ATTACHMENT Q - NRZ_Checklist-POAM_Items.pdf
PDF 56 KB Posted
- Solicitation number
- N4008526R0004
About this file
This is a NAVFAC Red Zone (NRZ) Checklist/Plan of Action and Milestones (POAM) document designed to track the status of critical activities required for Basis of Delivery (BOD) and facility acceptance and turnover to prevent project delays. The checklist is organized into three sections by responsible party: Contractor Responsibility (Section 1), Client Responsibility (Section 2), and NAVFAC Responsibility (Section 3).
Section 1 outlines contractor obligations organized into two categories: activities required for facility delivery and activities required for contract closeout. Facility delivery activities include final connections for electrical, water, and gas systems; critical system startups and testing (DALT duct leakage, TABS air balancing, ACATS controls, electrical systems, generators, plumbing/backflow, elevators, boilers, cranes, and fire alarm/sprinkler systems); superchlorination of potable water; NMCI connections and IT systems testing; telecommunications connections; final commissioning; system training of Navy personnel; pre-warranty conferences; punch list completion; and inspections leading to BOD/Use and Possession. Contract closeout activities include delivery of Operations & Maintenance (O&M) manuals, product warranties, LEED documentation, energy sustainability records, site restoration, final landscaping, spare parts, as-built drawings, final demobilization and cleanup, and project closeout meetings.
Section 2 identifies client responsibilities for facility delivery, including keying plan meetings, telecommunications installation, modification of service contracts, NMCI or network installations, Government Furnished Equipment (GFE) status tracking, client-provided equipment installation, intrusion detection systems testing, secure network installations, and training attendance. Contract closeout items for the client include planned user move-in and ribbon-cutting ceremonies. Section 3 details NAVFAC's verification, certification, and administrative responsibilities, including coordination of final utility connections, performance verification of generators and transformers, certification of elevators and cranes, training coordination, inspections, BOD documentation, contractor evaluations, permit closeouts, and warranty documentation transfer to Facilities Management Services (FMS). Each section includes columns for points of contact, scheduled completion dates, actual completion dates, and notes to track progress and ensure comprehensive completion of all critical activities.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC Red Zone (NRZ) Checklist/POAM
The NRZ Checklist/POAM is a tool to track the status of critical activities required for BOD to help ensure their timely completion to prevent delays with the facility acceptance and turnover.
The critical activities are organized by section according to the responsible party (i.e. Contractor, Client, and
NAVFAC)
Critical items missing from this list should be added as necessary to ensure the list is comprehensive.
Likewise, unnecessary items should be deleted.
Any critical items left off the NRZ Checklist that are later identified after initial NRZ meeting is conducted should be added immediately so their progress can be tracked.
A copy of the NRZ Checklist/POAM shall be maintained in the contract file.
Section 1
Contractor Responsibility Critical Activities
Point of Contact
Sched Comp Date
Actual Comp Date
Notes
A. Required for Facility Delivery:
Final Electrical Connections Final Water Connections Final Gas Connections Critical System Start-up:
System:
System:
DALT (duct leakage) Testing TABS (air balancing) Testing ACATS (controls) Testing Electrical Systems Testing Generator Testing Superchlorination of potable water systems Plumbing/backflow Testing Elevator Testing Boiler Testing Crane Testing Fire Alarm/Sprinkler Testing Keying Plan Meeting Deliver Lockset Cores NMCI Connections/IT Systems Testing IDS & SCIF Testing Telecommunications Connections & Test Final Commissioning System Training of Navy Personnel System:
System:
Pre-Warranty Conference Contractor’s Pre Final Punch List Complete Pre Final Inspection Punch List Final Inspection BOD/Use and Possession
B. Required for Contract Close-out:
Delivery of O&M Manuals Delivery of Product Warranties LEED Documentation Energy & Sustainability Record Card Site Restoration Final Landscaping Spare Parts, Extra Stock, Special Tools, etc As-Built Drawings Final Demobilization and Clean-up Temp Construction Fence Removed Project Close-out Meeting Complete DD1354 Close-out Storm Water Permit 2nd Season TABS
Section 2
Client Responsibility Critical Activities
Point of Contact
Sched Comp Date
Actual Comp Date
Notes
A. Required for Facility Delivery:
Keying Plan Meeting Telecommunication install Mod service contracts for Phone/Utilities/ Custodial/Grounds
NMCI Installations or other networks GFE status/delivery schedule (GFCI, GFGI) Client provided equipment SELF installed Client provided equipment KTR installed Intrusion Detection Systems Test Secure Network Installations Attend Training
Planned User Move-in Ribbon-cutting ceremony
Section 3
NAVFAC Responsibility Critical Activities
Point of Contact
Sched Comp Date
Actual Comp Date
Notes
A. Required for Facility Delivery:
Coordinate Final Utility Connections Generator Performance Verification Transformer Performance Verification DALT Verification 1st Season TABs Verification ACATS Performance Verification Elevator Certification Crane Certification Boiler Certification Fire Alarm/Sprinkler Test IDS & SCIF Test Keying plan to contractor Locket Cores installed Training Coordinated/Scheduled with FMS O&Ms to FMS Client walk-thru Inspection Pre-Final Inspection Final Inspection BOD/Use and Possession
BOD Letter to Contractor Acceptance Letter to Client DD 1354 Signed & turned over to RPAO Closeout permits (e.g., NPDES) Contractor Evaluations (CCASS) Complete Finalize Outstanding Contract Mods Process recycled/recovered materials report BOD (A) entered into eContracts Inform PM of BOD Assist PM with AE Evaluation (ACASS) Warranty documentation to FMS As-Builts to FMS 2nd Season TABs Report Review Annual Elevator Maintenance Complete