
Five (5) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
ID068
(SWMU 68)
Bldg. 3637 and RCRA Permit
Five (5) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
LF003
(SWMU 3)
Old Northside
Landfill
Injections to address concentration rebound (Option) documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF010
(SWMU 10)
Bldg. 930
Area Former
Waste OTTO
Fuel S
LTM in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF016
(SWMU 16)
Landfill
LTM in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
MU17175A
(SWMU 79)
Marsh
Dumping Area
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
SA036
(SWMU 36)
Hazardous
Waste Storage and RCRA Permit
Eight (8) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
SS012
(SWMU 12)
Former
Bldg. 88
FY25 – FY33 AF, USACE, and Regulatory approval of RA-O documentation (e.g., Corrective Measures
Implementation Progress
SS012
(SWMU 12)
Former
Bldg. 88
(Supplemental Site Investigation
(SSI), Revised Conceptual Site
Model (CSM), and Recommended
Monitoring Program Update)
2) Remedy Evaluation and
Recommendation (including results recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or
Modifications or Stmt. Of
Basis Amendments (i.e., Air
Force, and Regulatory signatures on new Final
ST042
(AOC G)
WW
Treatment
Facility
RA-O in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of RA-O documentation (e.g., Corrective Measures
Implementation Progress
ST042
(AOC G)
WW
Treatment
Facility
Alternate Objectives:
1) Advanced Site Characterization
(Supplemental Site Investigation
(SSI), Revised Conceptual Site
Model (CSM), and Recommended
Monitoring Program Update)
2) Remedy Evaluation and
Recommendation (including results recommended proposed remedial strategy including successful demonstration of the existing or alternate remedy (e.g., through pilot or
Modifications or Stmt. Of
Basis Amendments (i.e., Air
Force, and Regulatory signatures on new Final
TU014
(SWMU 14)
Bldg. 58
Former Waste
OTTO
LTM in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
TU927
(TU/US-C10)
AOC B-2
Bldg. 1025
Site Closeout (SC)
Five (5) years AF, USACE, and Regulatory documentation (e.g., Site
Closeout Report and Well
TU933
(TU/US-506)
Bldg. 724
LTM in accordance with the approved
Statement of Basis and RCRA Permit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
TU939
(TU/US-501)
AOC B-3
Old Bldg. 7
Five (5) years AF, USACE, and Regulatory documentation (e.g., Site
Closeout Report and Well
Abandonment Confirmation
XE001
(SWMU 82)
Northside Old
Grenade
Range
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XE002
(AOC N)
Munitions
Disposal Area
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XE003
(SWMU 22)
Annex
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XE004
(AOC-O)
Dredge Spoil
Area
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XE005
(SWMU 25)
Annex
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XE006
(SWMU 20)
Annex
Wash Area
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
XE007
(AOC-L)
Borrow Pit
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
XU018
(SWMU 18)
Open Burn
Open
Detonation
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
ZZ075
(SWMU 75)
Mustard Gas
Barges
FY25 – FY33 AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
North Auxiliary Airfield
DA100-2
(LF100)
Debris Area 2 in accordance with the Decision
Document
Ten (10) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
DA100-4
(LF100)
Debris Area 4
Document
Ten (10) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
Use Control Inspection
TA001
POL Tank
Storage Area
Document
Five (5) years AF, USACE, and Regulatory approval of SC documentation (e.g., Site
Closeout Report and Well
Seymour Johnson AFB
PFAS, etc.)
Community Involvement Plan (CIP) for
Geographically Separate Units (GSUs)*
One (1) year AF and USACE approval of
FT007
Fire Training
Area No.3
LTM in accordance with the approved
Statement of Basis, RCRA Permit and
Reduce LCC
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
Reports, Reduce LLC
Summary Report, etc.).
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF006
Landfill No. 4
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF008
Landfill No. 1
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF015
Landfill No. 2
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
LF016
Landfill No. 3
Statement of Basis and RCRA Permit
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
OT029
Radar Tower
Site
LTM in accordance with the approved
Statement of Basis, RCRA Permit and
Reduce LCC
Through the duration of the POP
AF, USACE, and Regulatory approval of LTM documentation (e.g., Annual
Land Use Control Inspection
Reports, Reduce LLC
Summary Report, etc.).
Monitoring documentation
(e.g., Annual Corrective
Measures Implementation
Progress Reports, Annual
RW502
SWMU 55/76
Site Closeout
Ten (10) years documentation (e.g., Site
Closeout Report and Well
SA501
SWMU
86/87/AOC A
and RCRA Permit
Seven (7) years AF, USACE, and Regulatory approval of RC documentation (e.g., Regulator approval of, and
Air Force signature on, Final documentation (e.g., Land
SS009
Site 7 Haz.
Waste and RCRA Permit
Seven (7) years AF, USACE, and Regulatory…