This is a Justification and Approval (J&A) document for use of other than full and open competition in federal contracting.
Naval Facilities Engineering Systems Command, Mid-Atlantic (NAVFAC MIDLANT) seeks authorization to use brand name specifications for stormwater management equipment manufactured by Contech Engineered Solutions in solicitation N4008526R0004, a Design Bid Build project for the Weapons Magazine & Ordnance Operations Facility at Naval Submarine Base, New London, Connecticut. The required products include three Underground Stormwater Quality (SWQ) Chambers, one Underground Detention Chamber, three Diversion Manholes, and three Hydrodynamic Separators. The broader construction project encompasses six Containerized Long Weapons Storage (CLWS) units, two Box C and one Box D earth-covered high-explosive magazines with overhead cranes, a new Ordnance Operations building, Truck Inspection and Sentry buildings, and demolition of 18 existing magazines and two buildings. The estimated total project value is redacted, with a portion designated for the brand name stormwater supplies. Work must be completed within 1,587 days after contract award and will be funded by FY24, FY26, and FY27 Military Construction, Navy (MCON) funds.
The justification cites statutory authority under 10 U.S.C. 3204(a)(1) for limited supplier use, based on the requirement that these specific Contech products are necessary to meet Connecticut Department of Environmental Protection (DEEP) stormwater management regulatory requirements within the site's space constraints. A sources sought notice was published on Sam.gov on October 1, 2025, with a response deadline of October 8, 2025, which resulted in no responses. The Contracting Officer will determine fair and reasonable pricing using techniques including RFP price comparisons, Independent Government Cost Estimates, historical data, and market surveys. The acquisition will be solicited as an unrestricted full and open construction solicitation as authorized by an approved DD2579 dated November 21, 2025.
View the file
Other files
Show 40 more
Latest 50 of 81 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND, MID-ATLANTIC
9324 VIRGINIA AVENUE
NORFOLK VIRGINIA 23511-3095
J&A No. ML-26-15
CON/322
JUSTIFICATION AND APPROVAL
FOR USE OF OTHER THAN FULL AND OPEN COMPETITION
1. Contracting Activity.
The contracting activity is Naval Facilities Engineering Systems Command, Mid-Atlantic (NAVFAC
MIDLANT)
2. Description of the Action Being Approved.
This Justification and Approval (J&A) authorizes the use of brand name specifications for three (3) Underground Stormwater Quality (SWQ) Chambers, one (1) Underground Detention Chamber, three (3) Diversion manholes, and three (3) Hydrodynamic Separators manufactured by Contech Engineered Solutions in solicitation N4008526R0004, Design Bid Build P1102 Weapons Magazine & Ordnance Operations Facility Naval Submarine Base, New London, Connecticut.
3. Description of Supplies/Services.
The intent of solicitation N4008526R0004 Design Bid Build P1102 Weapons Magazine & Ordnance Operations Facility Naval Submarine Base, New London, Connecticut is to construct six (6) Containerized Long Weapons Storage (CLWS), two (2) Box C, and one (1) Box D earth-covered, high-explosive magazines including overhead cranes, and incidental related work. Work also includes construction of new Ordnance Operations building, Truck Inspection, Sentry building, and demolition of 18 existing magazines, Bldg. 524, and Bldg. 393.
The solicitation will include brand name specifications for three (3) Underground Stormwater Quality (SWQ) Chambers, one (1) Underground Detention Chamber, three (3) Diversion manholes, and three
(3) Hydrodynamic Separators manufactured by Contech Engineered Solutions.
This acquisition will solicit proposals as an unrestricted full and open, stand-alone construction solicitation as authorized by the approved DD2579 on 21 November 2025. The estimated value of the work included in the construction solicitation is approximately , of which is estimated for the brand name supply. The project will be funded by FY24, FY26, and FY27 Military Construction, Navy (MCON) funds for construction. The work under this contract is required to be completed within 1587 after contract award.
The products listed below are required to provide stormwater quality management controls for the entire site:
Product: Reason: Cost:
Contech Engineering Solutions Underground Stormwater Quality Chamber
Required to meet stormwater management regulatory requirements set forth by Connecticut DEEP per unit. Total quantity of 3 units =
J&A No. ML-26-15
CON/322
For the reasons set forth in Paragraph 5, NAVFAC Mid-Atlantic has no plans at this time to compete future contracts for the types of supplies/services covered by this document. If another potential source emerges, NAVFAC Mid-Atlantic will assess whether competition for future requirements is feasible.