SECTION_32_01_16_Recycled_Asphalt_Paving.docx

DOCX document 24 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 32 01 16 RECYCLED ASPHALT PAVING

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 01 16

SECTION 32 01 16

RECYCLED ASPHALT PAVING

PART 1GENERAL
1.1SECTION INCLUDES
A.Placing RAC in base, leveling, or surface courses.
B.Mix design requirements.
1.2REFERENCES
A.ASTM D 2950: Standard Test Method for Density of Bituminous Concrete In Place by Nuclear Method.
B.ASTM D 3549: Standard Test Method for Thickness or Height of Compacted Bituminous Paving Mixture Specimens.
1.3DEFINITIONS
A.RAP (reclaimed asphalt pavement): Product of bitumen and aggregate recovered from milling an asphalt concrete pavement. No roadbase or Subgrade materials are contained in RAP.
B.RAC (recycled asphalt concrete): Product of mixing RAP, new aggregates and asphalt cement or recycle agent or both.
1.4SUBMITTALS
A.Prior to commencing work of this Section, submit.
1.Traffic control plan, Section 01 55 26.
2.A list of equipment to be used.
3.Type of asphalt to be used, Section 32 12 03.
B.RAC Mix Design: Determine the conditions and properties of the existing materials. Identify recycling agent and submit the following data as applicable.
1.When the amount of RAP is 15 percent or less of the RAC, submit a design mix formula if Supplier does not have a design mix formula at the plant. The formula shall be based on current test data.
2.When the amount of RAP added to the RAC is over 15 percent, submit a design mix formula.
C.RAC Delivery Tickets: Section 32 12 17.
PART 2PRODUCTS
2.1MATERIAL
A.Recycled Asphalt: RA grade, Section 32 12 03:
B.Tack Coat: Section 32 12 14.
C.Paving Geotextile: Section 31 05 19.
D.Paving Geogrid: Section 31 05 21.
2.2RECLAIMED ASPHALT PAVEMENT (RAP) AGGREGATE
A.Free of detrimental quantities of deleterious materials, with a minimum sand equivalent value of 50 and graded (on a non-dried basis) as follows.
Sieve
Percent Passing by Weight
1-1/2”
100
1”
90
PART 3EXECUTION
3.1CONSTRUCTION EQUIPMENT
A.Laydown Machine: Provide track equipment when operating on fabrics or geogrid, otherwise type of equipment to be provided is Contractor’s choice.
B.Compactors: Steel wheeled static or vibratory. Any use of a pneumatic tire roller is for intermediate compaction only.
3.2PREPARATION
A.General:
1.Coordinate utility location, Section 01 31 13. Contact utility companies and other agencies, for dangerous concentration of combustible, flammable, or explosive matter.
2.Lower Street Fixtures if Pavement recycler machine is not capable of releasing Pavement-cutting mechanism to protect fixtures.
3.Remove plant materials from cracks, edges and joints. Sweep surface clean. Blow cracks clean.
4.Stabilize portland cement concrete Subgrade slabs, if applicable.
5.Apply tack coat, Section 32 12 14.
6.Verify that surfaces are dry.
B.Trees, Plants, Ground Cover: Protect trees, plants and other ground cover from damage.
C.Traffic Control:
1.Control pedestrian and vehicular traffic, Section 01 55 26.
2.Protect pavement from traffic until mixture has cooled enough not to become marked.
3.Apply temporary traffic and lane marking tape or paint after layout and placement has been verified with COR.
D.Milling, Section 02 41 14
3.3PLACING RAC
A.Hot-laid RAC, Section 32 12 16.
B.Cold-laid RAC, Section 32 12 17.
C.Mix and blend milled aggregate, recycling asphalt, virgin asphalt and virgin aggregate per the mix design.
3.4TOLERANCES
A.Compaction, lift thickness, grade, cross slope, Section 32 12 17.
B.Complete compaction of RAC within 5 minutes of placing RAC and before its temperature drops below 200 deg. F.

END OF SECTION

RECYCLED ASPHALT PAVING Page 1