GI 01-02 - CONSTRUCTION STAGING PLAN.pdf
PDF 179 KB Posted
- Attached to
- Z2DA--626A4-19-101 - Renovate Ward 1B at the Alvin C. York VA Medical Center, Murfreesboro, TN 37129
- Solicitation number
- 36C24923R0114
About this file
This document contains construction staging plans and specifications for renovations to Ward 1B at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee. The project involves demolishing portions of the third floor and renovating the second and third floors. The construction staging plan outlines where materials and equipment will be stored on site, including a primary staging area that will be assigned to the contractor for the duration of the project. It also specifies requirements for fencing, security, and maintaining cleanliness at the staging sites. The contractor will have no interior elevator access during construction and must transport all personnel and materials via the building exterior. Disturbed areas must be returned to their original condition upon completion. Three-phase 480V power will be provided for a buck hoist at the specified location.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Proposed buckhoist location
D2. Secondary dumpster site. Must meet all fencing and security requirements. May only be used during demolition phase.
D1. Primary Staging area. Will be assigned to contractor for duration of project. Contractor is responsible for mowing, maintaining cleanliness and order.
Staging Plan: Building 1 is an active Medical Facility. All care must be taken to provide a safe and clean environment. The contractor will have NO interior elevator access during construction and must make accommodation for manpower and materials to be lifted.Contractor must return all disturbed areas to original condition. Provide location for buck hoist power supply, 480V 3-phase power will be needed from the north end of building 1 at room 349.
VETERANS C
IR
CLEVETERANS CIRCLE
2 9
D2
D1
12 Cadillac Dr., Suite 150 Brentwood, TN 37027 P 615.297.4554
©Copyright 2019
TLC No.:
www.tlc-engineers.com
118626
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg.
PROJECT TEAM:
Office of
Construction and Facilities Management o n e e ig h th in c h o n e fo o t 1
B
A
C
D
E
F th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t
VA FORM 08-6231
1 2 3 4 5 6 87 9
F
E
D
C
B
A
97 8654321
Department of Veterans Affairs
MURFREESBORO, TN
615.370.8500
615.370.8530 hfrdesign.com
214 Centerview Drive Suite 300 Brentwood, TN 37027
Phase
FULLY SPRINKLERED
C U s e rs \a tr a y lo r\ D o c u m e n ts
\M b o ro V
A W a rd b
R e n o a tr a y lo r2 X
N D
H .r v t
/1
/2
:2
:0
P
M
04-14-2023
626A4-19-101
GI 01.02
AE RENOVATE WARD 1BCONSTRUCTION STAGING PLAN
AT
HFR Project No: 2019056
100% CONSTRUCTION
DOCUMENTS
No. Date Description
| Sheets |
| AD 01.01 - THIRD FLOOR DEMOLITION PLAN - OVERALL |
| AE 01.00 - SECOND FLOOR PLAN AND REFLECTED CEILING PLAN |
| AE 01.01 - FOURTH FLOOR/ATTIC PLAN |
| AE 01.03 - THIRD FLOOR OVERALL PLAN |
| AE 01.11 - PARTIAL THIRD FLOOR PLAN - PART A NOTED |
| AE 01.12 - PARTIAL THIRD FLOOR PLAN - PART B NOTED |
| AE 01.13 - PARTIAL THIRD FLOOR PLAN - PART C NOTED |
| AE 01.14 - PARTIAL THIRD FLOOR PLAN - PART A DIMENSIONED |
| AE 01.15 - PARTIAL THIRD FLOOR PLAN - PART B DIMENSIONED |
| AE 01.16 - PARTIAL THIRD FLOOR PLAN - PART C DIMENSIONED |
| AE 02.01 - ENLARGED PLANS AND REFLECTED CEILING PLANS |
| AE 02.02 - ENLARGED PLANS AND REFLECTED CEILING PLANS |
| AE 02.03 - ENLARGED TOILET PLANS AND ELEVATIONS |
| AE 03.01 - DOOR ELEVATIONS, SCHEDULE, & NOTES |
| AE 03.02 - DOOR DETAILS |
| AE 03.03 - WINDOW DETAILS |
| AE 08.01 - MISC. DETAILS |
| AE 08.02 - MISC. DETAILS |
| AE 08.03 - MISC. DETAILS |
| AE 08.04 - MISC. DETAILS |
| AE 08.05 - MISC. INTERIOR DETAILS |
| AE 08.06 - MISC CEILING DETAILS |
| AE 09.01 - INTERIOR ELEVATIONS |
| AE 09.02 - INTERIOR ELEVATIONS |
| AE 09.03 - CORRIDOR ELEVATIONS |
| AE 09.04 - CORRIDOR ELEVATIONS |
| AE 09.05 - 3D VIEWS |
| AE 10.01 - CASEWORK SECTIONS AND DETAILS |
| AE 10.02 - CASEWORK SECTIONS AND DETAILS |
| AE 11.01 - THIRD FLOOR REFLECTED CEILING PLAN - OVERALL |
| AE 11.10 - THIRD FLOOR RCP - PART A |
| AE 11.11 - THIRD FLOOR RCP - PART B |
| AE 11.12 - THIRD FLOOR RCP - PART C |
| AE 12.01A - EQUIPMENT PLANS |
| AE 12.01B - EQUIPMENT PLANS |
| AE 12.01C - EQUIPMENT PLANS |
| AE 12.02 - EQUIPMENT PLANS - PATIENT ROOMS AREA B |
| AE 12.02B - EQUIPMENT PLANS - PATIENT ROOMS AREA C |
| GI 00.01 - COVER SHEET |
| GI 01.01 - GENERAL DATA |
| GI 01.02 - CONSTRUCTION STAGING PLAN |
| GI 01.10 - WALL TYPE DETAILS |
| GI 01.20 - ACCESSIBILITY DETAILS |
| GI 02.01 - THIRD FLOOR LIFE SAFETY PLAN - OVERALL |
| GI 03.01 - SECOND FLOOR ICRA PLAN |
| GI 03.02 - THIRD FLOOR ICRA PLAN |
| GI 04.01 - ACM DUCT WORK AND ACM PIPE INSULATION |
| GI 04.02 - LEAD PAINT AND TRANSITE PANELS |
| GI 05.01 - PHASING PLANS |
| IN 01.00 - THIRD FLOOR FINISH LEGEND |
| IN 01.02 - PARTIAL THIRD FLOOR FINISH PLAN - PART A |
| IN 01.03 - PARTIAL THIRD FLOOR FINISH PLAN - PART B |
| IN 01.04 - PARTIAL THIRD FLOOR FINISH PLAN - PART C |
| IN 01.05 - THIRD FLOOR PATTERN PLAN OVERALL |
| IN 01.06 - PARTIAL THIRD FLOOR PATTERN - PART A |
| IN 01.07 - PARTIAL THIRD FLOOR PATTERN - PART B |
| IN 01.08 - PARTIAL THIRD FLOOR PATTERN - PART C |
| IN 02.00 - THIRD FLOOR SIGNAGE LEGEND |
| IN 02.01 - THIRD FLOOR SIGNAGE SCHEDULE |
| IN 02.02 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART A |
| IN 02.03 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART B |
| IN 02.04 - PARTIAL THIRD FLOOR SIGNAGE PLAN - PART C |
| VN 01.00 - PATIENT LIFT VENDOR DRAWINGS |
File details come from the government source that posted it. Updated .