SECTION 03 11 00 CONCRETE FORMING

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 03 11 00

SECTION 03 11 00

CONCRETE FORMING

PART 1 GENERAL

1.1SECTION INCLUDES
A.Formwork for cast-in-place concrete.
B.Openings in formwork for other affected work.
C.Form accessories such as snap ties, bracing, etc.
D.Stripping formwork.
1.2REFERENCES

A.ACI 347: Recommended Practice for Concrete Formwork.

1.3DEFINITIONS
A.Shoring: The activity to support formwork.
B.Reshoring: The activity to reduce the amount of formwork supporting concrete elements. As concrete sets and strength increases, less need for formwork occurs gradually until concrete becomes free standing.
1.4SUBMITTALS
A.Shop Drawings: Fabrication and erection drawings of forms for specific finished concrete surfaces, as indicated. Show general construction of forms, jointing, special joints or reveals, location and pattern of form tie placement, and other items affecting exposed concrete visibility.
B.Form Release Agent: Where concrete surfaces are scheduled to receive special finishes or applied coverings which may be affected by agent submit manufacturer's instructions for use of agent.
1.5QUALITY ASSURANCE
A.Designer's Qualifications: Structural professional engineer who complies with Utah licensing law, has experience in concrete formwork, and is acceptable to the authority having jurisdiction.
B.Design Forms:
1.With sufficient strength to maintain finished tolerances indicated in Section 03 35 00, to support loads, pressures, and allowable stresses as outlined in ACI 347 and for design considerations such as wind loads, allowable stresses, and other applicable requirements of local Laws and Regulations.
2.To permit easy removal.
3.For required finishes.
C.The design, engineering, and construction of formwork is Contractor's responsibility.
1.6JOB CONDITIONS
A.For reference purposes, establish and maintain sufficient control points and bench marks to check tolerances. Maintain in an undisturbed condition and until final completion and acceptance of Work.
B.Regardless of tolerances specified, allow no portion of Work to extend beyond legal boundaries.
1.7FIELD SAMPLES
A.Prepare field samples and submit per Section 01 33 00.
B.Construct and erect sample formwork panel for architectural concrete surfaces receiving special treatment or finish as a result of formwork. Formwork to include vertical and horizontal form joints and typical rustication joints when required.
C.Size panel to indicate special treatment or finish required, including form release agent.
D.Remove formwork after casting concrete.
1.8ACCEPTANCE
A.Secure ENGINEER's inspection of form layout for concrete flat work.
PART 2PRODUCTS
2.1FORM MATERIALS
A.Faced with material which will produce smooth and uniform texture on concrete, unless indicated otherwise.
B.Arrange facing material orderly and symmetrical, keeping number of seams to a minimum.
C.Do not use material with raised grain, patches, or other defects which will impair texture of concrete surface.
2.2FORMWORK ACCESSORIES
A.Form Ties:
1.Use ties constructed so that end fasteners can be removed without spalling concrete faces.
2.After end fasteners of ties have been removed, embedded portion of ties are to terminate not less than 2 times the diameter or thickness of the fasteners from formed faces of concrete, but in no case greater than 3/4 inch.
3.When the formed face on concrete is not exposed, form ties may be cut off flush with formed surfaces. Use ties with 3/4 inch diameter cones on both ends or an approved equal for water retaining structures.
B.Premolded Expansion Joint Filler: Unless indicated otherwise, provide Type F1, Section 32 13 73.
C.Form Release Agent: Colorless material which will not stain concrete, absorb moisture, impair natural bonding or color characteristics of concrete. To prevent contamination, agents used on potable water structures are subject to review by COR prior to use.
D.Fillets for Chamfered Corners: Wood strips 1 inch x 1 inch size, maximum length possible.
PART 3EXECUTION
3.1INSPECTION
A.Verify lines, levels, and measurements before proceeding with formwork.
3.2FORM CONSTRUCTION
A.Make forms sufficiently tight to prevent loss of concrete.
B.Unless indicated otherwise, place chamfer strips in corners of forms to produce beveled edges on permanently exposed exterior corners.
C.To maintain specified finish tolerances, camber formwork to compensate for anticipated deflections.
D.Provide positive means of adjustment using wedges, jacks, Shores, and struts to take up all settlement during concrete placing operation.
E.Provide temporary ports in formwork to facilitate cleaning and Inspection. Locate openings at bottom of forms to allow flushing water to drain.
F.At construction joints, overlap forms over hardened concrete at least 6 inches. Hold forms against hardened concrete to prevent offsets or loss of mortar at construction joint and to maintain true surface.
G.Construct wood forms for wall openings to facilitate loosening, or counteract swelling.
H.Fasten wedges used for final adjustment of forms prior to concrete placement in position after final check.
I.Anchor formwork to Shores, supporting surfaces or members to prevent upward or lateral movement and deflection of any part of formwork system during concrete placement.
J.Provide runways for moving equipment with struts or legs, supported directly on formwork or structural member without resting on reinforcing.
K.Position expansion joint material and other embedded items accurately and support to prevent displacement.
L.To prevent entry of concrete, fill voids in sleeves, inserts, and anchor slots temporarily with readily removable material.
M.For architectural concrete, limit deflection of facing materials between studs as well as deflection of studs and walers to 0.0025 times span.
N.For underground concrete work, do not use soil walls for forming unless authorized by ENGINEER.
3.3INSERTS, EMBEDDED PARTS, AND OPENINGS
A.Provide formed openings for elements embedded in or passing through concrete.
B.Coordinate work of other sections for the forming and setting of openings, slots, recesses, chases, sleeves, bolts, anchors, and other inserts.
C.Install accessories per manufacturer's instructions. Ensure items are not disturbed during concrete placement.
3.4FORM FINISHES
A.Use forms with smooth rubbed, scrubbed, sand floated finishes that meet ACI 347 unless indicated otherwise.
B.For As-cast Finishes:
1.Install form panels in orderly arrangement with joints planned in approved relation to building elements.
2.Where panel joints are recessed or otherwise emphasized, locate form ties within joints, not within panel areas.
3.Where an as-cast finish is required, no grouting will be permitted in the finishing operation.
C.Textured Finishes: As indicated.
3.5APPLICATION OF FORM RELEASE AGENT
A.Apply form release agent on formwork per manufacturer's instructions. Apply prior to placing reinforcing steel, anchoring devices, and embedded items.
3.6FORM REMOVAL
A.Do not pry against face of concrete. Use only wooden wedges.
B.When repair of surface defects or finishing is required at an early age, remove forms as soon as concrete has hardened sufficiently to resist damage from removal operations.
C.Remove top forms on sloping surfaces of concrete as soon as concrete has attained sufficient stiffness to prevent sagging. Perform needed repairs or treatment required on such sloping surfaces at once, followed by specified curing.
D.Loosen wood forms for wall openings as soon as it can be accomplished without damage to concrete.
E.Formwork for columns, walls, sides of beams, and other members not supporting the weight of concrete may be removed as soon as the concrete has hardened sufficiently to resist damage from removal.
F.Where no Reshoring is planned, leave forms and Shoring used to support weight of concrete in beams, slabs, and other concrete members in place until concrete has attained its specified strength.
G.Where Reshoring is planned, supporting formwork may be removed when concrete has reached 70 percent of specified strength, provided Reshoring is installed immediately.
H.When Shores and other vertical supports are so arranged that non-load carrying, form-facing material may be removed without loosening or disturbing Shores and supports, facing material may be removed at an earlier age as directed.
3.7RESHORING
A.When Reshoring is permitted or required, plan operations in advance and obtain approval.
B.During Reshoring do not subject concrete in beam, slab, column, or any other structural member to combined dead and construction loads and live loads in excess of loads permitted for developed concrete strength at time of Reshoring.
C.Place Reshores as soon as practical after stripping operations are complete, but in no case later than end of working day on which stripping occurs.
D.Tighten Reshores to carry required loads without over-stressing.
E.Leave Reshores in place until the concrete being supported has reached its specified strength.
F.For floors supporting Shores under newly placed concrete, level original supporting Shore or Reshore.
1.Reshoring system shall have a capacity to resist anticipated loads in all cases equal to at least 1/2 the capacity of the Shoring system.
2.Unless otherwise specified locate Reshores directly under a Shore.
3.In multistory buildings, extend Reshoring through a sufficient number of stories to distribute the weight of newly placed concrete, forms, and construction live loads in such a manner that design loads of floors and supporting Shores are not exceeded.
G.Design, engineering, and construction of Shoring and Reshoring is the responsibility of the CONTRACTOR.
3.8REMOVAL STRENGTH
A.When removal of formwork or Reshoring is based on concrete reaching a specified strength, it shall be assumed that concrete has reached this strength when either of the following conditions has been met:
1.When test cylinders, field cured along with the concrete they represent, have reached the specified strength.
2.When concrete has been cured per Section 03 39 00 for the same length of time as the site-cured cylinders that reached specified strength. Determine the length of time the concrete has been cured in the structure by cumulative number of days or fractions thereof, not necessarily consecutive, during which the air temperature is above 50 deg. F. and concrete has been damp or sealed from evaporation and loss of moisture.
3.9REUSE OF FORMS
A.Do not reuse forms if there is any evidence of surface wear or defect which would impair quality of concrete surface.
B.Thoroughly clean and properly coat forms before reuse.
3.10FIELD QUALITY CONTROL
A.Before commencing a pour, verify connections, form alignment, ties, inserts and Shoring are placed and secure.
B.Observe formwork continuously while concrete is being placed to verify that the forms are plumb and there are no deviations from desired elevation, alignment, or camber.
C.If during construction any weakness develops and false-work shows undue settlement or discoloration, stop work, remove affected construction if permanently damaged, and strengthen false-work.

END OF SECTION