SECTION 02 41 13.13 PAVEMENT REMOVAL

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 02 41 13.13

SECTION 02 41 13.13

PAVEMENT REMOVAL

PART 1 GENERAL

1.1SECTION INCLUDES
A.Removal of roadway Pavement.
B.Milling roadway Pavement.
C.Removal of curb, gutter, sidewalk, Driveway Approach, waterway, or similar flatwork.
D.Disposal of removed materials.
1.2RELATED WORK
A.Demolition of structures and utilities.
1.3DEFINITIONS
A.ADA: Americans with Disabilities Act.
B.UFAS: Uniform Federal Accessibility Standards
1.4SUBMITTALS
A.Traffic control plan, Section 01 55 26.
1.5SITE CONDITIONS
A.Control dust, Section 01 57 00.
PART 2PRODUCTSNot Used
PART 3EXECUTION
3.1PREPARATION
A.General
1.Coordinate utility location, Section 01 31 13.
2.Preserve all active utilities.
3.Notify neighborhood of day and time of operation.
4.Make sure invert covers are properly installed in storm drain and sanitary sewer systems, Section 01 71 13.
5.Mark existing utilities on redline drawings.
B.Traffic Control: Provide worker and public safety, Section 01 55 26.
C.Tree Roots:
1.Avoid or minimize damage to tree roots. Roots provide anchorage, storage of energy, and absorption and conduction of water and mineral elements. Loss of root connection affects health and stability of tree and safety of people and property.
2.Provide certified arborist observation of root cuts larger than 4 inches diameter. Notify COR 48 hours prior to such root cut.
D.Existing Surfaces:
1.Do not damage adjacent concrete surfaces that are not scheduled for removal.
2.Use rubber cleats or Pavement pads when operating backhoes, outriggers, track equipment, or any other equipment on or crossing paved surfaces.
3.Restore paved surfaces that are damaged by removal operations at no additional cost to the OWNER. Match the existing Pavement surface plus 1 inch.
3.2SAW-CUT CURB HORIZONTALLY
A.Saw cut curbs for ADA ramps at 1:12 slope. No trip hazard at gutter flow line.
B.Saw cut curbs for flares:
1.1:4 slope measured to grade, or
2.1:12 slope measured horizontally when complying with ADA and UFAS.
3.3REMOVE PORTLAND CEMENT CONCRETE
A.Remove concrete to the nearest expansion joint or vertical saw cut.
B.Make concrete cuts straight, vertical to the surface, true, full depth.
C.DO NOT use machine mounted impact hammers.
3.4REMOVE ASPHALT CONCRETE
A.Saw cut full depth and remove Pavement.
B.When asphalt concrete overlays Portland cement concrete Pavements do not use a machine mounted impact hammer.
3.5MILLING
A.Machine:
1.Equipped to prevent air pollution.
2.Equipped with a system to control slope of mill cut.
B.Tolerances:
1.Milling Depth: As indicated plus or minus 10 percent not uniformly high or uniformly low.
2.Striation Texture: Uniform, discontinuous, longitudinal, 3/16 inch deep maximum, 3/4 inch center to center.
3.Smoothness: Plus or minus 5/16 inch in 25 feet.
4.Cross Slope: Plus or minus 1/4 inch in 10 feet.
C.Performance:
1.Lower utility frames, covers, and other Street Fixtures.
2.Mill surfaces to the depth shown on the Drawings or indicated by COR. Do not disfigure adjacent work or existing surface improvements.
3.If milling exposes smooth underlying Pavement surfaces, mill the smooth surfaces to make them rough.
4.Mill off material if it ponds water or if it has been damaged by water.
5.Where vehicles or pedestrians must pass over milled edges provide safe temporary ramps suitable to speed of user vehicles (or suitable for wheel chair user needs).
6.Remove excess material and clean milled surfaces.
7.If work equipment is removed from the milling site and milled surface awaits further work, provide appropriate traffic control and cleaning.
3.6GRINDING
A.Machine:
1.Cutting head 36 inches wide minimum.
2.50 to 60 diamond blades per foot of head.
B.Preparation:
1.Control traffic.
2.Provide water truck, waste truck, and other support machinery.
3.Mark areas to be ground.
C.Tolerances:
1.1/4 inch lip transverse to the direction of vehicular travel. Potential for ponding not allowed.
2.1/8 inch lip (or dent) parallel to direction of vehicular travel.
3.Taper ground areas from the lane/shoulder line into the shoulder area at 1/4 inch per foot.
D.Performance:
1.Skid resistance of final ground surface must be comparable to adjacent sections not requiring corrective work.
2.Surface treatement of ground areas.
a.Asphalt Concrete: Asphalt tack coat and sand blotter, Section 32 12 14.
3.Waste grindings legally.
4.Protect wildlife habitat.
3.7CLEANING
A.Remove all debris and concrete dust. Clean surrounding rails, sidewalks, Driveways, landscaping and other objects in vicinity of work.

END OF SECTION