Section_32_12_13_Prime_Coat_Tack_Coat.docx

DOCX document 24 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 32 12 13 PRIME COAT/TACK COAT

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 12 13

SECTION 32 12 13

PRIME COAT/TACK COAT

PART 1 GENERAL

1.1SECTION INCLUDES
A.Materials and procedures for applying:
1.Prime coat: Liquid or emulsified asphalt to a prepared subgrade or untreated base course.
2.Tack coat: Cutback or emulsified asphalt to the existing surface or new pavement surface and intermediate lifts.
B.Blotter materials and procedures for absorbing excess asphalt as required.
1.2REFERENCES
A.AASHTO T 27: Sieve Analysis of Fine and Coarse Aggregates
B.AASHTO T 201: Kinematic Viscosity of Asphalts
1.3SUBMITTALS
A.Certificate showing asphaltic material complies with Section 32 12 03.

PART 2 PRODUCTS

2.1PRIME COAT
A.MC-70 or MC-250, meeting the requirements of Section 32 12 03.
B.Blotter material: Granular materials following AASHTO T 27, meeting the following criteria:

Table 1 Granular Materials

Sieve Size
Percent Passing

No. 4 No. 10 No. 200 90 to 100 25 to 80 0 to 15

2.2TACK COAT
A.CSS-1h emulsified asphalt meeting the requirements of Section 32 12 03.
1.Diluted 2:1 – two parts concentrate to one part water by the manufacturer.
a)Dilute at terminal only.
b)Do not change dilution without obtaining prior written approval from the Engineer.
B.Tack coat referred to for paving fabrics is a PG 58-22 or PG 64-22.
C.Do not use an emulsion or cutback in paving fabric placement.

PART 3 EXECUTION

3.1SURFACE PREPARATION
A.Prime Coat:
1.A prime coat is an application required on aggregate base courses to receive new HMA pavement less than 4 inches thick.
1.Shape the surface to the required grade and section.
2.Keep the surface free from ruts, corrugations, or other irregularities.
3.Compact the surface following Section 02056.
B.Tack Coat:
1.Clean the surface of all materials that prevent the tack coat from bonding to the existing surface such as mud, dirt, leaves, etc.
2.Cover all tacked surface areas with surfacing materials the same day the tack coat is applied.
3.2APPLICATION
A.Apply at the following rates:
1.Prime Coat:0.5 gal/yd2
2.Tack Coat:0.15 gal/yd2
3.The above application rates may vary according to field conditions. Obtain approval for the quantities, rate of application, temperatures, and areas to be treated before any application.
B.Do not apply prime coat or tack coat:
1.On a wet surface.
2.When the surface temperature is below 50 degrees F.
3.When weather conditions prevent it from adhering properly.
C.Protect all structures including guardrails, guide posts, etc. from being spattered or marred.
D.Use a pressure distributor to apply the asphalt in a uniform, continuous spread.
E.Keep the viscosity between 50 and 100 centistokes. AASHTO T 201.
F.Immediately apply another application to under primed surface.
G.Apply a prime or tack coat to all surfaces, including vertical that will come in contact with Hot Mix Asphalt.
H.Spread blotter material if the prime coat fails to penetrate. Use the quantities required to absorb the excess asphalt.
3.3TRAFFIC CONTROL
A.Refer to Section 01 55 26.
B.Maintain the prime coat/tack coat until the next course is placed.
C.Keep all traffic off the prime coat until it has cured and dried.

END OF SECTION