SECTION_31_23_23.13_Backfilling_for_Structures.docx

DOCX document 26 KB Posted

Attached to
Dugway Proving Ground, Utah Road Maintenance
Solicitation number
W911S6-17-B-0001
Issued by

About this file

SECTION 31 23 23.13 BACKFILLING FOR STRUCTURES

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTOIN 31 23 23.13

SECTION 31 23 23.13

BACKFILLING FOR STRUCTURES

PART 1GENERAL
1.1SECTION INCLUDES
A.Structural backfill materials.
B.Structural backfilling requirements.
1.2SUBMITTALS
A.Submit maximum laboratory dry density and optimum laboratory moisture content for:
1.Subgrade material, and
2.Each type of fill to be used.
B.Upon COR's request, submit a written quality control Inspections and testing report describing source and field quality control activities performed by Contractor and its Supplier.
1.3QUALITY ASSURANCE
A.Do not change material sources, or aggregate without COR's knowledge.
B.Reject backfill material that does not comply with requirements specified in this section.
1.4STORAGE
A.Safely stockpile backfill materials.
B.Separate differing materials, prevent mixing, and maintain optimum moisture content of backfill materials.
C.Avoid displacement of and injury to Work while compacting or operating equipment.
D.Movement of construction machinery over Work at any stage of construction is solely at CONTRACTOR's risk.
1.5SITE CONDITIONS
A.Do not place, spread, or roll any backfill material over material that is damaged by water. Remove and replace damaged material at no additional cost to Governmenet.
B.Control traffic and erosion. Keep area free of trash and debris. Repair settled, eroded, and rutted areas.
C.Reshape and compact damaged structural section to required density.
1.6ACCEPTANCE
A.General:
1.Native material may be wasted if there is no additional cost to substitute material acceptable to COR.
2.For material acceptance refer to.
a.Common fill, Section 31 05 13.
b.Crushed aggregate base, Section 32 11 23.
c.Cement treated fill, Section 31 05 15.
B.Structure Backfilling: One test per Lot.

Table 1: Lot Size for Structural Backfilling Operations

Structure Type
Test Criteria
Lot Size
Strip Footings
Standard (a)
Subgrade: 200 lineal feet
Modified (a)
Crushed aggregate base: 200 lineal feet per lift.
Structure Footing excluding strip footings
Standard (a)
Subgrade: 225 square feet.
Modified (a)
Crushed aggregate base: Each 225 square feet per lift
Embankments
Standard (a)
Fill: 625 square feet per lift
Miscellaneous small structures e.g. Manholes, drainage boxes, etc.)
Standard (a)
Subgrade: Each footprint area

Fill: Each lift

Modified (a)
Crushed aggregate base: Each lift

NOTES

(a) Proctor density, Section 31 23 26

(b) Lift thickness before compaction is 8 inches.

1.7WARRANTY
A.Restore incidentals damaged by settlement at no additional cost to Government.
PARTPRODUCTS
2.1BACKFILL MATERIALS
A.Common fill, Section 31 05 13.
B.Crushed aggregate base, Section 32 11 23.
C.Cement treated fill, Section 31 05 15.
2.2ACCESSORIES
A.Water:
1.Make arrangements for sources of water during construction and make arrangements for delivery of water to site.
2.Comply with local Laws and Regulations at no additional cost to OWNER when securing water from water utility company.
PART 3EXECUTION
3.1PREPARATION
A.Verify:
1.Stockpiled fill meets gradation requirements.
2.Foundation walls are braced to support surcharge forces imposed by backfilling operations, areas to be backfilled are free of debris, snow, ice or water.
3.Ground surface is not frozen.
B.If subgrade is not readily compactable secure written authorization for extra excavation and backfill, Section 31 23 16.
C.Identify required line, levels, contours, and datum.
D.Stake and flag locations of underground utilities.
E.Upon discovery of unknown utility or concealed conditions, notify COR.
3.2PROTECTION
A.Protect existing trees, shrubs, lawns, existing structures, fences, roads, sidewalks, paving, curb and gutter and other features.
B.Protect above or below grade utilities. Contact utility companies to repair damage to utilities. Pay all cost of repairs.
C.Protect Subgrade from desiccation, flooding and freezing.
D.Do not fill adjacent to structures until Excavation is checked by COR.
E.Do not use compaction equipment adjacent to walls or retaining walls that may cause wall to become over-stressed or moved from alignment.
F.Do not disturb or damage foundation perimeter drainage, foundation, damp-proofing, foundation waterproofing and protective cover, or utilities in Trenches.
G.Restore any damaged structure to its original strength and condition.
3.3LAYOUT
A.Maintain all benchmarks, control monuments and stakes, whether newly established by surveyor or previously existing. Protect from damage and dislocation.
B.If discrepancy is found between Contract Documents and site, COR shall make such minor adjustments in the Work as necessary to accomplish the intent of Contract Documents without increasing the Cost of the Work to Contractor or Government.
3.4FOUNDATIONS AND SLABS ON GRADE
A.Place backfill materials in lifts not exceeding 8 inches after compaction.
B.Do not backfill against walls until concrete has obtained 14 day strength. Backfill against foundation walls simultaneously on each side.
C.Fill unauthorized excavations with material acceptable to COR at no additional cost to Government.
D.Do not damage adjacent structures or service lines.
E.Where flowable fill is used, use fill that flows easily and vibration for compaction is not required.
3.5MODIFIED BACKFILL LAYER METHOD
A.Refer to Section 33 05 20.
3.6COMPACTION
A.Compact backfill; Section 33 05 05 to the following maximum dry densities.
1.Under Footings: 98 percent.
2.Interior Crawl Spaces: 90 percent.
3.Interior Slab-On-Grade: 98 percent.
4.Side of Foundation Walls and Retaining Walls:
a.Exterior: 95 percent.
b.Interior: 98 percent.
5.Miscellaneous Structures: 95 percent.
3.7CLEANING
A.Remove stockpiles from the site. Grade site surface to prevent free standing surface water.
B.Leave borrow areas clean and neat.

END OF SECTION

BACKFILLING FOR STRUCTURES Page 1

File details come from the government source that posted it. Updated .