CN-370000-CN230-T61CO1.pdf

PDF 4 MB Posted

Attached to
Master Agreement FL|CN230|5f4ec01f5eb38b1957861cb8292c2183
Contract number
CN230
Issued by
Florida

About this file

This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for engineering and construction administration services related to Hurricane Ian damage repairs at Cayo Costa State Park. The contract involves FDEP as the client, Weiler Engineering Corporation as the consultant, and multiple sub-consultants including CHW, Universal Engineering, and Passarella for specialized services. The change order modifies existing contract CN230, Task Assignment TA61, and extends the project timeline and budget to accommodate comprehensive design, permitting, and construction oversight services.

The contract provides engineering, permitting, and construction administration services for design plans to replace structures damaged by Hurricane Ian at Cayo Costa State Park. The total contract value is $702,940.96, comprising $682,625.36 in fixed fee costs and $40,975.60 in reimbursable expenses, with an increase of $40,975.60 from previous change orders. Services include 30%, 60%, and 100% design development across five buildings and waterside dredging areas, permit applications and approvals for upland and in-water work, 16 monthly construction inspections over 18 months, submittal reviews, response to contractor requests for information, and substantial and final completion certifications. The original task end date of February 28, 2025 was extended to December 31, 2026, representing a net change of 671 days to accommodate design, permitting, and construction phases. Payment is contingent upon FDEP approval of deliverables for each subtask.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T53CO2.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 TA61 1 6I408C (formerly 6I403C)

Hurricane Ian Redevelopment

Weiler Engineering Corporation

R. Jeff Weiler, P.E. (941) 505-1700 weiler7@mac.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Consultant to provide engineering, permitting, and construction administration services for design plans to replace structures damaged by Hurricane Ian, per attached proposal dated May 30, 2023, as well as time extension per request on June 13, 2023.

$ 0.00 $ 20,660.00 $ 20,660.00 $ 0.00 $ 20,660.00 $ 20,660.00

$ 40,975.60 $ 661,965.36 $ 702,940.96 $ 40,975.60 $ 682,625.36 $ 723,600.96

02/08/2023

02/28/2025

02/28/2025

12/31/2026

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.06.15 10:20:20 -04'00'

Terry McCullum, Jr. Terry McCullum, Jr.

Digitally signed by Terry McCullum, Jr.

Date: 2023.06.15 10:23:26 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.06.15 11:36:34 -04'00'

R. Jeff Weiler, P.E.

Mara Gambineri Mara Gambineri Digitally signed by Mara Gambineri Date: 2023.07.14 21:35:54 -04'00' 7/14/2023

6I408C FD091 37504003127 088040/23 675002 U3200 131500 XR $ 702,940.96

$ 702,940.96

Cayo Costa State Park

Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.06.22 12:13:54 -04'00'

McCullum, Terry

From: rpalmer@weilerengineering.org Sent: Tuesday, June 13, 2023 1:55 PM To: McCullum, Terry Subject: TA61 Cayo Costa State Park Time Extension Request

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Hi Terry, The current TA61 for the Cayo Costa State Park: Park Redevelopment from Hurricane Ian expires on 2/28/2025. I am reques ng a me extension for this task assignment un l December 31, 2026 in order to provide enough me for design, permi ng, and construc on services for the project. Please let me know if you have any ques ons.

Thank you, Robin Palmer, P.E.

Environmental Engineer

March 30, 2023 - Revision 5 - May 30, 2023

Mr. Terry McCullum, Jr

Project Manager

Bureau of Design and Construction

Florida Department of Environmental Protection

3900 Commonwealth Boulevard 260-L, MS 520

Tallahassee, FL 32399

RE: Cayo Costa State Park - Hurricane Damage Repairs - Design and Permitting, CN -

230, TA - 61 - Change Order No. 1

Dear Mr. McCullum, Thank you for the opportunity to provide this proposal to assist the Department to prepare the necessary plans and documentation to demolish and replace the buildings (Upland work landward of MHWL) and dredge (work waterside of MHWL) the Cayo Costa Marina and Jug Creek as outlined below:

Site 1: Existing Conditions

*Buildings 1 & 2 were demolished and removed by FEMA after Hurricane Ian.

Building 3 and the bicycle shed are still present and will be removed as part of this scope.

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702

MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2

WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG http://www.weilerengineering.org/ mailto:INFO@WEILERENGINEERING.ORG

April 6, 2023 - Rev 5 - 05/30/23 Mr. Terry McCullum, Jr Cayo Costa State Park Hurricane Repairs

CN 230/TA61 - CO 1

Site 1: Proposed Conditions - Upland – Maintenance

Building (Building 1), Pole Barn (Building 2), Gift Shop (Building

3) (See above) & Waterside - Dredge Cayo Costa Marina (See below)

Mr. Terry McCullum, Jr Cayo Costa State Park

Site 2 - Upland - Residence was demolished by Hurricane Ian. To be reconstructed in the same location under this contract. (No in-water work this site).

Site 3 - Upland - New Storage bldg. ti elevating site & Waterside - Dredge Jug Creek access

Mr. Terry McCullum, Jr Cayo Costa State Park

For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the services and tasks identified.

Please feel free to contact me if you have any questions or wish to discuss matters further.

Sincerely, R. Jeff Weiler, P.E.

President

The Weiler Engineering Corporation

Hurricane Repairs - Design & Permitting Cayo Costa State Park

Contract Number 230, Task Assignment Number 61 Change Order No. 1

Subtask 1: 30% Site 1, 2 & 3 Site/Civil Development Design

1) A - Design

a) WEC will conduct one site visit.

b) Consultant will conduct a pre-application meeting with the Army Corps of Engineers, Water Management District or FDEP and the Local Regulatory agency.

c) Consultant will prepare a site plan for each site.

1) B – Surveys

a) Consultant will coordinate with Survey Sub-Consultant to prepare a special Purpose

Survey of the existing structures and area 50 feet beyond the structures and a Bathymetric

Survey of Jug Creek and the Cayo Costa Marina.

1) C –Geotechnical Reports

a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct soil borings and sub-surface investigation to establish bearing capacities and foundation requirements.

Mr. Terry McCullum, Jr Cayo Costa State Park

1) D – Lead/Asbestos Reports

a) Consultant will coordinate with Geotechnical Sub-Consultant to conduct NESHAP

Asbestos and Lead Based paint screening (up to 50 samples for asbestos and 5 lead samples) on the gift shop, bicycle shed, and ramp to the Ranger Station.

1) E – Benthic Report

a) Consultant will coordinate with an Environmental Sub-Consultant to conduct Complete a Benthic survey of the area proposed for dredging in Jug Creek & Cayo Costa Marina.

Deliverable:

1) A - Site’s 1,2 & 3 Site & Dredging 30% Plans, Conceptual Site – Consultant shall deliver 30% Civil Plans for all three sites to the client via digital PDF. Plans will include:

Cover sheet

Survey

Existing Conditions

Best Management Plan

Demolition Plan to remove Gift Shop and Bicycle shed

Site Plans

1) B - Surveys

Completed Survey – Sixty days from execution of Task Assignment, consultant shall deliver a special Purpose Survey of the upland improvement areas and bathymetric survey of Jug

Creek & Cayo Costa Marina via CAD and a digitally Signed and Sealed PDF.

1) C –Geotechnical Reports

Geotechnical Report – Sixty days from execution of task assignment, consultant shall deliver a completed geotechnical Report identifying structural capacities of the subsurface beneath the proposed structures via digital PDF.

Mr. Terry McCullum, Jr Cayo Costa State Park

1) D – Lead/Asbestos Report

Written results of asbestos survey will be delivered via email to the BDC via digital PDF. Lead

Asbestos testing will be completed on the existing gift shop, ranger station ramp, and bicycle shed only. All other existing structures that are within the scope of the project were previously demolished by FEMA after Hurricane Ian.

1) E – Benthic Survey

Written results of the Benthic survey of Jug Creek and the Cayo Costa Marina will be delivered via email to the BDC via digital PDF.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Fixed Price Cost:

Subtask 1A - 30% Plans Site’s 1,2 & 3

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 31 4495

Weiler Engineering

Principal in Charge 195 6 1170

Weiler Engineering

Registered Professional Engineer

145 38 5510

Weiler Engineering

Registered Engineer Intern 115 62 7130

Weiler Engineering

Senior Engineering Designer 100 140 14000

Weiler Engineering

Engineering Technician 80 188 15040

Weiler Engineering

Clerical 55 15 825

Total

48170

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 1B - Survey

Firm Name Position Classification Unit Unit Rate Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 10 1450

CHW 3 Person Field Crew Hr 177.54 112 19884.48

CHW Project Surveyor Hr 74.75 40 2990

CHW Professional Surveyor & Mapper

Hr 163.93 32 5245.76

CHW Senior CAD/GIS Hr 103.13 64 6600.32

Total Survey 36170.56

Subtask 1C Geotech

Firm Name Position Classification Unit Unit Rate

Number Units

Total Fixed Price Cost

Weiler Engineering Project Manager Hr 145 4 580

Universal

Universal Senior Project Engineer Hr 165.84 60 9950.4

Universal Project Engineer Hr 94.50 60 5670

Universal Staff Engineer Hr 68.46 120 8215.2

Universal CAD Drafting Hr 54.00 120 6480

Universal Total Geotech 30895.6

Subtask 1D - Lead/Asbestos Report

Firm Name Position Classification Rate Hours Total Fixed

Price Cost

Weiler Engineering Registered Professional

Engineer

145 2 290

Mr. Terry McCullum, Jr Cayo Costa State Park Hurricane Repairs

CN 230/TA61 - CO 1

Registered Engineer

Intern

115 2 230

Universal Engineering Senior Geotechnical

Engineer. PE

165.84 40 6633.6

Sr Engineering

Technician

49.14 60 2948.4

Total Sub-Task 1D Total Lead/Asbestos

Report

10102

Subtask 1E - Benthic Report

Firm Name Position Classification Rate Hours Total Fixed

Price Cost

Weiler Engineering Registered Professional

Engineer

145 4 580

Registered Engineer

Intern

115 4 460

Passarella Senior Ecologist 149.50 32 4784

Passarella Ecologist 104.65 48 5023.2

Total Sub-Task 1E Benthic Report 10847.2

Reimbursable Cost: (if applicable)

Mr. Terry McCullum, Jr Cayo Costa State Park

Description Number @ Total

Postage

Printing

Overnight Travel

(if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total Cost 1A

Total Subtask 1 136185.36

Subtask 2A: Gift Shop Building Design 30% documents

Description: Plans completed to 30% to be included with 30% Site Plans.

Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:

Individual Site Plan

Floor Plan

Exterior Elevations

Subtask 2A - 30% Gift Shop Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 9 1305

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 8 1160

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler

Registered Engineer Intern 115 20 2300

Weiler Engineering

Senior Engineering Designer 100 37 3700

Weiler Engineering

Engineering Technician 80 37 2960

Weiler

Clerical 55 4 220

12035

Printing

0.445 0

Reimbursable Total Cost 2A

Total Subtask 2A Gift Shop 30%

12035

Subtask 2B: 3 Bay Shop Bldg Building Design 30% documents

Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:

Individual Site Plan

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 2B - 30% Shop Building Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 8 1160

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 8 1160

Weiler Engineering

Registered Engineer Intern 115 20 2300

Weiler Engineering

Senior Engineering Designer 100 37 3700

Weiler Engineering

Engineering Technician 80 37 2960

Weiler

Clerical 55 4 220

11890

Description Number @ Total

Postage

Printing

0.445 0

Reimbursable Total Cost 2B

Total Subtask 2B Gift Shop 30%

11890

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 2C: Pole Barn Building Design 30% documents

Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:

Individual Site Plan

Subtask 2C - 30% Pole Barn Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 5 725

Weiler Engineering

Principal in Charge 195 1 195

Weiler Engineering

Registered Professional Engineer

145 8 1160

Weiler Engineering

Registered Engineer Intern 115 24 2760

Weiler Engineering

Senior Engineering Designer 100 24 2400

Weiler Engineering

Engineering Technician 80 26 2080

Weiler

Clerical 55 2 110

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing

0.445 0

Reimbursable Total Cost 2C

Total Subtask 2C Pole Barn 30%

Subtask 2D: Residence Building Design 30% documents

Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:

Individual Site Plan

Subtask 2D - 30% Residence Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 24 3480

Weiler Engineering

Principal in Charge 195 4 780

Weiler Engineering

Registered Professional Engineer

145 22 3190

Weiler

Registered Engineer Intern 115 28 3220

Mr. Terry McCullum, Jr Cayo Costa State Park

Senior Engineering Designer 100 88 8800

Weiler Engineering

Engineering Technician 80 116 9280

Weiler

Clerical 55 11 605

29355

Printing

0.445 0

Reimbursable Total Cost 2D

Total Subtask 2D Residence 30%

29355

Subtask 2E: Jug Creek Storage Building Design 30% documents

Description: Plans completed to 30% to be included with 30% Site Plans.

Deliverable: Plans consultant shall deliver 30% Plans (digital PDF only) including:

Individual Site Plan

Mr. Terry McCullum, Jr Cayo Costa State Park

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 5 725

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 8 1160

Weiler Engineering

Registered Engineer Intern 115 30 3450

Weiler Engineering

Senior Engineering Designer 100 30 3000

Weiler Engineering

Engineering Technician 80 25 2000

Weiler

10835

Printing

0.445 0

Reimbursable Total Cost 2E

Total Subtask 2E Storage bldg 30%

10835

Subtask 2E - 30% Jug Creek Storage Bldg Plans

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 3: 60% Site/Civil Documents Site’s 1,2 & 3

Description: Site plans completed to 60% incorporating comments from 30% Site Documents.

Deliverable: Consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost for each site (Broken down by site, with tabled project total summary)

Cover sheet

Survey

Existing Conditions

Best Management Plan

Demolition Plan

Site, Utility & Grading Plans

Dredging Plan & Details incl. spoil location

Site Details and General Notes

Sections

Subtask 3 - 60% Site Development Plans Site’s 1,2 & 3

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 45 6525

Weiler Engineering

Principal in Charge 195 7 1365

Weiler Engineering

Registered Professional Engineer

145 38 5510

Weiler Engineering

Registered Engineer Intern 115 60 6900

Weiler Engineering

Senior Engineering Designer 100 151 15100

Weiler

Engineering Technician 80 207 16560

Mr. Terry McCullum, Jr Cayo Costa State Park

Clerical 55 15 825

Total 52785

Printing

0.445 0

Reimbursable Total Cost

Total Subtask 3 S & D 60%

52785

Subtask 4A: Gift Shop Building Design 60% documents

Description: Plans completed to 60% to be included with 60% Site Plans.

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Site Plan

Floor Plans

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Building Cross sections and details

MEP Plans

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 4A - 60% Gift Shop Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 15 2175

Weiler Engineering

Principal in Charge 195 3 585

Weiler Engineering

Registered Professional Engineer

145 13 1885

Weiler Engineering

Registered Engineer Intern 115 30 3450

Weiler Engineering

Senior Engineering Designer 100 62 6200

Weiler Engineering

Engineering Technician 80 70 5600

Weiler

Clerical 55 7 385

Total 4A Gift Shop 60% Plans

20280

Printing

0.445 0

Reimbursable Total Cost 4A

Total Subtask 4A Gift Shop 60%

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 4B: 3 Bay Shop Bldg Building Design 60% documents

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Site Plan

Floor Plans

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Subtask 4B - 60% Shop Building Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 15 2175

Weiler Engineering

Principal in Charge 195 3 585

Weiler Engineering

Registered Professional Engineer

145 13 1885

Weiler Engineering

Registered Engineer Intern 115 30 3450

Weiler Engineering

Senior Engineering Designer 100 62 6200

Weiler Engineering

Engineering Technician 80 70 5600

Weiler

Clerical 55 7 385

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing

0.445 0

Reimbursable Total Cost 4B

Total Subtask 4B Shop Building 60%

Subtask 4C: Pole Barn Building Design 60% documents

Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Floor Plans

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Subtask 4C - 60% Pole Barn Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler

Project Manager 145 10 1450

Mr. Terry McCullum, Jr Cayo Costa State Park

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 8 1160

Weiler Engineering

Registered Engineer Intern 115 16 1840

Weiler Engineering

Senior Engineering Designer 100 38 3800

Weiler Engineering

Engineering Technician 80 48 3840

Weiler

Clerical 55 3 165

12645

Printing

0.445 0

Reimbursable Total Cost 4C

Total Subtask 4C Pole Barn 60%

12645

Subtask 4D: Residence Building Design 60% documents

Mr. Terry McCullum, Jr Cayo Costa State Park

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Floor Plans

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Subtask 4D - 60% Residence Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 22 3190

Weiler Engineering

Principal in Charge 195 4 780

Weiler Engineering

Registered Professional Engineer

145 18 2610

Weiler Engineering

Registered Engineer Intern 115 32 3680

Weiler Engineering

Senior Engineering Designer 100 70 7000

Weiler Engineering

Engineering Technician 80 95 7600

Weiler

Clerical 55 6 330

25190

Printing

Mr. Terry McCullum, Jr Cayo Costa State Park

0.445 0

Reimbursable Total Cost 4D

Total Subtask 4D Residence 60%

25190

Subtask 4E: Jug Creek Storage Building Design 60% documents

Floor Plans

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Building Cross sections and details

Onsite sewage disposal system plans and details

Subtask 4E - 60% Jug Creek Storage bldg. Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 22 3190

Weiler Engineering

Principal in Charge 195 4 780

Weiler Engineering

Registered Professional Engineer

145 20 2900

Weiler

Registered Engineer Intern 115 37 4255

Mr. Terry McCullum, Jr Cayo Costa State Park

Senior Engineering Designer 100 76 7600

Weiler Engineering

Engineering Technician 80 95 7600

Weiler

Clerical 55 6 330

26655

Printing

0.445 0

Reimbursable Total Cost 4E

Total Subtask 4E Storage bldg. 60%

26655

Subtask 5: Site 1, 2 & 3 Upland Site/Civil Permitting Excluding Dredging Jug Creek and

Cayo Costa Marina

Description:

5) A – Permit Applications (Upland Work)

Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals as follows:

Lee County:

Site #1- LDO Site #2- Septic Permit (DOH) Site #3- LDO + Septic Permit (DOH)

SFWMD:

Site #1: ERP - Uplands only Site #2: Verification of Exemption Site #3- ERP - Uplands only

Mr. Terry McCullum, Jr Cayo Costa State Park

State Fire Marshal:

Site #1: Required Site #2: Required Site #3: Required

5) B – Permit Approvals, Consultant will coordinate with agencies and assist Client to respond to agencies for additional information.

Deliverable:

5) A – Permit Applications

Incorporate Client review comments from 60% plans and deliver permit applications for the Lee County

LDO permits, Florida Department of Health (Septic Permit), and SFWMD applications in PDF format with the

Delivery of the 60% design plans. The SFM Application is completed online and no signature is needed.

5) B – Permit Approvals

Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation. Approvals from Lee County (LDO), ERP/Verification of Exemptions from

SFWMD, and Department of Health, and State Fire Marshal will be provided in PDF format.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are

Subtask 5A Site 1,2 & 3 Upland Permit Applications No Dredging

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 25 3625

Weiler Engineering

Principal in Charge 195 4 780

Weiler

Registered Professional Engineer 145 20 2900

Mr. Terry McCullum, Jr Cayo Costa State Park

Registered Engineer Intern 115 32 3680

Weiler Engineering

Senior Engineering Designer 100 83 8300

Weiler Engineering

Engineering Technician 80 112 8960

Weiler Engineering

Clerical 55 11 605

Total 5A - Upland Permit Applications 1,2 & 3

28850

Subtask 5B Site 1, 2 & 3 Upland Permit Approvals

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 7 1015

Weiler Engineering

Principal in Charge 195 1 195

Weiler Engineering

Registered Professional Engineer 145 5 725

Weiler Engineering

Registered Engineer Intern 115 10 1150

Weiler Engineering

Senior Engineering Designer 100 16 1600

Weiler Engineering

Engineering Technician 80 16 1280

Weiler Engineering

Clerical 55 1 55

Total 5B - Permit approvals 1, 2 & 3 6020

Reimbursable Cost:

Postage 1 35 35

Printing 210 2.3 483

Mr. Terry McCullum, Jr Cayo Costa State Park

Permit application fees estimate

1 25000 25000

Reimbursable Total Cost for 5A

25515

Total for

Subtask 5

60388

Subtask 6: Site 1 & 3 Dredge & Fill Permitting

Description:

6) A – Permit Applications Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals to Lee County for LDO, the South Florida Water Management District for ERP and the ACOE

For the dredging permits for Cayo Costa and Jugg Creek.

6) B – Permit Approvals, Consultant will coordinate with agencies and assist Client to respond to agencies for additional information.

Deliverable:

6) A – Permit Applications Incorporate Client review comments from 60% plans and deliver permit applications for Lee County, SFWMD, and ACOE in PDF format.

6) B – Permit Approvals

Depends on agencies but anticipate at least 180 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with permits and revised (if necessary) plans and documentation in PDF format.

Mr. Terry McCullum, Jr Cayo Costa State Park

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 42 6090

Weiler Engineering

Principal in Charge 195 6 1170

Weiler Engineering

Registered Professional Engineer 145 34 4930

Weiler Engineering

Registered Engineer Intern 115 54 6210

Weiler Engineering

Senior Engineering Designer 100 138 13800

Weiler Engineering

Engineering Technician 80 180 14400

Weiler Engineering

Clerical 55 18 990

Total 6A Site 1 & 3 Applications (In- Water Work)

47590

Subtask 6B Sites 1 & 3 Dredge & Fill Permit Approvals

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 10 1450

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer 145 7 1015

Weiler Engineering

Registered Engineer Intern 115 12 1380

Weiler Engineering

Senior Engineering Designer 100 20 2000

Weiler Engineering

Engineering Technician 80 20 1600

Subtask 6A Sites 1 & 3 Dredge & Fill Permit Applications

Mr. Terry McCullum, Jr Cayo Costa State Park

Clerical 55 1 55

Total 6B - Sites 1 & 3 Dredge & Fill Approvals

Printing 210 2.3 483

Permit application fees estimate

1 14000 14000

Reimbursable Total Cost for 6A

14518

Subtask 6

69998

Subtask 7A: Gift Shop Building Design 100% documents

Description: Plans completed to 100%.

Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure only including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Site Plan

Floor Plan

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 7A - 100% Gift Shop Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 6 870

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 6 870

Weiler Engineering

Registered Engineer Intern 115 8 920

Weiler Engineering

Senior Engineering Designer 100 20 2000

Weiler Engineering

Engineering Technician 80 28 2240

Weiler

Total 7A Gift Shop 100%

Printing 40 2.80 112

0.445 0

Reimbursable Total Cost 7A

Total Subtask 7A Gift Shop 100%

Subtask 7B: 3 Bay Shop Bldg Building Design 100% documents

Mr. Terry McCullum, Jr Cayo Costa State Park

Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:

Site Plan

Floor Plan

Foundation/Piling Plans and details;

Beam schedules

Exterior Elevations

Subtask 7B - 100% Shop Building Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 6 870

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 6 870

Weiler Engineering

Registered Engineer Intern 115 8 920

Weiler Engineering

Senior Engineering Designer 100 20 2000

Weiler Engineering

Engineering Technician 80 28 2240

Weiler

Total 7B - Shop Bldg. Plans

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 40 2.8 112

0.445 0

Reimbursable Total Cost 7B

Total Subtask 7B Shop Building 100%

Subtask 7C: Pole Barn Building Design 100% documents

Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Site Plan

Floor Plan

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 7C - 100% Pole Barn Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 4 580

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 4 580

Weiler Engineering

Registered Engineer Intern 115 6 690

Weiler Engineering

Senior Engineering Designer 100 14 1400

Weiler Engineering

Engineering Technician 80 18 1440

Weiler

Total 7C Pole Barn 100% Plans

Printing 40 2.80 112

0.445 0

Reimbursable Total Cost 7C

Total Subtask 7C Pole Barn 100%

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 7D: Residence Building Design 100% documents

Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:

Site Plan

Floor Plan

Foundation/Piling Plans and details

Beam schedules

Exterior Elevations

Fixed Price Cost:

Subtask 7D - 100% Residence Plans

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 8 1160

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 6 870

Weiler Engineering

Registered Engineer Intern 115 10 1150

Weiler Engineering

Senior Engineering Designer 100 28 2800

Weiler Engineering

Engineering Technician 80 38 3040

Weiler Engineering

Clerical 55 4 220

Total 7D - Residence 100 % Plans

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 52 2.80 145.6

0.445 0

Reimbursable Total Cost 4D

145.6

Total Subtask 7D Residence 100%

9775.6

Subtask 7E: Jug Creek Storage Building Design 100% documents

Description: Plans completed to 100%.

Deliverable: Plans consultant shall deliver 100% Plans (digital PDF only), CAD, and two hard copies of the plans for this structure including:

Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Site Plan

Floor Plan

Foundation/Piling Plans and details

Beam Schedules

Exterior Elevations

Building Cross sections and details

Onsite sewage disposal system Plans and Details

Fixed Price Cost:

Subtask 7E - 100% Jug Creek Storage bldg Plans

Firm Name Position Classification Hourly Rate

Hours Total Fixed Price

Mr. Terry McCullum, Jr Cayo Costa State Park

Project Manager 145 4 580

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 6 870

Weiler Engineering

Registered Engineer Intern 115 8 920

Weiler Engineering

Senior Engineering Designer 100 18 1800

Weiler Engineering

Engineering Technician 80 20 1600

Weiler Engineering

Clerical 55 3 165

Total 7E - Jug Creek Storage bldg 100 % Plans

Printing 40 2.80 112

0.445 0

Reimbursable Total Cost 7E

Total Subtask 7E Jug Creek Storage bldg 100%

Subtask 8: 100% Site’s 1,2 & 3 Upland Site/Civil Documents

Description: Site Development plans for upland improvements completed to 100%.

Mr. Terry McCullum, Jr Cayo Costa State Park

Deliverable: Incorporate Client review of 100% plans, Consultant shall deliver two (2) sets of

100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Opinion of Probable Cost;

Cover sheet

Survey

Existing Conditions

Best Management Plan

Demolition Plan

Site, Utility & Grading Plans incl Septic for residence only

Subtask 8 - 100% Site’s 1,2 & 3 Upland Site & Development Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 24 3480

Weiler Engineering

Principal in Charge 195 3 585

Weiler Engineering

Registered Professional Engineer

145 22 3190

Weiler Engineering

Registered Engineer Intern 115 34 3910

Weiler Engineering

Senior Engineering Designer 100 82 8200

Weiler Engineering

Engineering Technician 80 112 8960

Weiler Engineering

Clerical 55 9 495

Total 28820

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 60 2.30 138

Overnight Travel

(if applicable)

Reimbursable Total Cost

Subtask 8

100% Site’s 1, 2, & 3 S/Civil

Plans

28993

Subtask 9: 100% Site 3 Site/Civil Documents (In-Water Work) Description:

Site Development plans completed to 100% for in-water work (dredging).

Deliverable: Incorporate Client review of 100% plans, Consultant shall deliver two sets of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:

Updated Opinion of Probable Cost (Broken down by site, with tabled project total summary)

Survey

Existing Conditions

Best Management Plan

Demolition Plan

Site, Utility & Grading Plans

Dredging Plan & Details incl. spoil location & BMP

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 9 - 100% Site 3 Site & Development Plans

Hourly Rate

Hours Total Fixed Price Cost

Weiler Engineering

Project Manager 145 20 2900

Weiler Engineering

Principal in Charge 195 2 390

Weiler Engineering

Registered Professional Engineer

145 18 2610

Weiler Engineering

Registered Engineer Intern 115 28 3220

Weiler Engineering

Senior Engineering Designer 100 68 6800

Weiler Engineering

Engineering Technician 80 94 7520

Weiler Engineering

Clerical 55 8 440

Total 23880

Printing 60 2.30 138

Overnight Travel

(if applicable)

Reimbursable Total Cost

Subtask 9 Site

3 100% S/Civil

Plans (In-

Water)

24053

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 10: Attend a Pre-Bid meeting on-site

Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.

Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 10 - Pre-bid

Firm Name Position Classification Hourly

Rate

Hours Total

Fixed

Price

Cost

Weiler Engineering Project Manager 145 8 $1160.00

Weiler Engineering Principal in Charge 195 0 $0.00

Weiler Engineering Registered Professional Engineer

145 0 $0.00

Weiler Engineering Registered Engineer Intern 115 8 $920.00

Weiler Engineering Senior Engineering Designer 100 8 $800.00

Weiler Engineering Engineering Technician 80 8 $640.00

Weiler Engineering Clerical 55 0 $0.00

Total $3520.00

Postage Not anticipated

Overnight Travel

(if applicable)

Not anticipated

Mileage (@ $0.445 per mile)

Reimbursable Total Cost

$0.00

$0.00

Mr. Terry McCullum, Jr Cayo Costa State Park

Total Subtask 10 $3520.00

Subtask 11: Attend Pre-Construction Meeting

Description: WEC will provide representation at the Pre-Construction Meeting.

Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.

Subtask 11 - Pre-Construction Mtg

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 2 110

Total 2990

Postage 0

Printing 2.3 0

Mr. Terry McCullum, Jr Cayo Costa State Park

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile) 0

Reimbursable Total Cost 0

Total subtask 11 2990

Subtask 12: Review Contractor Submittals

Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.

Deliverable:, Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.

Subtask 12 - Review Submittals

Cost

Weiler Engineering Project Manager 145 2 290

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 0 0

Weiler Engineering Registered Engineer Intern 115 16 1840

Weiler Engineering Senior Engineering Designer 100 16 1600

Weiler Engineering Engineering Technician 80 6 480

Weiler Engineering Clerical 55 2 110

Total 4320

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 0 applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total

Total Subtask 12 4320

Subtask 13: Respond to Contractor RFI's

Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase 18 months.

Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.

Subtask 13- Respond to RFI’s

Cost

Weiler Engineering Project Manager 145 77 11165

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 18 2610

Weiler Engineering Registered Engineer Intern 115 24 2760

Weiler Engineering Senior Engineering Designer 100 20 2000

Weiler Engineering Engineering Technician 80 20 1600

Weiler Engineering Clerical 55 4 220

Total 20355

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 6C 20355

Subtask 14A: Provide Construction Inspections (Month 1)

Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.

Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.

Subtask 14A - Month 1 Inspection

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Weiler Engineering Clerical 55 0 0

Total 2252.5

Mr. Terry McCullum, Jr Cayo Costa State Park

Postage 35 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Reimbursable Total

Total Subtask 14A 2252.5

Subtask 14B: Construction Inspection (Month 2)

Deliverable: WEC will provide original digitally signed and sealed reports to the FDEP Project Manager, in PDF format. The inspection report will be submitted within 3 days of each inspection.

Subtask 14B

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Senior Engineering Designer 100 1 100

Weiler Engineering Engineering Technician 80 0 0

Total 2252.5

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Reimbursable Total

Total Subtask 14B 2252.5

Subtask 14C: Construction Inspection (Month 3)

Subtask 14C Month 3 Inspection

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Total 2952.5

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14C 2952.5

Subtask 14D: Construction Inspection (Month 4)

Subtask 14D - Inspection Month 4

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Total 1937.5

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

0.445 0

Total Subtask 14D 1937.5

Subtask 14E: Construction Inspection (Month 5)

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14E Month 5 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14E 1937.5

Subtask 14F: Construction Inspection (Month 6)

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14F Month 6 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14F 1937.5

Subtask 14G: Construction Inspection (Month 7)

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14G Month 7 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14G 1937.5

Subtask 14H: Construction Inspection (Month 8)

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14H Month 8 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14H 1937.5

Subtask 14I: Construction Inspection (Month 9)

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14I Month 9 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14I 1937.5

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14J: Construction Inspection (Month 10)

Subtask 14J Month 10 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14J 1937.5

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 14K: Construction Inspection (Month 11)

Subtask 14K Month 11 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Mr. Terry McCullum, Jr Cayo Costa State Park

Total Subtask 14K 1937.5

Subtask 14L: Construction Inspection (Month 12)

Subtask 14L Month 12 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Mr. Terry McCullum, Jr Cayo Costa State Park

Total Subtask 14L 1937.5

Subtask 14M: Construction Inspection (Month 13)

Subtask 14M Month 13 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Mr. Terry McCullum, Jr Cayo Costa State Park

Total Subtask 14M 1937.5

Subtask 14N: Construction Inspection (Month 14)

Subtask 14N Month 14 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Printing 0

Overnight Travel (if

Mr. Terry McCullum, Jr Cayo Costa State Park

Mileage (@ $0.445 per mile)

Total Subtask 14N 1937.5

Subtask 14O: Construction Inspection (Month 15)

Subtask 14O Month 15 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Mr. Terry McCullum, Jr Cayo Costa State Park

Mileage (@ $0.445 per mile)

Total Subtask 14O 1937.5

Subtask 14P: Construction Inspection (Month 16)

Deliverable: WEC will provide one digitally signed and sealed reports to the FDEP Project

Subtask 14P Month 16 Inspection

Cost

Weiler Engineering Project Manager 145 1 145

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 .5 72.5

Weiler Engineering Registered Engineer Intern 115 8 920

Weiler Engineering Senior Engineering Designer 100 8 800

Weiler Engineering Engineering Technician 80 0 0

Mr. Terry McCullum, Jr Cayo Costa State Park

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 14P 1937.5

Subtask 15A: Substantial Completion Walk-Through w/Punchlist Site’s 1, 2 & 3 Upland Improvements

Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection in PDF via email.

Subtask 15 Substantial

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 4 580

Weiler Engineering Registered Engineer Intern 115 16 1840

Weiler Engineering Senior Engineering Designer 100 16 1600

Weiler Engineering Engineering Technician 80 0 0

Total 5400

Mr. Terry McCullum, Jr Cayo Costa State Park

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 15A

Substantial 1,2,3

Uplands

Subtask 15B: Substantial Completion Walk-Through w/Punchlist Buildings input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of

Subtask 15B Substantial Buildings

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 6 870

Weiler Engineering Registered Engineer Intern 115 20 2300

Weiler Engineering Senior Engineering Designer 100 20 2000

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Engineering Technician 80 0 0

Total 6550

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 15B

Substantial Buildings

Subtask 15C: Substantial Completion Walk-Through w/Punchlist Site’s 1 & 3 Dredge and Fill input related to the punchlist.

Deliverable: WEC will provide comments and input on punchlist within one (1) day of

Subtask 15C Substantial Site’s 1 & 3 Dredge & Fill

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Registered Professional Engineer 145 8 1160

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Registered Engineer Intern 115 24 2760

Weiler Engineering Senior Engineering Designer 100 24 2400

Weiler Engineering Engineering Technician 80 0 0

Total 7700

Printing 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 15A

Substantial 1,2,3

Uplands

Subtask 16: Final Completion w/ Certification Sites 1,2 & 3 Upland Improvements

Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection and prepare the necessary record information based on WEC inspections and as-builts by contractor’s surveyor.

Deliverable: WEC will provide completed record drawings and certifications to FDEP Project Manager in PDF via email.

Subtask 16 - Final Site’s 1,2 & 3 Site Upland Improvements

Mr. Terry McCullum, Jr Cayo Costa State Park

Weiler Engineering Project Manager 145 10 1450

Weiler Engineering Registered Professional Engineer 145 4 580

Weiler Engineering Registered Engineer Intern 115 20 2300

Weiler Engineering Senior Engineering Designer 100 20 2000

Weiler Engineering Engineering Technician 80 24 1920

Weiler Engineering Clerical 55 8 440

Total 8690

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 16 8690

Subtask 17: Final Completion w/ Certification Buildings on WEC inspections and as-builts by contractor’s surveyor.

Deliverable: WEC will provide completed record drawings and certifications to FDEP Project Manager via PDF.

Mr. Terry McCullum, Jr Cayo Costa State Park

Subtask 17- Final Buildings

Cost

Weiler Engineering Project Manager 145 8 1160

Weiler Engineering Principal in Charge 195 0 0

Weiler Engineering Registered Professional Engineer 145 8 1160

Weiler Engineering Registered Engineer Intern 115 20 2300

Weiler Engineering Senior Engineering Designer 100 20 2000

Weiler Engineering Engineering Technician 80 24 1920

Total 8980

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 17 8980

Subtask 18: Final Completion w/ Certification Site 1 & 3 Dredge & Fill on WEC inspections and as-builts by contractor’s surveyor.

Mr. Terry McCullum, Jr Cayo Costa State Park

Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager via PDF.

Subtask 18 - Final Site 3

Cost

Weiler Engineering Project Manager 145 12 1740

Weiler Engineering Principal in Charge 195 1 195

Weiler Engineering Registered Professional Engineer 145 8 1160

Weiler Engineering Registered Engineer Intern 115 32 3680

Weiler Engineering Senior Engineering Designer 100 32 3200

Weiler Engineering Engineering Technician 80 48 3840

Total 14255

Printing 2.3 0

Overnight Travel (if applicable)

Mileage (@ $0.445 per mile)

Total Subtask 18 Final 1

& 3 Dredging

14255

Project Schedule:

Mr. Terry McCullum, Jr Cayo Costa State Park

Activity Duration (Calendar Days) Days from Execution

Subtask 1A Upland & Waterside 30% Plans Site/Civil Development

60 60

Subtask 1B Survey 60 60

Subtask 1C Geotech 60 60

Subtask 1D Lead/Asbestos 60 60

Subtask 1E Benthic 60 60

Subtask 2A: 30% Gift Shop plans 60 - includes 14 days for Client review

Subtask 2B: 30% Shop bldg.

plans

60 - includes 14 days for Client review

Subtask 2C: 30% Pole Barn plans 60 - includes 14 days for Client review

Subtask 2D: 30% Residence plans 60 - includes 14 days for Client review

Subtask 2E: 30% Storage bldg.

plans

60 - includes 14 days for Client review

Subtask 3: 60% Upland & Waterside Site/Civil Development Plans 1,2 & 3

45 – includes 14 days for Client review

Subtask 4A: 60% Gift Shop plans 45 - includes 14 days for Client review

Subtask 4B: 60% Shop bldg.

plans

45 - includes 14 days for Client review

Subtask 4C: 60% Pole Barn plans 45 - includes 14 days for Client review

Subtask 4D: 60% Residence plans 45 - includes 14 days for Client review

Subta…

This is the start of the file's text. The full file is on GovTribe.