SECTION 33 31 00 SANITARY SEWERAGE SYSTEMS

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 33 31 00

SECTION 33 31 00

SANITARY SEWERAGE SYSTEMS

PART 1GENERAL
1.1SECTION INCLUDES
A.Gravity sanitary sewerage systems.
B.Pressure systems are indicated in Section 33 11 00.
1.2REFERENCES
A.ASTM C 478: Standard Specification for Precast Reinforced Concrete Manhole Section.
B.ASTM C 891: Standard Practice for Installation of Underground Precast Concrete Utility Structures.
C.ASTM C 923: Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes and Laterals.
1.3PERFORMANCE REQUIREMENTS
A.Vertical Cover: Unless indicated otherwise, 2 feet minimum for laterals and 4 feet when subjected to light construction equipment loads.
B.Remove any section of pipe already placed that is found to be out of alignment tolerance indicated, defective, or damaged. Relay or replace at no additional cost to OWNER.
1.4PROJECT CONDITIONS
A.Minimize traffic interruptions. Barricade stockpiles.
B.Provide access to adjacent properties for local traffic and pedestrians, Section 01 31 13.
C.Repair public and private facilities damaged by Contractor.
D.Prior to Backfilling: Commission pipeline per Section 33 08 00. Provide sizes and types of equipment connections and fittings which match pipe materials when pressure testing system.
1.5ACCEPTANCE
A.Each sanitary sewer system component must pass applicable requirements in Section 33 08 00.
PART 2PRODUCTS
2.1PIPING AND FITTINGS
A.Provide piping materials and factory fabricated piping products of sizes, types, and classes indicated.
B.Where not indicated, provide proper selection acceptable to COR to comply with installation requirements.
C.Provide pipe fittings and accessories of same material and weight or class as pipe, with joining method indicated or recommended by manufacturer.
2.2MORTAR, GROUT AND CONCRETE
A.Mortar: Cement, Section 04 05 16.
B.Grout: Cement, Section 03 61 00.
C.Concrete:
1.Cast-in-place: Class 4000, Section 03 30 04.
2.Precast: Class 5000, Section 03 40 00.
2.3MANHOLES
A.Basin: Precast concrete, ASTM C 478.
B.Steps: None.
C.Top: Concentric cone. Concentric flat slab concrete deck allowed only with COR's permission.
D.Frame and Cover: Scoriated, asphalt coated, heavy duty, ductile iron; Section 05 56 00 with flat top design meeting load rating H-20 and appropriate utility lettering. Shape, size and lifting device as indicated.
E.Pipe Connectors: Resilient, ASTM C 923. Sand mortar grout pipe connections.
F.Joints in Sections: Bituminous mastic gasket-type sealant unless indicated otherwise.
PART 3EXECUTION
3.1PREPARATION
A.Verify Trench Excavation is ready to receive work, and dimensions, and elevations are as indicated.
B.Hand trim Excavations to required elevations. Backfill over excavations and compact, Section 31 23 26.
C.Examine areas and conditions under which materials and products are to be installed. Do not proceed with system installation until unsatisfactory conditions have been corrected in manner acceptable to system installer.
D.Clearly identify and promptly set aside defective or damaged pipe.
E.Use pipe cutting tool acceptable to pipe manufacturer.
3.2INSTALLATION - PIPE AND FITTINGS
A.Place bell or groove end facing upstream.
B.Install gaskets per manufacturer's recommendations.
C.Plug leakproof such pipeline branches, stubs or other open ends which are not to be immediately connected.
D.Clean interior of pipe of dirt and debris as work progresses.
E.Meet line and grade tolerance specified in Section 33 08 00.
3.3INSTALLATION - MANHOLES
A.Form bottom of Excavation clean and smooth to correct elevation.
B.Place structures in location indicated.
C.Install precast units, ASTM C 891.
D.Provide elevations and pipe inverts for inlets and outlets indicated.
E.When structures occur in Pavements, mount frame and cover 1/2 inch below finished surface, elsewhere set 3 inches above finished grade. Provide a concrete Cover Collar between the frame and asphalt Pavement.
3.4ABANDONED UTILITIES
A.Plug and cap with concrete all open ends of abandoned underground utilities which are to remain in place.
B.Provide closure to withstand hydrostatic or earth pressure which may result after ends of abandoned utilities have been closed.
3.5TAP CONNECTIONS - 6 INCHES AND SMALLER
A.Field cutting into new or existing piping will not be permitted unless written permission is obtained from COR.
B.Make connections to existing pipe and underground structures, so connections will conform as nearly as practicable to requirements specified for new work.
C.Use commercially manufactured wyes for branch connections. Spring wyes into existing line and encase entire wye, plus 6 inches overlap, with not less than 6 inches of concrete.
D.For taps into existing 24 inches or larger piping, or to underground structures, cut opening into unit sufficiently large to allow 3 inches of concrete to be packed around entering connection. Cut ends of connection passing through pipe or structure wall to conform to shape of and parallel with inside wall, unless otherwise indicated. Grout connection to provide smooth transition inlet into pipe.
3.6TAP CONNECTIONS - LARGER THAN 6 INCHES
A.Not allowed. Provide a Manhole structure.
3.7JOINTS
A.Join pipe per manufacturer's recommendation or as indicated.
B.Joining Pipe of Different Sizes: At Manholes only.
C.Use neoprene couplings with stainless steel bands to make connections between dissimilar pipe, or where standard pipeline joints are impractical.
3.8BACKFILLING
A.Prior to Backfilling: Commission pipeline, Section 33 08 00. Provide sizes and types of equipment connections and fittings which match pipe materials when pressure testing system.
B.Trenches: Section 33 05 20.
C.Structures or Landscapes: Section 31 23 23.
3.9CLEANING
A.Remove debris, concrete, or other extraneous material which accumulates in existing pipes or structures.
B.Clean all pipelines after testing. Do not flush sand, gravel, concrete, debris or other materials into existing piping system.
3.10SURFACE RESTORATIONS
A.Provide temporary paved surfaces where Trenches pass through roadways, Driveways, or sidewalks.
B.Restore paved surfaces, Section 33 05 25.
C.Restore affected landscaped surfaces.

END OF SECTION