SECTION_03_61_00_Cementitious_Grouting.docx

DOCX document 23 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 03 61 00 CEMENTITIOUS GROUTING

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
SECTION_01_66_00_Product_Storage_and_Protection.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 03 61 00

SECTION 03 61 00

CEMENTITIOUS GROUTING

PART 1GENERAL
1.1SECTION INCLUDES
A.Pre-mixed non-metallic shrinkage resistant grout, pre-mixed water stop hydraulic cement grout, epoxy grout, and portland cement grout.
1.Grout for leveling beds of structural steel plates.
2.Sealing of joints and gaps between piping and structures.
3.Sealing of joints between construction components.
1.2REFERENCES
A.ASTM C 109: Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2 in. or 50 mm Cube Specimens).
B.ASTM C 144: Standard Specification for Aggregate for Masonry Mortar.
C.ASTM C 150: Standard Specification for Portland Cement.
D.ASTM C 190: Standard Test Method for Tensile Strength of Hydraulic Cement Mortars.
E.ASTM C 207: Standard Specification for Hydrated Lime for Masonry Purposes.
F.ASTM C 472: Standard Methods for Physical Testing of Gypsum Plasters and Gypsum Concrete.
G.ASTM C 595: Standard Specification for Blended Hydraulic Cements.
H.ASTM C 881: Standard Specification for Epoxy - Resin - Base Bonding Systems for Concrete.
I.ASTM C 1090: Standard Test Method for Measuring Changes in Height of Cylindrical Specimens from Hydraulic-Cement Grout.
J.ASTM C 1107: Standard Specification for Packaged Dry Hydraulic Cement (Non-Shrink).
K.ASTM C 1157: Standard Performance Specification for Blended Hydraulic Cement.
L.ASTM D 570: Standard Test Method for Water Absorption of Plastics.
M.ASTM D 638: Standard Test Method for Tensile Properties of Plastics.
N.ASTM D 695: Standard Test Method for Compressive Properties of Rigid Plastics.
1.3SUBMITTALS
A.Grout mix components. Indicate proportions used, environmental conditions, and admixture limitations. Indicate material "Type", "Grade", and "Class" which suits Project requirements.
B.Manufacturer's data for latex bonding agent.
PART 2PRODUCTS
2.1MATERIALS - GENERAL
A.Cement:
1.ASTM C 150 natural color Type II (normal) or Type IIA (air entrained).
2.ASTM C 595, or C 1157: Blended.
B.Lime: ASTM C 207, Type S, hydrated.
C.Water: Clean, non-staining and non-detrimental.
D.Grout Aggregate: ASTM C 144, standard masonry type.
2.2PORTLAND CEMENT GROUT
A.Proportions by Volume: 1 part Portland cement, and sand equal to 2-1/2 to 3 times sum of volumes of cement and lime.
B.Mix thoroughly with water to form a stiff workable plastic putty.
C.Compressive Strength: ASTM C 109, 2800 psi in 28 days.
2.3CEMENT BASED SHRINKAGE RESISTANT GROUT
A.Grade B or grade C premixed, non-metallic, non-gaseous product; ASTM C 1107 at a fluid consistency (flow cone) of 20 to 30 seconds. Thirty-minute-old grout shall flow through flow cone after slight agitation, in temperatures of 40 deg. F. to 90 deg. F.
B.Bleeding: None.
C.Compressive Strength: 6500 to 9000 psi, ASTM C 109 in 28 days.
D.Non-shrink percentage: 0.5 percent, ASTM C 1090.
2.4EPOXY ADHESIVE GROUT
A.Two component material suitable for use on dry or damp surfaces, 100 percent solids, high modulus, moisture insensitive, complying with ASTM C 881.
1.Tensile Strength: ASTM D 638, 5000 psi, minimum in 14 days.
2.Tensile Elongation: ASTM D 638, 2 percent minimum.
3.Compressive Strength: ASTM D 695, 6500 psi minimum in 24 hours and 70 deg. F., 12,500 psi in 28 days and 70 deg. F.
4.Water Absorption: ASTM D 570, 1 percent maximum.
5.Bond Strength:
a.Direct Shear: 400 psi.
b.Direct Tension: 250 psi.
c.Beam Break: 800 psi.
6.Pot Life: 5 minutes maximum at 70 deg. F.
PART 3EXECUTION
3.1INSTALLATION
A.Fill joints, voids, and pockets, completely.
B.Comply with manufacturer's instructions and UBC Chapter 47.
C.Finish surfaces exposed to view smooth.
D.Pneumatically Placed Plaster: Screened and reused rebound material in an amount not greater than 25 percent of the total sand in any batch.

END OF SECTION