Alburg Springs LPOE Conference-Site Visit meeting minutes 2026 05 06.pdf

PDF 328 KB Posted

Attached to
Design Bid Build (DBB) Construction Requirement for Alburg Springs Land Port of Entry (LPOE), Alburg, Vermont
Solicitation number
47PB5126R0008
Issued by
Not on record

About this file

This document is the pre-proposal conference meeting minutes for GSA solicitation 47PB5126R0008, held on May 6, 2026, for the Alburg Springs Land Port of Entry Construction Project located at 303 Alburgh Springs Road in Alburgh, Vermont. The project is being procured by the U.S. General Services Administration on behalf of the U.S. Customs and Border Protection (CBP). The primary contract officer is Emily Jackson, with Molly Lewis as alternate and Alan Bombardier serving as the program manager/contracting officer's representative. The A/E contractor is Schwartz/Silver Architects, Inc., and the construction manager is CBRE Heery, Inc.

The proposal submission deadline is June 15, 2026, at 2:00 PM EST, with proposals to be emailed to emily.jackson@gsa.gov and molly.lewis@gsa.gov. Proposals are valid for 90 calendar days and must include a scanned bid bond. Written questions regarding specifications and drawings must be submitted by May 18, 2026, at 12:00 PM EST, with responses posted as an amendment by June 1, 2026. Access to controlled documents requires completion of Attachment 05 (Proprietary Information Agreement) and a Data Entry role on SAM.gov. The evaluation will use a trade-off process where non-price factors, when combined, are significantly more important than total evaluated cost. Both CLINs will be individually priced with their sum going into SF Form 1442 Block 17. Davis-Bacon prevailing wage requirements apply under Wage Determination VT20250027 (Grand Isle County, Vermont), with weekly certified payroll reports required on Form WH-347. Single email attachments must not exceed 25 megabytes and must be in PDF format. Site visits were conducted on May 6, 2026, with escorted access permitted but photography limited to locations away from the building due to security sensitivity.

View the file

Other files

File Type Posted
27. Amendment 47PB5126R0008 0008 2026 07 13.pdf PDF
3. Agreement Rev 2 2026 06 18.pdf PDF
25. Amendment 47PB5126R0008 0007 2026 06 18.pdf PDF
6. WD VT20250027 2026 05 18.pdf PDF
1. Solicitation Rev 1_2026 06 11.pdf PDF
2. SF1442 Rev 1 dated 2026 06 15.pdf PDF
3. Agreement Rev 1 2026 06 12.pdf PDF
21. Amendment 47PB5126R0008 0006 2026 06 15.pdf PDF
20. Amendment 47PB5126R0008 0005 2026 06 02.pdf PDF
19. Amendment 47PB5126R0008 0004 2026 05 29.pdf PDF
16. Alburg Springs - Port Signage SOW-ASR 01.pdf PDF
15. Amendment 47PB5126R0008 0003 2026 05 21.pdf PDF
Alburg Springs LPOE Conference-Site Visit meeting minutes_Rev 1 Amendment 0002_ 2026 05 15.pdf PDF
14. Amendment 47PB5126R0008 0002 2026 05 15.pdf PDF
13. Amendment 47PB5126R0008 0001 2026 05 12.pdf PDF
Alburg Springs LPOE Conference-Site Visit meeting minutes 2026 05 06.pdf PDF
Alburg Springs LPOE Conference-Site Visit meeting minutes 2026 05 06.pdf PDF
RP - Vertical Radiant Panel Cutsheet.pdf PDF
RG - Return Grille Cutsheet.pdf PDF
SG - Supply Grille Cutsheet.pdf PDF
ET - Expansion Tank Cutsheet.pdf PDF
FT - Fin Tube Cutsheet.pdf PDF
GFT - Glycol Feed Tank Cutsheet.pdf PDF
BT - Buffer Tank Cutsheet.pdf PDF
FB - Filter Box Cutsheet.pdf PDF
PUH - Propeller Unit Heater Cutsheet.pdf PDF
GI and GR - Gravity Intake and Relief Cutsheet.pdf PDF
DH - Duct Mounted Humidifier Cutsheet.pdf PDF
SG and EG - Security Grille Cutsheet.pdf PDF
BSF - Booth Supply Fan Cut Sheet.pdf PDF
RP - Horizontal Radiant Panel Cutsheet.pdf PDF
AS - Air Separator Cutsheet.pdf PDF
EHC - Electric Heating Coil Cutsheet.pdf PDF
2026-02-06 Review of Proposed Renovations - Historic Context (1).pdf PDF
4. GSA527-21a 2026 04 15.pdf PDF
FCU - Fan Coil Unit Cutsheet.pdf PDF
6. WD VT20250027 2026 04 15.pdf PDF
CP and GP - Pump Cutsheets.pdf PDF
3. Agreement 2026 04 15.pdf PDF
EH - Electric Wall Heater Cutsheet.pdf PDF
7. PBS PPQ 2026 04 15.pdf PDF
GSHP - Ground Source Heat Pump Cutsheet.pdf PDF
L - Louver Cutsheet.pdf PDF
HP and CU - Heat Pump Mini-Split Cutsheet.pdf PDF
8. Tips on Preparing a Subcontracting Plan 2026 04 15.pdf PDF
HUM - Steam Humidifier Cutsheet.pdf PDF
Alburg Springs VT LPOE Code Report - 20260206 (1).pdf PDF
9. Model Subcontracting Plan 2026 04 15.docx DOCX document
5. Proprietary Information Agreement 2026 04 15.docx DOCX document
EF - Exhaust Fan Cutsheet.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Public Building Services Acquisition Project Delivery Northeast Capital Construction Team

47PB5126R0008 Alburg Springs LPOE Construction Project, Pre-Proposal Conference Meeting Minutes

Alburg Springs Land Port of Entry Construction Project 303 Alburgh Springs Road, in Alburgh, VT

Solicitation # 47PB5126R0008

PRE-PROPOSAL CONFERENCE/SITE VISIT MEETING MINUTES

May 6, 2026 at 12:00 pm EST

OPENING

Introduction

The following are GSA personnel:

Primary Contract Officer Emily Jackson, Emily.Jackson@gsa.gov Alternate Contract Officer Molly Lewis, molly.lewis@gsa.gov Program Manager/COR Alan Bombardier, alan.bombardier@gsa.gov

Client/Government Agency: U.S. Customs and Border Protection (CBP) A/E Contractor: Schwartz/Silver Architects, Inc CMa Contractor: CBRE Heery, Inc.

The purpose of this meeting is to gain a better understanding of the Solicitation requirements and visit the project site. Only changes made by the issuance of an amendment are to be considered in preparing your proposal.

CLARIFICATION OF SPECIFICATIONS AND DRAWINGS

Contractor desiring an explanation or interpretation of the solicitation, drawings, specifications, etc. must request in writing by 12:00PM EST on May 18, 2026 to allow a reply before the submission of proposal. An amendment with the answers will be posted on or about June 1, 2026, or sooner.

Oral explanations or instructions given before the award of the contract will not be binding. Any information given concerning the solicitation will be furnished promptly as an amendment of the solicitation, if that information is necessary in submitting proposals, or if the lack of it would be damaging to any other Offeror.

All questions shall be e-mailed to Emily Jackson, emily.jackson@gsa.gov.

SITE VISIT:

Will be on May 6 at 12:00pm EST.

• Attendees will be allowed to walk around the building but MUST be escorted.

• Attendees are welcome to take photographs but your back HAS TO be to the building due to the sensitivity of the building.

ACCESSING DOCUMENTS

Pre-proposal Conference minutes will be posted to www.sam.gov.

mailto:Emily.Jackson@gsa.gov mailto:molly.lewis@gsa.gov mailto:alan.bombardier@gsa.gov

47PB5126R0008 Alburg Springs LPOE Construction Project, Pre-Proposal Conference Meeting Minutes

You must log-in to www.sam.gov to be able to request the controlled documents. When requesting access to the documents, you must download Attachment 05, Proprietary Information Agreement, and send the signed copy to me, Emily Jackson, emily.jackson@gsa.gov. Then you go into Sam.Gov and request access by clicking on the documents. If you have been assigned a Viewer Role then you won’t be able to request the documents. You will need to be assigned a Data Entry role by the Sam.gov administrator of your company when you first set up your Sam.gov account. This will not come to the government or an administrator of the Sam.gov site; it will go directly to your company administrator that established when you created your Sam.gov account. Once you have the data entry role then you will be able to request the secure documents which will come directly to me. All requests will be received to make sure we have the signed Attachment 05, Proprietary Information Agreement on file and then all requests are approved immediately during business hours as I receive them.

If the www.sam.gov request is sent before I have signed Attachment 05, Proprietary Information Agreement, I will send an email requesting that it be filled out and sent to me. Once I have the signed Attachment 05, Proprietary Information Agreement on file and then all requests are approved immediately during business hours as I receive them.

LABOR RATES

The Davis-Bacon Act requires contractors on federally funded construction projects over $2k to pay laborers and mechanics no less than the locally prevailing wages and fringe benefits for corresponding work. The U.S. Department of Labor (DOL) determines these rates, which are updated annually and found on www.sam.gov. The government will require weekly certified payroll reports utilizing form WH- 347 to ensure compliance. The Applicable Davis Bacon Wage Determination is VT20250027 Dated 01/02/2026 which covers Grand Isle County in Vermont. Any modifications to this wage determination will be included in a forthcoming amendment. This will be routinely checked all the way up to award.

BEST VALUE EVALUATION PROCESS

The two most common methods of a best value solicitation are the lowest price technically acceptable and then the trade-off process. For this solicitation we are utilizing the trade-off process.

Lowest Priced Technically Acceptable (LPTA) The winning proposal is the lowest-priced offer that meets all technical standards (technically acceptable). This is a PASS or FAIL situation regarding the technical requirements. The non-cost factors are rated simply "acceptable" or "unacceptable". There are a time and place to use this evaluation, and the program team decided it would not be in the best interest for this specific project.

Trade-off Process A best-value solicitation that allows the government to trade off cost against technical capabilities (e.g., higher performance, better past performance). Unlike LPTA this is not a pass/fail evaluation. It is a comparative assessment where proposals are ranked and balanced against price to determine which offer provides the greatest overall benefit rather than simply meeting a minimum threshold. In this specific solicitation we state Non-Price Factors, when combined, are significantly more important than Total Evaluated Price. Proposals are evaluated on a competitive, relative basis to determine the best overall value, which may warrant a higher price.

http://www.sam.gov/ https://www.google.com/search?q=Trade-off+Process&sca_esv=344f3e5e0d3315c7&rlz=1C1GCEA_enUS1087US1087&sxsrf=ANbL-n7rR_p4AngVZ3X0VEUHKgQEYtvyDQ%3A1776084725899&ei=9ebcadjCNpGtiLMPhfr-kAw&biw=1280&bih=551&ved=2ahUKEwiik_mr7-qTAxVDKVkFHYJ8DRgQgK4QegQIBBAB&uact=5&oq=what+is+the+difference+between+the+trade+off+process+and+lowest+priced+technically+acceotable&gs_lp=Egxnd3Mtd2l6LXNlcnAiXXdoYXQgaXMgdGhlIGRpZmZlcmVuY2UgYmV0d2VlbiB0aGUgdHJhZGUgb2ZmIHByb2Nlc3MgYW5kIGxvd2VzdCBwcmljZWQgdGVjaG5pY2FsbHkgYWNjZW90YWJsZUjDf1AAWN56cAB4AZABAJgBmgKgAccUqgEGMi4xOC4xuAEDyAEA-AEBmAIDoAL2AsICBBAhGAqYAwDiAwUSATEgQJIHAzAuM6AH00ayBwMwLjO4B_YCwgcFMC4yLjHIBweACAA&sclient=gws-wiz-serp&safe=active&ssui=on&mstk=AUtExfBTxfe2UF_VBHfrdEqXscbKQznCjqhnSwPEaZutWQsba9p5m0DgtqvvU10Wj-NbUrG1Hv0pEDsBBB7n5oCJQ0XCc785xa3YbMA5Y6iYJw-m7mkkzJgHOhWr5g8UnJaxnU-TICHX0nuOH3LQpEp03hhH86M9kWYiEKC7BBLmGwkFshgYKHZhfYl4Rd7xX7QODa-C&csui=3

47PB5126R0008 Alburg Springs LPOE Construction Project, Pre-Proposal Conference Meeting Minutes

The government has decided the best solution for this project may not necessarily be the cheapest, and that superior performance for this project provides greater value.

SF FORM 1442: Solicitation, Offer and Award.

Page 3 you will see two (2) CLINS. Both CLINS will be individually priced and the total evaluated cost = CLIN 1 + 2 will go directly into block 17. Directly below will be where you acknowledge all amendments with the date issued of the amendment.

PROPOSAL DUE DATE AND METHOD OF SUBMISSION

In order to be considered for award, proposals conforming to the requirements of the Solicitation must be received at the following email no later than 2:00 PM EST on the following date and at the following address:

DATE: June 15, 2026 Email: emily.jackson@gsa.gov and molly.lewis@gsa.gov

Proposals shall be good for a period of ninety (90) calendar days. The bid bond should be scanned and sent with the proposal. Make sure that we can see the stamp. We do not need the original copy mailed to us.

Please be advised that single emails with attachments of 25 megabytes or more, or attachments other than those in PDF format, may be rejected by GSA's servers.

NOTE: Any proposal received after the time and date specified above will be considered LATE and may be rejected.

CLOSING

Please remember that anything stated here today, would not bind the government unless it is incorporated into the solicitation by a written amendment.

All questions should be sent to Emily at emily.jackson@gsa.gov.

mailto:emily.jackson@gsa.gov mailto:molly.lewis@gsa.gov mailto:emily.jackson@gsa.gov

File details come from the government source that posted it. Updated .