SECTION 03 30 10 CONCRETE PLACEMENT

View the file

Other files

File Type Posted
W911S6-17-B-0001-0001.pdf PDF
Revised_Technical_Exhibit_A_Through_E__21_March_2017.xlsx XLSX spreadsheet
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Site_visit_sign_in_roster_(2).pdf PDF
W911S6-1-B-0001_Site_Visit_Slides_DPG_Road_Maintenance_13_Mar_2017.pptx PPTX presentation
SECTION_01_74_13_Progress_Cleaning.docx DOCX document
Section_02_41_13.13_Pavement_Removal.docx DOCX document
Technical_Exhibit_A_Through_E__11NOV16.xlsx XLSX spreadsheet
Section_32_12_36.14_Chip_Seal_Coat.docx DOCX document
SECTION_31_37_00_Riprap_or_rock_lining.docx DOCX document
SECTION_01_71_16_Acceptance.docx DOCX document
Section_33_05_13.13_Utility_Grade_Adjustment.docx DOCX document
Section_32_12_36.15_Micro-Surface_Seal.docx DOCX document
SECTION_33_13_00_Disinfection.docx DOCX document
SECTION_33_11_00_Water_Distribution_and_Transmission.docx DOCX document
SECTION_33_08_00_Commissioning_of_Water_Utilities.docx DOCX document
Section_32_12_15_HMA_for_Airfields.docx DOCX document
Section_32_11_23_Untreated_Aggregate_Base_Course.docx DOCX document
Section_33_11_00.07_Polyvinyl_Chloride_Pipe.docx DOCX document
SECTION_32_01_16_Recycled_Asphalt_Paving.docx DOCX document
SECTION_05_05_10_Metal_Galvanizing.docx DOCX document
SECTION_32_13_73_Concrete_Paving_Joint_Sealants.docx DOCX document
Section_01_55_26_Traffic_Control.docx DOCX document
Section_01_78_39_Record_Documents.docx DOCX document
Section_01_71_23.16_Construction_Surveying.docx DOCX document
SECTION_05_12_00_Structural_Steel.docx DOCX document
SECTION_03_61_00_Cementitious_Grouting.docx DOCX document
SECTION_32_12_16.19_Cold_Mix_Asphalt.docx DOCX document
SECTION_33_31_00_Sanitary_Sewerage_Systems.docx DOCX document
Section_32_12_16_Hot_Mix_Asphalt_for_Roads.docx DOCX document
Section_32_17_23_Pavement_Markings.docx DOCX document
Section_32_31_13_Chain_Link_Fence.docx DOCX document
SECTION_03_39_00_Concrete_Curing.docx DOCX document
Section_01_77_00_Closeout_Procedures.docx DOCX document
SECTION_03_11_00_Concrete_Forming.docx DOCX document
SECTION_31_23_23.23_Compaction.docx DOCX document
Section_32_11_28_Cold_Recycled_Asphalt_Base.docx DOCX document
Section_31_05_19.13_Geotextiles.doc DOC document
SECTION_33_11_11_Relocate_Water_Meters_and_Fire_Hydrants.docx DOCX document
SECTION_03_20_00_Concrete_Reinforcing.docx DOCX document
Section_32_01_13.61_Slurry_Seal.docx DOCX document
SECTION_05_05_23_Bolts_Nuts_and_Accessories.docx DOCX document
SECTION_03_40_00_Precast_Concrete.docx DOCX document
Section_31_11_00_Clearing_and_Grubbing.docx DOCX document
Section_32_12_19.19_Open-Graded_Surface_Course.docx DOCX document
SECTION_31_05_19.19_Geogrids_Geocomposites.docx DOCX document
SECTION_05_56_00_Metal_Castings.docx DOCX document
SECTION_01_11_00_SUMMARY_of_WORK.docx DOCX document
Section_34_71_13_Vehicle_Barriers.docx DOCX document
SECTION_32_12_43_Porous_Paving.docx DOCX document
Show 40 more

Latest 50 of 87 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 03 30 10

SECTION 03 30 10

CONCRETE PLACEMENT

PART 1GENERAL
1.1SECTION INCLUDES
A.Concrete placement for slabs on grade, slabs on fill, structural building frame, and other concrete components.
1.2REFERENCES
A.ACI 301: Specifications for Structural Concrete for Buildings.
B.ACI 305: Hot Weather Concreting.
C.ACI 306: Cold Weather Concreting.
D.ACI 309: Standard Practice for Consolidation of Concrete.
E.ASTM C 881: Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete.
F.ASTM C 1059: Standard Specification for Latex Agents for Bonding Fresh to Hardened Concrete.

1.3 SUBMITTALS

A.Batch Delivery Ticket: For each batch delivered to site, identify.
1.Date and Project description.
2.Producer and plant.
3.Name of contractor.
4.Serial number of ticket.
5.Mix identification.
6.Truck number and time dispatched.
7.Volume of concrete.
8.Type and amount of cement.
9.Total water and water/cement ratio.
10.Water added for receiver of concrete and receiver's initials.
11.Admixture types.
12.Separate weights of fine and coarse aggregate.
13.Statement of whether batch is pre-mixed at plant or mixed in transit.
B.Record of Placed Concrete: Identify record date, location of pour, quantity, air temperature, and CONTRACTOR’s quality control test samples taken.
C.Bonding Compound: Identify product name, type, and chemical analysis.
1.4QUALITY ASSURANCE
A.Provide ACI certified finishers.
B.Remove and replace any placed concrete suffering hot or cold weather damage.
C.For control testing follow Section 03 30 05 requirements.
1.5ACCEPTANCE
A.Concrete work that fails to meet any of the following requirements will be considered defective. Replace any Defective Work at no additional cost to the Governement.
1.Placement:
a.Reinforcing steel size, quantity, strength, position, damage, orarrangement is not as specified or does not comply with code.
b.Formwork differs from required dimensions or location in such a manner as to reduce concrete’s strength or load carrying capacity or physical esthetics.
c.Workmanship likely to result in deficient strength.
2.Finishing:
a.Concrete exposed to view has defects that adversely affect appearance.
b.Slab tolerances of Section 03 35 00 are not met.
3.Protection:
a.Method of curing is not as specified.
b.Inadequate protection of concrete during early stages of hardening and strength development from
1)temperature extremes.
2)rapid moisture loss.
c.Mechanical injury, construction fires, accidents, or premature removal of formwork likely to result in deficient strength development.
PART 2PRODUCTS
2.1MATERIALS
A.Concrete, Section 03 30 04. Class as indicated.
B.Bonding compound, ASTM C 1059. Either polyvinyl acetate base or acrylic base latex.
1.Use type I in areas not subject to high humidity or immersion in water with minimum bond strength of 400 psi.
2.Use type II in areas subject to high humidity or immersion in water with minimumbond strength of 1250 psi.
C.Vapor retarder, 10 mil thick clear polyethylene sheet. Type recommended for below grade application.
D.Forms, Section 03 11 00.
E.Reinforcement, Section 03 20 00.
F.Coverings and curing compound, Section 03 39 00.
G.Shinkage compensating grout, Section 03 61 00.
H.Epoxy adhesive, Section 03 61 00.
PART 3EXECUTION
3.1PREPARATION
A.Notify COR minimum 24 hours prior to commencement of concrete placement operations.
B.Do not allow construction loads to exceed structural capacity.
C.Clean previously placed concrete. Apply bonding compound per manufacturer's instructions.
D.At locations where new concrete is dowelled to existing work, drill, remove dust, insert and pack steel dowels with shrink compensating grout.
3.2EXAMINATION
A.Verify items to be cast into concrete are accurately placed and held securely.
B.Verify slump, air content range, mix identity, and batch time on delivery ticket matches mix design.
C.Verify slab steel mats are supported by steel chairs, precast concrete blocks, or other slab bolsters. Do not pour if absent.
3.3DELIVERY
A.Slump and Air Content: Keep slump and air content within the allowable range.
B.Placement Time:
Air Temperature
Time After Initial Batching
Less than 90 deg. F.
1–1/2 hours
Greater than 90 deg. F.
1–hour (without retarder)
Greater than 90 deg. F.
1–1/2 hours (with retarder)

To increase time past 1-1/2 hours, a hydration stabilizer that is acceptable to Supplier may be used.

C.Tempering:
1.Water may be added if all following conditions are met.
a.The mix design water/cement ratio is not exceeded.
b.The delivery ticket allows for addition of water based upon water/cement ratio.
c.The amount of water added is accurately measured to within 1 gallon of the design addition.
d.Water addition is followed by 3 minutes of mixing at mixing speed prior to discharge.
e.Supplier and Contractor mutually agree on who is authorized to add water.
2.Do not add water after 1 cubic yard of concrete has discharged from the delivery vehicle.
D.Super-plasticizer: Comply with manufacturer's requirements. If none, then as follows.
1.If added at site, add agent using injection equipment capable of rapidly and uniformly distributing the admixture to the concrete. Prior to discharge, mix for a minimum of 5 minutes at a drum rate not less than 12 rpm or more than 15 rpm.
2.If added at plant; do not deliver to site unless batch delivery ticket displays water/cement ratio prior to super-plasticizer addition.
3.4CONCRETE PLACEMENT
A.Place concrete, ACI 301.
1.Hot Weather Placement: ACI 305. If the rate of evaporation approaches 0.2 lb./ft2/hr. precautions against plastic shrinkage cracking are necessary. (i.e. dampening Subgrade and forms; placing concrete at the lowest possible temperature; erecting windbreaks and sunshades; fog sprays; use of evaporation retardants; or rescheduling time of placement).
2.Cold Weather Placement: ACI 306. Non-chloride accelerating admixture may be used in concrete work placed at ambient temperatures below 50 deg. F. Use of admixtures will not relax cold weather placement, curing, or protection requirements.
B.Concrete Temperature: Keep mixed concrete temperature at time of placement between 60 deg. F. and 90 deg. F.
C.Do not disturb reinforcement, inserts, embedded parts, and formed joints.
D.Do not break or interrupt successive pours such that cold joints occur.
E.Honeycomb or embedded debris in concrete is not acceptable.
3.5JOINTS AND JOINT SEALING
A.Steel edging and jointing tools are acceptable. Preferred are magnesium, aluminum or wood tools
B.Pavement joint sealing, Section 32 13 73.
3.6CONSOLIDATION
A.Keep spare vibrator available during concrete placement operations, ACI 309.
3.7FINISHING
A.Section 03 35 00 and as follows.

Table 1: Finishes

Type of work
Type of finish
Sidewalks, garage floors, ramps, exterior concrete Pavement
Broom or belt finish
Exterior platforms, steps, and landings, exterior and interior pedestrian ramps, not covered by other finish materials
Non-slip finish
Surfaces intended to receive bonded applied cementitious applications
Scratched finish
Surfaces intended to receive roofing, except future floors, waterproofing membranes, and roof surfaces that are future floors or sand bed terrazzo
Floated finish
Floors and roof surfaces that are floors intended as walking surfaces or to receive floor coverings
Troweled
Unpainted concrete surfaces not exposed to public view
Rough as-cast form finish
Unpainted concrete surfaces exposed to public view
Smooth as-cast form finish
Concrete surfaces to receive paint or plaster
Grout cleaned finish
3.8CURING
A.Section 03 39 00. Use a membrane forming compound unless specified otherwise.
3.9PROTECTION AND REPAIR
A.Protection: Section 01 66 00.
1.Immediately after placement, protect concrete from premature drying, excessively hot or cold temperatures, graffiti, and mechanical injury.
2.Maintain concrete with minimal moisture loss at relatively constant temperature for period necessary for hydration of cement and hardening of concrete.
B.Repair:
1.Modify or replace concrete not conforming to required levels, lines, details, and elevations.
2.Structural analysis and additional testing may be required at no additional cost to OWNER when the strength of a structure is considered potentially deficient.
3.To patch imperfections refer to Section 03 35 00 requirements.
4.Remove graffiti and mechanical injury.

END OF SECTION