About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN230, Task Assignment No. 83. The document involves FDEP and Weiler Engineering Corporation, an engineering services firm based in Punta Gorda, Florida. The change order pertains to the Indian Key Historic State Park Dock and Pavilion Replacement project, with Jeff Weiler, P.E., serving as the consultant representative and Ralph Perkins as the FDEP Contract Manager.
The change order authorizes a time extension only, with no additional cost to FDEP. The original task end date of June 30, 2024, has been extended by 304 days to April 29, 2025, to allow sufficient time for the United States Army Corps of Engineers (USACE) permit application review and plan modifications. The fixed fee for the task remains $11,460.00, with no changes to reimbursement or total task amounts. The modification was requested at no additional cost to the state and was signed by all required parties, including the FDEP Budget Representative, Project Manager, Contract Manager, and Contract Authority, as well as the consultant representative, on June 28, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 83 1 6I506C
Indian Key Historic State Park Dock and Pavilion Replacement
Weiler Engineering
Jeff Weiler, P.E. 941-505-1700 weiler7@mac.com
Ralph Perkins or successor 850-245-2460 Ralph.Perkins@FloridaDEP.gov
The TA is for a time extension only for plan modification and permits. Per attached dated 6/27/2024.
$ 0.00 $ 11,460.00 $ 11,460.00 $ 0.00 $ 11,460.00 $ 11,460.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 11,460.00 $ 11,460.00
02/07/24
02/07/2024
06/30/2024
4/29/2025
Tamika Bass
Garland Sandel
Ralph Perkins
Jeff Weiler, P.E.
Michael W. Foster Jr., P.E.
6I506C FD073 37505000097 0880039/23 423001 U3200 131500 QK $ 11,460.00
$ 11,460.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE- SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505-1700 | FAX 941-505-1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4162 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
June 27, 2024
Garland Sandel Design Project Manager
Bureau of Design and Construction Florida Department of Environmental Protection
Re: Indian Key Historic State Park- Dock and Pavilion Replacement FDEP Contract No: CN230 Task Assignment No: 83, Project No: 61506C
Mr. Sandel, We are requesting a time extension for the Indian Key Historic State Park- Dock and Pavilion Replacement project. This extension would be at no additional cost to the FDEP. The current contract expires on 6/30/2024. We are requesting a 304-day extension to allow enough time for the USACE Permit Application review.
If you have any questions, or require additional information, please do not hesitate to contact me at (941) 505-1700 or electronically at rpalmer@weilerengineering.org.
Sincerely, Robin Palmer, P.E.
Project Manager Weiler Engineering Corporation
File details come from the government source that posted it. Updated .