SECTION_32_05_10_Backfilling_Roadways.docx

DOCX document 27 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 32 05 10 BACKFILLING ROADWAYS

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 32 05 10

SECTION 32 05 10

BACKFILLING ROADWAYS

PART 1GENERAL
1.1SECTION INCLUDES
A.Roadway backfill materials.
B.Roadway backfilling requirements.
1.2DEFINITIONS
A.Embankment: A raised earthen structure to carry a roadway.
B.Pavement: Artificially covered surfaces including but not limited to roadway surfaces, parking lot surfaces, sidewalks, curb, gutter, curb ramps, Driveway ramps, etc.
C.Subgrade: A surface of earth or Rock leveled off as to receive backfill materials.
1.3SUBMITTALS
A.Submit maximum laboratory dry density and optimum laboratory moisture content for:
1.Subgrade material, and
2.Each type of fill to be used.
B.Submit aggregate batch delivery tickets showing name of material source, Serial number of ticket; date and truck number; name of Supplier; job name and location; volume of material delivered, And aggregate classification.
C.Upon COR’s request, submit a written quality control Inspections and testing report describing source and field quality control activities performed by Contractor and its Suppliers.
1.4QUALITY ASSURANCE
A.Do not change material sources, or aggregate without COR’s approval.
B.Reject backfill material that does not comply with requirements specified in this section.
1.5STORAGE
A.Safely stockpile backfill materials.
B.Separate differing materials, prevent mixing, and maintain optimum moisture content of backfill materials.
C.Avoid displacement of and injury to Work while compacting or operating equipment.
D.Movement of construction machinery over Work at any stage of construction is solely at Contractor's risk.
1.6SITE CONDITIONS
A.Do not place, spread, or roll any backfill material over material that is damaged by water. Remove and replace damaged material at no additional cost to Government.
B.Control traffic and erosion. Keep area free of trash and debris. Repair settled, eroded, and rutted areas.
C.Reshape and compact damaged structural section re required density.
D.Soil Cement: Do not spread soil cement mixture when air temperature is less than 40 deg. F. in the shade.
E.Drainage: Immediately prior to suspension of construction operations for any reason, provide proper and necessary drainage of Work area.
1.7ACCEPTANCE
A.General:
1.Native material may be wasted as directed by COR, if there is no additional cost to substitute material acceptable to COR.
2.For material acceptance refer to.
a.Common fill, Section 31 05 13.
b.Crushed aggregate base, Section 32 11 23.
c.Cement treated fill, Section 31 05 15.
B.Backfilling: One test per Lot.
Material
Lot Size
Subgrade (a)
1000 square yards
Common Fill (a)
PCC or AC Surface Course: 1,000 square yards per lift.

Driveway Approach: 400 square feet per lift.

Sidewalk: 400 lineal feet per lift.

Crushed Aggregate Base (a)
PCC or AC Surface Course: 1,000 square

yards per lift.

Driveway Approach: 400 square feet per lift.

Sidewalk: 400 lineal feet per lift.

Curb, Gutter, and Waterways: 200 lineal feet per lift.

Flowable Fill (b)
250 cubic yards

NOTES

(a) Proctor density, Section 31 23 26.

(b) Cement Treated Fill, Section 31 05 15.

(c) Lift thickness before compaction, 8 inches.

1.8WARRANTY
A.Any settlement noted in Embankment or Pavement construction will be considered to be caused by improper compaction methods and shall be corrected at no cost to the Government.
B.Restore incidentals damaged by settlement at no additional cost to Government.
PART 2PRODUCTS
2.1BACKFILL MATERIALS
A.Common Fill, Section 31 05 13.
B.Crushed aggregate base, Section 32 11 23.
C.Cement treated fill, Section 31 05 15.
2.2ACCESSORIES
A.Water:
1.Make arrangements for sources of water during construction and make arrangements for delivery of water to site.
2.Comply with local Laws and Regulations at no additional cost to Government when securing water from water utility company.
B.Geotextile Fabric, Section 31 05 19.
PART 3EXECUTION
3.1PREPARATION
A.Verify.
1.Backfill material meets gradation requirements.
2.Areas to be backfilled are free of debris, snow, ice or water, and
3.Bearing surfaces are not frozen.
B.If extra excavation is required, secure COR’s written permission and follow Section 31 23 16 requirements.
C.Place geotextile fabrics, Section 31 05 19.
3.2SUBGRADE PREPARATION
A.Protect Subgrade from desiccation, flooding, and freezing.
B.If ground water table is in the intended construction operations, dewater.
C.Before beginning backfilling operations over Subgrade, secure ENGINEER's review of Subgrade surface preparations.
3.3EMBANKMENTS
A.Place backfill material in lifts not exceeding 8 inches after compaction.
B.Build shoulders to a grade higher than that of adjacent fills. Provide surface runoff at all times.
C.Commence compaction along edge of area to be compacted and gradually advance toward center.
D.Operate compaction equipment along lines parallel or concentric with the center-line of the Embankment being constructed.
E.Do not damage subsurface structures or utilities.
3.4BASE COURSES
A.Place backfill material in lifts not exceeding 8 inches before compaction.
B.Maintain moisture content in compaction operations.
C.Avoid segregation when spreading backfill. Keep surfaces free from pockets of coarse and fine aggregate.
D.Rework fills which do not conform to compaction requirements until requirements are met.
E.Protect cement treated fill against freezing and traffic for 7 days.
3.5MODIFIED BACKFILL LAYER METHOD
A.Section 33 05 20.
3.6COMPACTION
A.Compact backfill, Section 31 23 26 as follows.
1.A-1 soils: greater than or equal to 95 percent of a Modified Proctor Density.
2.Other soils: greater than or equal to 95 percent of a Standard Proctor Density.
3.7COMPRESSIVE STRENGTH
A.Where a flowable fill is used, provide compressive strength indicated in Section 31 05 15.
3.8PROOF ROLLING TEST
A.Prior to placing fill material for roadbed backfills, proof roll Subgrade using gross weight of 18,000 pounds/tandem axle, with a tire pressure at least 90 psi.
B.All proof roll passes will traverse the Subgrade parallel to the roadbed centerline. All subsequent passes will be offset 1/2 the vehicle width until the entire Subgrade is tested.
C.COR will designate the areas, if any, requiring additional compaction or reconstruction.
D.Once Subgrade passes the proof rolling test, protect the surface from construction operations and traffic damage. Repair all cuts, ruts, and breaks. Keep surface in a satisfactory condition until geotextile fabric or base course has been placed.
3.9CLEANING
A.Remove stockpiles from the site upon Work Completion. Grade site to prevent free standing surface water.
B.Leave borrow areas clean and neat.

END OF SECTION

BACKFILLING ROADWAYS Page 1

File details come from the government source that posted it. Updated .