This document is a Request for Proposal (RFP) form issued by the City of Carmel for an unspecified project, designed to formally request a proposal for a potential contract change. The form provides a structured template for contractors to submit detailed proposals regarding increases, decreases, or no changes in Contract Price and/or Contract Time. The document requires contractors to submit four copies of a comprehensive breakdown including quantities, material costs, equipment expenses, labor, overhead, profit, and any basis for additional time within fifteen (15) calendar days of the request date.
The form emphasizes that submission of the proposal does not authorize the contractor to proceed with the proposed work or stop previously scheduled work. Upon approval, a Contract Change Order and a Notice to Proceed will be issued. The contractor must also specify the potential impact on the project's Substantial Completion and Final Completion dates if the proposed changes are accepted. The form includes spaces for an Engineer's signature, date, and approval by an Owner's Representative, indicating a formal review and approval process for the proposed contract modifications.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
TO: REQUEST FOR PROPOSAL NO
DATE:
PROJECT NAME:
PROJECT NO.:
Specification Reference:
Drawing Reference: _____________ Drawing Date:____________
Identification of Attachments:
Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any.
DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST:
REASON FOR CHANGE:
SPECIAL INSTRUCTIONS:
THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK
NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract Change Order and a Notice To Proceed will be issued.
Please state in your proposal the effect the acceptance of this Request will have on the Project’s Substantial Completion and Final Completion, if accepted within ___ days of proposal due date.
YOUR PROPOSAL DUE DATE: _____________________________________
By: _____________________________________ _________________ Engineer Date