About this file

This document contains Pre-Proposal Inquiry (PPI) responses to questions submitted by potential contractors regarding a federal construction solicitation. The questions and government responses address pricing, scheduling, wage determination, site visit procedures, and administrative submission requirements.

Key clarifications include: Line Item 0009, Option 8 requires bidding a per-hour unit price for 100% work shutdown per the RFP as written, despite contractor concerns about cost variability across project phases. For FF&E (Line Items 0005, 0006, and 0007), contractors must bid per the RFP, with clarification that the FF&E option will be awarded at least six months prior to contract completion for procurement through installation, while FF&E design must be completed nine months prior to Beneficial Occupancy Date per specification section 12 00 01.00 20. The wage determination applicable to the New London, Connecticut project location is addressed in Amendment 0002. CAD files will be provided at time of award, with estimated award occurring around August 2026. The solicitation is located at a naval facility requiring site visit attendance; attendees must email the Point of Contact before 1300 on March 25, 2026, bring completed SECNAV 5512 forms and identification, and arrive no later than 0730, with the gate opening at 0545. Financial statements and working capital information may be submitted as password-protected files in PIEE with passwords provided separately. The solicitation documents are not classified as Controlled Unclassified Information (CUI).

View the file

Other files

File Type Posted
Amend 0014 Spec 1667770.pdf PDF
N4008526R00040013 SF 30.pdf PDF
N4008526R00040012 SF 30.pdf PDF
N4008526R00040010 SF 30.pdf PDF
ATTACHMENT V - SUBASEINST 8020.1G.pdf PDF
1667770spc08.25.26.pdf PDF
ATTACHMENT T - P1102_PROD.xlsx XLSX spreadsheet
P1102_GC101 - CONSTRUCTION PHASING PLAN - PHASE 1.pdf PDF
Revised Attachment H - Price Proposal Form REV 3.docx DOCX document
N4008526R00040008 SF 30.pdf PDF
Revised Attachment H Price Proposal Form REV2.docx DOCX document
P-1102_Amend 0007_Specifications.pdf PDF
P-1102_Amend 0007_Drawings1of3.pdf PDF
ATTACHMENT S - UPDATED Wage Determination.pdf PDF
N4008526R00040007 SF 30.pdf PDF
JA ML-26-14 P1102 Rock Fall_Redacted.pdf PDF
ATTACHMENT P - NAVSEA OP 5 REV 9.pdf PDF
ATTACHMENT O - MK48 STORAGE FACILITY.pdf PDF
ATTACHMENT M - Permits Record of Decision (PROD).pdf PDF
UPDATED ATTACHMENT H Price Proposal Form REV1.docx DOCX document
P1102_Amend 0006_Specifications_rev.pdf PDF
N4008526R00040006 SF 30.pdf PDF
N4008526R00040005 SF 30.pdf PDF
Attachment G- Small Business Subcontracting Plan (SBSP) Rev.pdf PDF
Amendment N4008526R00040004 SF 30.pdf PDF
Attachment F-Small Business Participation Commitment.pdf PDF
Amendment 0003PPIs.pdf PDF
N4008526R00040003 SF 30.pdf PDF
Attachment K - P1102 Site Visit Log.pdf PDF
N4008526R00040002 SF 30.pdf PDF
Attachment J - SECNAV 5512.pdf PDF
N4008526R00040001 SF 30.pdf PDF
Solicitation - N4008526R0004.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment E - Historical Small Business Utilization.pdf PDF
Attachment F - Small Business Participation Commitment.pdf PDF
FINAL DESIGN_1667770dwg1of2Sentry.pdf PDF
FINAL DESIGN_1667770dwg1of1TypeG.pdf PDF
FINAL DESIGN_1667770dwg1of1TypeH.pdf PDF
Attachment A - Pre Proposal Inquiry Log.xlsx XLSX spreadsheet
Attachment H - P1102 Price Proposal Form.pdf PDF
FINAL DESIGN_1667770dwg1of2CLWS.pdf PDF
FINAL DESIGN_1667770dwg2of2CLWS.pdf PDF
FINAL DESIGN_1667770dwg3of3Operations.pdf PDF
P-1102_1667770spc2of3.pdf.pdf PDF
Attachment C - Construction Experience Project Data.pdf PDF
Attachment G - Individual Small Business Subcontracting Plan.pdf PDF
FINAL DESIGN_1667770dwg1of3Operations.pdf PDF
FINAL DESIGN_1667770dwg1of4Site.pdf PDF
FINAL DESIGN_1667770dwg4of4Site.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Pre- proposal Inquiry Responses

PPI

Page Section Paragraph Question Response

Attachment H - Price Proposal Form

RFP

Line Item 0009, Option Item No. 8, requests a per hour unit price for 100% work shutdown.

The hourly cost of this this impact will vary greatly depending on the phase of the project and how much manpower and how many pieces of equipment are working at any given time. The manpower and equipment needs for this project will not be linear across its duration. Given this significant variability, the Contractor will not be able to provide a single price, without being overly conservative.

It is recommended that the Government change this Option from a unit price to an allowance. This will allow for the Government to pay for the actual cost of the impact based upon actual conditions at the time of the occurrence.

Please bid per RFP.

Attachment H - Price Proposal Form

Ref. BID NOTES FOR AV AND FF&E

(LINE ITEMS 0005, 0006, AND 0007),

Item f.

It is recommended that the Government extend the noted award of these options from "at least six months prior to the contract completion date" to "at least nine months prior to the contract completion date".

From the award of the option, the Contractor must:

- Contract with an Interior Designer

- Obtain NAVFAC approval of the Contractor's Interior Designer's qualifications

- Execute the FF&E design services

- Obtain approval of the Final FF&E Procurement Package

- Procure the FF&E materials

- Deliver and install the FF&E materials

It is unlikely that all of these steps can be completed within a six month timeframe.

For Line Items 0005 (A/V) and 0007 (A/V), bid per the RFP.

Clarification for Line Item 0007 (FF&E) is as follows: The FF&E option will be awarded at least 6 months prior to contract completion. The FF&E option is for procurement to installation. The rest of FF&E is detailed in specification section 12 00 01.00 20 to include information that the FF&E design must be completed 9 months prior to BOD.

3 Amendment

Wage Determination

The wage determination issued with Amendment 1 is listed as applying to "Rhode Island Statewide". Please confirm that this is

Please see Amendment 0002.

the correct wage determination for this project at New London, CT.

page 3-15

4. Wage Determination

Would you please confirm that, per addendum 01, the wage determination to be used for this project in New London CT is a Rhode Island wage determination?

Please see Amendment 0002.

Would you please provide CAD files for this project.

CAD files will be provided at time of award.

00 70 00

The project Solicitation provides for a period of 15 Calendar Days from date of lead time event to begin performing this work. Would you please advise when you intend to issue this award so we can prepare a proposal schedule?

Award is estimated to occur around August 2026, however, that is subject to change.

Just as a precaution, we do not see that anything has been designated as CUI, but can you please confirm that nothing here is considered CUI?

Solicitation Documents are not CUI.

Amendment of

Solicitation

00 21 00 4.1 Site Visit

Please clarify a few points regarding the upcoming site visit. a) are the attendees required to submit SECNAV 5512 ahead of the site visit, or should they just bring a completed form, along with the required forms of identifications, with them on the day of the visit? b) is it necessary to make a badging appointment ahead of the site visit, or how early would you recommend the attendees arrive the morning of in order to gain access prior to the 10:00AM start?

a) Attendees do not submit SECNAV 5512 ahead of site visit.

Attendees need to bring completed SECNAV 5512 form, along with the required forms of identifications with them on the day of the visit.

However, you do need to email the POC with information provided on Amendment 0001 before 1300, 25 March 2026.

b) Attendees do not make a badging appointment ahead of the site visit. The gate opens at 0545. It is recommended to arrive no later than 0730.

11 3.3 9

The Solicitation, “Additional Information to be Submitted with Price Proposal Package”, Item 2 requests the last three years of financial statements and working capital information. This information is considered highly confidential. Can these documents be submitted as a separate password-protected file in PIEE, while providing the password in a separate email to Angela Clifton at angela.j.clifton2.civ@us.navy.mil?

This is acceptable.