SECTION 32 11 28 COLD RECYCLED ASPHALT BASE

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 11 28

SECTION 32 11 28

COLD RECYCLED ASPHALT BASE

PART 1GENERAL
1.1SECTION INCLUDES
A.Mill existing asphalt material to required depth and width.
B.Mix with emulsified asphalt, quick lime slurry, and water if required, place to line and grade and compact.
1.2REFERENCES
A.AASHTO T 26: Quality of Water to be Used in Concrete
B.AASHTO T 166: Bulk Specific Gravity of Compacted Bituminous Mixtures Using Saturated Surface-Dry Specimens
C.AASHTO T 245: Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus
D.ASTM C 110: Standard Test Methods for Physical Testing of Quicklime, Hydrated Lime, and Limestone
E.ASTM C 977: Standard Specification for Quicklime and Hydrated Lime for Soil Stabilization
F.ASTM D 2950: Test Method for Density of Bituminous Concrete in Place by Nuclear Method
1.3SUBMITTALS
A.Submit mix design for Engineer’s approval prior to starting cold recycling operation.
B.Provide a Manufacturer’s Certificate of Compliance for Quick Lime.
1.4ACCEPTANCE
A.The Contractor shall run five density tests on each test lot.
1.A test lot is defined as the amount of cold recycled material placed during one full day’s production.
2.Each density test consists of the mean of three in-place nuclear wet density tests. ASTM D 2950.
3.Establish the target density by obtaining a sample of loose material from the roadway just ahead of the rolling operation.
a.Heat sample in oven at 140 degrees F for two hours maximum.
b.Compact mix immediately using standard 50 blow Marshall procedure. AASHTO T 245.
c.The target for roadway compaction is 96 percent of the mean of 3 Marshall briquettes for each test lot. AASHTO T 166.
B.The COR verifies the surface with a 10-ft straightedge at selected sites. Correct surface variations in excess of ⅜ inch by removing or adding material.
1.7PAYMENT PROCEDURES
A.Include all costs for quick lime slurry in the Cold Recycled Asphalt Base.

PART 2 PRODUCTS

2.1MATERIALS
A.Cold Recycled Asphalt Base gradation:
Sieve
Percent Passing by Weight
1-1/2”
100
1”
90
B.Use asphalt emulsion as shown on the plans. Refer to Section 32 12 03.
C.Use high calcium pebble quick lime (Hot hydrated lime slurry) that has a minimum dry solids content of 35 percent by weight and that is a pumpable suspension of solids in water. Quick lime slurry must conform to ASTM C 977 using test method ASTM C 110.
D.Use 1.5 percent quick lime by weight of cold recycled base.
E.Use potable water for the quick lime slurry. Refer to AASHTO T 26.
2.2EQUIPMENT
A.Use self-propelled equipment with sufficient power, traction and stability to maintain an accurate depth of cut.
B.Use equipment that will process full depth and lane width in one pass, with screening and crushing capability.
C.Use a machine capable of mixing the pulverized material, emulsified binding agent, and quick lime slurry to a homogeneous mixture.
D.Provide lime slurry equipment that accurately proportions quick lime and water, mixes these ingredients to obtain proper slaking, and maintains a uniform, homogenous slurry. Agitate slurry sufficiently to prevent separation while transporting. Add the lime slurry to the pulverized surfacing by a spray bar at the cutting head on the mill. Accurately meter the slurry into the recycled materials.
E.Use a mixing machine capable of placing the mixed material into a windrow or directly into the hopper of a paver.
F.Separate machinery may be used for mixing.
G.Use a positive displacement pump capable of accurately metering the required quantity of additive down to a minimum rate of 4 gallons per minute.
H.Use a mixing machine that has a meter capable of measuring the flow and total delivery of the additive.
I.Use a machine capable of picking up the entire windrow when a pick-up machine is used to feed the paver.
J.Use 30-ton minimum pneumatic rollers.

PART 3 EXECUTION

3.1PREPARATION
A.Clean or clear away all debris and vegetation within 1 ft of pavement edge.
3.2RECLAIMED MATERIALS
A.Crush or screen the reclaimed material to pass a 1½ inch sieve.
B.Reclaimed material must be free of organic materials, soil, or other foreign substances.
3.3PLACEMENT
A.Place the mixed material with a self-propelled asphalt paver.
B.Adjust emulsion content as pavement conditions change. Repair reclaimed materials when surface ruts or ravels before placement of final wearing surface.
C.Use watering device to prevent materials from adhering to the tires for breakdown or intermediate rolling.
D.Add water to milled material as necessary to facilitate uniform mixing.
E.Continue breakdown rolling until no displacement is noted.
F.Use steel wheel rollers in static or vibratory mode as required for final rolling.
G.Wait 72 hours after a rain or confirm that moisture content is less than 1.5 percent before placing flush, tack, or final surfacing on cold recycled material.
3.4LIMITATIONS
A.Do not disturb underlying crushed aggregate base.
B.Do not heat screed.
C.Do not park roller or leave idle on uncompacted recycled surface.
D.Perform recycling operations when ambient temperature exceeds 50 degrees F in the shade and pavement temperature exceeds 70 degrees F. Stop recycling operations when weather is foggy or rainy.
E.Prohibit traffic on compacted recycled material for 2 hours after compacting is completed. Remove all loose aggregates by power brooming before allowing traffic on the compacted recycled material.

END OF SECTION