This is a comprehensive project specifications document for the P-1102 Weapons Magazine & Ordnance Operations Facility at Naval Submarine Base New London in Groton, Connecticut. The project involves the replacement of 18 arch-type magazines built between 1968-1974 with six (6) containerized long weapons storage (CLWS) magazines, two (2) Type G magazines, and one (1) Type H magazine. The work also includes replacement of Building 524 (Ordnance Operations Building) and Building 393 (Truck Inspection and Sentry Building), as well as installation of overhead cranes with 25-ton capacity for CLWS magazines and 5-ton capacity for Type G and H magazines. The total contract duration is 1,587 calendar days with phased milestones: Phase 1A (294 days), Phase 1B (190 days), Phase 1C (35 days), Phase 2 (210 days), Phase 3 (269 days), and remaining work in Areas E-K (1,587 days cumulative).
The specifications establish stringent requirements for site management, security, and environmental compliance. Contractor must maintain physical security and access control for active magazines during construction, coordinate with NMCI contractors for telecommunications infrastructure, obtain all required permits including NPDES and wetlands permits, and comply with explosive safety training per DESR 6055.09. Key restrictions include prohibitions on tree clearing and blasting between April 1 and October 31 due to endangered species habitat, wetland work restrictions until permit approval, and requirement for ribbon snake mitigation plan coordination. The contractor must implement cybersecurity requirements for all computers and temporary IP networks, provide temporary facilities including administrative offices and QC manager workspace, establish backflow preventers on all water connections, submit all technical documents via the eCMS system, and maintain dust control and traffic management plans. Government will furnish nine internal lock devices (ILD) for magazine doors; the contractor must supply remaining door hardware and complete a DoD Lock Program form. All work must comply with Navy installation security protocols including DBIDS registration for contractor personnel and personnel citizenship verification.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1102 Weapons Magazine & Ordnance Operations Facility 1667770 2 June 2026
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/22 WORK RESTRICTIONS
01 20 00 11/20, CHG 2: 08/21 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 2: 05/22 ADMINISTRATIVE REQUIREMENTS
01 30 02.00 22 07/22 DESIGN, PROCUREMENT, AND INSTALLATION
OF AUDIOVISUAL EQUIPMENT
01 31 23.13 20 05/17, CHG 7: 11/21 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18, CHG 3: 08/20 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 11/20, CHG 3: 02/22 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 11/11, CHG 8: 02/21 QUALITY CONTROL
01 45 25 02/20 QUALITY ASSURANCE FIELD INSPECTION
01 45 35 11/20 SPECIAL INSPECTIONS
01 45 36 06/23 SPECIAL INSPECTIONS - EARTH COVERED
MAGAZINES
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 01 58 00 01 74 19
08/22 TEMPORARY ENVIRONMENTAL CONTROLS
08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 08/15, CHG 2: 08/21 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 02/15, CHG 3: 08/21 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
01 78 30.00 22 01/23 GIS DATA DELIVERABLES
01 91 00.15 22 03/23 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION AND DECONSTRUCTION
02 65 00 11/22 UNDERGROUND STORAGE TANK REMOVAL
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION
02 83 00 11/18 LEAD REMEDIATION
02 84 16 11/22 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
02 84 33 11/22 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
03 70 00 02/10, CHG 2: 08/20 MASS CONCRETE
PROJECT TABLE OF CONTENTS
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 14 00 02/12, CHG 2: 02/18 FLUID-APPLIED WATERPROOFING
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 54 23 05/20 THERMOPLASTIC-POLYOLEFIN (TPO) ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 34 59 08/08, CHG 1: 11/12 VAULT DOORS AND DAY GATES
08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES
08 39 55.00 20 11/24 NAVY STANDARD EARTH-COVERED MAGAZINE
DOORS
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 71 00 02/16 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
08 95 00 08/09 BLAST RESISTANCE
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 68 00 11/17, CHG 2: 08/20 CARPETING
09 90 00 02/21 PAINTS AND COATINGS
09 97 13.27 02/21, CHG 1: 08/22 HIGH PERFORMANCE COATING FOR STEEL
STRUCTURES
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS
12 93 00 08/17, CHG 1: 08/18 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 05/22 BRACING FOR MISCELLANEOUS EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 05/18, CHG 2: 08/20 BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 23 00 08/21 REFRIGERANT PIPING
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 83 00.00 20 04/06 ELECTRIC SPACE HEATING EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.23 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS UTILITY MONITORING AND
CONTROL SYSTEM (UMCS)
25 05 11.28 11/17 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS ELECTRONIC SAFETY AND
SECURITY INCLUDING CCTV, ACCESS
CONTROL SYSTEMS, AND INTRUSION
DETECTION SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 26.00 40 08/19 GROUNDING AND BONDING FOR ELECTRICAL
SYSTEMS
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 13 00 05/21, CHG 1: 05/22 SF6/HIGH-FIREPOINT FLUIDS INSULATED
PAD-MOUNTED SWITCHGEAR
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 13 23.00 40 11/14 COMMUNICATIONS OPTICAL BACKBONE CABLING
27 41 00 11/21 AUDIO-VISUAL SYSTEMS
27 51 16 05/20, CHG 1: 05/22 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 08/23 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/16 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/08, CHG 2: 02/21 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
31 23 06.00 02/21, CHG 1: 11/21 BLASTING - SURFACE
31 31 16.13 08/22 CHEMICAL TERMITE CONTROL
31 66 13 02/19 RIGID INCLUSIONS
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 20 05/22 BASE COURSE FOR RIGID AND SUBBASE FOR
FLEXIBLE PAVING
32 11 23.23 08/22 BASE COURSE DRAINAGE AND SEPARATION
LAYERS
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 13 73.19 11/19 COMPRESSION CONCRETE PAVING JOINT
SEALANT
32 15 00 05/17 AGGREGATE SURFACING
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK) AND
GATES
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 46 13 05/20 FOUNDATION DRAINAGE
33 46 16 05/18 SUBDRAINAGE PIPING
33 71 01 05/19, CHG 1: 11/19 OVERHEAD TRANSMISSION AND DISTRIBUTION
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.14 11/19, CHG 1: 02/21 BRIDGE CRANES, OVERHEAD ELECTRIC, TOP
RUNNING
41 22 13.15 11/22 BRIDGE CRANES, OVERHEAD ELECTRIC,
UNDER RUNNING TROLLEY
-- End of Project Table of Contents --
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
As set forth in UFC 1-300-02 , 2-3.1, in project specifications directed to the Construction Contractor, replace the word "shall" with the word "must ".
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
UFC 1-300-02 (2014; with Change 3, 2021) Unified Facilities Guide Specifications (UFGS) Format Standard
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Salvage Plan ; G
1.3 WORK COVERED BY CONTRACT DOCUMENTS
1.3.1 Project Description
The work includes the replacement of 18 arch type magazines built between 1968 and 1974, that are not configured for storage of modern containerized ordnance and will construct six (6) containerized long weapons storage (CLWS), two (2) Type G magazines, one (1) Type H magazine; will replace Building 524 (Ordnance Operations Building), Building 393 (Truck Inspection and Sentry Building), and install overhead cranes in all new magazines (the CLWS magazines require 25-ton capacity cranes; the Type G and H magazines require 5-ton capacity cranes) and incidental related work.
1.3.2 Location
The work is located within the existing Weapons Storage Compound located at the northern end of the Naval Submarine Base New London along Triton Drive SUBASE New London, Groton, CT, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.4 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract.
SECTION 01 11 00 Page 1
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.5 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.6 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.6.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.7 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish the following materials and equipment for installation by the Contractor:
SECTION 01 11 00 Page 2
DESIGNATION
NO.
DESCRIPTION QUANTITY NOTES
Internal Lock Device (ILD
Magazine Door Lock
9 Internal Lock Contractor to supply all door boltwork components with the exception of the ILD. Complete the Contractor Magazine Bid Information: Door Locking System form and submit to the DoD Lock Program.
Quantities indicated for the above-listed items marked with an asterisk are estimates. It is the intention of the Government to furnish all quantities of the asterisk items required to complete the work as specified, and the various quantities will be adjusted when necessary.
Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Provide any additional quantities that are required.
1.7.1 Delivery Schedule
Notify the Contracting Officer in writing at least 60 calendar days in advance of the date on which the materials and equipment are required.
Pick up materials and equipment no later than 30 calendar days after such date.
1.7.2 Delivery Location
The materials and equipment will be delivered to the job site.
1.8 GOVERNMENT-INSTALLED WORK
The Government will be responsible for the handling of all ordnance and will ensure that ordnance has been removed from existing magazines prior to the start of work/demolition of a particular magazine.
1.9 NAVY AND MARINE CORPS INTRANET( NMCI) COORDINATION REQUIREMENTS
1.9.1 NMCI Contractor Access
Allow the NMCI Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections.
Coordinate efforts with the NMCI Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the NMCI Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
1.10 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 1 mile of the construction site.
Provide a salvage plan , listing material and equipment to be salvaged, and
SECTION 01 11 00 Page 3 their storage location. Maintain property control records for material or equipment designated as salvage. Provide a system for property control in the salvage plan. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
The manual chain falls on a ll existing cranes within existing magazines are to be salvaged and returned to the government at the Rigging Loft in Building B460. The remaining crane components, including rails, beams, and trolleys are to be demolished and disposed of off government property .
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
SECTION 01 14 00
WORK RESTRICTIONS
11/22
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
DESR 6055.09, Edition 1 (2019) Defense Explosive Safety Regulation 6055.09, Edition 1
NEW LONDON INSTRUCTION
SUBASE 8020.IG SUBASE NEW LONDON INSTRUCTION 8020.IG
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
Personnel List
Phasing Plan ; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
All ground disturbance and work in the wetlands will be restricted for 90 days after award in order to obtain both the NPDES and wetlands permit approvals.
All work must be phased in such a way as to minimize impacts to installation weapons handling operations. The new Operations must be constructed, and all staff relocated from the existing Operations Building (B524) into the new operations Building as early as possible in the construction phasing. Physical security requirements (fencing, cameras, intrusion detection/access control, etc.) for the weapons compound (magazine area/compound) and all existing magazines still in operation must be maintained or provided by the contractor. During all phases of construction, the Government shall maintain access control to all magazines that are still in operation; the contractor shall maintain separate construction entrances independent from the weapons compound (magazine area/compound) secured entry. Prior to the start of construction and within 15 days of contract award, provide a Phasing Plan for review and approval by the Contracting Officer and the Weapons Officer. A preliminary Phasing Plan has been provided on the Civil drawings to help
SECTION 01 14 00 Page 1 inform the contractor of phasing requirements.
The Construction Phasing drawings indicate which magazines are to be demolished during the respective construction phasing. The other magazines not indicated for demolition must remain operational during the corresponding construction phase. Each phase has a separate milestone and activity completion date in the schedule.
The Contractor shall be required to (a) commence work under this contract within fifteen (15) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 1,587 calendar days. The time stated for completion shall include final cleanup of the site
The calendar days for the milestones are as follows:
Milestone # Title Time for Completion
Milestone 1 Phase 1A 294 calendar days
Milestone 2 Phase 1B 190 calendar days
Milestone 3 Phase 1C 35 calendar days
Milestone 4 Phase 2 210 calendar days
Milestone 5 Phase 3 269 calendar days
Milestone 6 Work in Areas E, F, G, H, I, J & K
1587 calendar days
The milestones are described as follows:
Milestone 1 (Phase 1A):
No construction activities or demolition associated with the existing magazines in Phase 1A can be performed until government receives Request to Terminate Existing Site Approval from NOSSA. Please allow 14 days for government to receive approval.
Work includes but is not limited to provide temporary construction access and security fencing to ensure a secure perimeter around existing magazines to remain in place during Phase 1 operations (Magazines A94-A97, A100-A104, A105-A109, A113 and A114). Demolition of existing magazines A98, A99, A110 and A111 and including associated pavements and utilities. Install temporary sediment Traps 1 and 3.
Rock blasting and excavation for Ordnance Operations Facility and near Magazines A98, A99, A110 and A111. Construct permanent storm water Facility A East of EXST-001 (A114). Maintain treatment chambers offline until final site stabilization. Ordnance Operations Facility construction including site preparation, drainage infrastructure, utility installation, access road, and parking lot. Convert temporary sediment Trap 1 to permanent storm water facility. Maintain treatment chambers offline until final site stabilization.
Milestone 2 (Phase 1B): Work includes but is not limited to install temporary sediment Trap 2. Reroute and demolish existing utilities necessary to construct Type H magazine. Site preparation, utility
SECTION 01 14 00 Page 2 installation, and construct Type H magazine. Convert temporary sediment Trap 2 to permanent storm water facility. Maintain treatment chambers offline until final site stabilization.
Milestone 3 (Phase 1C): Work includes but is not limited to demolition of existing Building 524, utilities and pavements.
Milestone 4 (Phase 2):
No construction activities or demolition associated with the existing magazines in Phase 2 can be performed until government receives Request to Terminate Existing Site Approval from NOSSA. Please allow 14 days for government to receive approval.
Work includes but is not limited to maintain temporary construction access and provide temporary security fencing to ensure a secure perimeter around existing magazines to remain in place during Phase 2 operations (A100-A104, A105-A109, A113, A114, and Type H-001).
Demolish pavement west of EXT-002 (A113), install temporary sediment Trap 4. Demolish existing magazines A94, A95, A96 and A97 including associated pavements and utilities. Rock blasting and excavation for Type G magazines near magazines A94, A95, A96 and A97. Construct Type G magazines (Type G-001 and Type G-002) adjacent to EXT-002 (A113), including associated pavements and utilities. Replace EXST-002 ground ring during pavement demolition and replacement associated with Type G magazine construction. Site preparation, including utility installation and construction of Sentry Building. Installation of power and telecommunications equipment and intrusion detection system in Sentry Building.
Milestone 5 (Phase 3):
No construction activities or demolition associated with the existing magazines in Phase 3 can be performed until government receives Request to Terminate Existing Site Approval from NOSSA. Please allow 14 days for government to receive approval.
Work includes but is not limited to provide temporary construction access and security fencing to ensure a secure perimeter around existing magazines to remain in place during Phase 3 operations (A113, A114, Type H-001, Type G-001, and Type G-002). Demolish existing pavement East of Magazine A105 and install temporary sediment Trap 5.
Demolish existing magazines A100 to A104 and A105 to A109 including associated pavements and utilities. Construct six (6) CLWS magazines including utilities and associated pavement. Ensure Type H magazine is complete and operational and EXT-001 is empty prior to demolition and replacement of EXST-001 concrete apron. Replace EXT-001 ground ring during pavement demolition and replacement. Demolish existing Building 393 including associated utilities and pavements. Ensure power equipment and intrusion detection system have been relocated and are operational prior to demolition of Building 393.
Milestone 6 (Remainder of Work): The remainder of work not listed in the previous milestones including but not limited to work in Areas E, F, G, H, I, J, and K located on the Site Drawing Sheet C-003. Work for milestone 6 can be performed concurrently with Milestones 1 - 5 .
SECTION 01 14 00 Page 3
1.3.1 Termination of Existing Magazine Operations Between Construction Phases
No construction activities or demolition associated with the existing magazines in Phases 1A, 2, and 3 can be performed until government receives Request to Terminate Existing Site Approval from NOSSA. Please allow 14 days for government to receive approval for each of the aforementioned Phases.
1.3.2 Goose Run Golf Course
The Contractor will be working within a portion of Goose Rune Golf Course. Trenching and installation of new underground utilities are to be conducted within the following time period:
a. 01 November through 30 March
Do not enter the golf course grounds without prior approval of the Contracting Officer and golf course management. All work within the golf course will require a minimum of 30 calendar day advance notice and can not proceed without written authorization from the Contracting Officer and golf course management.
1.3.3 Procedure for Blasting During Construction
Blasting operations are to be conducted in accordance with SUBASE 8020.IG and specification 31 23 06.00 BLASTING - SURFACE.
1.3.4 Time of Year Restriction on Tree Clearing and Blasting
Tree clearing and rock blasting will not be permitted during nesting times of sensitive and endangered species. Tree clearing restrictions is between April 01 and October 31, and blasting restrictions is between April 01 and October 31, due to the presence of habitat for the northern long eared and tricolored bat.
All work associated with the removal or disturbance of vegetation (tree removal, pruning, etc.) is prohibited between April 01 and October 31 of any given year. All timber removed from the project site shall become the property of the Contractor. The Contractor shall reimburse the Government for the value of the timber. The Contractor shall submit payment to the Contracting Officer by cashier's or certified check in the amount of $760.00 made payable to the U.S. Treasury. Payment shall be made no less than five (5) days prior to the start of land clearing operations. See the Temporary Environmental Control specifications 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS and 31 11 00 CLEARING AND GRUBBING, paragraph 3.3.1 for additional requirements.
1.3.5 Wetland Permitting
The contractor is responsible for complying with the wetland permit as NAVFAC's representative. No work within the wetland limits is permitted (including laydown) until the wetland permit is received. A copy of approved permit is to be submitted tot he Public Works New London Environment (PW NLON EV) Division.
The contractor is responsible for completing and submitting all required monitoring and inspection reports. Any natural resource damage claim resulting from construction is the sole responsibility of the construction
SECTION 01 14 00 Page 4 contractor at no additional cost to the government. A copy of any monitoring or inspection reports require by this permit are to be submitted to the Public Works New London Environment (PW NLON EV) Division.
1.3.6 Ribbon Snake Mitigation Plan
The limits of disturbance extend into known habitat of State Protected Species. The contractor serves as the environmental monitor for this effort to ensure that the measures described in the Eastern Ribbon Snake Construction Impact Protection Plan are implemented properly. All work must be completed (and scheduled) in accordance with the contractor provided Ribbon Snake Mitigation Plan. Schedule an meeting with Public Works New London Environment (PW NLON EV) Division a minimum of 21 calendar days in advance of executing the mitigation plan to review the plan and discuss any questions/concerns that might hinder or threaten full plan compliance. The Construction Impact Protection Plan is included as an attachment to these specifications.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.
Occupants of any construction trailers near the job site must be directly involved with the project construction. Administrative personnel are not permitted in job site trailers and must be located outside of all installation inhabited building distance (IBD) arcs. Any windows utilized in construction trailers must meet the criteria of OP5 para 8-3. Brake rooms must be outside the IBD as well.
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
SECTION 01 14 00 Page 5
1.4.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.4.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.4.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.4.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office
SECTION 01 14 00 Page 6 are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.4.1.3 NCACS Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.
Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a. NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.
The Government performs background screening and credentialing.
Throughout the year the Contractor employee will continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON). Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com or by calling 1-877-727-4342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
b. One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation.
The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
The following documents will be required to be presented for base access:
a. Verified license
b. Passport
c. Birth Certificate with SSN card
1.4.1.4 Gate Information
Contractors/Commercial vehicles must use Commercial Gate 7 (CVIS) located
SECTION 01 14 00 Page 7 separately from main gate between the hours of 5:45am - 1:30pm, Monday through Friday. Closed weekends and holidays. Phone number: 860-694-4360
1.4.1.5 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.2 Working Hours
Regular working hours will consist of a 9 hour period, between 6:30 a.m.
and 4:30 p.m. Monday through Friday, excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.4.4 Occupied and Existing Buildings
The Contractor shall be working in existing building and around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
The Government will remove and relocate other Government property in the areas of the buildings scheduled to receive work.
1.4.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and security systems are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
SECTION 01 14 00 Page 8
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's Sanitary Sewer Connection Permit 2 weeks prior to connection and in accordance with Section 33 30 00 SANITARY SEWERAGE.
1.5 SECURITY REQUIREMENTS
Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:
Installation Security Requirements.
1.5.1 Personnel List
Submit for approval, at least 15 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Citizenship
c. Company employee works for
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown."
Signature/Firm Name
1.5.1.1 Citizenship Requirements
Aliens are not allowed on the project site. Work under this contract is restricted to U.S. citizens.
1.6 EXPLOSIVE SAFETY TRAINING
Contractor personnel shall participate in explosive safety training set forth on the requirements of DESR 6055.09, Edition 1 , "Ammunition and Explosives Safety Standards". Coordinate with Naval Submarine Base New London on training requirements and scheduling.
Existing ordnance magazines will remain in service during construction.
Construction activities shall not impact ordnance operations.
1.6.1 Hazards of Electromagnetic Radiation to Ordnance (HERO)
All contractor personnel must adhere to HERO requirements associated with the use of mobile and hand-held transmitters. Coordinate with Naval Submarine Base New London safety personnel on training and guidance.
1.6.2 Explosive Safety Requirements
All work must be conducted in accordance with Navy Explosive Safety Requirements for working within explosive arcs and conducting blast operations. No explosives may be brought and stored on the Installation without the approval of the Installation Explosive Safety Officer.
SECTION 01 14 00 Page 9
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 14 00 Page 10
SECTION 01 31 23.13 20
ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
05/17, CHG 7: 11/21
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
Utilize the Naval Facilities Engineering Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or e-mail submission, including originals or copies, of the documents identified in Table 1 are not permitted, except where eCMS is unavailable, non-functional, or specifically requested in addition to electronic submission.
1.1.1 Format Naming Convention for Files Uploaded Into eCMS
Include the identification number of the document, the type of document, the name/subject or title, and for daily reports, the date (day of work) with format YYYY/MM/DD in the filename. For example, for RFI's, 0011_RFI_Roof_Leaking.doc; for submittals, 0032a_Submittals_Light_Fixture.pdf; for Daily Reports, 0132_Daily_Report_20190504.xls. Contact the Contracting Officer's Representative (COR) regarding availability of eCMS training and reference materials.
1.1.2 Uploading Documents Processed Outside of eCMS
When specifically requested to provide documents outside of eCMS, upload all final project documentation (e.g., documents that are signed and/or adjudicated by the Government) mentioned in Table 1 into eCMS by creating a record in the module associated with that document type and uploading the document(s). Subject/title of the record should include the type of record i.e., RFI/Submittal/Other, the identification number(s), and the statement "Processed Outside of eCMS". For example, "RFI 001-012 Processed Outside of eCMS".
1.2 USER PRIVILEGES
The Contractor will be provided access to eCMS. All technical submittals and documents must be transmitted to the Government via the COR. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
SECTION 01 31 23.13 20 Page 1
List of Contractor's Personnel ; G
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
The eCMS requires a web-browser (platform-neutral) and Internet connection. Obtain from an approved vendor an External Certification Authority (ECA), Primary Key Infrastructure (PKI) certificate, or other similar digital identification to support two-factor authentication and access to eCMS. Provide and maintain computer hardware and software for the eCMS access throughout the duration of the contract for all Contractor-designated users. Provide connectivity, speed, bandwidth, and access to the Internet to ensure adequate functionality. 70 mbps download speed recommended, 40 mbps minimum for loading large files. Neither upgrading of the Contractor's computer system nor delays associated from the usage of the eCMS will be justification or grounds for a time extension or cost adjustment to the Contract.
1.4.2 Contractor Personnel List
Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic technical submittals and documents and will require access to the eCMS. Project personnel roles to be filled in the eCMS include the Contractor's Project Manager, Superintendent, Quality Control (QC) Manager, and Site Safety and Health Officer (SSHO). Personnel must be capable of electronic document management. Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users. Provide the following information:
First Name Last Name E-mail Address Office Address Project Role (e.g. Project Manager, QC Manager, Superintendent)
1.5 SECURITY CLASSIFICATION
In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.
The eCMS and tablet computer must only be used for the transaction of unclassified information associated with construction projects. In conformance with the Freedom of Information Act (FOIA), DoD INSTRUCTION
5200.48 CONTROLLED UNCLASSIFIED INFORMATION (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED
INFORMATION"
(CUI).
1.6 ECMS UTILIZATION
Establish, maintain, and update data and documentation in the eCMS
SECTION 01 31 23.13 20 Page 2 throughout the duration of the contract.
Personally Identifiable Information (PII) transmittal is not permitted in the eCMS.
1.6.1 Information Security Classification/Identification
The eCMS must be used for the transmittal of the following documents.
This requirement supersedes conflicting requirements in other sections, however, submittal review times in Section 01 33 00 SUBMITTAL PROCEDURES remain applicable. Table 1 - Project Documentation Types provides the appropriate U and CUI designations for various types of project documents. Construction documents requiring CUI status must be marked accordingly. Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on U documents.
Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration). If a designated application is not functional within 4 hours of initial attempt, defer to the Submittal application and submit the required data as an uploaded portable document (e.g. PDF), word processor, spreadsheet, drawing, or other appropriate format. Hard copy or e-mail submission of these items is acceptable only if eCMS is documented to be not available or not functional or specifically requested in addition to electronic submission. After uploading documents to the Submittal application, transmit the submittals and attachments to the COR via the Transmittal application. For Submittals, select the following:
Preparation by = Contractor personnel assigned to prepare the submittal Approval by = Contracting Officer Representative (COR) Returned by = Design Lead/Manager Forwarded to = Contractor project manager
Table 1 - Project Documentation Types
SUBJECT/NAME DESIG REMARKS ECMS APPLICATION
As-Built Drawings U Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
Submittals and Transmittals
Building Information Modeling (BIM)
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
SECTION 01 31 23.13 20 Page 3
SUBJECT/NAME DESIG REMARKS ECMS APPLICATION
Construction Permits U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Construction Schedules (Activities and Milestones)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (Cost-Loaded)
U After the schedule submittal is approved by the COR, import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Submittals, Transmittals and Scheduling App
Construction Schedules (3-Week Lookahead)
U Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline
Scheduling App
DD 1354 Transfer of Real Property
U Submittals and Transmittals
Daily Production Reports
U Provide weather conditions, crew size, man-hours, equipment, and materials information
Daily Report
Daily Quality Control (QC) Reports
U Provide QC Phase, Definable Features of Work Identify visitors
Daily Report
Designs and Specifications
U 1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager
2. Design reviews will be performed in existing "Dr Checks"
Submittals and Transmittals
Environmental Notice of Violation (NOV), Corrective Action Plan
U Refer to rules of the issuing activity, state or jurisdiction
Submittals and Transmittals
Environmental Protection Plan (EPP)
U Submittals and
SECTION 01 31 23.13 20 Page 4
SUBJECT/NAME DESIG REMARKS ECMS APPLICATION
Invoice (Supporting Documentation)
U Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)
Submittals and Transmittals
Jobsite Documentation, Bulletin Board, Labor Laws, SDS
U Submittals and Transmittals
Meeting Minutes U Meeting Minutes
Modification Documents
U Provide final…