Task Assignment Notification and Proposal Summary
This document is a Task Assignment Notification Form and detailed engineering services proposal issued by the Florida Department of Environmental Protection (FDEP) to Weiler Engineering Corporation for the Bill Baggs Cape Florida State Park Restroom #2 Remodel project. The task assignment, designated as CN230/TA79, was executed on November 15-21, 2023, with a completion date of June 30, 2025. The FDEP's Bureau of Design and Construction, under Project Manager Garland Sandel and Contract Manager Ralph Perkins, engaged Weiler Engineering, represented by Jeff Weiler, P.E., to provide comprehensive design, permitting, and construction administration services.
The scope encompasses ten subtasks totaling $80,485.80, comprising $77,514.60 in fixed-price costs and $2,971.20 in reimbursable expenses. Subtasks 1-5 address the design and permitting phase, including lead and asbestos testing ($4,589.60), 60% design plans ($23,288.75), 100% design plans with specifications ($7,160.75), permit applications and approvals ($12,952.50), and pre-bid meeting attendance ($3,662.40). Subtasks 6A-6J cover construction phase services valued at $26,130.00 in fixed costs, including pre-construction and final completion meetings, submittal reviews, regulatory responses, contractor RFI responses, four monthly construction inspections, substantial completion walk-through with punchlist review, and final completion certification. The project involves multiple disciplines including senior and registered engineers, engineering designers and technicians, and geotechnical specialists. Payment is contingent upon FDEP approval of deliverables for each subtask.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN230 79 FDEP/DRP 61550C
Bill Baggs Cape Florida State Park Remodel Bathroom #2
Weiler Engineering
Jeff Weiler 941-628-4732 weiler7@mac.com
Ralph Perkins 850-245-2460 ralph.perkins@floridadep.gov
Design, permit and remodel bathhouse #2 for ADA compliance, per the attached proposal dated 11.13.23.
Garland Sandel
Execution date $ 77,514.60 6/30/2025 $ 2,971.20
$ 80,485.80
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.11.15 13:48:24 -05'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.11.15 14:29:53 -05'00'
Michael W Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.11.15 15:45:49 -05'00'
Jeff Weiler Jeff Weiler Digitally signed by Jeff Weiler Date: 2023.11.16 11:21:18 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.11.21 11:16:32 -05'00'
61550C 37505000011 080039/24 675002 U3200 131500 XR $ 80,485.80
$ 80,485.80
November 9, 2023- Revision 1 November 13, 2023
Mr. Garland Sandel
Project Manager
Bureau of Design and Construction
Florida Department of Environmental Protection
3900 Commonwealth Boulevard 260-L, MS 520
Tallahassee, FL 32399
RE: Bill Baggs Cape Florida State Park - Restroom 2 Remodel, CN - 230, TA - 79
Dear Mr. Sandel, Thank you for the opportunity to provide this proposal to prepare the plans and documentation necessary to renovate the existing restroom.
The scope of work is to evaluate an existing restroom and provide design and specifications to make the existing structure ADA compliant. This includes, but is not limited to, replacing partitions, ensuring wall dimensions are compliant, hardware replacement, flooring, electric, and hand dryers. The existing restroom is 4 stalls and 4 sinks for each side and constructed on grade.
For your review, the Weiler Engineering Corporation, has provided a proposal summary and man-hour documentation for the tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, R. Jeff Weiler, P.E.
President
The Weiler Engineering Corporation
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702
MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289- 416 2
WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG http://www.weilerengineering.org/ mailto:INFO@WEILERENGINEERING.ORG
Rev 1 November 13, 2023 Mr. Garland Sandel Bill Baggs State Park Restroom Remodel
CN 230/TA79
Bill Baggs State Park Existing Restroom ADA Compliant Contract Number
230, Task Assignment Number 79
Subtask 1: Lead/Asbestos Testing
Description: Sixty days from execution of task assignment, consultant shall deliver a completed
Lead and Asbestos report vis digital PDF.
Deliverable: Lead and Asbestos report (digital PDF only).
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1 – Lead/Asbestos Report
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 2 290
Universal Senior Geotechnical Engineer 165.84 20 3316.80
Senior Engineering Technician
49.14 20 982.80
Total 4589.60
Total for Subtask 1
4589.60
Mr. Garland Sandel Bill Baggs State Park
Subtask 2: 60% documents - Existing Restroom Remodel
Description: Plans completed to 60% incorporating comments from 30%.
Deliverable: Plans consultant shall deliver 60% Plans (digital PDF only) including:
Opinion of Probable Cost;
Cover sheet Existing Conditions Demolition Plan Plumbing fixture location plan Floor Plan Interior Finish Schedules Electrical Plans & Details Plumbing Plans & Details
Subtask 2 - 60% Plans - Existing Restroom
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 16 2320
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 28 4060
Registered Engineer Intern 115 32 3680
Senior Engineering Designer 100 72 7200
Engineering Technician 80 72 5760
Clerical 55 4 220
Mr. Garland Sandel Bill Baggs State Park
Total 23288.75
Total for
Subtask 2 Ex
Restroom
23288.75
Subtask 3: 100% documents Existing Restroom
Description: Plans completed to 100%.
Deliverable: Incorporate Client review of 60% plans, Consultant shall deliver one set of 100% signed and sealed plans, digital 1-PDF and 1-CAD including:
Opinion of Probable Cost Cover sheet
Existing Conditions Demolition Plan
Plumbing fixture location plan Floor Plan
Interior Finish Schedules Electrical Plans & Details Plumbing Plans & Details
ADA Ramp Plan with sections & Details Specifications
Subtask 3 - 100% Plans - Existing Restroom
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 4 580
Principal in Charge 195 .25 48.75
Registered Professional Engineer
145 8 1160
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 16 1600
Engineering Technician 80 32 2560
Clerical 55 3 165
Mr. Garland Sandel Bill Baggs State Park
Total 7033.75
Reimbursable Cost:
Description Number @ Total
Postage 1 35 35
Printing 40 2.30 92
Overnight Travel
(if applicable)
Reimbursable Total Cost
Subtask 3
100% Existing
Restroom
7160.75
Subtask 4: Permitting Existing Restroom
Description:
4) A – Permit Applications, Consultant will assist Client and Clients contractor to submit permit applications for Local and State approvals. WEC will complete applications for the State Fire Marshal and DHR for site development approval. WEC staff will coordinate with the Client to ensure that desired layout fits to the specific jurisdiction requirements and work with the Client to make changes as may be necessary.
4) B – Permit Approvals, Consultant will coordinate with agencies and assist Client and Clients contractor to respond to agencies for additional information.
Deliverable:
4) A – Permit Applications, Incorporate Client review comments from 60% plans and deliver five sets of permit applications with 100% plans.
4) B – Permit Approvals, Depends on agencies but anticipate 60 days after submittal. Consultant will respond to agency requests for additional information and copy Client on all responses. Upon approval, Consultant will provide Client with approvals and revised (if necessary) plans and documentation.
Mr. Garland Sandel Bill Baggs State Park
Subtask 4A Permit Applications
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 12 1740
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 6 870
Registered Engineer Intern 115 26 2990
Senior Engineering Designer 100 18 1800
Engineering Technician 80 24 1920
Total 9588.75
Subtask 4B Permit Approvals
Hourly Rate
Hours Total Fixed Price Cost
Weiler Engineering
Project Manager 145 2 290
Principal in Charge 195 .25 48.75
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 8 800
Engineering Technician 80 12 960
Clerical 55 1 55
Total 3363.75
Mr. Garland Sandel Bill Baggs State Park
Printing 200 2.3 460
State Fire Marshal
1 1000 1000
Reimbursable Total Cost for 3A
Subtask 4
14447.5
Subtask 5: Attend a Pre-Bid meeting on-site
Description: Consultant will attend one pre-bid meeting on site to respond to questions and prepare minutes.
Deliverable: Consultant will provide digital minutes of meeting and responses to contractor questions.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Subtask 5 - Pre-bid
Firm Name Position Classification Hourly
Rate
Hours Total
Fixed
Price
Cost
Weiler Engineering Project Manager 145 8 $1160.00
Principal in Charge 195 0 $0.00
Registered Professional
Engineer
145 0 $0.00
Registered Engineer Intern 115 8 $920.00
Senior Engineering Designer 100 8 $800.00
Engineering Technician 80 8 $640.00
Clerical 55 0 $0.00
Total $3520.00
Mr. Garland Sandel Bill Baggs State Park
Postage Not anticipated
Overnight Travel Not anticipated
(if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost
320 0.445 $142.40
$142.40
Total Subtask 5 $3662.40
Subtask 6A – 6J: Construction Phase Services complete, accurate, and timely. (Please do not alter this language)
Subtask 6A: Attend Pre-Construction Meeting
Description: WEC will provide representation at the Pre-Construction Meeting.
Deliverable: Meeting notes within 2 days from meeting date for inclusion by FDEP Project Manager in Meeting Minutes.
Subtask 6A - Pre-Construction Mtg
Firm Name Position Classification Hourly Rate Hours Total Fixed Price
Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 0 0
Registered Professional Engineer 145 0 0
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 0 0
Engineering Technician 80 0 0
Clerical 55 0 0
Total 2080
Mr. Garland Sandel Bill Baggs State Park
Postage 0
Printing 2.3 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile) 320 0.445 142.4
Reimbursable Total Cost 142.4
Total subtask 5A 2222.4
Subtask 6B: Review Contractor submittals
Description: WEC will review and comment on Contractor submittal package within 14 days of receipt.
Deliverable: Stamped acceptance of final submittals in PDF digital form to FDEP Project Manager within 7 days of final approvals.
Subtask 6B - Review Submittals
Cost
Weiler Engineering Project Manager 145 4 580
Principal in Charge 195 0 0
Registered Professional Engineer 145 0 0
Registered Engineer Intern 115 12 1380
Senior Engineering Designer 100 16 1600
Engineering Technician 80 4 320
Clerical 55 2 110
Total 3990
Printing 0
Mr. Garland Sandel Bill Baggs State Park
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total
Cost
Total Subtask 6B 4025
Subtask 6C: Respond to Building Department Comments
Description: WEC will assist Client and/or Client's Contractor in responding to comments from the Building Department, and revise plans accordingly within 14 days of receipt of comments.
Specifically, when WEC's involvement is required for RFI responses, WEC will prepare a response and send it to FDEP Project Manager for review and comment. WEC will then discuss and/or revise accordingly prior to formal submittal of RFI response to Building Department.
Deliverable: RFI response documents submitted to Building Department.
Subtask 6C
Cost
Weiler Engineering Project Manager 145 2 290
Principal in Charge 195 0 0
Registered Professional Engineer 145 1 145
Registered Engineer Intern 115 6 690
Senior Engineering Designer 100 8 800
Engineering Technician 80 0 0
Clerical 55 1 55
Total 1980
Mr. Garland Sandel Bill Baggs State Park
Postage 35 0
Printing 2.30 0.00
Overnight Travel
(if applicable)
Not anticipated
Mileage (@ $0.445 per mile)
Not anticipated
Reimbursable Total
Total - 6C 1980
Subtask 6D: Respond to Contractor RFI's
Description: WEC will respond to RFI's from Contractor within 7 days throughout the course of the construction phase.
Deliverable: WEC will provide copies of all RFI responses to FDEP Project Manager in PDF digital format.
Subtask 6D- Respond to RFI’s
Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 0 0
Registered Professional Engineer 145 8 1160
Registered Engineer Intern 115 24 2760
Mr. Garland Sandel Bill Baggs State Park
Senior Engineering Designer 100 16 1600
Engineering Technician 80 0 0
Total 6900
Postage 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Reimbursable Total Cost 0
Total Subtask 6D 6900
Subtask 6E: Provide Construction Inspections (Month 1)
Description: WEC will provide a monthly inspection (NLT every 30 days) during construction.
Deliverable: WEC will provide two (2) original signed and sealed reports to the FDEP Project Manager, as well as a digital version in PDF format. The inspection report will be submitted within 3 days of each inspection.
Subtask 6E - Month 1 Inspection
Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Mr. Garland Sandel Bill Baggs State Park
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 1 100
Engineering Technician 80 10 800
Total 1577.5
Postage 35 0
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.4
Reimbursable Total
142.4
Total Subtask 6E 1719.9
Subtask 6F: Construction Inspection (Month 2)
Manager, as well as a digital version in PDF format. The inspection report will be submitted
Subtask 6F
October 16, 2023 Mr. Garland Sandel Bill Baggs State Park
Subtask 6G Month 3 Inspection
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Registered Engineer Intern 115 4 460
Senior Engineering Designer 100 1 100
Engineering Technician 80 10 800
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.4
Reimbursable Total
177.4
Total Subtask 6F 1754.9
Subtask 6G: Construction Inspection (Month 3)
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Mr. Garland Sandel Bill Baggs State Park
Registered Professional Engineer 145 .5 72.5
Senior Engineering Designer 100 1 100
Engineering Technician 80 10 800
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
320 0.445 142.4
Reimbursable Total Cost 177.4
Total Subtask 6G 1754.9
Subtask 6H: Construction Inspection (Month 4)
Subtask 6H – Inspection Month 4
Cost
Weiler Engineering Project Manager 145 1 145
Principal in Charge 195 0 0
Registered Professional Engineer 145 .5 72.5
Senior Engineering Designer 100 1 100
Mr. Garland Sandel Bill Baggs State Park
Engineering Technician 80 10 800
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 5H 1754.9
Subtask 6I: Substantial Completion Walk-Through w/Punchlist
Description: WEC will assist Client with the Substantial Completion inspection and punchlist, with WEC representative attending the Substantial Completion inspection and providing engineer input related to the punchlist.
Deliverable: WEC will provide comments and input on punchlist within one (1) day of Substantial Completion inspection.
Subtask 6I substantial
Cost
Weiler Engineering Project Manager 145 8 1160
Principal in Charge 195 0 0
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 2 200
Engineering Technician 80 0 0
Total 2570
Mr. Garland Sandel Bill Baggs State Park
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 6I 2747.4
Subtask 6J: Final Completion w/ Certification
Description: WEC will assist Client with the Final Completion inspection, with WEC representative attending the Final Completion inspection.
Deliverable: WEC will also provide complete the final completion certification form required by FDEP Project Manager.
Subtask 6J - Final
Cost
Weiler Engineering Project Manager 145 4 580
Principal in Charge 195 0 0
Registered Professional Engineer 145 2 290
Registered Engineer Intern 115 8 920
Senior Engineering Designer 100 4 400
Engineering Technician 80 0 0
Clerical 55 2 110
Total 2300
Mr. Garland Sandel Bill Baggs State Park
Printing 0
Overnight Travel (if applicable)
Mileage (@ $0.445 per mile)
Total Subtask 6J 2477.4
Project Schedule:
Activity Duration (Calendar Days) Days from Execution
Subtask 1: Lead and Asbestos Testing
60 - includes 7 days for Client review
Subtask 2: 60% plans 60 - includes 7 days for Client review
Subtask 3: 100% plans ERR 30 – includes 7 days for Client review
Subtask 4A: Permit applications
ERR
30 – includes 7 days for Client review
Subtask 4B: Permit approvals
ERR
60 – includes response for additional information
Subtask 5: Prebid 30 210
Subtask 6A – Pre-construction 30 TBD
Subtask 6B: Review Submittals 30 TBD
Subtask 6C: Respond to RAI's 60 TBD
Subtask 6D: Respond to Contractor
RFI's
240 (Est max overall calendar days;
RFI's will be responded to within 7 days of receipt from Contractor)
TBD
Subtask 6E: Provide Construction
Inspections w/ (Month 1)
30 TBD
Subtask 6F: Provide Construction
Inspections w/ Report (Month 2)
30 TBD
Subtask 6G: Provide Construction
Inspections w/ Report (Month 3)
30 TBD
Subtask 6H: Provide Construction
Inspections w/ (Month 4)
30 TBD
Subtask 6I: Substantial Completion
Walk-Through w/ Punchlist
30 TBD
Mr. Garland Sandel Bill Baggs State Park
Subtask 6J: Final Completion w/
Certification
30 TBD
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1: Lead/Asbestos Testing $4589.60 $0.00
Subtask 2: 60% plans $23288.75 $0.00
Subtask 3: 100% plans $7033.75 $127.00
Subtask 4A: Permit applications $9588.75 $0.00
Subtask 4B: Permit approvals $3363.75 $1495.00
Subtask 5: Pre-Bid $3520.00 $142.40
Total Design & Permitting $51384.60 $1764.40
Subtask 6A: Pre-Construction Meeting
$2080.00 $142.40
Subtask 6B: Submittal Review $3990.00 $35.00
Subtask 6C: Regulatory Response $1980.00 $0.00
Subtask 6D: Assistance during construction
$6900.00 $0.00
Subtask 6E: Inspection 1 $1577.50 $142.40
Subtask 6F: Inspection 2 $1577.50 $177.40
Subtask 6G: Inspection 3 $1577.50 $177.40
Subtask 6H: Inspection 4 $1577.50 $177.40
Subtask 6I: Substantial Completion
$2570.00 $177.40
Subtask 6J: Final Completion $2300.00 $177.40
Total during Construction $26130.00 $1206.80
Total Fixed Price Cost: $77514.60
Total Fixed Price Cost: $2971.20
Overall Total Cost: $80485.80
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified. (Please do not alter this language)
| BLANK TA Form.pdf |
| Proposal Bill Braggs SP Restroom Remodel_Rev 1.pdf |
File details come from the government source that posted it. Updated .