SECTION_01_71_16_Acceptance.docx

DOCX document 22 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 01 71 16 ACCEPTANCE

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 71 16

SECTION 01 71 16

ACCEPTANCE

PART 1GENERAL
1.1SECTION INCLUDES
A.COR’s acceptance provisions.
B.Dispute resolution.
1.2DEFINITIONS
A.Acceptance Testing: Testing to verify product or work complies with the Contract Documents. Contractor is responsible for accomplishing the testing and for supplying copies of test results to COR.
B.Independent Testing Agency: A testing agency NOT owned by affiliated with, or in any way associated with Contractor, or any of Contractor’s Subcontractors and Suppliers, that is accredited by a national authority.
C.Lot: A lot is an isolated quantity of material produced essentially by the same process. Example: One day's production or 1500 tons.
D.Sample: A sample is one measurement or count that represents a part or all of the Lot. Example: Five density measurements that represent the day's production (or Lot) are five separate samples.
1.3ACCEPTANCE
A.Acceptance of Product and Material: Based upon visual examination or physical testing. Contracting Officer may have such examination or testing done by a separate agency.
B.Control Testing: Contracting Officer retains right to accept or reject material or work based upon Contractor's control testing.
C.Acceptance of Lots:
1.Samples in a Lot will be randomly collected.
2.A Lot may be evaluated on the basis of fewer Samples when the minimum specified number of Samples cannot be collected.
3.A Lot will not be passed until the Contracting Officer accepts or passes all sub-lots.
4.A Lot with a defective sub-lot may be accepted at a reduced price if an appropriate pay factor is used to determine the price adjustment for the whole Lot. Do not apply pay factors only against defective sub-lots.
D.Submittals: Acceptance of submittal data supercedes specified criteria. Example; Mix design acceptance may alter specified mix design criteria.
1.4DEFECTIVE WORK
A.Failure to detect any Defective Work or materials does not prevent later rejection when such defect is discovered, nor does it obligate Contracting Officer for acceptance.
B.If work or material is obviously defective, it must be corrected even if it or they are not a part of a set of random Samples.
1.5DISPUTE RESOLUTION
A.Contractor must provide basis of disagreement in writing to Contracting Officer.
B.If Contractor desires to do any retesting, Contractor must submit a written plan to the Contracting Officer for approval. Any retesting done without Contracting Officer’s written approval will be rejected.
C.The retesting must be performed by a mutually acceptable Independent Testing Agency.
D.Retesting for acceptance will be done at no cost to the Government.
E.Contracting Officer reserves the sole right not to utilize the retest results for evaluation of the Work.
PART 2PRODUCTSNot Used
PART 3EXECUTIONNot Used

END OF SECTION

ACCEPTANCE Page 2

File details come from the government source that posted it. Updated .