CN-370000-CN230-T61CO1.pdf
PDF 4 MB Posted
- Contract number
- CN230
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for engineering and construction administration services related to Hurricane Ian damage repairs at Cayo Costa State Park. The contract involves FDEP as the client, Weiler Engineering Corporation as the consultant, and multiple sub-consultants including CHW, Universal Engineering, and Passarella for specialized services. The change order modifies existing contract CN230, Task Assignment TA61, and extends the project timeline and budget to accommodate comprehensive design, permitting, and construction oversight services.
The contract provides engineering, permitting, and construction administration services for design plans to replace structures damaged by Hurricane Ian at Cayo Costa State Park. The total contract value is $702,940.96, comprising $682,625.36 in fixed fee costs and $40,975.60 in reimbursable expenses, with an increase of $40,975.60 from previous change orders. Services include 30%, 60%, and 100% design development across five buildings and waterside dredging areas, permit applications and approvals for upland and in-water work, 16 monthly construction inspections over 18 months, submittal reviews, response to contractor requests for information, and substantial and final completion certifications. The original task end date of February 28, 2025 was extended to December 31, 2026, representing a net change of 671 days to accommodate design, permitting, and construction phases. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
(Revised 9-26-2018) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 TA61 1 6I408C (formerly 6I403C)
Hurricane Ian Redevelopment
Weiler Engineering Corporation
R. Jeff Weiler, P.E. (941) 505-1700 weiler7@mac.com
Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Consultant to provide engineering, permitting, and construction administration services for design plans to replace structures damaged by Hurricane Ian, per attached proposal dated May 30, 2023, as well as time extension per request on June 13, 2023.
$ 0.00 $ 20,660.00 $ 20,660.00 $ 0.00 $ 20,660.00 $ 20,660.00
$ 40,975.60 $ 661,965.36 $ 702,940.96 $ 40,975.60 $ 682,625.36 $ 723,600.96
02/08/2023
02/28/2025
02/28/2025
12/31/2026
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.15 10:20:20 -04'00'
Terry McCullum, Jr. Terry McCullum, Jr.
Digitally signed by Terry McCullum, Jr.
Date: 2023.06.15 10:23:26 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.15 11:36:34 -04'00'
R. Jeff Weiler, P.E.
Mara Gambineri Mara Gambineri Digitally signed by Mara Gambineri Date: 2023.07.14 21:35:54 -04'00' 7/14/2023
6I408C FD091 37504003127 088040/23 675002 U3200 131500 XR $ 702,940.96
$ 702,940.96
Cayo Costa State Park
Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.22 12:13:54 -04'00'
McCullum, Terry
From: rpalmer@weilerengineering.org Sent: Tuesday, June 13, 2023 1:55 PM To: McCullum, Terry Subject: TA61 Cayo Costa State Park Time Extension Request
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Hi Terry, The current TA61 for the Cayo Costa State Park: Park Redevelopment from Hurricane Ian expires on 2/28/2025. I am reques ng a me extension for this task assignment un l December 31, 2026 in order to provide enough me for design, permi ng, and construc on services for the project. Please let me know if you have any ques ons.
Thank you, Robin Palmer, P.E.
Environmental Engineer
March 30, 2023 - Revision 5 - May 30, 2023
Mr. Terry McCullum, Jr
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard 260-L, MS 520
Tallahassee, FL 32399
RE: Cayo Costa State Park - Hurricane Damage Repairs - Design and Permitting, CN -
230, TA - 61 - Change Order No. 1
Dear Mr. McCullum, Thank you for the opportunity to provide this proposal to assist the Department to prepare the necessary plans and documentation to demolish and replace the buildings (Upland work landward of MHWL) and dredge (work waterside of MHWL) the Cayo Costa Marina and Jug Creek as outlined below:
Site 1: Existing Conditions
*Buildings 1 & 2 were demolished and removed by FEMA after Hurricane Ian.
Building 3 and the bicycle shed are still present and will be removed as part of this scope.
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG http://www.weilerengineering.org/ mailto:INFO@WEILERENGINEERING.ORG
April 6, 2023 - Rev 5 - 05/30/23 Mr. Terry McCullum, Jr Cayo Costa State Park Hurricane Repairs
CN 230/TA61 - CO 1
Site 1: Proposed Conditions - Upland – Maintenance
Building (Building 1), Pole Barn (Building 2), Gift Shop (Building
3) (See above) & Waterside - Dredge Cayo Costa Marina (See below)
Mr. Terry McCullum, Jr Cayo Costa State Park
Site 2 - Upland - Residence was demolished by Hurricane Ian. To be reconstructed in the same location under this contract. (No in-water work this site).
Site 3 - Upland - New Storage bldg. ti elevating site & Waterside - Dredge Jug Creek access
Mr. Terry McCullum, Jr Cayo Costa State Park
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.
Please feel free to contact me if you have any questions or wish to discuss matters further.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
Hurricane Repairs - Design & Permitting Cayo Costa State Park
Contract Number 230, Task Assignment Number 61 Change Order No. 1
Subtask 1: 30% Site 1, 2 & 3 Site/Civil Development Design
1) A - Design
a) WEC will conduct one site visit.
b) Consultant will conduct a pre-application meeting with the Army Corps of Engineers, Water Management District or FDEP and the Local Regulatory agency.
c) Consultant will prepare a site plan for each site.
1) B – Surveys
a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose
Survey of the existing structures and area 50 feet beyond the structures and a Bathymetric
Survey of Jug Creek and the Cayo Costa Marina.
1) C –Geotechnical Reports
a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct soil borings and sub-surface investigation to establish bearing capacities and foundation requirements.
Mr. Terry McCullum, Jr Cayo Costa State Park
1) D – Lead/Asbestos Reports
a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct NESHAP
Asbestos and Lead Based paint screening (up to 50 samples for asbestos and 5 lead samples) on the gift shop, bicycle shed, and ramp to the Ranger Station.
1) E – Benthic Report
a) Consultant will coordinate with an Environmental Sub-Consultant to conduct Complete a Benthic survey of the area proposed for dredging in Jug Creek & Cayo Costa Marina.
Deliverable:
1) A - Site’s 1,2 & 3 Site & Dredging 30% Plans, Conceptual Site – Consultant shall deliver 30% Civil Plans for all three sites to the client via digital PDF. Plans will include:
Cover sheet
Survey
Existing Conditions
Best Management Plan
Demolition Plan to remove Gift Shop and Bicycle shed
Site Plans
1) B - Surveys
Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey of the upland improvement areas and bathymetric survey of Jug
Creek & Cayo Costa Marina via CAD and a digitally Signed and Sealed PDF.
1) C –Geotechnical Reports
Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report identifying structural capacities of the subsurface beneath the proposed structures via digital PDF.
Mr. Terry McCullum, Jr Cayo Costa State Park
1) D – Lead/Asbestos Report
Written results of asbestos survey will be delivered via email to the BDC via digital PDF. Lead
Asbestos testing will be completed on the existing gift shop, ranger station ramp, and bicycle shed only. All other existing structures that are within the scope of the project were previously demolished by FEMA after Hurricane Ian.
1) E – Benthic Survey
Written results of the Benthic survey of Jug Creek and the Cayo Costa Marina will be delivered via email to the BDC via digital PDF.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1A - 30% Plans Site’s 1,2 & 3
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 31 4495
Weiler Engineering
Principal in Charge 195 6 1170
Weiler Engineering
Registered Professional Engineer
145 38 5510
Weiler Engineering
Registered Engineer Intern 115 62 7130
Weiler Engineering
Senior Engineering Designer 100 140 14000
Weiler Engineering
Engineering Technician 80 188 15040
Weiler Engineering
Clerical 55 15 825
Total
48170
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 1B - Survey
Firm Name Position Classification Unit Unit Rate Number Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 10 1450
CHW 3 Person Field Crew Hr 177.54 112 19884.48
CHW Project Surveyor Hr 74.75 40 2990
CHW Professional Surveyor & Mapper
Hr 163.93 32 5245.76
CHW Senior CAD/GIS Hr 103.13 64 6600.32
Total Survey 36170.56
Subtask 1C Geotech
Firm Name Position Classification Unit Unit Rate
Number Units
Total Fixed Price Cost
Weiler Engineering Project Manager Hr 145 4 580
Universal
Universal Senior Project Engineer Hr 165.84 60 9950.4
Universal Project Engineer Hr 94.50 60 5670
Universal Staff Engineer Hr 68.46 120 8215.2
Universal CAD Drafting Hr 54.00 120 6480
Universal Total Geotech 30895.6
Subtask 1D - Lead/Asbestos Report
Firm Name Position Classification Rate Hours Total Fixed
Price Cost
Weiler Engineering Registered Professional
Engineer
145 2 290
Mr. Terry McCullum, Jr Cayo Costa State Park Hurricane Repairs
CN 230/TA61 - CO 1
Registered Engineer
Intern
115 2 230
Universal Engineering Senior Geotechnical
Engineer. PE
165.84 40 6633.6
Sr Engineering
Technician
49.14 60 2948.4
Total Sub-Task 1D Total Lead/Asbestos
Report
10102
Subtask 1E - Benthic Report
Firm Name Position Classification Rate Hours Total Fixed
Price Cost
Weiler Engineering Registered Professional
Engineer
145 4 580
Registered Engineer
Intern
115 4 460
Passarella Senior Ecologist 149.50 32 4784
Passarella Ecologist 104.65 48 5023.2
Total Sub-Task 1E Benthic Report 10847.2
Reimbursable Cost: (if applicable)
Mr. Terry McCullum, Jr Cayo Costa State Park
Description Number @ Total
Postage
Printing
Overnight Travel
(if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total Cost 1A
Total Subtask 1 136185.36
Subtask 2A: Gift Shop Building Design 30% documents
Description: Plans completed to 30% to be included with 30% Site Plans.
Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:
Individual Site Plan
Floor Plan
Exterior Elevations
Subtask 2A - 30% Gift Shop Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 9 1305
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 8 1160
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler
Registered Engineer Intern 115 20 2300
Weiler Engineering
Senior Engineering Designer 100 37 3700
Weiler Engineering
Engineering Technician 80 37 2960
Weiler
Clerical 55 4 220
12035
Printing
0.445 0
Reimbursable Total Cost 2A
Total Subtask 2A Gift Shop 30%
12035
Subtask 2B: 3 Bay Shop Bldg Building Design 30% documents
Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:
Individual Site Plan
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 2B - 30% Shop Building Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 8 1160
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 8 1160
Weiler Engineering
Registered Engineer Intern 115 20 2300
Weiler Engineering
Senior Engineering Designer 100 37 3700
Weiler Engineering
Engineering Technician 80 37 2960
Weiler
Clerical 55 4 220
11890
Description Number @ Total
Postage
Printing
0.445 0
Reimbursable Total Cost 2B
Total Subtask 2B Gift Shop 30%
11890
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 2C: Pole Barn Building Design 30% documents
Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:
Individual Site Plan
Subtask 2C - 30% Pole Barn Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 5 725
Weiler Engineering
Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer
145 8 1160
Weiler Engineering
Registered Engineer Intern 115 24 2760
Weiler Engineering
Senior Engineering Designer 100 24 2400
Weiler Engineering
Engineering Technician 80 26 2080
Weiler
Clerical 55 2 110
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing
0.445 0
Reimbursable Total Cost 2C
Total Subtask 2C Pole Barn 30%
Subtask 2D: Residence Building Design 30% documents
Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:
Individual Site Plan
Subtask 2D - 30% Residence Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 24 3480
Weiler Engineering
Principal in Charge 195 4 780
Weiler Engineering
Registered Professional Engineer
145 22 3190
Weiler
Registered Engineer Intern 115 28 3220
Mr. Terry McCullum, Jr Cayo Costa State Park
Senior Engineering Designer 100 88 8800
Weiler Engineering
Engineering Technician 80 116 9280
Weiler
Clerical 55 11 605
29355
Printing
0.445 0
Reimbursable Total Cost 2D
Total Subtask 2D Residence 30%
29355
Subtask 2E: Jug Creek Storage Building Design 30% documents
Description: Plans completed to 30% to be included with 30% Site Plans.
Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:
Individual Site Plan
Mr. Terry McCullum, Jr Cayo Costa State Park
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 5 725
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 8 1160
Weiler Engineering
Registered Engineer Intern 115 30 3450
Weiler Engineering
Senior Engineering Designer 100 30 3000
Weiler Engineering
Engineering Technician 80 25 2000
Weiler
10835
Printing
0.445 0
Reimbursable Total Cost 2E
Total Subtask 2E Storage bldg 30%
10835
Subtask 2E - 30% Jug Creek Storage Bldg Plans
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 3: 60% Site/Civil Documents Site’s 1,2 & 3
Description: Site plans completed to 60% incorporating comments from 30% Site Documents.
Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost for each site (Broken down by site, with tabled project total summary)
Cover sheet
Survey
Existing Conditions
Best Management Plan
Demolition Plan
Site, Utility & Grading Plans
Dredging Plan & Details incl. spoil location
Site Details and General Notes
Sections
Subtask 3 - 60% Site Development Plans Site’s 1,2 & 3
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 45 6525
Weiler Engineering
Principal in Charge 195 7 1365
Weiler Engineering
Registered Professional Engineer
145 38 5510
Weiler Engineering
Registered Engineer Intern 115 60 6900
Weiler Engineering
Senior Engineering Designer 100 151 15100
Weiler
Engineering Technician 80 207 16560
Mr. Terry McCullum, Jr Cayo Costa State Park
Clerical 55 15 825
Total 52785
Printing
0.445 0
Reimbursable Total Cost
Total Subtask 3 S & D 60%
52785
Subtask 4A: Gift Shop Building Design 60% documents
Description: Plans completed to 60% to be included with 60% Site Plans.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Site Plan
Floor Plans
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Building Cross sections and details
MEP Plans
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 4A - 60% Gift Shop Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 15 2175
Weiler Engineering
Principal in Charge 195 3 585
Weiler Engineering
Registered Professional Engineer
145 13 1885
Weiler Engineering
Registered Engineer Intern 115 30 3450
Weiler Engineering
Senior Engineering Designer 100 62 6200
Weiler Engineering
Engineering Technician 80 70 5600
Weiler
Clerical 55 7 385
Total 4A Gift Shop 60% Plans
20280
Printing
0.445 0
Reimbursable Total Cost 4A
Total Subtask 4A Gift Shop 60%
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 4B: 3 Bay Shop Bldg Building Design 60% documents
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Site Plan
Floor Plans
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Subtask 4B - 60% Shop Building Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 15 2175
Weiler Engineering
Principal in Charge 195 3 585
Weiler Engineering
Registered Professional Engineer
145 13 1885
Weiler Engineering
Registered Engineer Intern 115 30 3450
Weiler Engineering
Senior Engineering Designer 100 62 6200
Weiler Engineering
Engineering Technician 80 70 5600
Weiler
Clerical 55 7 385
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing
0.445 0
Reimbursable Total Cost 4B
Total Subtask 4B Shop Building 60%
Subtask 4C: Pole Barn Building Design 60% documents
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Floor Plans
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Subtask 4C - 60% Pole Barn Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler
Project Manager 145 10 1450
Mr. Terry McCullum, Jr Cayo Costa State Park
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 8 1160
Weiler Engineering
Registered Engineer Intern 115 16 1840
Weiler Engineering
Senior Engineering Designer 100 38 3800
Weiler Engineering
Engineering Technician 80 48 3840
Weiler
Clerical 55 3 165
12645
Printing
0.445 0
Reimbursable Total Cost 4C
Total Subtask 4C Pole Barn 60%
12645
Subtask 4D: Residence Building Design 60% documents
Mr. Terry McCullum, Jr Cayo Costa State Park
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Floor Plans
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Subtask 4D - 60% Residence Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 22 3190
Weiler Engineering
Principal in Charge 195 4 780
Weiler Engineering
Registered Professional Engineer
145 18 2610
Weiler Engineering
Registered Engineer Intern 115 32 3680
Weiler Engineering
Senior Engineering Designer 100 70 7000
Weiler Engineering
Engineering Technician 80 95 7600
Weiler
Clerical 55 6 330
25190
Printing
Mr. Terry McCullum, Jr Cayo Costa State Park
0.445 0
Reimbursable Total Cost 4D
Total Subtask 4D Residence 60%
25190
Subtask 4E: Jug Creek Storage Building Design 60% documents
Floor Plans
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Building Cross sections and details
Onsite sewage disposal system plans and details
Subtask 4E - 60% Jug Creek Storage bldg. Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 22 3190
Weiler Engineering
Principal in Charge 195 4 780
Weiler Engineering
Registered Professional Engineer
145 20 2900
Weiler
Registered Engineer Intern 115 37 4255
Mr. Terry McCullum, Jr Cayo Costa State Park
Senior Engineering Designer 100 76 7600
Weiler Engineering
Engineering Technician 80 95 7600
Weiler
Clerical 55 6 330
26655
Printing
0.445 0
Reimbursable Total Cost 4E
Total Subtask 4E Storage bldg. 60%
26655
Subtask 5: Site 1, 2 & 3 Upland Site/Civil Permitting Excluding Dredging Jug Creek and
Cayo Costa Marina
Description:
5) A – Permit Applications (Upland Work)
Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals as follows:
Lee County:
Site #1- LDO Site #2- Septic Permit (DOH) Site #3- LDO + Septic Permit (DOH)
SFWMD:
Site #1: ERP - Uplands only Site #2: Verification of Exemption Site #3- ERP - Uplands only
Mr. Terry McCullum, Jr Cayo Costa State Park
State Fire Marshal:
Site #1: Required Site #2: Required Site #3: Required
5) B – Permit Approvals, Consultant will coordinate with agencies and assist Client to respond to agencies for additional information.
Deliverable:
5) A – Permit Applications
Incorporate Client review comments from 60% plans and deliver permit applications for the Lee County
LDO permits, Florida Department of Health (Septic Permit), and SFWMD applications in PDF format with the
Delivery of the 60% design plans. The SFM Application is completed online and no signature is needed.
5) B – Permit Approvals
Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. Approvals from Lee County (LDO), ERP/Verification of Exemptions from
SFWMD, and Department of Health, and State Fire Marshal will be provided in PDF format.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are
Subtask 5A Site 1,2 & 3 Upland Permit Applications No Dredging
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 25 3625
Weiler Engineering
Principal in Charge 195 4 780
Weiler
Registered Professional Engineer 145 20 2900
Mr. Terry McCullum, Jr Cayo Costa State Park
Registered Engineer Intern 115 32 3680
Weiler Engineering
Senior Engineering Designer 100 83 8300
Weiler Engineering
Engineering Technician 80 112 8960
Weiler Engineering
Clerical 55 11 605
Total 5A - Upland Permit Applications 1,2 & 3
28850
Subtask 5B Site 1, 2 & 3 Upland Permit Approvals
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 7 1015
Weiler Engineering
Principal in Charge 195 1 195
Weiler Engineering
Registered Professional Engineer 145 5 725
Weiler Engineering
Registered Engineer Intern 115 10 1150
Weiler Engineering
Senior Engineering Designer 100 16 1600
Weiler Engineering
Engineering Technician 80 16 1280
Weiler Engineering
Clerical 55 1 55
Total 5B - Permit approvals 1, 2 & 3 6020
Reimbursable Cost:
Postage 1 35 35
Printing 210 2.3 483
Mr. Terry McCullum, Jr Cayo Costa State Park
Permit application fees estimate
1 25000 25000
Reimbursable Total Cost for 5A
25515
Total for
Subtask 5
60388
Subtask 6: Site 1 & 3 Dredge & Fill Permitting
Description:
6) A – Permit Applications Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals to Lee County for LDO, the South Florida Water Management District for ERP and the ACOE
For the dredging permits for Cayo Costa and Jugg Creek.
6) B – Permit Approvals, Consultant will coordinate with agencies and assist Client to respond to agencies for additional information.
Deliverable:
6) A – Permit Applications Incorporate Client review comments from 60% plans and deliver permit applications for Lee County, SFWMD, and ACOE in PDF format.
6) B – Permit Approvals
Depends on agencies but anticipate at least 180 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with permits and revised (if necessary) plans and documentation in PDF format.
Mr. Terry McCullum, Jr Cayo Costa State Park
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 42 6090
Weiler Engineering
Principal in Charge 195 6 1170
Weiler Engineering
Registered Professional Engineer 145 34 4930
Weiler Engineering
Registered Engineer Intern 115 54 6210
Weiler Engineering
Senior Engineering Designer 100 138 13800
Weiler Engineering
Engineering Technician 80 180 14400
Weiler Engineering
Clerical 55 18 990
Total 6A Site 1 & 3 Applications (In- Water Work)
47590
Subtask 6B Sites 1 & 3 Dredge & Fill Permit Approvals
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 10 1450
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer 145 7 1015
Weiler Engineering
Registered Engineer Intern 115 12 1380
Weiler Engineering
Senior Engineering Designer 100 20 2000
Weiler Engineering
Engineering Technician 80 20 1600
Subtask 6A Sites 1 & 3 Dredge & Fill Permit Applications
Mr. Terry McCullum, Jr Cayo Costa State Park
Clerical 55 1 55
Total 6B - Sites 1 & 3 Dredge & Fill Approvals
Printing 210 2.3 483
Permit application fees estimate
1 14000 14000
Reimbursable Total Cost for 6A
14518
Subtask 6
69998
Subtask 7A: Gift Shop Building Design 100% documents
Description: Plans completed to 100%.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure only including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Site Plan
Floor Plan
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 7A - 100% Gift Shop Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 6 870
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 6 870
Weiler Engineering
Registered Engineer Intern 115 8 920
Weiler Engineering
Senior Engineering Designer 100 20 2000
Weiler Engineering
Engineering Technician 80 28 2240
Weiler
Total 7A Gift Shop 100%
Printing 40 2.80 112
0.445 0
Reimbursable Total Cost 7A
Total Subtask 7A Gift Shop 100%
Subtask 7B: 3 Bay Shop Bldg Building Design 100% documents
Mr. Terry McCullum, Jr Cayo Costa State Park
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:
Site Plan
Floor Plan
Foundation/Piling Plans and details;
Beam schedules
Exterior Elevations
Subtask 7B - 100% Shop Building Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 6 870
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 6 870
Weiler Engineering
Registered Engineer Intern 115 8 920
Weiler Engineering
Senior Engineering Designer 100 20 2000
Weiler Engineering
Engineering Technician 80 28 2240
Weiler
Total 7B - Shop Bldg. Plans
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 40 2.8 112
0.445 0
Reimbursable Total Cost 7B
Total Subtask 7B Shop Building 100%
Subtask 7C: Pole Barn Building Design 100% documents
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Site Plan
Floor Plan
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 7C - 100% Pole Barn Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 4 580
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 4 580
Weiler Engineering
Registered Engineer Intern 115 6 690
Weiler Engineering
Senior Engineering Designer 100 14 1400
Weiler Engineering
Engineering Technician 80 18 1440
Weiler
Total 7C Pole Barn 100% Plans
Printing 40 2.80 112
0.445 0
Reimbursable Total Cost 7C
Total Subtask 7C Pole Barn 100%
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 7D: Residence Building Design 100% documents
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:
Site Plan
Floor Plan
Foundation/Piling Plans and details
Beam schedules
Exterior Elevations
Fixed Price Cost:
Subtask 7D - 100% Residence Plans
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 8 1160
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 6 870
Weiler Engineering
Registered Engineer Intern 115 10 1150
Weiler Engineering
Senior Engineering Designer 100 28 2800
Weiler Engineering
Engineering Technician 80 38 3040
Weiler Engineering
Clerical 55 4 220
Total 7D - Residence 100 % Plans
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 52 2.80 145.6
0.445 0
Reimbursable Total Cost 4D
145.6
Total Subtask 7D Residence 100%
9775.6
Subtask 7E: Jug Creek Storage Building Design 100% documents
Description: Plans completed to 100%.
Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:
Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Site Plan
Floor Plan
Foundation/Piling Plans and details
Beam Schedules
Exterior Elevations
Building Cross sections and details
Onsite sewage disposal system Plans and Details
Fixed Price Cost:
Subtask 7E - 100% Jug Creek Storage bldg Plans
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price
Mr. Terry McCullum, Jr Cayo Costa State Park
Project Manager 145 4 580
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 6 870
Weiler Engineering
Registered Engineer Intern 115 8 920
Weiler Engineering
Senior Engineering Designer 100 18 1800
Weiler Engineering
Engineering Technician 80 20 1600
Weiler Engineering
Clerical 55 3 165
Total 7E - Jug Creek Storage bldg 100 % Plans
Printing 40 2.80 112
0.445 0
Reimbursable Total Cost 7E
Total Subtask 7E Jug Creek Storage bldg 100%
Subtask 8: 100% Site’s 1,2 & 3 Upland Site/Civil Documents
Description: Site Development plans for upland improvements completed to 100%.
Mr. Terry McCullum, Jr Cayo Costa State Park
Deliverable: Incorporate Client review of 100% plans, Consultant shall deliver two (2) sets of
100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Updated Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Opinion of Probable Cost;
Cover sheet
Survey
Existing Conditions
Best Management Plan
Demolition Plan
Site, Utility & Grading Plans incl Septic for residence only
Subtask 8 - 100% Site’s 1,2 & 3 Upland Site & Development Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 24 3480
Weiler Engineering
Principal in Charge 195 3 585
Weiler Engineering
Registered Professional Engineer
145 22 3190
Weiler Engineering
Registered Engineer Intern 115 34 3910
Weiler Engineering
Senior Engineering Designer 100 82 8200
Weiler Engineering
Engineering Technician 80 112 8960
Weiler Engineering
Clerical 55 9 495
Total 28820
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 60 2.30 138
Overnight Travel
(if applicable)
Reimbursable Total Cost
Subtask 8
100% Site’s 1, 2, & 3 S/Civil
Plans
28993
Subtask 9: 100% Site 3 Site/Civil Documents (In-Water Work) Description:
Site Development plans completed to 100% for in-water work (dredging).
Deliverable: Incorporate Client review of 100% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Updated Opinion of Probable Cost (Broken down by site, with tabled project total summary)
Survey
Existing Conditions
Best Management Plan
Demolition Plan
Site, Utility & Grading Plans
Dredging Plan & Details incl. spoil location & BMP
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 9 - 100% Site 3 Site & Development Plans
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 20 2900
Weiler Engineering
Principal in Charge 195 2 390
Weiler Engineering
Registered Professional Engineer
145 18 2610
Weiler Engineering
Registered Engineer Intern 115 28 3220
Weiler Engineering
Senior Engineering Designer 100 68 6800
Weiler Engineering
Engineering Technician 80 94 7520
Weiler Engineering
Clerical 55 8 440
Total 23880
Printing 60 2.30 138
Overnight Travel
(if applicable)
Reimbursable Total Cost
Subtask 9 Site
3 100% S/Civil
Plans (In-
Water)
24053
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 10: Attend a Pre-Bid meeting on-site
Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 10 - Pre-bid
Firm Name Position Classification Hourly
Rate
Hours Total
Fixed
Price
Cost
Weiler Engineering Project Manager 145 8 $1160.00
Weiler Engineering Principal in Charge 195 0 $0.00
Weiler Engineering Registered Professional Engineer
145 0 $0.00
Weiler Engineering Registered Engineer Intern 115 8 $920.00
Weiler Engineering Senior Engineering Designer 100 8 $800.00
Weiler Engineering Engineering Technician 80 8 $640.00
Weiler Engineering Clerical 55 0 $0.00
Total $3520.00
Postage Not anticipated
Overnight Travel
(if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
$0.00
$0.00
Mr. Terry McCullum, Jr Cayo Costa State Park
Total Subtask 10 $3520.00
Subtask 11: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 11 - Pre-Construction Mtg
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 2 110
Total 2990
Postage 0
Printing 2.3 0
Mr. Terry McCullum, Jr Cayo Costa State Park
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 0
Reimbursable Total Cost 0
Total subtask 11 2990
Subtask 12: Review Contractor Submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Subtask 12 - Review Submittals
Cost
Weiler Engineering Project Manager 145 2 290
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 0 0
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 16 1600
Weiler Engineering Engineering Technician 80 6 480
Weiler Engineering Clerical 55 2 110
Total 4320
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 0 applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total
Total Subtask 12 4320
Subtask 13: Respond to Contractor RFI's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase 18 months.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 13- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 77 11165
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 18 2610
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 20 1600
Weiler Engineering Clerical 55 4 220
Total 20355
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 6C 20355
Subtask 14A: Provide Construction Inspections (Month 1)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 14A - Month 1 Inspection
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Weiler Engineering Clerical 55 0 0
Total 2252.5
Mr. Terry McCullum, Jr Cayo Costa State Park
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total
Total Subtask 14A 2252.5
Subtask 14B: Construction Inspection (Month 2)
Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 14B
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Senior Engineering Designer 100 1 100
Weiler Engineering Engineering Technician 80 0 0
Total 2252.5
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Reimbursable Total
Total Subtask 14B 2252.5
Subtask 14C: Construction Inspection (Month 3)
Subtask 14C Month 3 Inspection
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Total 2952.5
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14C 2952.5
Subtask 14D: Construction Inspection (Month 4)
Subtask 14D - Inspection Month 4
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Total 1937.5
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
0.445 0
Total Subtask 14D 1937.5
Subtask 14E: Construction Inspection (Month 5)
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14E Month 5 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14E 1937.5
Subtask 14F: Construction Inspection (Month 6)
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14F Month 6 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14F 1937.5
Subtask 14G: Construction Inspection (Month 7)
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14G Month 7 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14G 1937.5
Subtask 14H: Construction Inspection (Month 8)
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14H Month 8 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14H 1937.5
Subtask 14I: Construction Inspection (Month 9)
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14I Month 9 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14I 1937.5
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14J: Construction Inspection (Month 10)
Subtask 14J Month 10 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14J 1937.5
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 14K: Construction Inspection (Month 11)
Subtask 14K Month 11 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Mr. Terry McCullum, Jr Cayo Costa State Park
Total Subtask 14K 1937.5
Subtask 14L: Construction Inspection (Month 12)
Subtask 14L Month 12 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Mr. Terry McCullum, Jr Cayo Costa State Park
Total Subtask 14L 1937.5
Subtask 14M: Construction Inspection (Month 13)
Subtask 14M Month 13 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Mr. Terry McCullum, Jr Cayo Costa State Park
Total Subtask 14M 1937.5
Subtask 14N: Construction Inspection (Month 14)
Subtask 14N Month 14 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Printing 0
Overnight Travel (if
Mr. Terry McCullum, Jr Cayo Costa State Park
Mileage (@ $0.445 per mile)
Total Subtask 14N 1937.5
Subtask 14O: Construction Inspection (Month 15)
Subtask 14O Month 15 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr Cayo Costa State Park
Mileage (@ $0.445 per mile)
Total Subtask 14O 1937.5
Subtask 14P: Construction Inspection (Month 16)
Deliverable: WEC will provide one digitally signed and sealed reports to the FDEP Project
Subtask 14P Month 16 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 .5 72.5
Weiler Engineering Registered Engineer Intern 115 8 920
Weiler Engineering Senior Engineering Designer 100 8 800
Weiler Engineering Engineering Technician 80 0 0
Mr. Terry McCullum, Jr Cayo Costa State Park
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 14P 1937.5
Subtask 15A: Substantial Completion Walk-Through w/Punchlist Site’s 1, 2 & 3 Upland Improvements
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.
Subtask 15 Substantial
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 4 580
Weiler Engineering Registered Engineer Intern 115 16 1840
Weiler Engineering Senior Engineering Designer 100 16 1600
Weiler Engineering Engineering Technician 80 0 0
Total 5400
Mr. Terry McCullum, Jr Cayo Costa State Park
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 15A
Substantial 1,2,3
Uplands
Subtask 15B: Substantial Completion Walk-Through w/Punchlist Buildings input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of
Subtask 15B Substantial Buildings
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 6 870
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Engineering Technician 80 0 0
Total 6550
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 15B
Substantial Buildings
Subtask 15C: Substantial Completion Walk-Through w/Punchlist Site’s 1 & 3 Dredge and Fill input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of
Subtask 15C Substantial Site’s 1 & 3 Dredge & Fill
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Registered Professional Engineer 145 8 1160
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Registered Engineer Intern 115 24 2760
Weiler Engineering Senior Engineering Designer 100 24 2400
Weiler Engineering Engineering Technician 80 0 0
Total 7700
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 15A
Substantial 1,2,3
Uplands
Subtask 16: Final Completion w/ Certification Sites 1,2 & 3 Upland Improvements
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor’s surveyor.
Deliverable: WEC will provide completed record drawings and certifications to FDEP Project Manager in PDF via email.
Subtask 16 - Final Site’s 1,2 & 3 Site Upland Improvements
Mr. Terry McCullum, Jr Cayo Costa State Park
Weiler Engineering Project Manager 145 10 1450
Weiler Engineering Registered Professional Engineer 145 4 580
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 24 1920
Weiler Engineering Clerical 55 8 440
Total 8690
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 16 8690
Subtask 17: Final Completion w/ Certification Buildings on WEC inspections and as-builts by contractor’s surveyor.
Deliverable: WEC will provide completed record drawings and certifications to FDEP Project Manager via PDF.
Mr. Terry McCullum, Jr Cayo Costa State Park
Subtask 17- Final Buildings
Cost
Weiler Engineering Project Manager 145 8 1160
Weiler Engineering Principal in Charge 195 0 0
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 20 2300
Weiler Engineering Senior Engineering Designer 100 20 2000
Weiler Engineering Engineering Technician 80 24 1920
Total 8980
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 17 8980
Subtask 18: Final Completion w/ Certification Site 1 & 3 Dredge & Fill on WEC inspections and as-builts by contractor’s surveyor.
Mr. Terry McCullum, Jr Cayo Costa State Park
Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager via PDF.
Subtask 18 - Final Site 3
Cost
Weiler Engineering Project Manager 145 12 1740
Weiler Engineering Principal in Charge 195 1 195
Weiler Engineering Registered Professional Engineer 145 8 1160
Weiler Engineering Registered Engineer Intern 115 32 3680
Weiler Engineering Senior Engineering Designer 100 32 3200
Weiler Engineering Engineering Technician 80 48 3840
Total 14255
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 18 Final 1
& 3 Dredging
14255
Project Schedule:
Mr. Terry McCullum, Jr Cayo Costa State Park
Activity Duration (Calendar Days) Days from Execution
Subtask 1A Upland & Waterside 30% Plans Site/Civil Development
60 60
Subtask 1B Survey 60 60
Subtask 1C Geotech 60 60
Subtask 1D Lead/Asbestos 60 60
Subtask 1E Benthic 60 60
Subtask 2A: 30% Gift Shop plans 60 - includes 14 days for Client review
Subtask 2B: 30% Shop bldg.
plans
60 - includes 14 days for Client review
Subtask 2C: 30% Pole Barn plans 60 - includes 14 days for Client review
Subtask 2D: 30% Residence plans 60 - includes 14 days for Client review
Subtask 2E: 30% Storage bldg.
plans
60 - includes 14 days for Client review
Subtask 3: 60% Upland & Waterside Site/Civil Development Plans 1,2 & 3
45 – includes 14 days for Client review
Subtask 4A: 60% Gift Shop plans 45 - includes 14 days for Client review
Subtask 4B: 60% Shop bldg.
plans
45 - includes 14 days for Client review
Subtask 4C: 60% Pole Barn plans 45 - includes 14 days for Client review
Subtask 4D: 60% Residence plans 45 - includes 14 days for Client review