This document summarizes an infection control risk assessment plan for renovations on the second floor of a Veterans Affairs medical center. The plan requires contractors to install sticky mats at entrances to work areas, 6 mil fire-retardant plastic sheeting with zipper openings, and negative air pressure machines to run continuously. Dust barriers must extend above ceilings and seal to overhead structures to meet one-hour fire barrier standards. Air quality monitoring must occur before, during, and after construction. The related federal contract opportunity is for renovations to Ward 1B at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee under solicitation number 36C24923R0114.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GI 03.01
PROVIDE STICKY MATS AT
ENTRANCE TO ANY ROOM WITH
WORK BEING DONE. TYPICAL TO
ALL WORK ON SECOND FLOOR
PROVIDE STICKY MATS AT
ENTRANCE TO ANY ROOM WITH
WORK BEING DONE. TYPICAL TO
ALL WORK ON SECOND FLOOR
SUPPLY AND INSTALL 6 MIL HEAVY
DUTY, REINFORCED,
FIRE-RETARDANT POLY SHEETING
(VISQUEEN). PLASTIC SHEET SHALL
BE FULLY SEALED AT PERIMETER.
PROVIDE ZIPPER OPENING FOR
AREAS AFFECTED BY WORK.
SUPPLY AND INSTALL 6 MIL HEAVY
DUTY, REINFORCED,
FIRE-RETARDANT POLY SHEETING
(VISQUEEN). PLASTIC SHEET SHALL
BE FULLY SEALED AT PERIMETER.
PROVIDE ZIPPER OPENING FOR
AREAS AFFECTED BY WORK.
REFER TO
NOTE 1 BELOW
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2019
TLC No.:
www.tlc-engineers.com
118626
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg.
PROJECT TEAM:
Office of
Construction and Facilities Management o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
KEYPLAN
MURFREESBORO, TN
615.370.8500
615.370.8530 hfrdesign.com
214 Centerview Drive Suite 300 Brentwood, TN 37027
BLDG 2
BLDG 1
BLDG 9
Phase
FULLY SPRINKLERED
C U s e rs \a tr a y lo r\ D o c u m e n ts
\M b o ro V
A W a rd b
R e n o a tr a y lo r2 X
N D
H .r v t
/1
/2
:2
:2
P
M
04-14-2023
626A4-19-101
GI 03.01
AE RENOVATE WARD 1BSECOND FLOOR ICRA PLAN
AT
HFR Project No: 2019056
100% CONSTRUCTION
DOCUMENTS
1 SECOND FLOOR ICRA PLAN
ICRA NOTES:
1. WHEN PREFORMING DEMO AND NEW WORK IN EXISTING CORRIDORS AND
ROOMS, PROTECT ALL FURNITURE AND EQUIPMENT WITH STRING
REINFORCED 6 MIL PLASTIC SHEET COVERING. CAREFULLY REMOVE
EXISTING ACOUSTICAL CEILING TILES AS REQUIRED FOR NEW WORK. ALL
OTHER ITEMS ARE TO REMAIN IN PLACE AND PROTECTED FROM
CONSTRUCTION REQUIRED FOR ITEMS THAT PENETRATE THE SLAB. AFTER
INSTALLATION OF THESE ITEMS , GC TO INSTALL NEW ACOUSTICAL CEILING
TILES THAT MATCH ORIGINAL CEILING TILE. AFTER REPLACEMENT OF ALL
DAMAGED CEILING, GRID AND ALL OTHER EXISTING ITEMS INSTALLED IN
EXISTING CEILING SUCH AS LIGHT FIXTURES, I.T. DEVICES, FIRE ALARM
DEVICES, SPRINKLER HEADS, ETC. WHEN WORK IS COMPLETED, INSTALL
NEW ACOUSTICAL CEILING TILES. IF THERE IS ANY DAMAGE IN OR ABOVE,
CEILING NEEDS TO BE REPLACED. AREA OF WORK TO BE COMPLETELY
SWEPT AND CLEANED PRIOR TO LEAVING THE SITE FOR THE DAY. WORK IN
EXISTING ROOMS AND CORRIDORS SHALL BE OFF-SHIFT AND WILL REQUIRE
AN INFECTION CONTROL PLAN TO BE SUBMITTED FOR COR APPROVAL.
WHEN PERFORMING DEMOLITION AND NEW WORK THRU ANY AREA OF
WORK, CAREFULLY REMOVE THE AMOUNT OF EXISTING ACOUSTICAL
CEILING TILES AND GRIDS AS REQUIRED FOR NEW WORK. AT THE END OF
THE SHIFT INSTALL THE ACOUSTICAL CEILING TILES AND GRIDS BACK TO
ITS ORIGINAL STATE. AREA OF WORK TO BE COMPLETELY SWEPT AND
CLEANED PRIOR TO LEAVING THE SITE FOR THE DAY.
2. COORDINATE WORK WITH ZONES ON AE 01.00. COORDINATE FINAL
SCHEDULE WITH COR
3. PROVIDE STICKY MATS INTO ANY ROOM THAT REQUIRES WORK
4. SUPPLY AND INSTALL 6 MIL HEAVY DUTY, REINFORCED, FIRE-RETARDANT
POLY SHEETING (VISQUEEN). PLASTIC SHEET SHALL BE FULLY SEALED AT
PERIMETER. PROVIDE ZIPPER OPENING FOR AREAS AFFECTED BY WORK.
2 SECOND FLOOR TYPICAL ICRA LAYOUT
0 5' 10'
0 2' 4' 6'
10. ALL DEMOLITION, RENOVATION AND CONSTRUCTION AREAS ADJACENT TO OCCUPIED AREAS OR OTHERWISE CONNECTED TO OCCUPIED AREAS ARE TO BE MAINTAINED AT A RELATIVE NEGATIVE AIR PRESSURE SO AIRBORNE DUST, PARTICLES, FUMES, SMALLS, MOLD SPORES, ETC. DO NOT FLOW INTO OCCUPIED AREAS. NEGATIVE AIR PRESSURE SHALL BE MAINTAINED CONTINUOUS FROM BEGINNING OF DEMOLITION, RENOVATION AND CONSTRUCTION UNTIL COMPLETION OF WORK AND FINAL CLEANING.
NEGATIVE PRESSURE IS NOT TO BE SHUT OFF DURING NON-WORKING HOURS. NEGATIVE AIR PRESSURE MACHINES ARE NOT TO BE SHUT OFF FOR MAINTENANCE OR OTHER REASONS UNTIL A REPLACEMENT
MACHINE IS RUNNING TO ALLOW A QUICK SWITCH OVER.
9. DUST BARRIERS BETWEEN DEMOLITION / CONSTRUCTION ZONE AND OCCUPIED AREAS ARE TO EXTEND
ABOVE CEILING AND SEALED TO UNDERSIDE OF STRUCTURE ABOVE. RESULTING TEMPORARY
CONSTRUCTION SHALL MEET 1HR FIRE BARRIER REQUIREMENTS U.N.O.
8. PROVIDE STICKY MATS AT ALL CONSTRUCTION ENTRANCES AND REPLACE ON REGULAR BASIS TO
ENSURE DEBRIS IS NOT TRANSFERRED FROM CONSTRUCTION SIDE OF BARRIER TO CLEAN
(NON-CONSTRUCTION) SIDE OF BARRIER.
7. SITE SHALL BE INSPECTED BY OWNER'S INFECTION CONTROL OFFICER UPON COMPLETION OF
BARRIERS AND PRIOR TO START OF CONSTRUCTION.
6. PROVIDE REQUIRED TEMPORARY DUST BARRIERS, BARRICADES, INFECTION CONTROL MEASURES PER
THE COMPLETED RISK ASSESSMENT, ETC. TO PROTECT PERSONNEL AND ADJACENT SPACES.
5. WET MOP WORK AREA THOROUGHLY WITH DISINFECTANT UPON COMPLETION OF PROJECT.
4. INSTALL HEPA FILTERED NEGATIVE AIR MACHINE TO RUN 24 HOURS PER DAY UNTIL CONSTRUCTION IS
COMPLETED.
3. CONSTRUCTION DEBRIS SHALL BE TRANSPORTED IN A WHEELED TILT TRUCK WITH DOME LID AT A MIN.
2. AIR QUALITY MONITOR TESTING SHALL BE PERFORMED BEFORE THE START OF CONSTRUCTION, PERIODICALLY DURING THE CONSTRUCTION PROCESS, AND AT COMPLETION OF CONSTRUCTION.
1. REFER TO INFECTION CONTROL RISK ASSESSMENT PERFORMED BY FACILITIES INFECTION CONTROL
OFFICER FOR SPECIFIC ICRA LEVEL & REQUIREMENTS
GENERAL ICRA NOTES
No. Date Description
| Sheets |
| AD 01.01 - THIRD FLOOR DEMOLITION PLAN - OVERALL |
| AE 01.00 - SECOND FLOOR PLAN AND REFLECTED CEILING PLAN |
| AE 01.01 - FOURTH FLOOR/ATTIC PLAN |
| AE 01.03 - THIRD FLOOR OVERALL PLAN |
| AE 01.11 - PARTIAL THIRD FLOOR PLAN - PART A NOTED |
| AE 01.12 - PARTIAL THIRD FLOOR PLAN - PART B NOTED |
| AE 01.13 - PARTIAL THIRD FLOOR PLAN - PART C NOTED |
| AE 01.14 - PARTIAL THIRD FLOOR PLAN - PART A DIMENSIONED |
| AE 01.15 - PARTIAL THIRD FLOOR PLAN - PART B DIMENSIONED |
| AE 01.16 - PARTIAL THIRD FLOOR PLAN - PART C DIMENSIONED |
| AE 02.01 - ENLARGED PLANS AND REFLECTED CEILING PLANS |
| AE 02.02 - ENLARGED PLANS AND REFLECTED CEILING PLANS |
| AE 02.03 - ENLARGED TOILET PLANS AND ELEVATIONS |
| AE 03.01 - DOOR ELEVATIONS, SCHEDULE, & NOTES |
| AE 03.02 - DOOR DETAILS |
| AE 03.03 - WINDOW DETAILS |
| AE 08.01 - MISC. DETAILS |
| AE 08.02 - MISC. DETAILS |
| AE 08.03 - MISC. DETAILS |
| AE 08.04 - MISC. DETAILS |
| AE 08.05 - MISC. INTERIOR DETAILS |
| AE 08.06 - MISC CEILING DETAILS |
| AE 09.01 - INTERIOR ELEVATIONS |
| AE 09.02 - INTERIOR ELEVATIONS |
| AE 09.03 - CORRIDOR ELEVATIONS |
| AE 09.04 - CORRIDOR ELEVATIONS |
| AE 09.05 - 3D VIEWS |
| AE 10.01 - CASEWORK SECTIONS AND DETAILS |
| AE 10.02 - CASEWORK SECTIONS AND DETAILS |
| AE 11.01 - THIRD FLOOR REFLECTED CEILING PLAN - OVERALL |
| AE 11.10 - THIRD FLOOR RCP - PART A |
| AE 11.11 - THIRD FLOOR RCP - PART B |
| AE 11.12 - THIRD FLOOR RCP - PART C |
| AE 12.01A - EQUIPMENT PLANS |
| AE 12.01B - EQUIPMENT PLANS |
| AE 12.01C - EQUIPMENT PLANS |
| AE 12.02 - EQUIPMENT PLANS - PATIENT ROOMS AREA B |
| AE 12.02B - EQUIPMENT PLANS - PATIENT ROOMS AREA C |
| GI 00.01 - COVER SHEET |
| GI 01.01 - GENERAL DATA |
| GI 01.02 - CONSTRUCTION STAGING PLAN |
| GI 01.10 - WALL TYPE DETAILS |
| GI 01.20 - ACCESSIBILITY DETAILS |
| GI 02.01 - THIRD FLOOR LIFE SAFETY PLAN - OVERALL |
| GI 03.01 - SECOND FLOOR ICRA PLAN |
| GI 03.02 - THIRD FLOOR ICRA PLAN |
| GI 04.01 - ACM DUCT WORK AND ACM PIPE INSULATION |
| GI 04.02 - LEAD PAINT AND TRANSITE PANELS |
| GI 05.01 - PHASING PLANS |
| IN 01.00 - THIRD FLOOR FINISH LEGEND |
| IN 01.02 - PARTIAL THIRD FLOOR FINISH PLAN - PART A |
| IN 01.03 - PARTIAL THIRD FLOOR FINISH PLAN - PART B |
| IN 01.04 - PARTIAL THIRD FLOOR FINISH PLAN - PART C |
| IN 01.05 - THIRD FLOOR PATTERN PLAN OVERALL |
| IN 01.06 - PARTIAL THIRD FLOOR PATTERN - PART A |
| IN 01.07 - PARTIAL THIRD FLOOR PATTERN - PART B |
| IN 01.08 - PARTIAL THIRD FLOOR PATTERN - PART C |
| IN 02.00 - THIRD FLOOR SIGNAGE LEGEND |
| IN 02.01 - THIRD FLOOR SIGNAGE SCHEDULE |
| IN 02.02 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART A |
| IN 02.03 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART B |
| IN 02.04 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART C |
| VN 01.00 - PATIENT LIFT VENDOR DRAWINGS |