SECTION 01 77 00 CLOSEOUT PROCEDURES
View the file
Other files
Show 40 more
Latest 50 of 87 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 77 00
SECTION 01 77 00
CLOSEOUT PROCEDURES
| PART 1 | GENERAL | |
| 1.1 | SECTION INCLUDES | |
| A. | Administrative provisions for Substantial Completion, Final Inspection and acceptance. | |
| 1.2 | SUBSTANTIAL COMPLETION | |
| A. | When Work, or designated portion thereof, is Substantially Complete, submit written notice with list of items to be completed and corrected. | |
| B. | After receipt of Contractor’s certification of Work completion, COR will make Final Inspection to determine status of completion. | |
| C. | Should Work not be Substantially Complete, remedy deficiencies and re-submit a written notice. | |
| 1.3 | ACCEPTANCE OF WORK | |
| A. | Protect Work until acceptance occurs. | |
| B. | Neither COR’s determination that Work is complete, nor acceptance thereof by the Government, shall operate as a bar to claim against the Contractor under the provisions of the Contract Documents. | |
| 1.4 | CLOSEOUT SUBMITTALS | |
| A. | Delivery Order Record Drawings: Refer to Section 01 78 39. | |
| B. | Final Summary Report of Independent Testing Agency: Refer to Section 01 45 00 requirements. |
| PART 2 | PRODUCTS | Not Used |
| PART 3 | EXECUTION | Not Used |
END OF SECTION