About this file
This is a Task Assignment Notification Form and associated Scope of Work from the Florida Department of Environmental Protection (FDEP) for Contract No. CN230. The project involves Weiler Engineering Corporation as the consultant, with R. Jeff Weiler, P.E. serving as the consultant representative and Alyssa Skehan as the FDEP Contract Manager. The project concerns the Sandspur Campground Restoration at Bahia Honda State Park, specifically addressing restroom and parking restoration for the Sand Spur Campground area with permit closeout and bathroom components.
The scope of work consists of twelve subtasks spanning plan revisions, comprehensive 100% design document preparation, bidding support, permitting coordination, construction administration, and final completion certification. Task 1 involves removing bathhouse references from current plans and delivering two sets of signed and sealed plans for $665.00 in fixed costs plus $510.00 in reimbursables. Tasks 2 through 12 cover design development, bid package preparation, bidder clarifications, pre-bid meetings, permitting, pre-construction meetings, submittal reviews, RFI responses, monthly construction inspections, substantial completion walk-throughs, and final completion certification. The total contract amount is $15,053.24, comprising $14,105.00 in fixed price costs and $948.24 in cost reimbursement not to exceed. The project runs from execution date through February 28, 2022, with funding allocated from FDEP grants FD073 and FD073 across two project numbers (6i504 and 6i505).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230
Task Assignment No.:
3 DRP 6i504 & 6i505
Bahia Honda State Park Sandspur Campground Restoration
Weiler Engineering
R. Jeff Weiler, P.E. 941-505-1700 jeff7@mac.com
Alyssa Skehan or successor 850-245-2781 Alyssa Skehan@FloridaDEP.gov Description of Task:
Task 32 Subtask 1 - Remove Bathhouse from current project plans and submit revised signed and sealed plan sets.
Task 32 Subtask 2-12 - Preparing separate bid set plan package for the remodeling of the Bathhouse and associated bid and construction phase services.
James Post
Upon execution $ 14,105.00 02/28/2022 $ 948.24
$ 15,053.24
James Post James Post Digitally signed by James Post Date: 2021.05.03 12:09:59 -04'00'
Michael W. Foster Jr.
Bryan Bradner
Gregory Turral Digitally signed by Gregory Turral Date: 2021.05.04 15:44:04 -04'00'
Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.05.04 16:09:11 -04'00'
R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.05.12 10:59:16 -04'00'
Bryan Bradner Digitally signed by Bryan Bradner Date: 2021.05.13 11:06:49 -04'00'
Wiman_A Cross-Out
Wiman_A Sticky Note 890, reflected in total and in checksum on last page
File details come from the government source that posted it. Updated .