SECTION 32 05 10 BACKFILLING ROADWAYS
View the file
Other files
Show 40 more
Latest 50 of 87 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 32 05 10
SECTION 32 05 10
BACKFILLING ROADWAYS
| PART 1 | GENERAL |
| 1.1 | SECTION INCLUDES |
| A. | Roadway backfill materials. |
| B. | Roadway backfilling requirements. |
| 1.2 | DEFINITIONS |
| A. | Embankment: A raised earthen structure to carry a roadway. |
| B. | Pavement: Artificially covered surfaces including but not limited to roadway surfaces, parking lot surfaces, sidewalks, curb, gutter, curb ramps, Driveway ramps, etc. |
| C. | Subgrade: A surface of earth or Rock leveled off as to receive backfill materials. |
| 1.3 | SUBMITTALS |
| A. | Submit maximum laboratory dry density and optimum laboratory moisture content for: |
| 1. | Subgrade material, and |
| 2. | Each type of fill to be used. |
| B. | Submit aggregate batch delivery tickets showing name of material source, Serial number of ticket; date and truck number; name of Supplier; job name and location; volume of material delivered, And aggregate classification. |
| C. | Upon COR’s request, submit a written quality control Inspections and testing report describing source and field quality control activities performed by Contractor and its Suppliers. |
| 1.4 | QUALITY ASSURANCE |
| A. | Do not change material sources, or aggregate without COR’s approval. |
| B. | Reject backfill material that does not comply with requirements specified in this section. |
| 1.5 | STORAGE |
| A. | Safely stockpile backfill materials. |
| B. | Separate differing materials, prevent mixing, and maintain optimum moisture content of backfill materials. |
| C. | Avoid displacement of and injury to Work while compacting or operating equipment. |
| D. | Movement of construction machinery over Work at any stage of construction is solely at Contractor's risk. |
| 1.6 | SITE CONDITIONS |
| A. | Do not place, spread, or roll any backfill material over material that is damaged by water. Remove and replace damaged material at no additional cost to Government. |
| B. | Control traffic and erosion. Keep area free of trash and debris. Repair settled, eroded, and rutted areas. |
| C. | Reshape and compact damaged structural section re required density. |
| D. | Soil Cement: Do not spread soil cement mixture when air temperature is less than 40 deg. F. in the shade. |
| E. | Drainage: Immediately prior to suspension of construction operations for any reason, provide proper and necessary drainage of Work area. |
| 1.7 | ACCEPTANCE |
| A. | General: |
| 1. | Native material may be wasted as directed by COR, if there is no additional cost to substitute material acceptable to COR. |
| 2. | For material acceptance refer to. |
| a. | Common fill, Section 31 05 13. |
| b. | Crushed aggregate base, Section 32 11 23. |
| c. | Cement treated fill, Section 31 05 15. |
| B. | Backfilling: One test per Lot. |
| Material |
| Lot Size |
| Subgrade (a) |
| 1000 square yards |
| Common Fill (a) |
| PCC or AC Surface Course: 1,000 square yards per lift. |
Driveway Approach: 400 square feet per lift.
Sidewalk: 400 lineal feet per lift.
| Crushed Aggregate Base (a) |
| PCC or AC Surface Course: 1,000 square |
yards per lift.
Driveway Approach: 400 square feet per lift.
Sidewalk: 400 lineal feet per lift.
Curb, Gutter, and Waterways: 200 lineal feet per lift.
| Flowable Fill (b) |
| 250 cubic yards |
NOTES
(a) Proctor density, Section 31 23 26.
(b) Cement Treated Fill, Section 31 05 15.
(c) Lift thickness before compaction, 8 inches.
| 1.8 | WARRANTY |
| A. | Any settlement noted in Embankment or Pavement construction will be considered to be caused by improper compaction methods and shall be corrected at no cost to the Government. |
| B. | Restore incidentals damaged by settlement at no additional cost to Government. |
| PART 2 | PRODUCTS |
| 2.1 | BACKFILL MATERIALS |
| A. | Common Fill, Section 31 05 13. |
| B. | Crushed aggregate base, Section 32 11 23. |
| C. | Cement treated fill, Section 31 05 15. |
| 2.2 | ACCESSORIES |
| A. | Water: |
| 1. | Make arrangements for sources of water during construction and make arrangements for delivery of water to site. |
| 2. | Comply with local Laws and Regulations at no additional cost to Government when securing water from water utility company. |
| B. | Geotextile Fabric, Section 31 05 19. |
| PART 3 | EXECUTION |
| 3.1 | PREPARATION |
| A. | Verify. |
| 1. | Backfill material meets gradation requirements. |
| 2. | Areas to be backfilled are free of debris, snow, ice or water, and |
| 3. | Bearing surfaces are not frozen. |
| B. | If extra excavation is required, secure COR’s written permission and follow Section 31 23 16 requirements. |
| C. | Place geotextile fabrics, Section 31 05 19. |
| 3.2 | SUBGRADE PREPARATION |
| A. | Protect Subgrade from desiccation, flooding, and freezing. |
| B. | If ground water table is in the intended construction operations, dewater. |
| C. | Before beginning backfilling operations over Subgrade, secure ENGINEER's review of Subgrade surface preparations. |
| 3.3 | EMBANKMENTS |
| A. | Place backfill material in lifts not exceeding 8 inches after compaction. |
| B. | Build shoulders to a grade higher than that of adjacent fills. Provide surface runoff at all times. |
| C. | Commence compaction along edge of area to be compacted and gradually advance toward center. |
| D. | Operate compaction equipment along lines parallel or concentric with the center-line of the Embankment being constructed. |
| E. | Do not damage subsurface structures or utilities. |
| 3.4 | BASE COURSES |
| A. | Place backfill material in lifts not exceeding 8 inches before compaction. |
| B. | Maintain moisture content in compaction operations. |
| C. | Avoid segregation when spreading backfill. Keep surfaces free from pockets of coarse and fine aggregate. |
| D. | Rework fills which do not conform to compaction requirements until requirements are met. |
| E. | Protect cement treated fill against freezing and traffic for 7 days. |
| 3.5 | MODIFIED BACKFILL LAYER METHOD |
| A. | Section 33 05 20. |
| 3.6 | COMPACTION |
| A. | Compact backfill, Section 31 23 26 as follows. |
| 1. | A-1 soils: greater than or equal to 95 percent of a Modified Proctor Density. |
| 2. | Other soils: greater than or equal to 95 percent of a Standard Proctor Density. |
| 3.7 | COMPRESSIVE STRENGTH |
| A. | Where a flowable fill is used, provide compressive strength indicated in Section 31 05 15. |
| 3.8 | PROOF ROLLING TEST |
| A. | Prior to placing fill material for roadbed backfills, proof roll Subgrade using gross weight of 18,000 pounds/tandem axle, with a tire pressure at least 90 psi. |
| B. | All proof roll passes will traverse the Subgrade parallel to the roadbed centerline. All subsequent passes will be offset 1/2 the vehicle width until the entire Subgrade is tested. |
| C. | COR will designate the areas, if any, requiring additional compaction or reconstruction. |
| D. | Once Subgrade passes the proof rolling test, protect the surface from construction operations and traffic damage. Repair all cuts, ruts, and breaks. Keep surface in a satisfactory condition until geotextile fabric or base course has been placed. |
| 3.9 | CLEANING |
| A. | Remove stockpiles from the site upon Work Completion. Grade site to prevent free standing surface water. |
| B. | Leave borrow areas clean and neat. |
END OF SECTION