Task Assignment Notification and Proposal Summary

This document is a Task Assignment Notification Form and associated engineering proposal from the Florida Department of Environmental Protection (FDEP) for design and permitting services related to wastewater collection and transmission system construction at Koreshan State Park. The task assignment (CN230, Task 39) was executed between FDEP and Weiler Engineering Corporation, a consulting engineering firm based in Punta Gorda and Marathon, Florida. The project involves coordination with local regulatory agencies including Lee County, the Village of Estero, and the Southwest Florida Water Management District (SWFWMD). The contract was executed in November 2021 with FDEP Project Manager Andrew Lippens and Contract Manager Alyssa Skehan overseeing the engagement.

The scope encompasses fourteen subtasks spanning design and permitting phases through construction phase support services. Subtasks include site survey ($3,243), asbestos reporting ($1,218.20), preliminary 30% design plans ($12,720), 60% design documents ($12,515), permit applications and approvals ($9,525 total), 100% final design plans ($7,845), pre-bid and pre-construction meeting attendance, contractor submittal reviews ($3,490), construction phase assistance ($3,275), on-site observation ($4,415), substantial completion and punchlist inspection ($1,380), and final completion certification ($4,565). The total fixed price cost is $67,791.20 with reimbursable costs capped at $3,000, bringing the overall project cost to $70,791.20. Payment is contingent upon FDEP approval of deliverables for each subtask. The project schedule extends through June 30, 2023, with design and permitting activities planned for approximately 416 calendar days followed by construction phase services over approximately 120 calendar days.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
CN-370000-CN230-T53CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN230 39 FDEP 61367C

Koreshan State Park Sewage Connection

Weiler Engineering Corporation

Robin Palmer PE 941-505-1700 rpalmer@weilerengineering.org

Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov

Consultant to provide design and permitting documents to construct a wastewater collection transmission system at Koreshan State Park as per proposal dated 11/1/21.

Andrew Lippens

Upon Execution $ 47,066.20 6/30/2023 $ 3,000.00

$ 50,066.20

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.11.02 09:22:14 -04'00'

Andrew Lippens Andrew Lippens Digitally signed by Andrew Lippens Date: 2021.11.02 09:57:03 -04'00'

Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.11.02 10:00:24 -04'00'

Jeff Weiler, PE R. Jeff Weiler Digitally signed by R. Jeff Weiler Date: 2021.12.09 13:01:51 -05'00'

Michael W. Foster Jr., P.E. Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2022.01.21 08:51:59 -05'00'

61367C 37504000045 080039/22 423001 U3200 131500 QK $ 50,066.20

$ 50,066.20

October 6, 2021 - Revision 3 - November 1, 2021

Mr. Wayne Thomas

Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520 Tallahassee, FL 32399

RE: Koreshan State Park - Sewage Collection System - Contract 230, TA 39

Dear Mr. Thomas;

We are pleased to submit this proposal for design and permitting to construct a wastewater collection and transmission system at Koreshan State Park. Our general understanding is as follows:

Site #1: Art Hall Sewer Connection: Connect the existing (2) stall restroom to public sewer along US 41 (FDOT ROW) and abandon the on-site septic system.

Site #2: Manufactured Home Sewer Connection: Connection to be put into place for proposed manufactured home (staff residence). Proposed manufactured home site design will be completed by FDEP staff.

Site #3: Volunteer Village Sewer Connection: Connect several existing buildings and RV campsites to an internal sewer collection system, which will be connected to public sewer along US 41 (FDOT ROW)

There is currently sewer located at the intersection of Corkscrew and US 41 and proposed sewer along the west side of US 41. We spoke to the Utility Department and the proposed sewer is slated to begin construction at the end of next year. It appears that locations 1 and 2 will connect to sewer located along the south side of Corkscrew Road at either 1 or 2 locations.

I have stricken the CEI services for this task assignment but have left them for future reference when the BDC proceeds with construction. Additionally, we understand that the BDC will provide an inspector to provide additional observation during installation of the sewer mains and will provide photos and a daily report of the progress to the project manager..

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President The Weiler Engineering Corporation

September 28, 2021 - Rev 3 - 11/01/21 Mr. Wayne Thomas Koreshan State Park Sewage Collection System

CN 230 TN 39

Koreshan State Park Sewage Collection System

Contract Number 230, Task Assignment Number 39

Subtask 1: Survey Description: The Weiler Engineering Corporation (Consultant) will coordinate with a Florida Registered Surveyor to prepare a special purpose survey adequate for design and permitting.

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702 Marathon: 6805 Overseas Highway, Marathon, Florida 33050 | Tel 305-289-4161 | Fax 305-289-4162

Mr. Wayne Thomas

Deliverable: Consultant will provide a Signed and Sealed Special Purpose topographic survey of each site (Not a Boundary Survey) in PDF format via email to the Bureau of Design and Construction (BDC).

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 2: Asbestos Report Description: Consultant will coordinate with Universal Engineering to complete an asbestos survey/report for the four remaining septic tanks.

Deliverable: (These are the payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc)

Written results of asbestos survey will be delivered via email to the BDC via digital PDF.

Subtask 1 - Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 3 435

Dagostino 3 Person Field Crew Hr 121.50 8 972

Dagostino Survey Technician Hr 54.00 10 540

Dagostino PSM Manager Hr 162 8 1296

Dagostino Total Survey 3243

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 1 Survey

$3243.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost: (if applicable)

Subtask 4 - Asbestos Report

Firm Name Position Classification Rate Hours Total Fixed Price Cost

Weiler Engineering Registered Professional Engineer 145 1 $145.00

Registered Engineer Intern 115 1 $115.00

Universal Engineering Senior Geotechnical Engineer, PE

165.84 4 $663.36

Sr. Engineering Technician 49.14 6 $294.84

Total Asbestos Survey $1218.20

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total for Subtask 2 - Asbestos Report

$1218.20

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 3: Preliminary Design - 30% Plans Description: The Weiler Engineering Corporation (Consultant) shall conduct one site visit with staff to inspect the site and to discuss proposed ideas, research existing/available data and permits, conduct a pre-application meeting with the County, the Village of Estero and the Florida Department of Environmental Protection. WEC will evaluate the most feasible means of installation between open cut and directional bore and include the cost for each in the OPC.

Deliverable: Consultant will provide a summary of meetings with local and State regulatory agencies outlining permit requirements, plans prepared to 30% and a preliminary opinion of probable cost in PDF format via email to the Bureau of Design and Construction (BDC).

Cover Sheet Existing Conditions Best Management Plan Demolition Plan Utility Plans for each site Opinion of Probable Cost (OPC)

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 3 - Preliminary Design

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Weiler Engineering Principal in Charge 195 2 $390.00

Weiler Engineering Registered Professional Engineer 145 10 $1450.00

Weiler Engineering Registered Engineer Intern 115 12 $1380.00

Weiler Engineering Senior Engineering Designer 100 38 $3800.00

Weiler Engineering Engineering Technician 80 54 $4320.00

Weiler Engineering Clerical 55 4 $220.00

Total $12720.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Reimbursable Cost: (if applicable)

Subtask 4: 60% documents Description: Plans completed to 60% incorporating comments from 30%.

Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:

Cover Sheet Survey Existing Conditions Best Management Plan Demolition Plan Utility/Site Plan Plan and Profiles Each Site Lift station plans and details Specifications

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language) Fixed Price Cost:

Postage

Printing

Overnight Travel (if applicable) Mileage (@ $0.445 per mile)

Reimbursable Total Cost $0.00

Total Subtask 3 Preliminary Design

$12720.00

Subtask 4 – 60% Plans

Firm Name Position Classification

Hour ly

Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 8 $1160.00

Principal in Charge 195 2 $390.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Reimbursable Cost:

Subtask 5: Permitting A – Permit Applications, Description: Consultant will assist Client to submit permit applications for the Village of Estero, Lee County and the Florida Department of Environmental Protection permits.

Deliverable: Consultant shall deliver five sets of permit applications with 100% plans.

B – Permit Approvals, Description Consultant will coordinate with Client to respond to regulatory requests for additional information through approval.

Deliverable: Consultant will provide via email to the BDC the completed permits for the County, City and SWFWMD for site approvals.

Registered Professional Engineer

145 10 $1450.00

Registered Engineer Intern 115 11 $1265.00

Senior Engineering Designer 100 39 $3900.00

Engineering Technician 80 53 $4240.00

Clerical 55 2 $110.00

Total $12515.00

Postage No prints/provided digitally via email

Printing Not anticipated

Overnight Travel (if applicable) Mileage (@ $0.445 per mile) Reimbursable Total Cost

$0.00

Total Subtask 4 $12515.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Fixed Price Cost:

Reimbursable Cost:

Subtask 5A Permit Applications

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 4 $580.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer 100 22 $2200.00

Engineering Technician 80 30 $2400.00

Clerical 55 2 $110.00

Total $7275.00

Subtask 5B Permit Approvals

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 290

Principal in Charge 195 1 $195.00 Registered Professional Engineer 145 2 $290.00

Registered Engineer Intern 115 4 $460.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 7 $560.00

Clerical 55 1 $55.00

Total $2250.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 6: 100% documents Description: Plans completed to 100%.

Deliverable: Consultant shall deliver five sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Cover Sheet Survey Existing Conditions Best Management Plan Demolition Plan Utility/Site Plan Plan and Profiles Each Site Lift station plans and details Specifications

Opinion of Probable Cost

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Postage 3 Fed-x at $35 $105.00

Printing 200 sheets @ $2.30/ sheet

$460.00

County Permits $1100.00

Estero Permits Estimate $500.00

FDEP Permit $500.00

Reimbursable Total Cost $2665.00

Total for Subtask 5 $12190.00

Subtask 6 - 100 % Plans

Firm Name Position Classification Hourly Rate Hours

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 7: Assistance during bidding Description: Consultant will respond to bidders’ questions and provide clarifications during bidding.

Deliverable: Consultant will provide digital pdf of all responses and communication with bidders.

they are complete, accurate, and timely.

Fixed Price Cost:

Registered Professional Engineer 145 6 $870.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer 100 20 $2000.00

Engineering Technician 80 36 $2880.00

Clerical 55 2 $110.00

Total $7845.00

Postage 3 Fed-x at $35 = $105 105 Printing 100 sheets @ $2.30 per sheet

Overnight Travel (if applicable)

Not anticipated

Reimbursable Total Cost

$335.00

Total for Subtask 6 $8180.00

Subtask 7 Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 2 $290.00

Principal in Charge 195 0 $0.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 8: Attend a Pre-Bid meeting on-site Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

they are complete, accurate, and timely.

Fixed Price Cost:

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern 115 6 $690.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 1 $55.00

Total $1580.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage ($0.445 per mile)

Not anticipated

Reimbursable Total Cost

$0.00

Total for Subtask 7 $1580.00

Subtask 8 - Pre-bid

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 9: Attend Pre-Construction Meeting Description: WEC staff will attend one pre-construction meeting on site, respond to questions and prepare minutes.

Deliverable: WEC will provide representation at the Pre-Construction Meeting and deliver meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern 115 4 $460.00

Senior Engineering Designer 100 0 $0.00

Engineering Technician 80 0 $0.00

Clerical 55 0 $0.00

Total $1040.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated $0.00

Reimbursable Total Cost

$0.00

Total Subtask 8

$1040.00

Subtask 9 - Pre-construction Mtg

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 10: Review Contractor submittals

Description: WEC will provide engineering review of Contractor's shop drawing submittals. WEC will prepare an anticipated submittal list and maintain a log.

Deliverable: WEC will review and comment on Contractor submittal package within 7 days of receipt and provide stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 0 $0.00

Senior Engineering Designer

100 4 $400.00

Engineering Technician 80 0 $0.00

Clerical 55 0 $0.00

Total $980.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0

Reimbursable Total Cost

$0.00

Total Subtask 9 $980.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Subtask 11: Assistance during construction (3 Months)

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase. WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Deliverable: Correspondence with Contractor and regulatory agencies provided via

PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 10 - Submittal Review

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern

115 16 $1840.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician

80 2 $160.00

Clerical 55 2 $110.00

Total $3490.00

Postage Not anticipated (all deliverables in digital form only)

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Not anticipated

Reimbursable Total Cost

$0.00

Total Subtask 10 - Submittals

$3490.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Fixed Price Cost:

Subtask 12: On-Site Observation

Description: Utilizing photos and reports from BDC inspector and weekly visits by a WEC inspector, WEC will provide on-site observation during installation of sewer mains, connection to offsite mains and installation and startup of lift stations.

Deliverable: Progress reports provided via PDF.

Subtask 11

Firm Name Position Classification Hourly Rate

Ho urs

Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 4 $580.00

Registered Engineer Intern

115 8 $920.00

Senior Engineering Designer

100 6 $600.00

Engineering Technician 80 0 $0.00

Clerical 55 2 $110.00

Total $3275.00

Postage Not anticipated

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $0.00

Total Subtask 11 $3275.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Fixed Price Cost:

Reimbursable Cost:

Subtask 13: Substantial Completion Walk-Through w/Punchlist Description: WEC will assist Client with the Substantial Completion inspection and punch list, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punch list.

Subtask 12

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 6 $870.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 0 $0.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer 100 4 $400.00

Engineering Technician 80 24 $1920.00

Clerical 55 2 $110.00

Total $4415.00

Postage Not anticipated

Printing Not anticipated (all deliverables in digital form only)

Overnight Travel (if applicable) Not anticipated

Mileage (@ $0.445 per mile) Not anticipated

Reimbursable Total Cost $0.00

Total Subtask 12 $4415.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Deliverable: WEC will provide punchlist and input on punch list within one (1) day of Substantial Completion inspection.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Subtask 14: Final Completion w/ Certification

Description: WEC will assist Client with the Final Completion Certification of the site with WEC representative attending the Final Completion inspection.

Subtask 13

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Project Manager 145 4 $580.00

Principal in Charge 195 1 $195.00

Registered Professional Engineer

145 1 $145.00

Registered Engineer Intern

115 4 $460.00

Senior Engineering Designer

100 0 $0.00

Engineering Technician 80 0 $0.00

Clerical 55 0 $0.00

Total $1380.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 13 $1380.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Deliverable: WEC will prepare final as-built drawings based on surveyed information from Contractor and prepare certifications necessary for regulatory close out and deliver five sets of record plans and certifications and one PDF set via email.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Fixed Price Cost:

Reimbursable Cost:

Project Schedule:

Subtask 14 - Final

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering Prroject Manager 145 4 $580.00

Principal in Charge 195 0 $0.00

Registered Professional Engineer

145 2 $290.00

Registered Engineer Intern 115 8 $920.00

Senior Engineering Designer

100 8 $800.00

Engineering Technician 80 24 $1920.00

Clerical 55 1 $55.00

Total $4565.00

Postage Not anticipated

Printing Not anticipated

Overnight Travel (if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

$0.00

Reimbursable Total Cost

$0.00

Total Subtask 14 $4565.00

Activity Duration (Calendar Days) Dates to be based on date of execution of task order

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Summary of Fees:

Subtask 1 Survey 45

Subtask 2 Asbestos 30

Subtask 3 30% Plans 30

Subtask 4: 60% plans 21 - includes 7 days for Client review

Subtask 5A: Permit applications 30 – includes 7 days for Client review

Subtask 5B: Permit approvals 240 – includes 7 days for Client review

Subtask 6: 100% plans 30 – includes response for additional information

Subtask’s 7-14 120

Subtask Subtask Fixed Price Cost

Subtask Reimbursable

Subtask 1 Survey $3243.00 $0.00

Subtask 2 Asbestos $1218.20 $0.00

Subtask 3 30% Plans $12720.00 $0.00

Subtask 4: 60% plans $12515.00 $0.00

Subtask 5A: Permit applications $7275.00 $2665.00

Subtask 5B: Permit approvals $2250.00 $0.00

Subtask 6: 100% plans $7845.00 $335.00

Total Design & Permitting $50066.20 $47066.20 $3000.00

Subtask 7: Assistance during bidding

$1580.00 $0.00

Subtask 8: Pre-bid meeting $1040.00 $0.00 Subtask 9: Attend Pre-Con Mtg $980.00 $0.00

Subtask 10: Review Submittals $3490.00 $0.00

Subtask 11: Assistance during Construction - 2 Months

$3275.00 $0.00

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

Mr. Wayne Thomas

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)

Subtask 12: On Site Observation 3

- Weeks

$4415.00 $0.00

Subtask 13: Substantial Completion Walk-Through w/ Punchlist

$1380.00 $0.00

Subtask 14: Final Completion w/ Certification

$4565.00 $0.00

Subtotal Construction Services $20725.00 $20725.00 $0.00

Total Fixed Price $67791.20

Total Reimbursable Cost $3000.00

Total Overall Cost $70791.20

Punta Gorda: 201 West Marion Avenue - Suite 1306 | Punta Gorda, Florida 33950 | Tel 941 - 505 - 1700 | Fax 941-505-1702

BLANK TA FORM
rev 3 11012021 Proposal Koreshan SP Sewer

File details come from the government source that posted it. Updated .