8-BEH-FRM-609.SAW Prime Self Performance Declaration.docx

DOCX document 114 KB Posted

Attached to
Southwest 96-inch Water Transmission Pipeline Project
Solicitation number
CIZ-DWU-26 003
Issued by
Dallas County, Texas

About this file

This is a Small Business Enterprise (SBE) Prime Self-Performance Declaration form used by the City of Dallas for contracts under the Dallas Regional Inclusive Vendor Enterprise (DRIVE) Policy. The document is specifically designed for the Southwest 96-inch Water Transmission Pipeline Project in Texas, which involves the installation of approximately 14,300 linear feet of 96-inch steel water pipe, 570 linear feet of 78-inch steel water pipe, and 30 linear feet of 54-inch prestressed concrete cylinder water pipe. The project scope includes both open cut and tunneling installation methods, cathodic protection, electrical and instrumentation systems for electrically actuated valves, and site and paving restoration. Plans, specifications, and bid proposal spreadsheets are available on Bonfire beginning Friday, March 13, 2026 prior to 4:00 p.m., with Tracey Long, PE serving as the project manager.

The declaration requires SBE prime contractors to identify and document all self-performed work, including applicable NAICS codes, work elements, and estimated contract values with corresponding percentages of total contract value. All self-performed work must meet Commercially Useful Function (CUF) requirements, meaning the prime contractor must use its own workforce, manage and supervise the work, use its own equipment or standard commercial leases, and maintain responsibility for execution. The form requires contractor certification that self-performed work complies with DRIVE Policy requirements and that commercially reasonable subcontracting opportunities were evaluated without artificially consolidating scopes to increase prime self-performance. Any changes to approved subcontractor participation require prior approval from the Business Enterprise HUB (BEH), and self-performed work will be subject to monitoring and compliance review throughout the contract term.

View the file

Other files

File Type Posted
14-DWU-FRM-170-CS Request For Competitive Sealed Proposals 26 003.pdf PDF
6-BEH-FRM-607.SAW SBE Good Faith Effort Documentation Form.docx DOCX document
23-Table 3 Subcontractors and Suppliers.pdf PDF
43-Table 10 Proposed Project Quality Control Managers.docx DOCX document
28-Table 8 Proposed Project Superintendents.pdf PDF
13-Form 25 Cement Preference Certification.pdf PDF
12-Conflict of Interest Questionnaire.pdf PDF
3-BEH-FRM-610.SAW SBE Subcontractor Intent Form.docx DOCX document
48-26 003 Bid Proposal Spreadsheet.xlsx XLSX spreadsheet
32-Table 12 Financial Information.pdf PDF
9-Sample Contract for Services.pdf PDF
7-BEH-FRM-604.SAW Local Participation Workforce Impact.docx DOCX document
10-BIDDERS AFFIDAVIT.pdf PDF
25-Table 5 Demonstation of Budget Performance.pdf PDF
40-Table 7 Proposed Project Managers.docx DOCX document
44-Table 11 Project Information for Key Personnel.docx DOCX document
11-Acknowledgement of Addendum.docx DOCX document
15-TWDB-0459.pdf PDF
21-Table 1 General Information.pdf PDF
24-Table 4 Current Projects and Projects Completed.pdf PDF
47-Table 13 Affidavits.docx DOCX document
36-Table 3 Subcontractors and Suppliers.docx DOCX document
37-Table 4 Current Projects and Projects Completed.docx DOCX document
27-Table 7 Proposed Project Managers.pdf PDF
42-Table 9 Proposed Project Safety Managers.docx DOCX document
34-Table 1 General Information.docx DOCX document
1-DRIVE Policy.pdf PDF
49-Volume I - Specifications - SWPL.pdf PDF
29-Table 9 Proposed Project Safety Managers.pdf PDF
19-26-003 SWP Summit GST to Hwy 67 Bid Set Specs Vol 5.pdf PDF
39-Table 6 Demonstration of On-Time Performance.docx DOCX document
20-26-003 SWPL Summit GST to Hwy 67 BID SET FULL BW.pdf PDF
26-Table 6 Demonstration of On-Time Performance.pdf PDF
46-Table 12 Financial Information.docx DOCX document
30-Table 10 Proposed Project Quality Control Managers.pdf PDF
17-26-003 SWP Summit GST to Hwy 67+Bid Set Specs Vol 3.pdf PDF
16-26-003 SWP Summit GST to Hwy 67 Bid Set Specs Vol 2.pdf PDF
45-Table 11 B Project Information for Key Personnel.docx DOCX document
35-Table 2 A B Contractors Approach.docx DOCX document
4-BEH-FRM-605.SAW SBE Utilization Plan Commitment to Local Eco Impact.docx DOCX document
38-Table 5 Demonstation of Budget Performance.docx DOCX document
2-BEH-FRM-602.SAW SBE Affidavit.docx DOCX document
33-Table 13 Affidavits.pdf PDF
22-Table 2 A B Contractors Approach.pdf PDF
5-BEH-FRM-606.SAW Engagement Score Past Commitment Form.docx DOCX document
18-26-003 SWP Summit GST to Hwy 67 Bid Set Specs Vol 4.pdf PDF
31-Table 11 Project Information for Key Personnel.pdf PDF
41-Table 8 Proposed Project Superintendents.docx DOCX document
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dallas Regional Inclusive Vendor Enterprise Prime Self-Performance Declaration

BEH-FRM-609.SAW

Prime Vendor Information

Prime Vendor Name
Solicitation Number
Solicitation Title

Under the DRIVE Policy, Small Business Enterprise (SBE) primes may count self-performed work toward the contract-specific SBE goal only when that work meets Commercially Useful Function (CUF) requirements and when the SBE firm is properly certified in the NAICS code(s) associated with the work it will perform.

This declaration confirms the SBE prime’s self-performance scope and enables the Business Enterprise HUB (BEH) staff to verify CUF compliance and appropriate NAICS certification before contract execution.

Description of Self – Performed Work Identify the specific portion(s) of work your firm will self-perform as the SBE prime. Include NAICS code(s), work element/packages(s), and a brief description of work.

NAICS Code(s):
Work Element/Package Identify the discrete subcontracting opportunity or supplier package (e.g., trade discipline or bid package):
Description of Work

Briefly describe portion of work included in this package for this contract. Focus on what is include or excluded, not the full contract scope.)

EXAMPLE

238220 – Plumbing, Heating, and Air-Conditioning Contractors

Mechanical Equipment Installation – Building A HVAC Package
Self-perform installation of five (5) owner-furnished rooftop HVAC units and associated ductwork for Building A only. Includes labor, supervision, duct fabrication, and installation. Excludes purchase of HVAC units, electrical connections, BAS programming, and work in other buildings.

(Add additional pages as needed)

Prime’s Estimated Contract Value ($):
Percentage (%) of Total Contract:

CUF & NAICS Certification Attestation To count toward the SBE goal, self-performed work must be performed under a Commercially Useful Function (CUF), meaning the Prime:

• Uses its own workforce

• Manages and supervises the work

• Uses its own equipment (or standard commercial lease)

• Is responsible for execution of the work ☐ We certify that all self-performed work listed above will be performed under a CUF and within the Prime’s certified NAICS code(s).

☐ We further certify that all SBE subcontractors identified in the approved SBE Utilization Plan are certified in the NAICS code(s) associated with their scopes of work.

Subcontracting Opportunity Attestation ☐ We certify that commercially reasonable subcontracting opportunities were evaluated consistent with DRIVE policy, and that our firm has not restricted, reduced, or artificially consolidated scopes of work in order to increase SBE prime self-performance.

Subcontracting & No Substitution Statement ☐ We understand that any change to approved subcontractor participation or reallocation of work requires prior BEH approval through submission of the applicable revision and change request forms.

Certification I certify that the information provided in this Self-Performance Declaration is accurate and that all self-performed SBE work will comply with DRIVE Policy requirements, CUF requirements, and NAICS certification requirements.

☐ We understand that self-performed work will be subject to monitoring and compliance review throughout the life of the contract in accordance with DRIVE Monitoring & Compliance procedures.

Officer Signature:

Printed Name:
Title:
Date:

BEH-FRM-609.SAW Revision Date: 2026.03.01 Page 1 of 1 image1.png