SECTION 31 05 13 COMMON FILL

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 31 05 13

SECTION 31 05 13

COMMON FILL

PART 1GENERAL
1.1SECTION INCLUDES
A.Common fill materials.
1.2REFERENCES
A.AASHTO M 145: Classification of Soils and Soil-Aggregate Mixtures for Highway Construction Purposes.
B.ASTM C 136: Standard Method for Sieve Analysis of Fine and Coarse Aggregates.
C.ASTM D 1883: Standard Test Method for CBR (California Bearing Ratio) of Laboratory-Compacted Soils.
D.ASTM D 2487: Standard Test Method for Classification of Soils for Engineering Purposes.
E.ASTM D 2844: Test Method for Resistance R-Value and Expansion Pressure of Compacted Soils.
F.ASTM D 3282: Standard Practice for Classification of Soils and Soil- Aggregate Mixtures for Highway Construction Purposes.
G.ASTM D 3740: Standard Recommended Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction.
1.3SUBMITTALS
A.Prior to delivering material to site, identify.
1.Name of Supplier and source, and
2.Type and gradation of common fill material.
B.If a change in source of material is required, submit name of Supplier, source and gradation analysis of material to COR for approval prior to delivery to site. Allow a minimum of 2 days for approval.
1.4QUALITY ASSURANCE
A.Use a laboratory that follows and complies with Section 01 45 00 and ASTM D 3740.
B.Reject common fill products that do not meet requirements of this section.
C.Remove any product found defective after installation and install acceptable product at no additional cost to Government.
1.5ACCEPTANCE
A.General:
1.Acceptance is by Lot. One Lot is one day’s production.
2.Dispute resolution; Section 01 35 10.
B.Roadway Backfill: Sub-lot size is 5,000 tons.
PART 2PRODUCTS
2.1BORROW
A.Classifications A-1-a through A-4, ASTM D 3282.
2.2GRANULAR BORROW (PIT RUN)
A.Classifications A-1-a, A-1-b, A-2-4, or A-3, ASTM D 3282.
B.Material meets design CBR-value (ASTM D 1883) or R value (ASTM D 2844) for suitability of source, not for project control testing.
2.3GRANULAR BACKFILL BORROW
A.Classification A-1, ASTM D 3282.
B.Well graded.
C.Particle size; 2 inch maximum.
D.Material meets design CBR-value (ASTM D 1883) or R value (ASTM D2844) for suitability of source, not for project control testing.
2.4RECYCLED FILL
A.Material: Pulverized portland cement concrete either mixed with or not mixed with a new aggregate as approved by COR.
B.Gradation: Meet the requirements of this Section based upon use; e.g. borrow, granular borrow, granular backfill borrow, etc.
2.5NATIVE
A.When allowed by COR, material obtained from Excavations may be used as fill, provided organic material, rubbish, debris, and other objectionable materials are removed and Contractor has submitted the appropriate Proctor data (see Section 31 23 26).
B.When native fill is approved for use, Government will only pay for labor and equipment costs.
2.6SAND
A.Friable river or bank aggregate, free of loam and organic matter. Graded per Table 1.

Table 1: Sand Gradation

Sieve
Percent Passing by Weight
3/8
100
100
1 – 10
2.7GRAVEL
A.Material: Rock, stone, or other high quality mineral particle or combination.
B.Gradation: ASTM D 448 narrow band.
1.Sewer Rock.

Table 2: Sewer Rock

Nominal Size
ASTM Size No.
3.5 to 1.5”
1
2.5 to 1.5”
2
2 to 1”
3
1.5 to 3/4”
4
1 to 1/2"
5

2. Pea Gravel.

Table 3: Pea Gravel

Nominal Size
ASTM Size No.
3/4 to 3/8”
6
1/2 to No. 4
7
3/8 to No. 8
8
No. 4 to No. 16
9
No. 4 (screenings)
10
2.8TOPSOIL
A.Chemical Characteristics:
1.Acidity/alkalinity range: pH 5.5 to 7.7
2.Soluble Salts: Less than 2.0 mmhos/cm.
3.Sodium Absorption Ratio (SAR): less than 3.0
4.Nitrogen (NO3N): 48 ppm minimum
5.Phosphorus (P): 11 ppm minimum
6.Potash (K): 130 ppm minimum
7.Iron (Fe): 5.0 ppm minimum
B.Physical Characteristics:
1.Fertile, loose, friable.
2.Containing more than 2 percent organic matter.
3.Free of weeds, subsoil, lumps or clods of hard earth, plants or their roots, sticks, toxic minerals, chemicals and stones greater than 1-1/2 inch diameter.
4.Composition.

Table 4: Topsoil

Material
Percent Passing
Sand
15 – 60
Silt
10 – 70
Clay
5 – 30
2.9SOURCE QUALITY CONTROL
A.Verify gradation, ASTM C 136.
B.Select Samples on a random location and time basis.
C.If tests indicate materials do not meet specified requirements, change materials and retest at no additional cost to Government.
PART 3EXECUTION
3.1INSTALLATION
A.Trenches, Section 33 05 20.
B.Structures, Section 31 23 23.
C.Pavements, Section 32 05 10.

END OF SECTION

COMMON FILL Page 2