Task Assignment DC028B Summary
Task Assignment DC028B is a state contract entered into between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. to conduct site assessment activities at the Signature Cleaners site located at 9719-5 San Jose Boulevard in Jacksonville, Duval County, Florida. The task assignment is issued under Contract Number HW681 and was effective upon signature on December 12, 2022, with a completion date of September 1, 2023.
The scope of work authorizes CDM Smith Inc. to complete an initial site assessment including project management, underground utility survey, Stage I field investigation, Stage II field investigation, and preparation of a site assessment report. The total task assignment value is $96,194.58, payable on a fixed unit rate basis upon submittal and FDEP approval of deliverables. Specific invoice milestones include: Underground Utility Survey ($2,055.36) due January 15, 2023; Stage I Field Investigation Data Summary ($64,394.92) due March 15, 2023; Stage II Field Investigation Data Summary ($13,601.13) due April 15, 2023; and Site Assessment Report plus Project Management ($16,143.17) due May 31, 2023. The scope encompasses ten soil borings with laboratory analysis for volatile organic halocarbons, vapor extraction well installation with Modified Active Gas Sampling testing, direct-push groundwater profiling, monitoring well installation, and investigation-derived waste characterization and disposal. Subcontractors selected include Betts Environmental for drilling services ($30,033.30), Southeastern Surveying and Mapping for surveying ($2,465.00), Site Lines LLC for utility location ($800.00), and Erwin Remediation for investigation-derived waste disposal ($1,800.00).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW681
DC028B Completion September 1, 2023
This Task Assignment authorizes CDM Smith Inc. to conduct site assessment activities at the Signature Cleaners site located in Jacksonville, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on November 15, 2022.
Kevin Kane 850-245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
CDM Smith Inc.
CDM Smith Inc.
Shayne Wood 904-527-6703
ERIC_4556
9719 San Jose Boulevard, Jacksonville, Duval County
Signature Cleaners
✔ $ 96,194.58
$ 96,194.58
Scope of Work
Shayne Wood
Vice President
12/12/2022
Shayne Wood Digitally signed by Shayne Wood DN: C=US, E=woodsh@cdmsmith.com, CN=Shayne Wood Date: 2022.12.12 14:33:57-05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2022.12.09 13:15:42 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Underground Utility Survey 01/15/2023
Stage I Field Investigation Data Summary 03/15/2023
Stage II Field Investigation Data Summary 04/15/2023
Site Assessment Report + Project Management 05/31/2023
Subtask 2: Upon submittal and FDEP approval of the Underground Utility Survey $ 2,055.36
Subtask 3: Upon submittal and FDEP approval of the Stage I Field Investigation Data Summary $ 64,394.92
Subtask 4: Upon submittal and FDEP approval of the Stage II Field Investigation Data Summary $ 13,601.13
Subtasks 1 & 5: Upon submittal and FDEP approval of the Site Assessment Report + Project Management $ 16,143.17
$ 96,194.58
HW681
DC028B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW681 Contract File
FROM: Kevin Kane, Contract Manager
DATE: November 21, 2022
SUBJECT: Task Assignment DC028B
Signature Cleaners
ERIC_4566
Initial Site Assessment
This Task Assignment authorizes CDM Smith Inc. to conduct initial site assessment activities at the subject site in accordance with the November 15, 2022, revised cost proposal. CDM and the DEP confirmed on October 20, 2022, that a Site Access Agreement with the current real property owner of the subject site has been executed.
Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is automatically calculated at 13% of the direct labor.
Subtask 2: Site Survey and Site Preparation Three bids were solicited for utility location services Site Lines LLC was selected as the lowest responsive and responsible bidder. Southeastern Surveying and Mapping was selected to perform the site survey.
Subtasks 3 and 4: Stage I and II Field Investigations CDM Smith will complete ten (10) soil borings using hand augers. Concrete coring will be completed at each of the nine locations. The soil samples will be submitted for laboratory analysis by EPA Method 8260 for VOHs. CDM Smith assumes up to 40 samples will be collected. A duplicate sample will be collected at each interval for SPLP analysis. Those samples to be run for SPLP analysis will be identified based upon the initial analytical data. Costs associated with SPLPs are not included in this cost estimate and will be addressed via work change directive if determined necessary.
One (1) soil boring in the vicinity of the former drycleaning machine will be completed as a 1-inch diameter monitoring well and sampled for VOH analyses by EPA Method 8260. Five (5) of the soil borings will be completed as vapor extraction wells (VEW) for Modified Active Gas Sampling (MAGS™) testing. Two
(2) vapor monitoring points (VMPs) will be installed to assess radius of influence.
One (1) soil gas sample from each VEW will be submitted for TO-15 analysis.
Following MAGS™ testing, vertical groundwater profiling will be conducted at six
(6) locations using a direct-push technology (DPT). Groundwater samples will be collected, and laboratory analyzed for VOCs by EPA Method 8260. In addition, a continuous lithologic boring to 50’ below ground surface or refusal will be installed to obtain site-specific lithologic and stratigraphic information. Upon completion of the field events, the marked utilities and all boring locations will be surveyed.
The monitoring well locations will be finalized based on the Stage I results. Four
(4) monitoring wells will be installed. Prior to well installation, continuous soil cores will be collected to the total depth form each location. The wells will be purged and sampled for VOHs following installation and a full round of water levels will be collected to map the potentiometric surface. The monitoring wells will be surveyed at the completion of installation and investigation derived waste (IDW) will be characterized and transported off-site for disposal. CDM Smith estimates 14 soil drums and 4 water drums of nonhazardous IDW will be generated.
Ambient Technologies Inc. (ATI) provided the lowest original bid, however their bid did not include the required Geoprobe sampling activities cost, equipment decontamination costs, and IDW drum costs. ATI was contacted by CDM Smith to revise their original bid but declined so CDM Smith had to adapt line-item costs from the incomplete submitted bid to the CDM Smith Bid Summary Table to develop a complete bid comparable to that of the other bidders for comparison purposes. Betts Environmental, the second lowest bid, was selected as the lowest responsive and responsible bidder. Erwin Remediation was selected as the lowest responsive and responsible bidder for IDW transport and disposal services.
The final cost total for Task Assignment DC028B is $96,194.58. Documentation of costs is included in the attached Cost Estimate Form (CEF), Level-of-Effort sheets (LOEs), and cost proposal. The final deliverable (Site Assessment Report) will be submitted on or before May 31, 2023. The Task Assignment Completion Date is August 29, 2023.
FDEP COST ESTIMATEContractor: CDM Smith, Inc.
Date: 11/15/2022
Task #: HW684 DC028B SubTask 1 Project Management SubTask 6
Site: Signature Cleaners SubTask 2 Mobilization SubTask 7
Activity/Phase: Site Assessment SubTask 3 Stage I Field Investigation SubTask 8
Project Manager: Kara Fincham SubTask 4 Stage III Field Investigation SubTask 9
SubTask 5 Site Assessment Report SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$59.98 Project Manager 25.9 25.9 $0.00 Senior Officer 0 0.0 0.0 0.0 0.0 0 0 0 0 0
$81.53 Senior Technical Expert TD 9 0.0 5.0 0.0 4.0 0 0 0 0 0 $59.98 Project Technical Leader KF 16 0.0 6.0 2.0 8.0 0 0 0 0 0
$0.00 Senior Professional 0 0.0 0.0 0.0 0.0 0 0 0 0 0 $43.01 Professional II AR 171.5 0.0 83.5 38.0 50.0 0 0 0 0 0 $24.04 Professional I CQ 100 12.0 62.0 10.0 16.0 0 0 0 0 0 $30.36 Professional I KP 16 0.0 0.0 0.0 16.0 0 0 0 0 0
$0.00 Staff Technician 0 0 0 0 0 0 0 0 0 0 $0.00 Project Administration 0 0 0 0 0 0 0 0 0 0 $0.00 Senior Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 Staff Support Services 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 338.4 25.9 12 156.5 50 94 0 0 0 0 0
Direct Labor $13,514.16 $1,554.73 $288.48 $5,849.35 $1,994.74 $3,826.86 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 135.00% $18,244.12 $2,098.89 $389.45 $7,896.62 $2,692.90 $5,166.26 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $5,094.84 $586.13 $108.76 $2,205.20 $752.02 $1,442.73 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $36,853.12 $4,239.75 $786.69 $15,951.17 $5,439.66 $10,435.85 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $1,920.00 $120.00 $1,200.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,920.00 $120.00 $1,200.00 $600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $30,033.30 $0.00 $30,033.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $2,465.00 $0.00 $0.00 $2,465.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $1,800.00 $0.00 $0.00 $1,800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Private Utility Locate $800.00 $800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $35,098.30 $800.00 $30,033.30 $4,265.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $3,509.83 $80.00 $3,003.33 $426.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $38,608.13 $880.00 $33,036.63 $4,691.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $6,735.00 $0.00 $6,160.00 $575.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $1,154.00 $0.00 $949.00 $205.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $2,119.00 $0.00 $1,793.00 $326.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $10,008.00 $0.00 $8,902.00 $1,106.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $440.00 $40.00 $240.00 $160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $3,315.00 $0.00 $2,665.00 $650.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $930.00 $0.00 $640.00 $290.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $165.00 $0.00 $165.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Site Recon Kit $270.00 $150.00 $0.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,120.00 $190.00 $3,710.00 $1,220.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $92,509.25 $4,239.75 $1,976.69 $62,799.80 $13,057.16 $10,435.85 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,685.33 $423.98 $78.67 $1,595.12 $543.97 $1,043.59 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $96,194.58 $4,663.73 $2,055.36 $64,394.92 $13,601.13 $11,479.44 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE :
SUBTASK 2: Mobilization
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Professional I CQ Utilities Oversight 10
Travel 2
TOTAL LABOR 12.00
VEHICLE TYPE RATE UNIT USEAGE
Truck $120 each 1 $120.00
$0.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Site Lines LLC Private Utility Locate $800.00
$0.00
TOTAL $800.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 1 $40.00
$0.00
Site Recon Kit $150.00 Each 1 $150.00
TOTAL EQUIPMENT $190.00
Signature Cleaners
44880
SUBTASK 3: Stage I Field Investigation
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Seniot Tech Expe TD Determine field activities based on VEW/MAGs data 5 Project Tech LeadKF Prepare field scope of work 2
Determine Field Activities based on field data 4 Professional II AR Field Event Preparation 2
Arrange for site access with owner 2 Prepare Sample Kit request 1.5 Prepare HASP 2 Travel (6 days) 24 10 soil borings (2 day) 16 Vapor Extraction Well/VMP Installation (1 day) 10 MAGs Testing (2 days) 16 7 Vertical profiles (1 day) 10
Professional I CQ 10 soil borings 16 Vapor Extraction Well/VMP Installation 10 7 vertical profiles 10 MAGS Testing 16 IDW Management/Survey oversight 10
TOTAL LABOR 156.5
VEHICLE TYPE RATE UNIT USEAGE
Truck $480 weekly 2 $960.00 Truck $120.00 daily 2 $240.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE RATE UNIT USEAGE
Betts See Attachment A $30,033.30
TOTAL $30,033.30
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Soil 8260B 73 40 0 $2,920.00 1 week turnaround 20% $584.00
Sample Shipping $150.00 3 $450.00 Ice $6.50 6 $39.00 Groundwater 8260B $73 25 0 $1,825.00 1 week turnaround 20% $365.00
Soil Gas TO-15 $200.00 5 0 $1,000.00 Soil TCLP VOCs $210.00 1 0 $210.00 Water TCLP VOCs $205.00 1 0 $205.00
Sample Shipping $150.00 8 0 $1,200.00 Ice $6.50 16 $104.00
TOTAL LAB $8,902.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Encore Sampler $16.00 Each 40 $640.00 Expendables $40.00 Days 6 $240.00
Soil Sampling Kit (through concrete) $235.00 Days 2 $470.00 Shallow Groundwater Sampling/Soil Vapor Screening $290.00 Days 3 $870.00 Monitoring Well Installation Kit $325.00 Days 1 $325.00 Mags Investigation Kit $500.00 Days 2 $1,000.00
Summa Canister $33.00 each 5 $165.00
TOTAL EQUIPMENT $3,710.00
SUBTASK 4: Stage III Field Investigation
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Tech LeadKF Determine Field activities based on field data 2
Professional II AR Field Event Preparation 2
Prepare Sample Kit 1
Prepare Field forms/labesl 1
Travel 8
Install 5 Monitoring Well 16
Sample 5 Monitoring Wells plus PFAS 8
PFAS Notification Letter 2
Professional I CQ Survey oversight/IDW Management 10
TOTAL LABOR 50
VEHICLE TYPE RATE UNIT USEAGE
Truck 480 Week 1 480
Truck $120.00 Daily 1 120
TOTAL VEHICLE 600
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM 0
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Betts See Attachment A covered in LOE 3 0
Southeastern Survey See Attachment A 1 $2,465.00 2465
Erwin Remediation See Attachment A 18 $100.00 1800
TOTAL 4265
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
Groundwater 8260B $73.00 5 0 365
Groundwater PFAS $0.00 0 0 0
Soil TCLP VOCs $210.00 1 0 210
Water TCLP VOCs $205.00 1 0 205
Sample Shipping $150.00 2 0 300
Ice $6.50 4 26
TOTAL LAB 1106
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 Days 4 160
Shallow Groundwater Sampling Kit $290.00 Days 1 290
Monitor Well Installation Kit $325.00 Days 2 650
Drums $100.00 Each 0 0
Tubing/HDPE $0.40 per foot 300 120
TOTAL EQUIPMENT 1220
SUBTASK 5Site Assessment Report
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Senior Tech Expe TD SAR Preparation/PG seal 4
Project Manager KF SAR Preparation of conclusions and recommendations 8
Professional II AR SAR Preparation - body of document 50
Professional I CQ Assist in SAR Preparation - data tables, field notes, laboratory results, etc 16
Professional I KP Prepare Figures 16
TOTAL LABOR 94
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
4651 Salisbury Road, Suite 420
Jacksonville, Florida 32256 tel: 904.731.7109
Revised November 15, 2022
Mr. Aaron Cohen, FCCM Florida Department of Environmental Protection Drycleaning and Waste Cleanup Programs 2600 North Blair Stone Road Tallahassee, Florida 32399
Subject: Signature Cleaners Site Assessment Proposal
ERIC_4556
9719-5 San Jose Boulevard Jacksonville, Duval County, Florida
Dear Mr. Cohen:
CDM Smith Inc. (CDM Smith) is pleased to respond to the Florida Department of Environmental Protection (FDEP) Task Assignment Request to provide site assessment services for the Signature Cleaners site under Contract Number HW681. The scope of work, and project schedule are described below, and the cost estimate is also attached.
Site Assessment Scope of Work CDM Smith understands that FDEP would like to complete the initial site assessment within approximately 8 months, leaving 4 months as a contingency to complete the site assessment within 1 year. The subtasks are described below.
Subtask 1 – Project Management Project management activities performed under this task generally consist of administrative functions required to maintain the project schedule, adhere to budget, and deliver the quality of the work products defined by CDM Smith's quality standards. We will prepare and submit invoices upon approval of each deliverable or milestone completion.
Project Kickoff and Progress Meetings CDM Smith expects to have a kickoff meeting or telephone conference with the FDEP to review the status of the project and address FDEP comments regarding the Task Assignment. CDM Smith will prepare meeting agendas and notes as part of this task.
Project Quality Technical Review CDM Smith's Quality Management System guidelines will be followed. Internal quality reviews will be conducted on plans and on investigation findings and reports.
Mr. Aaron Cohen, FCCM October 24, 2022
Project Status Reports CDM Smith's Project Manager will prepare and submit monthly status reports to accompany each invoice throughout the duration of this project. The Project Manager will also discuss the status of the project with the FDEP on a bi-weekly basis until the project is complete.
Subtask 2 – Site Survey Underground Utility Survey The work plan identified only a portion of the underground utilities. CDM Smith will subcontract a utility location services company to provide a complete survey of the utilities and provide oversight for the Utility Survey.
Deliverable: Surveys, paid invoices to surveyors
Subtask 3 – Stage I Field Investigation The Stage I Field Investigation will delineate the extent of volatile organic halocarbons (VOHs) exceeding the Soil Cleanup Target Levels (SCTLs). Split soil samples will be collected and held for Synthetic Precipitate Leaching Procedure (SPLP) testing for samples that are below the direct-contact SCTL and above the default leachability SCTL.
Soil borings will be completed by CDM Smith at ten locations (Figure 1). Borings will be installed using hand augers and concrete coring will be completed at each of the ten locations.
Soil samples will be collected for laboratory analyses at the following depths: 0 to 0.5 feet below land surface (bls), 0.5 to 2 feet bls, and at 2-foot intervals thereafter to the water table. The soil samples will be submitted for laboratory analysis by United States Environmental Protection Agency (EPA) Method 8260 for VOHs. CDM Smith assumes up to 40 samples will be collected. The sample quantities are summarized in Table 1. CDM Smith will collect duplicate samples at each interval to be analyzed by SPLP but will identify which samples to run for SPLP after the initial data are received from the laboratory. Therefore, costs associated with SPLPs are not included in this cost estimate.
One soil boring in the vicinity of the former drycleaning machine will be completed as a 1-inch diameter monitoring well. The well will be installed in the upper shallow zone to a depth of 15 feet bls using a 420M portable drill rig. The well will be developed and sampled for VOH analyses by EPA Method 8260.
Five of the soil borings will be completed as vapor extraction wells (VEW) for Modified Active Gas Sampling (MAGS™) testing. CDM Smith will also install two vapor monitoring points (VMPs) to provide additional data to assess radius of influence (Figure 2). The VEW and VMP well screens will be installed to a depth of one foot above the water table and the top of the screen will terminate at a depth of approximately 1-foot bls. The total depth of the VEWs and VMPs is expected to be 6 feet bls. The VEWs will be constructed using 2-inch diameter polyvinyl chloride (PVC) and the VMPs will be 0.75-inch diameter PVC. The annulus of each VEW and VMP will be backfilled with sand pack and sealed at land surface with a sand/cement mortar mix.
MAGS™ testing will be performed at each proposed VEW. A step test will be completed on VEW- 001 only to select the MAGS™ test flow rates. The MAGS™ tests for each VEW will be completed within one hour or less, and CDM Smith assumes that setup, testing, and breakdown for all tests will require 2 days. A total of one soil gas sample from each VEW will be submitted to the laboratory for TO-15 analyses with standard reporting times.
Following MAGS™ testing, vertical groundwater profiling will be conducted at six locations using a direct-push technology (DPT) drill rig equipped with a groundwater screen point sampling system.
Groundwater samples will be collected using DPT screen points at the following depth intervals: 6 to 10 feet bls, 11 to 15 feet bls, 21 to 25 feet bls, and 31 to 35 feet bls or to depth of refusal or limestone, whichever occurs first. The groundwater samples will be collected directly, and laboratory analyzed for VOCs by EPA Method 8260. (Figure 3)
In addition, a continuous lithologic boring will be cored using DPT to obtain detailed site-specific lithologic and stratigraphic information for the site at a location immediately north of the facility (Figure 1). The target boring depth will be 50 feet bls, refusal, or the top of the SAS limestone. A detailed geologic log will be recorded, and the boring will be grouted using a tremie pipe.
At the completion of field events, the utilities that were marked during mobilization and all boring locations will be surveyed. Investigation-derived waste (IDW) collected up to this point will be characterized and transported off-site for disposal. A total of four soil drums and one water drum of nonhazardous IDW are anticipated at the completion of Stage I.
Deliverable: Laboratory analytical reports, field documentation, boring logs, data tables, paid invoices for subcontractors
Subtask 4 – Stage II Field Investigation The monitoring well locations will be finalized based on the Stage I results. CDM Smith currently plans to install four additional permanent groundwater monitoring wells. Prior to well installation, continuous soil cores will be collected to the total depth. Three of the wells will be shallow wells installed to a total depth of 15 feet bls and one intermediate well to a total depth of 25 feet bls. All wells will be 2-inch diameter PVC and have 10-foot screens. Sand pack will be installed to a depth of 1 ft above the screen followed by a 1-foot-thick fine-grained sand seal and the remainder of the borehole grouted. The wells will be developed following completion.
The wells will be purged and sampled for VOHs following installation and a full round of water levels will be collected to map the potentiometric surface. The monitoring wells will be surveyed at the completion of Subtask 4, and IDW will be characterized and transported off-site for disposal. A total of 14 soil drums and 4 water drums of nonhazardous IDW are anticipated at the completion of Stage II.
Deliverable: Completed well logs, laboratory analytical reports, paid invoices
Subtask 5 – Site Assessment Report CDM Smith will prepare a Site Assessment Report in general accordance with the requirements of FDEP Chapter 62-780, FAC. The report will summarize the history of the Site, physical and geologic conditions, all field work completed by CDM Smith, field and laboratory data, conclusions, and recommendations. Additional elements of the report will include the following:
Figures depicting site conditions
Figures depicting soil and groundwater data and estimated extent of impact
Groundwater elevation contour map
Tables summarizing field and analytical data
Soil/lithological logs
Monitor well completion reports
Groundwater sampling logs and field equipment calibration records
Laboratory analytical reports and chain of custody documentation
Waste disposal manifests and weigh tickets
Subcontractors Subcontracted services are required for drilling, surveying, utility location, sewer camera survey, and IDW disposal. The bidding, results, and subcontractor selections are described below, and Attachment A includes a summary of the subcontractor cost comparisons.
Drilling Request for Quotations (RFQs) were sent to three pre-qualified drilling companies for all drilling services. The lowest cost bid was from Ambient Technologies Inc. (ATI). However, ATI did not provide costs for Geoprobe sampling, required decontamination, and did not account for the number of drums required to complete the work. Betts Environmental Recovery, Inc. (Betts) was the next lowest bid at 17 percent higher than ATI. CDM Smith discussed the bid and project details with Betts, and we are satisfied that Betts can do the required work. Betts is the recommended drilling subcontractor.
Surveying Southeastern Surveying and Mapping is a primary subcontractor for HW681 and other bids were not solicited for this project. The total quote is included in Attachment A.
Utility Location Bids were obtained from Blood Hound, GeoView Inc., and Site Lines LLC to complete the utility survey. The total quotes are shown in Attachment A.
IDW Disposal Rates for IDW removal and disposal were previously requested for HW681 from Erwin Remediation, Clean Earth, ERS, and Clark Environmental. These rates were used to assess the current IDW disposal costs for the HandiCraft Cleaners site assessment. Erwin Remediation was the lowest cost and has been selected as the IDW disposal subcontractor for this project as shown in Attachment A.
Assumptions This scope and schedule have been prepared predicated on unknown site conditions. The scope and schedule may change depending on surveys and the drilling conditions. Drillers and other subcontractors’ availability may be limited and impact the schedule. In addition, this scope does not consider any weather delays. CDM Smith will communicate with the FDEP in a timely manner if this occurs to prepare the necessary paperwork for change orders.
Schedule CDM Smith’s proposed project schedule is shown below, with targeted completion of the Site Assessment process within eight months. The final dates on the schedule depend on Notice to Proceed (NTP) and subcontractor availability. Once CDM Smith receives NTP, the subcontractor’s availability will be confirmed, and the schedule may be adjusted. The deliverables and due dates are summarized in Table 2 below.
Table 2: Deliverables Schedule
Subtask 2 Deliverable:
Due Date:
Site Preparation Underground Utility Survey January 15, 2023
Subtask 3 Deliverable:
Due Date:
Stage I Field Investigation Laboratory analytical reports, field documentation, boring logs, data tables, paid invoices for subcontractors March 15, 2023
Subtask 4 Deliverable:
Stage II Field Investigation
Due Date: Laboratory analytical reports, field documentation, boring logs, data tables, paid invoices for subcontractors April 15, 2023
Subtask 5 Deliverable:
Due Date:
Site Assessment Report Site Assessment Report May 31, 2023
We look forward to working on this important project. Feel free to contact me at 904-527-6716 or by email with any questions or comments.
Sincerely, Kara E. Fincham, PMP Shayne Wood, P.E., PMP, BCEE Senior Project Manager Vice President CDM Smith CDM Smith FinchamKE@cdmsmith.com WoodSH@CDMSmith.com cc: Tom Duffey, P.G., CDM Smith
Surveying Southeastern Surveying and Mapping is a primary subcontractor for HW681 and other bids were not solicited for this project. The total quote is included in Attachment A.
Utility Location Bids were obtained from Blood Hound, GeoView Inc., and Site Lines LLC to complete the utility survey. The total quotes are shown in Attachment A.
IDW Disposal Rates for IDW removal and disposal were previously requested for HW681 from Erwin Remediation, Clean Earth, ERS, and Clark Environmental. These rates were used to assess the current IDW disposal costs for the HandiCraft Cleaners site assessment. Erwin Remediation was the lowest cost and has been selected as the IDW disposal subcontractor for this project as shown in Attachment A.
Assumptions This scope and schedule have been prepared predicated on unknown site conditions. The scope and schedule may change depending on surveys and the drilling conditions. Drillers and other subcontractors’ availability may be limited and impact the schedule. In addition, this scope does not consider any weather delays. CDM Smith will communicate with the FDEP in a timely manner if this occurs to prepare the necessary paperwork for change orders.
Schedule CDM Smith’s proposed project schedule is shown below, with targeted completion of the Site Assessment process within eight months. The final dates on the schedule depend on Notice to Proceed (NTP) and subcontractor availability. Once CDM Smith receives NTP, the subcontractor’s availability will be confirmed, and the schedule may be adjusted. The deliverables and due dates are summarized in Table 2 below.
Table 2: Deliverables Schedule
Subtask 2 Deliverable:
Due Date:
Site Preparation Underground Utility Survey November 30, 2022
Subtask 3 Deliverable:
Due Date:
Stage I Field Investigation Laboratory analytical reports, field documentation, boring logs, data tables, paid invoices for subcontractors January 30, 2023
Subtask 4 Deliverable:
Stage II Field Investigation
Due Date: Laboratory analytical reports, field documentation, boring logs, data tables, paid invoices for subcontractors March 1, 2023
Subtask 5 Deliverable:
Due Date:
Site Assessment Report Site Assessment Report March 30, 2023
We look forward to working on this important project. Feel free to contact me at 904-527-6716 or by email with any questions or comments.
Sincerely, Kara E. Fincham, PMP Shayne Wood, P.E., PMP, BCEE Senior Project Manager Vice President CDM Smith CDM Smith FinchamKE@cdmsmith.com WoodSH@CDMSmith.com cc: Tom Duffey, P.G., CDM Smith
Figures
Table
Sample Source Sample Type Sample Quantity Analysis Reporting Soil Borings Soil 40 VOH 5-Day Vertical Profiling Groundwater 25 VOH 5-Day Vapor Extraction Wells Soil Gas 5 TO-15 Standard Stage I IDW Soil 1 TCLP Standard Stage I IDW Water 1 VOH Standard Stage II Monitoring Wells Groundwater 5 VOH Standard Stage II IDW Soil 1 TCLP Standard Stage II IDW Water 1 VOH Standard
Sample Type Analysis Reporting Soil VOH 5-Day IDW Soil TCLP Standard Groundwater VOH 5-Day Groundwater VOH Standard IDW Water VOH Standard Soil Gas TO-15 Standard
Site Assessment Totals Totals
IDW - Investigation derived waste
VOH - Volatile organic halocarbons to include tetrachloroethene, trichloroethene, cis- and trans -1,2-dichloroethene, 1,1-dichloroethene, and vinyl chloride by Method 8260B.
SPLP - Synthetic Precipitate Leaching Procedure extraction by Method 5030B followed by VOH analysis by Method 8260B.
Table 1: Laboratory Analyses Signature Cleaners
ERIC_4556
Jacksonville, Duval County, Florida
Attachment A Subcontractor Quotes
Driller Item Est. Qty. Units Rate Total Est. Qty. Units Rate Total Est. Qty. Units Rate Total 1 - Mobilization/Demobilization 2 Lump Sum $1,250.00 $2,500.00 1 Lump Sum $575.00 $575.00 1 Lump Sum $3,150.00 $3,150.00 1 - Permits per GW profile 1 Lump Sum $175.00 $175.00 1 - Permits 5 per wells $175.00 $875.00 1 - Utility Clearance 2 Lump Sum $25.00 $50.00 1 Lump Sum $100.00 1 - Decontamation pad 2 Lump Sum $325.00 $650.00 2 Each $200.00 $400.00 2 - Crew Per Diem 15 Per Day $150.00 $2,250.00 6 Per Day $415.00 $2,490.00 7 Per Day $525.00 $3,675.00 3 - Concrete Coring 6 Per Day $100.00 $600.00 6 Each $50.00 $300.00 4 - DPT Rate 6 Per Day $2,250.00 $13,500.00 6.857 Per Day $1,575.00 $10,799.78 6 Per Day $2,300.00 $13,800.00 4 - Steam Cleaner/Core Dril 6 Per Day $75.00 $450.00 4 - DPT Supplies 88 Per LF $18.00 $1,584.00 1 Lump Sum $980.00 $980.00 123 Per LF $20.00 $2,460.00 4 - Geoprobe Soil sampling, Borehole Abandoment332 Per LF $4.00 $1,328.00 349 Per LF $2.00 $698.00 4 - open plug/resurface borehole 11 each $80.00 $880.00 5 -2x2 well bpad 5 Each $150.00 $750.00 13 Each $150.00 $1,950.00 5 - Decon between locations 6 Per day $250.00 $1,500.00 5 - Well Development 5 per wells $175.00 $875.00 5 - 3/4" PVC SVP 2 Each $115.00 $230.00
5 - 2" PVC SVEW 5 125 $125.00 $625.00
5 - 6: Manhole pad 8 Per SVP/SVE $100.00 $800.00 5 - 1 MW with 5' 1 each $150.00 $150.00 7 - Well Completion Reports 1 Each $100.00 $100.00 7 Each $115.00 $805.00 8 - 55-Gallon Drums 18 Each $70.00 $1,260.00 4 Each $65.00 $260.00 7 Each $110.00 $770.00
$33,277.20 $18,468.75 $30,033.30
Not Included
Subcontractor Evaluation Signature Cleaners
Preferred Drilling Solutions
Total
Ambient Technologies
Total
Betts Environmental
Total
Stage I Vertical Groundwater Profiling & Vapor Extraction Well Installation
Included Included
Not Required
Included
Not Included
Included
Included
Attachment A: Subcontractor Quotes Signature Cleaners
ERIC_4556
Jacksonville, Duval County, Florida
Driller
1 - Mobilization/Demobilization 1 Lump Sum $575.00 $575.00 1 - Decontamination Pad 2 - Crew Per Diem 1 Per Day $415.00 $415.00 3 - DPT Rate 1 per day $1,575.00 $1,575.00
1 half day $1,350.00 $1,350.00 3 - Access Attachment 3 - DPT Supplies 1 Lump Sum $875.00 $875.00 4 - Auger Boreholes 5 - 2" Monitoring Wells Per Foot 6 - 1" Indoors Well Per Foot 6 - 1" Each 7 - Well Completion 5 Each $120.00 $600.00 8 - permits 5 Each $155.00 $775.00 9 - 55-Gallon Drums 5 Each $65.00 $325.00
$0.00 $7,139.00 $0.00
Driller Stage I and Stage II Stage II Total
Company Locate Utilities
Stage I Stage II
Utility Location and Sanitary Sewer Camera Survey
6 Hours $800.00
$30,033.30 $0.00
Total $1,350.00
GeoView Inc.
$1,350.00
Surveying - Utilities, All Borings, and Monitoring Wells Southeastern Surveying and Mapping
Lump Sum Lump Sum
Total $2,465.00
Total $800.00 $1,225.00
$33,277.20
$18,468.75 $7,139.00
Total $1,225.00
Blood Hound Site Lines LLC
Total Total Total
Stage II Permanent Monitoring Well Installation Preferred Drilling Solutions Ambient Technologies Betts Environmental
$2,465.00
Preferred Drilling Solutions Ambient Technologies Betts Environmental Drilling Summary
$30,033.30$25,607.75
$33,277.20
Attachment A: Subcontractor Quotes Signature Cleaners
ERIC_4556
Jacksonville, Duval County, Florida
Cohen_A Highlight
Cohen_A Highlight
Cohen_A Highlight
Company
240 Miles $2.90 $696.00 3 Trips $696.00 $2,088.00
1 - Transport Cost < 100 mi. per drum 18 Drums $30.00 $540.00
1 - Transport Cost 101-250 mi. per drum 0 Drums $40.00 $0.00 1 - Transport Cost 250-400 mi. per drum 0 Drums $50.00 $0.00
2 - Liquid Disposal 4 Drums $100.00 $400.00 4 Drums $60.00 $240.00 4 Drums $100.00 $400.00 2 - Soil Disposal 14 Drums $100.00 $1,400.00 14 Drums $80.00 $1,120.00 14 Drums $100.00 $1,400.00
$1,800.00 $1,900.00 $3,888.00
1 - Delivery destination 755 Prairie Industrial Parkway, Mulberry, Florida: 60 miles
2 - Delivery destination 790 Tallyrand Avenue, Jacksonville, Florida: 240 miles
3 - Up to 40 drums per trip maximum
Total
1 - Transport Cost 3 per mi. per trip
Erwin Remediation Clark Environmental 1 Investigation-Derived Waste
ERS CORP 2
Included
Included
Included
Included
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Total Total
Included Not Applicable
Attachment A: Subcontractor Quotes Signature Cleaners
ERIC_4556
Jacksonville, Duval County, Florida
Cohen_A Highlight
Item Description of Work Quantity Units Rate Extension
1.0 General Requirements
1.1 Utility Clearance-Obtain Sunshine 811 Dig Ticket, have utilities marked 1 Lump Sum 100.00$ 100.00$
1.2 Potable water - obtain permission/meter from local municipality, pay for water usage if a source is not available on-site 0 Lump Sum 1,500.00$ -$
1.3 Mobilization/Demobilization including crew HASP(1) and Water Mgt.
District Well Installation Permits 1 Lump Sum 3,150.00$ 3,150.00$ permits $150 each two mobilizations
1.4 Access improvements to drilling location(s) (if applicable) Lump Sum -$
1.5 Construct Temporary Decontamination Pad 2 Lump Sum 200.00$ 400.00$
1.6 One Drill Rig and Crew Daily Rate 6 Per Day 2,100.00$ 12,600.00$
1.7 Second Drill Rig and Crew Daily Rate (if applicable) Per Day -$
1.8 Extra Man 6 Per Day 200.00$ 1,200.00$
1.9 Concrete Coring Machine & Bit 6 Per Day 50.00$ 300.00$
2.0 Monitor or SVE Well Installation, # Each/GeoProbe® Soil Sampling
2.1 2-Inch Sch. 40 PVC Well Installation & Materials, 5 or 10 ft. 0.01-Inch Slot Screens, 6 or 8-inch O.D. Borehole, Soil Sampling(2) 123 Per Linear Foot 20.00$ 2,460.00$
2.2 2' x 2' x 0.5' Well Pad, Flush-Mounted Bolt-Down 8-Inch Manhole 13 Each 150.00$ 1,950.00$
2.3 2' x 2' x 0.5' Well Pad, Above-Ground Aluminum Riser, 4 Protective Safety Painted PVC Bollards 0 Each 550.00$ -$
2.4 Decontamination between drilling locations and prior to demobilization Per Day -$
2.5 Well Development, 3 well volumes or until volume used during drilling has been extracted via a submersible pump plus stabilization of field parameters
Per Well -$
2.6 Investigation Derived Waste Mgt. - supply applicable DOT 55-gallon drums and handling/staging 7 Per Drum 110.00$ 770.00$
2.7 Skid Steer Rental (if applicable) 0 Per Day -$ -$
2.8 Water Mgt. District Well Completion Reports 0 Lump Sum -$ -$
2.9 Geoprobe® Soil Sampling, Borehole Abandonment 349 Per foot 2.00$ 698.00$
3.0 Additional Items, as needed
Drill Crew Per Diem 7 Per Day 525.00$ 3,675.00$
-$ -$ Add rows as needed
SUBTOTAL 27,303.00$
4.0 Contingency Cost (10%), use to be approved by CDM Smith 2,730.30$
TOTAL 30,033.30$
6 Days 9 Hours 6 Days 1 Each
1mil $
CLIENT WILL PROVIDE ACCESS TO EACH DRILLING LOCATION AND PROVIDE AN APPROVED WATER SOURCE CLIENT WILL CALL 811 AND MAINTAIN A UTILITY TICKET FOR THE DURATION OF THE PROJECT
CLIENT AGREES TO PAYMENT TERMS OF PWP NOT TO EXCEED 60 DAYS FROM INVOICE
2 - Soil sampling will be conducted at each well and samples collected on 5 ft centers for Hollow Stem Auger wells and continuous coring for wells installed by Sonic.
Authorized Representative Name and Title Blake Cabit - General Manger
Signature and Date August 30. 2022
Notes:
1 - All drilling crew members shall meet the required OSHA training and medical monitoring requirements contained in 29 CFR 1910.120 and work shall be conducted under the Contractor's site-specific Health and Safety Plan.
Betts Environmental Recovery, Inc.
Geoprobe 7822
Drill crew size/number of rigs & crews proposed/first available date to begin the work 3 man crew First available date is 10/17/22
Total number of staff and general function (include Florida Licensed Monitoring Well Driller & Certification Number) 40 total staff members FL License #2640
Total project duration Assumed work hours per day Assumed uninterrupted shift duration Assumed number of breaks Pollution Liability Insurance Limit per Occurrence
Company Name
Type and model of drill rig(s)
Site Name: Signature Cleaners Site Address: 9719-5 San Jose Boulevard, Jacksonville, FL FDEP ERIC No. 4556
DRILLING CONTRACTOR BID SHEET
Interstate Workers' Compensation Experience Modification Rate (EMR) 2019 0.93 2020 0.94 2021 0.91
Drilling Method: Hollow Stem Auger, Sonic, Geoprobe® or Other:
BID SHEET
FDEP Waste Cleanup Project
1.1 Utility Clearance-Obtain Sunshine 811 Dig Ticket, have utilities marked 1 Lump Sum 100.00$ 100.00$
1.2 Potable water - obtain permission/meter from local municipality, pay for water usage if a source is not available on-site 0 Lump Sum 1,500.00$ -$
1.3 Mobilization/Demobilization including crew HASP(1) and Water Mgt.
District Well Installation Permits 1 Lump Sum 4,350.00$ 4,350.00$ permits $150 each two mobilizations
1.4 Access improvements to drilling location(s) (if applicable) Lump Sum N/A
1.5 Construct Temporary Decontamination Pad 2 Lump Sum 200.00$ 400.00$
1.6 One Drill Rig and Crew Daily Rate 6 Per Day 2,100.00$ 12,600.00$
1.7 Second Drill Rig and Crew Daily Rate (if applicable) Per Day N/A
1.8 Extra Man 6 Per Day 200.00$ 1,200.00$
1.9 Concrete Coring Machine & Bit 6 Per Day 50.00$ 300.00$
2.0 Monitor or SVE Well Installation, # Each/GeoProbe® Soil Sampling
2.1 2-Inch Sch. 40 PVC Well Installation & Materials, 5 or 10 ft. 0.01-Inch Slot Screens, 6 or 8-inch O.D. Borehole, Soil Sampling(2) 123 Per Linear Foot 20.00$ 2,460.00$
2.2 2' x 2' x 0.5' Well Pad, Flush-Mounted Bolt-Down 8-Inch Manhole 12 Each 150.00$ 1,800.00$
2.3 2' x 2' x 0.5' Well Pad, Above-Ground Aluminum Riser, 4 Protective Safety Painted PVC Bollards 0 Each 550.00$ -$
2.4 Decontamination between drilling locations and prior to
demobilization Per Day N/C
2.5 Well Development, 3 well volumes or until volume used during drilling has been extracted via a submersible pump plus stabilization of field parameters
Per Well included in daily rate
2.6 Investigation Derived Waste Mgt. - supply applicable DOT 55-gallon drums and handling/staging 7 Per Drum 110.00$ 770.00$
2.7 Skid Steer Rental (if applicable) 0 Per Day -$ N/A
2.8 Water Mgt. District Well Completion Reports 0 Lump Sum -$ N/C
2.9 Geoprobe® Soil Sampling, Borehole Abandonment 329 Per foot 2.00$ 658.00$
3.0 Additional Items, as needed
Drill Crew Per Diem 6 Per Day 525.00$ 3,150.00$
-$ -$ Add rows as needed
SUBTOTAL 27,788.00$
4.0 Contingency Cost (10%), use to be approved by CDM Smith 2,778.80$
TOTAL 30,566.80$
6 Days 9 Hours 6 Days 1 Each
1mil $
CLIENT WILL PROVIDE ACCESS TO EACH DRILLING LOCATION AND PROVIDE AN APPROVED WATER SOURCE CLIENT WILL CALL 811 AND MAINTAIN A UTILITY TICKET FOR THE DURATION OF THE PROJECT
CLIENT AGREES TO PAYMENT TERMS OF PWP NOT TO EXCEED 60 DAYS FROM INVOICE
2 - Soil sampling will be conducted at each well and samples collected on 5 ft centers for Hollow Stem Auger wells and continuous coring for wells installed by Sonic.
Authorized Representative Name and Title Blake Cabit - General Manager
Signature and Date 8/30/2022
Notes:
1 - All drilling crew members shall meet the required OSHA training and medical monitoring requirements contained in 29 CFR 1910.120 and work shall be conducted under the Contractor's site-specific Health and Safety Plan.
Betts Environmental Recovery, Inc.
7822 Geoprobe Rig
Drill crew size/number of rigs & crews proposed/first available date to begin the work 3 man crew First available date is 10/17/22
Total number of staff and general function (include Florida Licensed Monitoring Well Driller & Certification Number) 40 total staff FL License #2640
Total project duration Assumed work hours per day Assumed uninterrupted shift duration Assumed number of breaks Pollution Liability Insurance Limit per Occurrence
Company Name
Type and model of drill rig(s)
Site Name: Touch of Class Cleaners Site Address: 6060 Fort Caroline Road, Jacksonville, FL FDEP ERIC No. 4611
DRILLING CONTRACTOR BID SHEET
Interstate Workers' Compensation Experience Modification Rate (EMR) 2019 0.93 2020 0.94 2021 0.91
Drilling Method: Hollow Stem Auger, Sonic, Geoprobe® or Other:
1.1 Utility Clearance-Obtain Sunshine 811 Dig Ticket, have utilities marked 1 Lump Sum 100.00$ 100.00$
1.2 Potable water - obtain permission/meter from local municipality, pay for water usage if a source is not available on-site 0 Lump Sum 1,500.00$ -$
1.3 Mobilization/Demobilization including crew HASP(1) and Water Mgt.
District Well Installation Permits 1 Lump Sum 4,050.00$ 4,050.00$ permits $150 each two mobilizations
1.4 Access improvements to drilling location(s) (if applicable) Lump Sum N/A
1.5 Construct Temporary Decontamination Pad 2 Lump Sum 200.00$ 400.00$
1.6 One Drill Rig and Crew Daily Rate 6 Per Day 2,100.00$ 12,600.00$
1.7 Second Drill Rig and Crew Daily Rate (if applicable) Per Day N/A
1.8 Extra Man 6 Per Day 200.00$ 1,200.00$
1.9 Concrete Coring Machine & Bit 6 Per Day 50.00$ 300.00$
2.0 Monitor or SVE Well Installation, # Each/GeoProbe® Soil Sampling
2.1 2-Inch Sch. 40 PVC Well Installation & Materials, 5 or 10 ft. 0.01-Inch Slot Screens, 6 or 8-inch O.D. Borehole, Soil Sampling(2) 118 Per Linear Foot 20.00$ 2,360.00$
2.2 2' x 2' x 0.5' Well Pad, Flush-Mounted Bolt-Down 8-Inch Manhole 11 Each 150.00$ 1,650.00$
2.3 2' x 2' x 0.5' Well Pad, Above-Ground Aluminum Riser, 4 Protective Safety Painted PVC Bollards 0 Each 550.00$ -$
2.4 Decontamination between drilling locations and prior to
demobilization Per Day N/C
2.5 Well Development, 3 well volumes or until volume used during drilling has been extracted via a submersible pump plus stabilization of field parameters
Per Well included in daily rate
2.6 Investigation Derived Waste Mgt. - supply applicable DOT 55-gallon drums and handling/staging 8 Per Drum 110.00$ 880.00$
2.7 Skid Steer Rental (if applicable) 0 Per Day -$ -$
2.8 Water Mgt. District Well Completion Reports 0 Lump Sum -$ -$
2.9 Geoprobe® Soil Sampling, Borehole Abandonment 344 Per foot 2.00$ 688.00$
3.0 Additional Items, as needed
Drill Crew Per Diem 6 Per Day 525.00$ 3,150.00$
-$ -$ Add rows as needed
SUBTOTAL 27,378.00$
4.0 Contingency Cost (10%), use to be approved by CDM Smith 2,737.80$
TOTAL 30,115.80$
6 Days 9 Hours 6 Days 1 Each
1mil $
CLIENT WILL PROVIDE ACCESS TO EACH DRILLING LOCATION AND PROVIDE AN APPROVED WATER SOURCE CLIENT WILL CALL 811 AND MAINTAIN A UTILITY TICKET FOR THE DURATION OF THE PROJECT
CLIENT AGREES TO PAYMENT TERMS OF PWP NOT TO EXCEED 60 DAYS FROM INVOICE
2 - Soil sampling will be conducted at each well and samples collected on 5 ft centers for Hollow Stem Auger wells and continuous coring for wells installed by Sonic.
Notes:
1 - All drilling crew members shall meet the required OSHA training and medical monitoring requirements contained in 29 CFR 1910.120 and work shall be conducted under the Contractor's site-specific Health and Safety Plan.
Drill crew size/number of rigs & crews proposed/first available date to begin the work
Total number of staff and general function (include Florida Licensed Monitoring Well Driller & Certification Number)
0.93 0.94 0.91
Authorized Representative Name and Title Blake Cabit - General Manager
Signature and Date 8/30/2022
3 man crew First available date is 10/17/22
40 total staff FL License #2640
Betts Environmental Recovery, Inc.
Company Name
Interstate Workers' Compensation Experience Modification Rate (EMR)
Pollution Liability Insurance Limit per Occurrence
Site Name: Handicraft Cleaners Site Address: 14333-1 Beach Boulevard, Jacksonville, FL FDEP ERIC No. 4565
Total project duration Assumed work hours per day Assumed uninterrupted shift duration Assumed number of breaks
DRILLING CONTRACTOR BID SHEET
Drilling Method: Hollow Stem Auger, Sonic, Geoprobe® or Other:
Type and model of drill rig(s) Geoprobe 7822
Contractor: CDM Smith Proposal No.: 22208043A Rev1 Contact Name: Andrew Ryan
Contact Phone: 407 660-6397 Date: 8/25/2022 Contact Email: ryanaj@cdmsmith.com 9/9/2022
Site Address: FDEP ID#:
PROPOSED SCOPE OF WORK: Estimator: MR
Direct Push Rig Daily Rate - (maximum 10 hours) whole day $1,575.00 6 $9,450.00 Direct Push Rig Half-Day Rate 1 - (maximum 5 hours) half day $1,350.00 1 $1,350.00 Prepack Well Screen (includes all materials) Length 5ft ID __1"____ each $90.00 1 $90.00 Well Riser (includes all materials) ID-1" 5' Length each $55.00 1 $55.00 PVC Well Screen (includes all materials) Length 5ft ID __3/4"____ each $55.00 2 $110.00 Well Riser (includes all materials) ID-3/4" 5' Length each $50.00 2 $100.00 PVC Well Screen (includes all materials) Length 5ft ID __2_"____ each $65.00 5 $325.00 Well Riser (includes all materials) ID-2" 5' Length _ each $60.00 5 $300.00 per well $115.00 7 $805.00 Open, Plug/resurface borehole each $80.00 11 $880.00
Mobilization (one rig) Miles round trip: round trip $575.00 1 $575.00 Daily travel each $70.00 Per Diem - Automatic when field work is longer than 9hr/day or round trip over 150 miles per crew/night $415.00 6 $2,490.00 DOT Approved 55-gal Drum each $65.00 4 $260.00 Special Order Closed Top Drums each $95.00 Small decon pad each $350.00 TBD Permits 2 (Drilling and abandonment only; cost according to WMD & Local Municipalities) each $155.00 TBC Predrilling conference call LS included Extra hour rate 5 hour $175.00 $0.00
TOTAL QUOTE PRICE $16,790.00
NOTES: This proposal is only valid for this specific scope of work. Any changes, prices shall be revised. Actual field days, materials and hours will be invoiced
Days to Complete Scope of Work: Approx. 6 days (depends on access, client sampling time or other restrictions) " Subcontractor Company Name: ATI Companies, LLC Subcontractor Mailing Address: 4610 Central Av. St. Petersburg FL 33711
Signature:___________________________ Reviewer:____________________________ Date: 8/25/2022
NOTE: to schedule work, contact 727-328-0268 Bid Valid…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .