About this file

This is Amendment 0009 to a Design-Bid-Build (DBB) solicitation for construction of a Weapons Magazine and Ordnance Operations Facility at Naval Submarine Base New London, Connecticut. The solicitation number is N4008526R0004, with project number 1667770.

The amendment incorporates significant updates to the contract including revised construction schedules, updated drawings and specifications, and new evaluation factors. Key milestone durations have been extended: Milestone 1 (Phase 1A) increased to 558 calendar days; Milestone 2 (Phase 1B) to 340 calendar days; Milestone 3 (Phase 1C) to 66 calendar days; Milestone 4 (Phase 2) to 378 calendar days; Milestone 5 (Phase 3) to 486 calendar days; and Milestone 6 (Areas E-K) to 1,828 calendar days. Associated liquidated damages have been updated accordingly, ranging from $11,295.61 to $312,854.12 per calendar day depending on the milestone. The amendment provides updated specifications for work restrictions, special inspections, environmental controls, magazine doors, coating requirements, and clearing/grubbing; introduces a revised Price Proposal Form (Rev 3); adds attachments including a Production Schedule (P1102_PROD), Soil Management Standard Operating Procedure, and Construction Phasing Plan; and updates evaluation criteria for the Management Approach and Schedule factor. The contract award date has been revised to 16 December 2026. The amendment also includes responses to 78 pre-proposal inquiries addressing technical questions regarding scheduling, material requirements, permitting responsibilities, sustainability requirements, and design specifications for various building components and site conditions.

View the file

Other files

File Type Posted
N4008526R00040014 SF 30.pdf PDF
Amend 0014 Spec 1667770.pdf PDF
N4008526R00040013 SF 30.pdf PDF
N4008526R00040011 SF 30.pdf PDF
N4008526R00040012 SF 30.pdf PDF
1667770spc08.25.26.pdf PDF
N4008526R00040010 SF 30.pdf PDF
ATTACHMENT H - Price Proposal Form REV4.docx DOCX document
APPENDIX_D_Air Leakage Rate by Fan Pressurization.xlsx XLSX spreadsheet
ATTACHMENT V - SUBASEINST 8020.1G.pdf PDF
Amendment_0010_Drawings.pdf PDF
APPENDIX_C_Test Agency Qualification Sheet.docx DOCX document
APPENDIX_A_Air Leakage Test Form.docx DOCX document
APPENDIX_B_Air Leakage Test Results Form.docx DOCX document
P1102_GC101 - CONSTRUCTION PHASING PLAN - PHASE 1.pdf PDF
ATTACHMENT T - P1102_PROD.xlsx XLSX spreadsheet
1667770spc07.28.26_rev.pdf PDF
Revised Attachment H - Price Proposal Form REV 3.docx DOCX document
ATTACHMENT U - NLON Soil Management SOP_JUN25.pdf PDF
N4008526R00040008 SF 30.pdf PDF
ATTACHMENT Q - NRZ_Checklist-POAM_Items.pdf PDF
P-1102_Amend 0007_Drawings2of3.pdf PDF
ATTACHMENT S - UPDATED Wage Determination.pdf PDF
P-1102_Amend 0007_Specifications.pdf PDF
P1102_Amend 0007_Drawings3of3.pdf PDF
ATTACHMENT R - Geo Inv Analytical Rep.pdf PDF
Revised Attachment H Price Proposal Form REV2.docx DOCX document
P-1102_Amend 0007_Drawings1of3.pdf PDF
N4008526R00040007 SF 30.pdf PDF
ATTACHMENT L - Explosive Safety-HERO training.pptx PPTX presentation
ATTACHMENT P - NAVSEA OP 5 REV 9.pdf PDF
JA ML-26-14 P1102 Rock Fall_Redacted.pdf PDF
JA ML-26-16 P1102 Interior Finishes_Redacted.pdf PDF
JA ML-26-15 P1102 Stormwater_Redacted.pdf PDF
P-1102_Amend 0006_Drawings_rev.pdf PDF
JA ML-26-12 P1102 ESS_Redacted.pdf PDF
ATTACHMENT N - NDDB Determination Renewal 16JAN2026.pdf PDF
JA ML-26-13 P1102 Fire Alarm_Redacted.pdf PDF
ATTACHMENT O - MK48 STORAGE FACILITY.pdf PDF
ATTACHMENT M - Permits Record of Decision (PROD).pdf PDF
N4008526R00040006 SF 30.pdf PDF
P1102_Amend 0006_Specifications_rev.pdf PDF
UPDATED ATTACHMENT H Price Proposal Form REV1.docx DOCX document
N4008526R00040005 SF 30.pdf PDF
Amendment N4008526R00040004 SF 30.pdf PDF
Attachment F-Small Business Participation Commitment.pdf PDF
Attachment G- Small Business Subcontracting Plan (SBSP) Rev.pdf PDF
Amendment 0004 PPIs.pdf PDF
N4008526R00040003 SF 30.pdf PDF
Amendment 0003PPIs.pdf PDF
Show 40 more

Latest 50 of 81 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): N40085-26-R-0004, Design-Bid-Build (DBB), P1102 WEAPONS MAGAZINE

&ORDNANCE OPERATIONS FACILITY, NAVAL SUBMARINE BASE, NEW LONDON, CONNECTICUT

SECTION SF30 BLOCK 14 CONTINUATION PAGE

ALL CORRESPONDENCE REGARDING THIS SOLICITATION SHALL BE DIRECTED VIA EMAIL TO ANGIE CLIFTON AT ANGELA.J.

CLIFTON2.CIV@US.NAVY.MIL.

This amendment is issued to incorporate the following:

1. Provide continuation sheet for drawings and specifications (Enclosed)

2. Provide Updated Drawings (attached separately)

3. Provide Updated Specifications (attached separately)

4. Provide Updated Evaluation Factors for Award: Factor 2 - Management Approach and Schedule (Enclosed)

5. Provide Revised ATTACHMENT H - Price Proposal Form REV 3 (attached separately)

6. Provide ATTACHMENT T - P1102_PROD (attached separately)

7. Provide ATTACHMENT U - NLON Soil Management SOP_JUN25 (attached separately)

8. Update Clauses and Provisions (Enclosed)

9. Provide PPI Responses (Enclosed)

Section 00 70 00 - Conditions of the Contract

Additional Information/Notes

The following clauses were modified:

52.211-12Liquidated Damages-Construction.Sep 2000 hereby reads as follows:

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of for each calendar day of delay for Milestone 1, for each calendar day of delay for Milestone 2,$37,004.25 $60,730.50 for each calendar day of delay for Milestone 3, for each calendar day of delay for Milestone 4, for each calendar$312,854.12 $54,625.32 $42,486.36 day of delay for Milestone 5, and for each calendar day of delay for Milestone 6 until the work is completed or accepted.$11,295.61

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

Please reference chart below. Liquidated Damages:

Number of Days Liquidated Damages

Milestone 1 558 calendar days $37,004.25 per calendar day

Milestone 2 340 calendar days $60,730.50 per calendar day

Milestone 3 66 calendar days $312,854.12 per calendar day

N4008526R00040009

Milestone 4 378 calendar days $54,625.32 per calendar day

Milestone 5 486 calendar days $42,486.36 per calendar day

Milestone 6 1828 calendar days $11,295.61 per calendar day

(End of clause)

Section 00 73 00 - Supplementary Conditions

The following attachments were added:

1667770spc07.28.26_rev

ATTACHMENT T - P1102_PROD

ATTACHMENT U - NLON Soil Management SOP_JUN25 Amendment 0009 Continuation Page

P1102_GC101 - CONSTRUCTION PHASING PLAN - PHASE 1

Revised Attachment H - Price Proposal Form REV 3

N4008526R00040009

SECTION SF30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by full text:

AMENDMENT 0009

This amendment is issued to incorporate the following:

1. Provide continuation sheet for drawings and specifications (Enclosed)

2. Provide Updated Drawings (attached separately)

3. Provide Updated Specifications (attached separately)

4. Provide Updated Evaluation Factors for Award: Factor 2 – Management Approach and Schedule (Enclosed)

5. Provide Revised ATTACHMENT H – Price Proposal Form REV 3 (attached separately)

6. Provide ATTACHMENT T – P1102_PROD (attached separately)

7. Provide ATTACHMENT U – NLON Soil Management SOP_JUN25 (attached separately)

8. Update Clauses and Provisions (Enclosed)

9. Provide PPI Responses (Enclosed)

1. Continuation Sheet for Drawings and Specifications (Enclosed)

DRAWINGS:

REPLACE the following drawings to the DRAWING INDEX under the corresponding discipline and drawing number. These drawings accompany this Amendment:

CG101 [12893809] CONSTRUCTION PHASING PLAN – PHASE 1 – REPLACED SHEET

On NAVFAC Drawing No. 12893809 (CG101)

A1/CG101 CONSTRUCTION PHASING PLAN – PHASE 1: ADD NORTH WETLAND MITIGATION

AREA and SOUTH WETLAND MITIGATION AREA GENERAL SHEET NOTES; ADD note 6 “REFER TO SHEET CE001 TO CE502 FOR WETLAND

MITIGATION INFORMATION.”

PHASING NOTES – PHASE 1A; ADD note 1 “CONSTRUCT NORTH AND SOUTH WETLAND

MITIGATION AREAS.”

SPECIFICATIONS:

PROJECT TABLE OF CONTENTS

REPLACE the following sections with the attached sections to accompany this Amendment.

01 14 00 WORK RESTRICTIONS, dated 28 July 2026 01 45 36 SPECIAL INSPECTIONS – EARTH COVERED MAGAZINES, dated 28 July

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS, dated 28 July 2026 08 39 55.00 20 NAVY STANDARD EARTH-COVERED MAGAZINE DOORS, dated 28 July

09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES, dated 28 July

31 11 00 CLEARING AND GRUBBING, dated 28 July 2026

SECTION 01 14 00 WORK RESTRICTIONS

1.3 Special Scheduling Requirements

Milestone 1 – Phase 1A: DELETE “294 calendar days” and REPLACE with: “558 calendar days” Milestone 2 – Phase 1B: DELETE “190 calendar days” and REPLACE with: “340 calendar days” Milestone 3 – Phase 1C: DELETE “35 calendar days” and REPLACE with: “66 calendar days” Milestone 4 – Phase 2: DELETE “210 calendar days” and REPLACE with: “378 calendar days” Milestone 5 – Phase 3: DELETE “269 calendar days” and REPLACE with: “486 calendar days” Milestone 6 – Work in Areas E, F, G, H, I, J & K: DELETE “1587 calendar days” and REPLACE with:

“1828 calendar days”

1.3 Special Scheduling Requirements, Milestone 1 (Phase 1A)

ADD sentence: ”Construct north and south wetlands per wetland mitigation drawing package east of Magazines A105 through A111”.

1.3.4 Time of Year Restriction on Tree Clearing and Blasting

DELETE sentence “The Contractor shall submit payment to the Contracting Officer by cashier’s or certified check in the amount of $760.00 made payable to the U.S. Treasury.” and REPLACE with: “The Contractor shall submit payment to the Contracting Officer by cashier’s or certified check in the amount of $988.00 made payable to the U.S. Treasury.”

1.4.1 Activity Regulations

DELETE sentence “Any windows utilized in construction trailers must meet the criteria of OP5 para 8- 3.” and REPLACE with: “Any windows utilized in construction trailers must meet the criteria of OP5 para 8-4.1.11.”

SECTION 01 45 36 SPECIAL INSPECTIONS – EARTH COVERED MAGAZINES

1.5 Special Inspector Qualifications

DELETE subparagraph 1.5.4 title “Cold Formed Steel Framing” and REPLACE with: “Concrete Construction”

SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

1.3 Submittals, SD-01 Preconstruction Submittals

DELETE references to “Dewatering Plan for OU 2 and 3” and REPLACE with “Dewatering Plan for Sites 2A, 2B, and 3”

1.5.1.1.2 Construction Dewatering

DELETE references to “Operable Units 2 and 3” and REPLACE with “Sites 2A, 2B, and 3” ADD “Soil Management Standard Operating Procedures (SOP)” as an attachment to specification section 01 57 19

SECTION 08 39 55.00 20 NAVY STANDAR EARTH-COVERED MAGAZINE DOORS

2.6 Finishes

DELETE this paragraph and REPLACE with: “Clean, prepare, and coat all exposed and non-exposed ferrous metal surfaces as part of the Section 09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES work, including all requirements, submittals, certifications, testing, and inspections required by Section 09 97 13.27. Do not coat finished bearing surfaces. Alternative coating systems or products will not be considered. Prepare surface and follow all temperature, humidity, and testing requirements listed in Section 09 97 13.27. After installation of the door, prep and touch up surfaces damaged during assembly and installation of the door. Prep and coat unfinished ferrous metal accessories such as bolts and brackets. Provide details and document compliance path in the Coating Submittal Package.”

SECTION 09 97 13.27 HIGH PERFORMANCE COATING FOR STEEL STRUCTURES

1.4 Quality Assurance

ADD subparagraph 1.4.3.3 “Qualifications of Coating Contractors” and “All Contractors and Subcontractors that perform surface preparation or coating application shall be certified to either ISO 9001 or SSPC QP 1 and SSPC QS 1 prior to contract award, and shall remain certified while accomplishing any surface preparation or coating application. The painting Contractors and paining Subcontractors must remain so certified for the duration of the project. If a Contractor’s or Subcontractor’s certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered and liquidated damages will apply. Notify the Contracting Officer of any changes in Contractor certification status.”

2.2 Coating System

DELETE this paragraph and REPLACE with: “Prepare surface and apply primer coating in the shop.

Do not apply primer, intermediate or top coating to non-exposed inaccessible surfaces interfacing with lightweight concrete. Adjust all shop preparation to avoid conflicts with final surface preparation requirements. Apply intermediate and top coat coating systems in the field. Follow all temperature, humidity, and testing requirements listed herein.”

3.1 Surfaces To Be Coated

DELETE this paragraph and REPLACE with: “Section 08 39 55.00 20 NAVY STANDARD EARTH- COVERED MAGAZINE DOORS references Section 09 97 13.27 and requires shop application of the primer coat and field application of the intermediate and top coats.”

SECTION 31 11 00 CLEARING AND GRUBBING

3.3.1 Saleable Timber

DELETE sentence “Reimburse the Government for the fair market value of the timber which the Government has appraised at $760.” and REPLACE with: “Reimburse the Government for the fair market value of the timber which the Government has appraised at $988.00.”

ATTACHMENTS:

1. Amendment 0009 – PPIs 383 - 387: ATTACHMENT T - P1102_PROD.xlsx

2. Amendment 0009 – PPI 454: ATTACHMENT U - NLON Soil Management SOP_JUN25.pdf

3. Amendment 0009 – Revised Attachment H – Price Proposal Form, Rev 3.docx

2. Updated P-1102_Amend 0009_Drawings are provided with this amendment (attached separately)

3. Updated P-1102_Amend 0009_Specifications are provided with this amendment (attached separately)

4. Provide Updated Evaluation Factors for Award: Factor 2 – Management Approach and Schedule (updates notated in red)

Factor 2 – Management Approach and Schedule

(i) Solicitation Submittal Requirements:

The offeror shall submit a narrative and schedule for this factor. The narrative shall not exceed ten (10) pages, 8-1/2" x 11" size. Provide the schedule, documenting any multiple critical paths, in 11" x 17" pages and in an Adobe PDF file. There is no page limit on the schedule.

The narrative shall include, but not limited to:

1. Provide a narrative describing the proposed approach to management, for both subcontractors and your workforce, to ensure schedule adherence, early detection and correction of problems and the execution of the base bid items and all options, as referenced in the RFP.

2. Identify activities that may affect the project timeline, including other/off site work activities.

3. Describe how your firm will handle technical complexities relating to: maintaining complex phasing plan that enables access and operations of existing weapons magazines during construction.

4. Describe how your firm will handle unforeseen problems with: material deliveries, subcontractor progress, weather, re-work, differing site conditions, and inspections relating to the subject project.

The schedule shall include, but not limited to:

1. Provide a Critical Path Method (CPM) construction schedule that illustrates your ability to achieve the schedule and meet all the requirements of the RFP (1828 calendar days inclusive of all options, including 15 days for bond approval). The schedule shall be based on a contract award date of 16 December 2026. This date is for proposal purposes only and is not intended to indicate an anticipated/planned award date. Any proposed duration shorter than the RFP requirements will be incorporated into the contract award.

(ii) Basis of Evaluation:

Offerors will be evaluated on the extent to which they demonstrate a thorough understanding of the requirements of the RFP.

A narrative work plan that identifies areas of risk in logistics and resource management, and provides a comprehensive contingency plan that addresses mitigation of any identified risks with potential solutions, may be considered more favorably.

A schedule that proposes a realistic shorter contract duration that the required duration indicated in the RFP may be considered more favorably.

5. UPDATED ATTACHMENT H – Revised Attachment H – Price Proposal Form, Rev 3 is provided with this amendment (attached separately)

6. ATTACHMENT T – P1102_PROD is provided with this amendment (attached separately)

7. ATTACHMENT U – NLON Soil Management SOP_JUN25 is provided with this amendment (attached separately)

8. Applicable Clauses and Provisions are updated with this amendment (Enclosed)

9. Pre-proposal Inquiry Responses (Enclosed)

PPI # Page Section Paragraph Question Response

Please verify that all load tests associated with the bridge cranes (Specification section 41 22 13.14) noted under subsection 3.4.5 are able to be performed on the project site and are not required to be done at the fabricator. Can the load tests in sub section 3.4.5 be applied to the certificates noted in subsection 1.6.3.f?

Load tests specified in Section 3 of 41 22 13.14 are to be performed on site after cranes are installed and checkout by the vendor. Load tests are performed by the vendor with witnesses representing user facility and/or NAVFAC.

Certificate required in subsection 1.6.3.f is required prior to load testing and states that overload tests up to 125% of rated load can be performed periodically. The design of crane assures that crane can be overload tested to 125% without damage. Load tests are expected for acceptance and periodically throughout the life of the crane at intervals of one to three years. This certificate is a design requirement and must be delivered before acceptance testing begins.

“The project drawings do not show us working in Sites 2A, 2B, and 3 and the contract documents do not provide enough chemical test data for us to adequately price soil disposal and the data that was provided for material off our work zone is from 2010.

Addendum 6 revised specification 01.57.19.

This spec describes contaminants found in Sites 2A, 2B, and 3, but does not provide any further information on soil we are actually going to work with.

Making the contractor responsible for the testing and disposal

1. No active intrusive activities are anticipated within Sites 2A and 2B for this project, the land use within these areas is limited to laydown areas for contractor use. Activities within Site 3 are limited to utility installation. All duct bank installation within this boundary should be considered contaminated and most of the soils may be reused. The land use control description is provided for worker safety notification purposes.

2. Pre-characterization of site soils is included within the Soil Management Plan Section of 01 57

19. All costs associated with pre-characterization are part of the base bid.

3. Please bid per the RFP.

4. Please bid per the RFP.

costs and schedule time for unknown soil conditions is not reasonable. Can a precharacterization item be created for the contractor to test soil samples from around the site to determine where problem soils might be located and develop an adequate soil management plan?

Additionally, is it possible to provide Unit Price Items for instate transportation and disposal, out of state transportation and disposal, and hazardous disposal to eliminate risk.

Lastly, only being able to store materials for 60 days is unrealistic due to the Phasing requirements. For example, all blasting happens early on and other phases of reuse are not available within a 60-day timeframe. The way the spec is currently written, all material will have to be disposed of. We request this requirement be removed.

S-010S & S-204

Reference is made to Drawing S010S as well as S-204 of the CLWS plans. Would you please provide details for the access hatch or blast door used to access the mechanical room on the CLWS magazines.

There is a door schedule on CLWS- S-701. Door Type A is intended for the exterior door to the mechanical room.

Reference PPI 329 response – It is our understanding that the Government has an implied responsibility to share information that may be critical to

No active intrusive activities are anticipated within Sites 2A and 2B for this project, the land use within these areas is limited to laydown areas for contractor use. Activities within Site 3 are limited to utility installation. All duct bank bidders. In that context, we respectfully request any available prior soil sampling and analytical reports within the project limits that may not already be reasonably accessible to all bidding contractors.

Such information could help inform pricing considerations and provide further clarity on the scope of work.

Depending on the contaminants present in the soils, it may significantly alter the disposal site location and increase/decrease the cost and the approval process duration.

installation within this boundary should be considered contaminated and most of the soils may be reused. The land use control description is provided for worker safety notification purposes. Pre-characterization of site soils is included within the Soil Management Plan Section of 01 57 19.

Ref Temp Electrical - Per PPI #369 response, we respectfully request a design for any temporary measures necessary to support ongoing operations during each phase.

Providing temporary power is the responsibility of the contractor pursuant to Specification 01 50 00 paragraph 3.2

384 PROD

Ref. Permitting – PROD documents identify several permits as the Contractor’s responsibility to “finalize permit with CT DEEP” or to “confirm final approval” with the applicable Government agencies prior to construction. However, the level of completeness for these permits is not clearly defined.

What is the current status of each listed permit (e.g., conceptual, partially complete, or substantially complete and pending final approval)?

Please see Amendment 0009, the PROD has been updated.

The erosion control and stormwater management permits (to include Clearing and General NPDES), have been submitted to CT DEEP and are currently in review for plan approval. The Government must submit a Notice of Termination and the Construction Contractor must file for a new permit with CT DEEP for approval prior to land disturbance activities since permits are no longer transferrable.

The wetlands and watercourses permit and Water Quality Certification from CT DEEP has been submitted and is in plan review by USACE and CT DEEP.

Final approval of this permit should be confirmed with the Government prior to land disturbance activities.

These permits, as required, must be transferred to the construction contractor prior to land disturbance activities.

The construction contractor must submit a mitigation and monitoring plan to USFWS and CT DEEP for site work related to habitat of the Eastern Ribbon Snake for final permit approval.

385 PROD

Ref. Permitting – PROD documents identify several permits as the Contractor’s responsibility to “finalize permit with CT DEEP” or to “confirm final approval” with the applicable Government agencies prior to construction. However, the level of completeness for these permits is not clearly defined.

Are bidders expected to assume responsibility for developing and submitting permit applications from the beginning, or only to complete and finalize existing applications?

Please see Amendment 0009, the PROD has been updated.

The erosion control and stormwater management permits (to include Clearing and General NPDES), have been submitted to CT DEEP and are currently in review for plan approval. The Government must submit a Notice of Termination and the Construction Contractor must file for a new permit with CT DEEP for approval prior to land disturbance activities since permits are no longer transferrable.

The wetlands and watercourses permit and Water Quality Certification from CT DEEP has been submitted and is in plan review by USACE and CT DEEP.

Final approval of this permit should be confirmed with the Government prior to land disturbance activities.

These permits, as required, must be transferred to the construction contractor prior to land disturbance activities.

The construction contractor must submit a mitigation and monitoring plan to USFWS and CT DEEP for site work related to habitat of the Eastern Ribbon Snake for final permit approval.

386 PROD

Ref. Permitting – PROD documents identify several permits as the Contractor’s responsibility to “finalize permit with CT DEEP” or to “confirm final approval” with the applicable Government agencies prior to

Please see Amendment 0009, the PROD has been updated.

The erosion control and stormwater management permits (to include Clearing and General NPDES), have been submitted to CT DEEP and are currently in review for plan approval. The Government must submit a Notice of Termination and construction. However, the level of completeness for these permits is not clearly defined.

What specific contract deliverables, documentation, or supporting materials are required to accompany the permit applications for final approval?

the Construction Contractor must file for a new permit with CT DEEP for approval prior to land disturbance activities since permits are no longer transferrable.

The wetlands and watercourses permit and Water Quality Certification from CT DEEP has been submitted and is in plan review by USACE and CT DEEP.

Final approval of this permit should be confirmed with the Government prior to land disturbance activities.

These permits, as required, must be transferred to the construction contractor prior to land disturbance activities.

The construction contractor must submit a mitigation and monitoring plan to USFWS and CT DEEP for site work related to habitat of the Eastern Ribbon Snake. for final permit approval.

387 PROD

Ref. Permitting – PROD documents identify several permits as the Contractor’s responsibility to “finalize permit with CT DEEP” or to “confirm final approval” with the applicable Government agencies prior to construction. However, the level of completeness for these permits is not clearly defined.

Are there any known outstanding comments, conditions, or approvals pending from CT DEEP or other agencies that should be incorporated into the Contractor’s scope?

Please see Amendment 0009, the PROD has been updated.

The erosion control and stormwater management permits (to include Clearing and General NPDES), have been submitted to CT DEEP and are currently in review for plan approval. The Government must submit a Notice of Termination and the Construction Contractor must file for a new permit with CT DEEP for approval prior to land disturbance activities since permits are no longer transferrable.

The wetlands and watercourses permit and Water Quality Certification from CT DEEP has been submitted and is in plan review by USACE and CT DEEP.

Final approval of this permit should be confirmed with the Government prior to land disturbance activities.

These permits, as required, must be transferred to the construction contractor prior to land disturbance activities.

The construction contractor must submit a mitigation and monitoring plan to USFWS and CT DEEP for site work related to habitat of the Eastern Ribbon Snake. for final permit approval.

389 4 01 30 02.00 22 1.5.a

Ref Existing AV Equipment - Please confirm the location, type, model and quantity of the existing AV Equipment that is required to be relocated and incorporated into the delegated design.

More information is necessary in order to provide accurate pricing.

Advertised A/V design does not reference any existing equipment.

All equipment is to be procured as new. 1.5 section A does not pertain to solicitation package.

390 4 01 45 36 1.5.4

Ref CFMF SI - Paragraph is labeled Cold Formed Steel Framing however the certifications below the heading seem to be for a concrete inspector.

Please confirm which is correct.

Please see Continuation Sheet provided with Amendment 0009.

The paragraph has been labeled

1.5.4 Concrete Construction. There

is no cold formed special inspection required.

391 TS001/T

Y001

Ref. Telecom & Security Conduit Installation Notes - Please confirm these notes will only apply to conduits installed within this contract by the installing contractor.

The conduit installation notes are applicable to the scope of work indicated on the telecom "T" series of drawings in association with Division 26 specifications.

Additional notes are located throughout the T series drawings.

392 TS001/T

Y002

Ref. Telecom & Security Conduit Installation Notes - Please confirm the existing pathways comply with these requirements or if the contractor will be required to modify the existing pathways if found later to be non-compliant.

Notes apply to new pathways shown in the T series drawings. It is the contractor’s responsibility to verify that existing conduits are usable and make corrections as required. The design assumes existing conduits required are usable. (there is no TY002 as referenced)

393 2 01 45

35/01 45

1.3.11

Ref. Frequency of Special Inspections - Paragraph directs the bidders to the Schedule of Special Inspections for frequency of inspection. Frequencies unclear from the SSI

The definitions for "perform" "observe", “document", and “Continuous" are found on the first page of the schedule of special inspections.

except for Continuous.

Please confirm the minimum frequency for each special inspection required for compliance.

394 S511

Ref. Aluminum Guardrails - Type G sheet S511 shows aluminum posts welded to galvanized embeds.

Is this correct? Type H & CLWS plans shows post-installed anchored aluminum baseplates. If so, please provide preferred method of welding these dissimilar metals.

The post-installed connection details shown on Type H and CLWS may be used in lieu of welding dissimilar metals at Type G.

395 05 52 00

Ref. Aluminum Guardrails - Type G, Type H & CLWS plans shows aluminum guardrails with details.

Does specification section 05 52 00 govern the construction of these guardrails? Section 05 52 00 seems to conflict with these details and includes many references to steel construction e.g. AWS D1.1/D1.1M, 1-3/4" Square shapes vs. detail shows 3" OD, 8 ft O.C.

posts vs. detail shows 6 ft O.C., anchored sleeves vs. baseplates or embeds. Please advise.

The specification 05 52 00 provides minimum dimensional and detailing information for railings that are not specifically detailed on the drawings. Comply with the details where railings and connections are specifically detailed on the drawings.

396 CS102

Ref. 30' Interior Perimeter Clear Zone - Please confirm what restrictions on construction are associated with the interior clear zone during the project duration. Note 7 instructs bidders to maintain clear zone from buildings and 'other obstructions', please define other obstructions. There are many site features

There are no restrictions on construction associated with the 30' interior clear zone. This dimension is provided to convey that no visual obstruction occur within 30' of the new perimeter fence once construction is complete.

requiring regular occupation within the clear zone.

397 CS504

Ref. Fence Legend - CS504 includes a legend for fence types, it is unclear where the fencing types are indicated elsewhere.

Please confirm if all the fencing is to be installed per detail A1 (FE6-TR- 84).

Perimeter fencing is to be installed as dimensioned in detail A1/CS504 with 7' of chain link fabric and single barbed wire outrigger (FE6-

TR-84).

398 CS504

Ref. Fence Bottom Rail

- Details show tension wire, however, Note C references bottom rails.

Please confirm if fence will have tension wire or bottom rails.

Perimeter fencing must have a bottom tension wire buried a minimum of 2" into finished grade.

399 1 31 00 00 1.1.G

Ref. Excavated Rock - Para. 1.1 requires re-use of the excavated rock after crushing to the specified gradation.

Please confirm which use the crushed rock will be acceptable for use. (e.g. structural fill, pavement sub-base, general fill, etc.) Note, achieving specified gradation may require the importation of other material for mixture to achieve specified gradation.

Excavated rock crushed on site may be reused as non-frost susceptible fill and rapid draining material in pavement sections provided gradation produced complies with the specifications. Excavated rock may also be used for rip rap material as specified.

400 16 01 57 19 1.5.1.1.2

Ref. Contaminated Soils

- 01 57 19 indicates all soils are to be considered contaminated and must be disposed of at a permitted, lined landfill.

Section 31 00 00 indicates re-use of satisfactory materials.

Will all soils be required to be removed and disposed of IAW 01 57 19?

Excavated soil may be reused on site provided it complies with the requirements for satisfactory materials specified in Section 31 00

00. Unsatisfactory and excavated spoil that is to be removed from the site must be disposed of in accordance with 01 57 19.

401 VARIES 31 00 00

Ref. Satisfactory Excavated Materials — Specification Sections 3.9, 3.14.2, 3.15, and

The construction contractor is responsible for soil testing per Specification 31 00 00, Paragraph 3.18, to determine suitability of

3.19 permit reuse of excavated materials where deemed satisfactory. Please clarify whether the Government will determine material suitability or if bidders are responsible for testing and determination of suitability.

Additionally, provide direction on how bidders should account for scenarios in which excavated soils do not meet the criteria and must be disposed of and replaced with imported materials. This uncertainty may result in inconsistent bids and could impact both project cost and schedule due to varying assumptions regarding testing, disposal, and import requirements.

Will this be handled as a changed condition?

excavated soils. Unsuitable materials must be disposed of per specification section 01 57 19 and 31 00 00.

402 VARIES 31 00 00

Ref. Satisfactory Excavated Materials — Specification Sections 3.9, 3.14.2, 3.15, and

3.19 permit reuse of excavated materials where deemed satisfactory. The geotechnical report does not clearly quantify the portion of excavated materials expected to meet this criterion. This may lead to inconsistent bids and affect both project cost and schedule if incorrect assumptions are made, as assumptions regarding import/export quantities may vary.

Please clarify the basis upon which bidders should assume and

Bids should be based on information provided in the solicitation, no additional information on subsurface conditions is available.

account for reuse of excavated soils.

403 2 01 14 00 1.3

Amendment 7 provided revised specification 01 14 00 para 1.3 which provided milestones completion durations and description for what is required to be completed to satisfy each milestone.

Milestone 1 does not reference the Transfer of Personnel from B524 to the Operations Building.

Please confirm that the Transfer of Personnel to Operations Building is required to be completed as part of milestone 1. If not, please confirm which Milestone includes the transfer of Government personnel.

Transfer of Personnel from B524 to the Operations Building following the completion of Milestone 1.

404 2 01 14 00 1.3

Amendment 7 provided revised specification 01 14 00 para 1.3 which provided milestones completion durations and description for what is required to be completed to satisfy each milestone.

Milestone 1 does not reference TAB and CX for to the Operations Building. Please confirm that TAB and CX for the Operations Building are required to be completed as part of milestone 1. If not please confirm which Milestone this is required for.

TAB and CX are to be completed under Milestone 1.

405 5 01 14 00 1.4.1

01 14 00 para 1.4.1 states that construction trailer windows must meet criteria of OP5 para 8-3. OP5 para 8-3 is titled "Lithium

Reference to paragraph 8-3 was for

ATTACHMENT P - NAVSEA

OP5 - Volume 1, Revision 7 (dated 25 March 2020). The Ninth Revision of NAVSEA OP5 was issued on 10 March 2023 with

Battery Facilities". This does not appear to be the correct reference for construction trailer window requirements.

Please provide updated requirements for construction trailers located near magazines or confirm this is the correct requirements to be used for the project.

corresponding requirements for windows located in paragraph 8-

4.1.11. Paragraph 1.4.1 Activity

Regulations have been revised to reference paragraph 8-4.1.11 per Amendment 0006.

PPI 369 stated that temporary power is to be provided from the existing bldg 393 to the Type H magazine.

Please confirm the existing bldg 393 has adequate power available to support new Type H magazine.

The determination of adequate temporary power is the responsibility of the contractor pursuant to Specification 01 50 00 paragraph 3.2.

407 2 01 14 00 1.3

Ref. Milestone 1 Duration - The process by which the contractor prepares to blast rock takes 6 months, per the specifications, and the Cx/Closeout will take 4 months per the specifications. This only leaves less than 2 months to construct the Operations building, 294 days would still be aggressive for the amount of work shown at this building. Less than two months is not reasonable for this amount of work. Does the milestone duration contemplate these specified processes for blasting approval and building acceptance?

Please see Amendment 0009.

The duration of Milestone 1 has been revised to 558 calendar days.

408 2 01 14 00 1.3

Ref. Milestone Durations - It appears the milestones 1-5 must be completed within the first 998 days of the project and the remaining 589 days are for work adjacent to the site. Can more time be allotted for the core

Please see Amendment 0009.

Durations of Milestones 1 through 6 have been revised.

demolition and construction? Given there are strict processes for submittals, approvals, quality control inspections, closeout, commissioning and acceptance of each phase and periods of non-work for 30-45 days after magazines work it may require multiple shifts and add significant risk to the schedule for any unforeseen circumstances to deliver this work in 998 days.

409 2 01 14 00 1.3

Ref. Milestone 1 MEP Equipment - The Milestone 1 gives the contractor 294 days from NTP. With procurement, submittals and lead time the MEP equipment may not arrive prior to the required milestone completion date even given the DPAS rating.

Does this duration include the equipment?

Please see Amendment 0009.

Milestone duration is inclusive of material lead times. The duration of Milestone 1 has been revised to 558 calendar days.

410 2 01 14 00 1.3

Ref. Milestone 1 FFE - The Milestone 1 gives the contractor 294 days from NTP to complete the Operations building, including FFE. With procurement, design, BVD, option awarded, FFE procurement, fabrication, lead time and installation of the FFE prior to the required milestone completion date. Does the 294 days duration include the FFE? The option may need to be awarded with the base to fulfill this scope before M1. Note the Government may wait until 6 mos. prior to CCD to award

Please see Amendment 0009.

FF&E is not included as part of Milestone 1. Duration of Milestone 1 has been revised to 558 calendar days. Revised specifications have also been provided with Amendment 0009.

furnish/install scope for ESS, FFE & AV which may also further impact M1.

411 pages 2-3 01 14 00

Amendmen t 7

1.3

Section 01 14 00 states that the Contractor shall complete the entire work ready for use not later than 1,587 calendar days, and separately lists the following per-phase milestone durations: Milestone 1 (Phase 1A) 294 days;

Milestone 2 (Phase 1B) 190 days; Milestone 3 (Phase 1C) 35 days;

Milestone 4 (Phase 2) 210 days; Milestone 5 (Phase 3) 269 days; and Milestone 6 (Areas E, F, G, H, I, J & K) 1,587 days.

The five interim phase milestone durations (Milestones 1–5) sum to 998 calendar days, which does not equate to the 1,587-day total contract duration. In addition, the specification provides no defined start (commencement) event from which each individual phase milestone duration is to be measured, and it expressly permits Milestone 6 work to be performed concurrently with Milestones 1–5, confirming that the phases and their milestones are not intended to run consecutively.

Based on the foregoing, it is the offeror's interpretation that:

(1) The only binding, Please see Amendment 0009.

All milestone dates and Liquidated Damages have been updated.

enforceable contract completion requirement is the total contract duration of 1,587 calendar days from Notice to Proceed (inclusive of final site cleanup); and

(2) The individual phase milestone durations in Milestones 1–5 are provided as guidance to convey the Government's expected phasing sequence and relative effort, and are not independently enforceable interim completion constraints

Kindly confirm the our interpretation above.

Reference is made to Amendment 00007 Drawings 3 of 3, pertaining to the North and the South Wetland Mitigation Areas. Are there limitations on means of accessing the North and South Wetland Mitigation Areas? Will the contractor be permitted to make use of the Perimeter Road? Will access roads be permitted to be constructed up to this perimeter road or from the other portions of the project site?

Contractors may use Perimeter Road to access the North and South Wetland Mitigation Areas.

Contractors will be permitted to construct up to Perimeter Road or other portions of the project site to access the mitigation areas.

Reference is made to Amendment 00007 Drawings 3 of 3, pertaining to the North and the South Wetland Mitigation Areas. Please provide an expanded Land Use Control Plan (H-101) that covers these mitigation sites.

Are these areas considered to be contaminated and

Wetland mitigation areas are located outside of the established and delineated Land Use Control areas.

treated similarly to Sites 2a, 2b and 3? Would you please provide any soil and water analytical reports that may be available?

Reference is made to Amendment 00007 Drawings 3 of 3, pertaining to the North and the South Wetland Mitigation Areas.

Would you please clarify the intended sequence for this work relative to the previous scope? Is this work included within Phase 1a, 1b, 1c, 2 or 3?

Wetlands Mitigation Area will be constructed in Phase 1a - please see Amendment 0008.

415 01 14 00 1.3

Reference is made to spec section 01 14 00 paragraph 1.3 SPECIAL

SCHEDULING

REQUIREMENTS as provided in Amendment 0007. This section provides a table of milestones. We have scheduled this project and feel that there it would be a difficult but highly achievable to complete this project in the requested 1587 calendar days, however, some of the interim milestones would be difficult if not impossible to achieve.

Would you please review and consider revising the durations of Milestones 1, 2, 3, 4 & 5?

Please see Amendment 0009.

The durations of Milestones 1 through 6 have been revised.

416 01 14 00 1.3

Reference is made to spec section 01 14 00 paragraph 1.3 SPECIAL

SCHEDULING

REQUIREMENTS as provided in Amendment 0007. This section provides a table of milestones. Would you please clarify if there are to be liquidated damages associated with

Please see Amendment 0009.

All milestone dates and Liquidated Damages have been updated.

Milestones 1, 2, 3, 4 & 5?

417 S-001 CLWS

Cast-In-

Place Concrete

Reinforcing steel required on this job must conform to ASTM A615 Deformed Bars (Grade 60). This section does not specify if the steel shall be plain, galvanized or epoxy coated. Please specify reinforcing steel coating requirements if any.

Provide plain reinforcing bars without coating.

418 2 12 00 01.00 20 1.3.1.d

Ref. 12 00 01.00 20 para 1.3.1.d "No schedule extensions will be granted if the option is awarded at least six months prior to the contract completion date". FF&E is required for the Ordnance Operations and Sentry Buildings as part of Milestone 1 and 4, respectively. Please confirm if the intent would be to award FF&E package prior to the required milestone completion dates for the Operations and Sentry Buildings. If so please confirm timing of this award so it can be included within the bid schedule. If the FF&E is awarded within 6 months of the overall project contract completion date please confirm how the FF&E would relate to the completion of milestone 1 and 4.

The intent is to award FF&E package prior to Milestones 1 and 4 completion dates with sufficient time for FF&E procurement and installation. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E product without impacting on the project completion date. General Contractor is advised to validate procurement, manufacturer production, delivery and installation durations with FF&E dealer/subcontractor to determine appropriate duration to incorporate into project schedule.

If the government decides to award the option item with less than six months prior to the contract completion date, the FF&E installation would need to occur after the Milestones 1 and 4 completion dates. This path is not a preferred option for timely tenant occupancy.

419 3 09 97 13.27 1.4.3

Ref. 09 97 13.27 para

1.4.3 which provides qualifications for the QC specialist coating inspector, Abrasive Blasting Individual, Testing Laboratory for

Please see Amendment 0009.

Qualifications for coating applicator have been revised.

Coatings and Abrasives.

There is no qualification requirements detailed for the coating applicator. Please confirm qualifications for high performance coating application.

427 31 23 09 00 3.5.6

Ref. 23 09 00 Para 3.5.6 which provides Table III for the Sequencing of PVT Testing Activities.

Table III includes item #4 and 5 which relate to the Cx Functional Performance testing.

PPI 367 confirmed that the only building to be commissioned is the Ordnance Operations Building. It is assumed that the activities listed in Table III would apply to the Sentry Building and CLWS Magazines as well due to the control systems at these buildings. Do all of these activities within Table III apply to both the Sentry Building and CLWS magazines?

Please confirm.

The controls performance verification testing sequence of testing activities applies to the Operation Support Bldg., Sentry, and CLWS magazines.

Each of the 17 sequences shall apply to each building.

428 CS-501 C3 N/A

Ref. drawing CS-501 detail C3. Is it correct to assume that the size and spacing of the dowels at the transverse contraction joints match those at the longitudinal contraction joints depicted in the typical concrete pavement joint detail C3/CS501

A 1" diameter dowel, 16" long, spaced 12" O.C. is to be used for each joint type indicated in the detail.

429 CS-502 C4 N/A

Ref. drawing CS-501 detail C3. Is it correct to assume that the dowel specified in the longitudinal contraction joint detail C3/CS501 will also be required at the construction and expansion joint locations.

A 1" diameter dowel, 16" long, spaced 12" O.C. is to be used for each joint type indicated in the detail.

430 12 33 13 13.06 2.3.4.2

Ref. 32 13 13.06 para

2.3.4.3 reference a slip form paver for the installation of concrete paving. Based on site layout plans CS102 and CS103, dowel baskets are called out and detailed for both the longitudinal and transverse conditions at all contraction joints.

Based on the provided layout, this makes installation difficult using the concrete paver. Reference spec section 2.3.4.3 references that laser screeds will not be allowed as another type of finishing. Based on the layouts of the contraction joints presently shown, this would be a perfect application for a laser screed. Please advise if a laser screed would be a viable alternative to the slip form paver, based on the designed contraction joints

Laser screeds will not be allowed on the project as specified in Section 32 13 13.06, Paragraph 2.3.4.3.

431 10 32 13 13.06 2.2

Ref. 32 13 13.06 para

2.2 Mix Design. The

mix design specifies a minimum flexural strength of 650 psi at 28 days. However, there is no compressive strength defined for the mix.

Please provide the compressive strength requirement for the concrete pavement.

Section 32 13 13.06 is specifically tailored for flexural strength design, and bids should be based on the flexural strength of the concrete as specified.

432 CD103

Ref. Existing Concrete Paving - Keynote 5 instructs bidders to remove full depth, please confirm how thick the pad is.

For bidding purposes an 8" thick welded wire fabric reinforced concrete surface, with doweled joints, on a 6" aggregate base should be used.

433 01 14 00 1.3

Reference is made to spec section 01 14 00 paragraph 1.3 SPECIAL

SCHEDULING

REQUIREMENTS as provided in Amendment 0007. This section provides a table of milestones. If there are to be liquidated damages associated with these milestones, could they be applied concurrently? If the contractor worked extended beyond two milestones, would there be LDs of $12,206.61 x 2 or $24,413.22 per day?

Please see Amendment 0009.

All milestone dates and Liquidated Damages have been updated.

434 2 12 00 01.00 20 1.3.1.d

Ref. 12 00 01.00 20 para 1.3.1.d "No schedule extensions will be granted if the option is awarded at least six months prior to the contract completion date". FF&E is required for the Ordnance Operations and Sentry Buildings as part of Milestone 1 and 4, respectively. Please confirm if the intent would be to award FF&E package prior to the required milestone completion dates for the Operations and Sentry Buildings. If so please confirm timing of this award so it can be included within the bid schedule. If the FF&E is awarded within 6 months of the overall project contract completion date please confirm how the FF&E would relate to the completion of milestone 1 and 4.

The intent is to award FF&E package prior Milestones 1 and 4 completion dates with sufficient time for FF&E procurement and installation. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E product without impacting on the project completion date. GC is advised to validate procurement, manufacturer production, delivery and installation durations with FF&E dealer/subcontractor to determine appropriate duration to incorporate into project schedule.

If the government decides to award the option item with less than six months prior to the contract completion date, the FF&E installation would need to occur after the Milestones 1 and 4 completion dates. This path is not a preferred option for timely tenant occupancy.

435 3 09 97 13.27 1.4.3

Ref. 09 97 13.27 para

1.4.3 which provides qualifications for the QC specialist coating

Please see Amendment 0009.

Qualifications for coating applicator have been revised.

inspector, Abrasive…

This is the start of the file's text. The full file is on GovTribe.