SECTION 33 08 00 COMMISSIONING OF WATER UTILITIES

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 33 08 00

SECTION 33 08 00

COMMISSIONING OF WATER UTILITIES

PART 1GENERAL
1.1SECTION INCLUDES
A.Testing requirements for potable and non-potable water piping systems.
B.Warning: DO NOT use hydrostatic pressures described in this section for air-pressure testing.
1.2DEFINITIONS
A.Leakage: The quantity of water required to maintain the specified hydrostatic test pressure after the pipeline has been filled with water and the air expelled.
B.Non-rigid Pipe: Any pipe that requires Bedding and backfill material for structural support.
1.3SUBMITTALS
A.Pipeline Test Report: Submit.
1.Type of test.
2.Identification of pipe system.
3.Size, type, location and length of pipe in test section.
4.Test pressure and time.
5.Video cassette and log of visual examination.
6.Amount of Leakage versus allowable.
7.Date of test approval.
8.Signature of test supervisor.
9.Signature of Resident Project Representative witnessing and accepting the test.
1.4PROJECT CONDITIONS
A.Repair pipeline system at no additional cost to Government until it passes specified commissioning tests.
1.5WARRANTY
A.At the end of the One Year Correction Period repeat any test requested by COR to verify warranty of pipeline performance.
PART 2PRODUCTS
2.1TESTING MATERIALS
A.Medium: Water, air.
B.Recording Equipment (pressure systems):
1.Supply all equipment and power to perform pressure testing.
2.Secure approval of pressure gages.
3.Locate all gages and recording equipment away from affect of sunshine or unsuitable weather conditions.
4.Place, vents, pressure taps and drains for the test. Repair pipeline at completion of test at no additional cost to Government.
PART 3EXECUTION
3.1PREPARATION
A.Notify COR 48 hours in advance of test.
B.Carry out tests as pipeline construction progresses to ensure construction methods are producing satisfactory results.
C.Remove debris, sediment and other material from installed pipe prior to testing. Do not discharge or flush sand, gravel, concrete, debris or other foreign material into any existing pipeline system. Flushing with clean water only will be allowed but with minimal flows to eliminate exceeding capacities of the existing gravity systems. Flushing into existing pressurized water systems will not be allowed.
3.2ALIGNMENT AND GRADE TEST
A.Do not allow line and grade of pipe to vary more than 1/2 inch in 10 feet and not more than 1 inch variance from true line at any location.
B.Do not allow grade of pipe to vary more than 1/4 inch in 10 feet for all design grades less than or equal to 1 percent and not more than 1/2 inch total variance from true grade at any location. Also, do not allow grade of pipe to vary more than 1/2 inch in 10 feet for all design grades greater than 1 percent and not more than 1 inch total variance from true grade at any location. Theses tolerances shall be acceptable provided that such variation does not result in a level or reverse sloping invert.
C.The variation in the invert elevation between adjoining ends of pipe due to eccentricity of joining surface and pipe interior surfaces shall not exceed 1/64 inch per inch of pipe diameter, or 1/4 inch maximum.
3.3PRESSURE TEST
A.Air Test: Per pipe manufacturer's recommendation.
B.Hydrostatic test:
1.Provide 225 psi test pressure for 2 hours unless specified otherwise.
2.Provide air release taps at pipeline’s highest elevations and expel all air before the test. Insert permanent plugs after test has been completed.
3.No piping installation will be acceptable until the leakage is less than the amount allowed by industry standards for the type of pipe material being tested or if no standard prevails than the number of gallons per hour as determined by the formula:

Q = LD x square root of P/133,200 Where Q = allowable leakage, in gallons per hour.

L = length of pipe under test in feet.

D = nominal diameter of pipe in inches.

P = average test pressure, in pounds per square inch (gage).

C.Locate and repair defective joints and retest until the leakage rate is less than allowable.
D.Repair any noticeable leakage even if total leakage is less than allowable.
3.4OBSTRUCTION AND DEFLECTION TEST
A.Obstructions: Maximum protuberance is 1 inch.
B.Deflections:
1.Do not use mechanical pulling equipment when pulling mandrels through pipe.
2.Maximum reduction of internal diameter in any plane measured full length of installation and not less than 30 days after installation as follows.
a.Polyvinyl chloride pipe, 7.5 percent.
b.High density polyethylene pipe, 5 percent.
c.Ductile iron pipe, 3 percent.
d.Corrugated metal pipe, 7.5 percent.
3.Recommend an alternate method of measurement if mandrel testing would cause damage to internal pipe coating.
3.5INFILTRATION TEST
A.Maximum is 50 gallons per inch diameter per mile per 24 hours.
3.6PIPE TESTING SCHEDULE
A.Sanitary Sewers:
1.Alignment and grade test.
2.Obstructions and deflection test.
3.Infiltration test for gravity pipeline systems.
4.Pressure test for pressure pipeline systems.
5.Video inspection.
B.Subdrains:
1.Grade test: All pipelines drain.
2.Obstructions and deflection test.
C.Storm Drains:
1.Alignment and grade test.
2.Obstructions and deflection test.
3.Infiltration test for gravity pipeline systems.
4.Pressure test for pressure pipeline systems.
5.Video inspection.
D.Potable Water System:
1.Obstruction and deflection test.
2.Pressure test.
3.Disinfection (Section 33 13 00).

END OF SECTION