SECTION_31_05_19.19_Geogrids_Geocomposites.docx

DOCX document 28 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 31 05 19.19 GEOGRIDS/GEOCOMPOSITES

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 31 05 19.19

SECTION 31 05 19.19

GEOGRIDS/GEOCOMPOSITES

PART 1GENERAL
1.1SECTION INCLUDES
A.Geogrid and geocomposite material requirements.
1.2REFERENCES
A.ASTM D 4354: Standard Practice for Sampling of Geotextiles for Testing.
B.ASTM D 4759: Standard Practice for Determining Specification Conformance of Geosynthetics.
C.ASTM D 4873: Standard Guide for Identification, Storage, and Handling of Geotextiles.
D.ASTM D 5321: Standard Practice for Determining the Coefficient of Soil and Geosynthetic by Direct Shear.
E.ASTM D 6213: Standard Tests to Evaluate the Chemical Resistance of Geogrids to Liquids.
F.ASTM D 6637: Standard Test Method for Determining Tensile Properties of Geogrid.
G.FHWA-SA-96-071: Mechanically Stabilized Earth Walls and Reinforced Soil Slopes Design and Construction Guidelines.
1.3DEFINITIONS
A.Geocomposite: Fabric composed of a geogrid and geotextile.
B.MARV: Defined in Section 31 05 19.
1.4SUBMITTALS
A.Geogrid sample.
B.Geocomposite sample
C.Manufacturer’s warranty.
D.Installer’s warranty.
1.5DELIVERY STORAGE AND HANDLING
A.Label, handle and store product, ASTM D 4873.
B.Deliver product dry, in a plastic wrapping that protects the entire roll.
C.Protect product from ultraviolet light and temperature greater than 160 deg. F. until application. Cover product within 14 days of deployment.
1.6QUALITY ASSURANCE
A.Provide manufacturer’s on-site technical supervision and assistance if required for manufacturer’s warranty.
1.7WARRANTY
A.Manufacturer: Warrant product for a period of 20 years on a prorated basis against manufacturing defects, workmanship, and deterioration due to exposure to the elements.
B.Installer: Warrant material and workmanship for 2 years.
PART 2PRODUCTS
2.1GEOGRID/GEOCOMPOSITES - GENERAL
A.Synthetic fiber net at least 85 percent by weight of polypropylene, polyethylene, polyester, polyvinyl alcohol, or polyamide.
B.Resistant to chemical attack, rot and mildew.
C.No tears or defects that will adversely alter properties of product.
2.2ROADWAY PAVEMENT GEOCOMPOSITE
A.Placement is between asphalt layers. Product is geogrid glued to a lightweight non-woven bitumen coated geotextile.

Table 1: Roadway Pavement Geocomposite

Property
ASTM
MARV
Ultimate Tensile Strength, lb/ft
D 6637
3425 x 3425
Tensile Strength at 3 percent Strain, lb/ft
D 6637
825 x 825
Melting Point (geogrid), deg. F.
–
490
Softening Point (geotextile), deg. F.
–
220
2.3ROADWAY AGGREGATE GEOGRID
A.Subbase geogrid is placed on the Subgrade below new fill or crushed aggregate base.
B.Base course geogrid is placed between fills or crushed aggregate bases.

Table 2: Roadway Aggregate Geogrid

Property
ASTM
MARV
Subbase
Base Course
Ultimate Tensile Strength, lbs/ft.
D 6637
900 x 1400
900 x 1400
Tensile Strength at 2 percent Strain, lbs/ft.
D 6637
–
300 x 445
Tensile Strength at 5 percent Strain, lbs/ft.
D 6637
580 x 920
–
Coefficient of Direct Shear
D 5321
1.0
1.0
Chemical Resistance range, pH
D 6213
2 – 12
2 – 12
Aperture Size range, inches
Measured
0.5 – 1.3
0.5 – 1.3
Open Area, percent
-
50 – 80
50 – 80
2.4EMBANKMENT GEOGRID
A.Geogrid is used for earth slope and retaining wall reinforcement.

Table 3: Embankment Geogrid

Property
ASTM
MARV
Type 1
Type 2
Type 3
Long Term Design Strength, lb/ft
(a)
700
1300
1900
Chemical resistance, pH
D 6213
2 – 12
2 – 12
2 – 12
Aperture Size inches
Measured
0.8 – 1.2
0.8 – 1.2
0.8 – 1.2

NOTES

(a) FHWA-SA-96-071.

2.5CLAMPS, TAPE, RUBBER PADS
A.Recommended by manufacturer.
2.6SOURCE QUALITY CONTROL
A.Sample geogrids and geocomposites using ASTM D 4354 standard practices.
B.Verify specification conformance, ASTM D 4759.
PART 3EXECUTION
3.1PREPARATION
A.Instruct workers about protecting product of this section.
B.Repair damage to Subgrade surface prior to installation.
C.Round edges of Excavation and grade changes.
3.2GRANULAR BASE REINFORCEMENT
A.Deploy each panel per manufacturer’s recommendations.
B.Provide sufficient material to allow for expansion and contraction.
C.Do not fold. Do not tie overlaps.
D.Install panels so overlapping panel is upgrade of the underlying panel.
E.Provide geogrid overlap as follows.
Soil CBR Rating
Minimum Overlap
3 +
0.5 foot
2 – 3
1.0 foot
1 – 2
2.0 feet
less than 1
3.0 feet
F.Provide a minimum fill thickness of six inches prior to operating tracked vehicles over geogrid.
3.3ASPHALT CONCRETE PAVEMENT REINFORCEMENT
A.Clean the surface of the asphalt concrete base course.
B.Seal cracks wider than 1/8 of an inch. Repair larger cracks, Potholes, depressions, and irregularities.
C.Spray on tack coat uniformly at 0.08 - 0.10 gal/yd2 and place geogrid on the tack coat.
D.Overlap in a shingle fashion in the direction of overlay placement. Overlap all roll edges and ends six inches.
E.Place 2 inches minimum asphalt concrete over the geogrid. Compact, Section 32 12 16.
3.4SOIL REINFORCEMENT
A.Compact Embankment Subgrade.
B.Place Embankment geogrid at the locations and elevations shown on the Plans or controlled by the geogrid manufacturer. Place any specified free draining crushed aggregate base above the geogrid. Compact the fill to a Standard Proctor of 95 percent or greater.
3.5PROTECTION
A.At least 6 inches of fill cover is required if tracked vehicles are operated over geogrid.