About this file

This document appears to be a set of phasing plans for the expansion and renovation of the Emergency Department in Building 50 at the Tucson VA Medical Center. The plans outline 5 phases of construction work, with detailed notes on the objectives and logistics for each phase. Key details include:

Phase 3 will construct 10 new exam rooms, including 2 mental health rooms, and a connecting corridor. Phase 4 will add 4 more exam rooms and a physician collaboration room. Phase 5 will build the ED procedure rooms, CT and radiographic rooms, and a women's restroom. Throughout the project, the contractor must maintain egress, access to imaging, and the emergency department's functionality in a limited capacity. Noise and vibration work is restricted to off-hours. The contractor must coordinate construction phasing with the VA's schedule, infection control, and interim life safety requirements.

This phasing plan is related to solicitation number 36c77623r0191 for the "Expand And Renovate Emergency Department - Tucson, Arizona 85723" project, issued by the Department of Veterans Affairs Technology Acquisition Center in Austin.

View the file

Other files

File Type Posted
50-EP601.pdf PDF
50-M703.pdf PDF
50-A701.pdf PDF
50-A102.pdf PDF
50-M601.pdf PDF
50-EP101.pdf PDF
50-M704.pdf PDF
50-A504.pdf PDF
50-A104.pdf PDF
50-CU101.pdf PDF
Addendum 1.pdf PDF
50-M505.pdf PDF
50-A502.pdf PDF
50-MG702.pdf PDF
50-AC101.1.pdf PDF
50-MH101.1.pdf PDF
50-EP102.pdf PDF
11 73 00 Ceiling Mounted Patient Lift_Rev.pdf PDF
08 80 00 Glazing_Rev.pdf PDF
50-A401.pdf PDF
50-AC101.4.pdf PDF
50-A303.pdf PDF
50-GC101.pdf PDF
50-MH104.pdf PDF
50-M602.pdf PDF
50-M702.pdf PDF
50-EP602.pdf PDF
01 00 00 Gen Reqs_Rev.pdf PDF
50-MG100.pdf PDF
Technical Questions Spreadsheet - Tucson - Final.pdf PDF
50-A602.pdf PDF
50-M503.pdf PDF
50-CD101.pdf PDF
50-S450.pdf PDF
50-MG701.pdf PDF
50-S310.pdf PDF
50-M701.pdf PDF
36C77623R0191 0003.pdf PDF
36C77623R0191 0002.pdf PDF
36C77623R0191 0001.pdf PDF
Site Visit Sign in Sheet Pg 1 and 2 - Tucson.pdf PDF
Attachment 8 - Architectural Drawings 2 of 2.pdf PDF
Attachment 14 - Mechanical Drawings.pdf PDF
Attachment 6 - Structural Drawings.pdf PDF
36C77623R0191 - 02-22-24.pdf PDF
Attachment 2 - Specifications - 2 of 3.pdf PDF
Attachment 5 - Civil Drawings.pdf PDF
Attachment 20 - Site Visit Instructions.pdf PDF
Attachment 17 - PTube Drawings.pdf PDF
Attachment 7 - Architectural Drawings 1 of 2.pdf PDF
Show 40 more

Latest 50 of 62 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TR

AV

EL

D

IS

TA

N C

E

TO

E

XI

T

LF

TRAVEL DISTANCE TO

EXIT = 194'-5"

TRAVEL DISTANCE TO EXIT = 182LF

TRAVEL DISTANCE TO EXIT = 87'-6"TRAVEL DISTANCE TO

EXIT = 188'-9"

TR

AV

EL

D

IS

TA

N C

E

TO

E

XI

T

LF

TR

AV

EL

D

IS

TA

N C

E

TO

E

XI

T

LF

TRAVEL DISTANCE TO EXIT =

173'-6"

TRAVEL DISTANCE TO EXIT = 123LF

TRAVEL DISTANCE TO EXIT = 89LF

CURRENT PHASE

NOT INCLUDED IN

AREA OF WORK

o n e e ig h th in c h o n e fo o t th re e in c h e s o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

A

B

C

D

E

F

A

B

C

D

E

F

Drawing Title Project Title

VA FORM 08-6231

Office of Facilities Management

U.S. Department of Veterans Affairs

STAMP

Date

Location

Building Number Checked Drawn Drawing Number

Project Number

BID SET

Approved: Director

Approved: Associate Director

Approved: Assistant Director

Approved: Assoc. Director for Patient Care Service/Nurse Executive

Approved: Deputy Assoc. Director of Patient Care Services

Approved: Chief of Staff

Approved: Deputy Chief of Staff

Approved: Chief of Engineering

Approved:

Approved:

ARCHITECT/ENGINEER/CONSULTANTS:

Bancroft Project No.

SAVAHCS, TUCSON, AZ 85723

3300 Dundee Road

Northbrook, IL 60062

T: 847.952.9362

04/30/2024GENERAL - PHASING PLANS EXPAND AND RENOVATE

EMERGENCY DEPARTMENT B50

50 CZ DTB

50-GC102

678-331

19-103

8-

E X

P A

N D

A N

D R

E N

O V

A T

E E

M E

R G

E N

C Y

D E

P A

R T

M E

N T

B

A

D D

E N

D U

M

N 1/16" = 1'-0"

PHASE 4

GENERAL PHASING NOTES

1. SAVAHCS WILL REQUIRE A MAXIMUM OF 28 CALENDAR DAYS BETWEEN PHASES TO MOVE INTO A

NEW SPACE AND OUT OF AN EXISTING SPACE FOR THE NEXT PHASE.

2. MAINTAIN EMERGENCY DEPARTMENT LOCK DOWN FEATURE DURING EACH PHASE.

3. CONTRACTOR SHALL BE RESPONSIBLE FOR SEQUENCING AND COORDINATION OF

CONSTRUCTION PHASING WITH THE VA'S SCHEDULE, INFECTION CONTROL, AND INTERIM LIFE

SAFETY REQUIREMENTS. REFER TO SPECIFICATIONS FOR PROJECT GENERAL CONDITIONS,

INFECTION CONTROL, SPECIAL NOTES, PROJECT SCHEDULE, ETC. FOR ALL PROJECT

REQUIREMENTS.

4. CONTRACTOR SHALL PROVIDE ALL SUB-PHASING ACTIVITIES AS REQUIRED FOR WORK

OCCURRING BETWEEN VARIOUS PHASES.

5. THE PHASING PLAN IS NOT TO BE TAKEN AS AN ALL INCLUSIVE LIST OF ALL ITEMS TO BE

COMPLETED WITHIN A SPECIFIC OUTLINED PHASE. PLEASE REFER TO ALL DISCIPLINES AND

CONTRACT DOCUMENTS FOR ALL WORK ASSOCIATED IN THESE AREAS

6. THE PHASING PLAN IS SUBJECT TO THE CONTRACTORS MEANS AND METHODS, SCHEDULING

AND TO EXISTING CONDITIONS AND TIME RESTRAINTS.

7. CONTRACTOR SHALL REFER TO ALL DEMOLITION AND CONSTRUCTION DRAWINGS FOR A

COMPLETE UNDERSTANDING OF THE SPECIFIED SCOPE OF WORK.

8. CONTRACTOR SHALL MAINTAIN EGRESS PASSAGE WAYS MAIN CORRIDOR, ELEVATOR LOBBY

AND STAIR EXITS DURING COMPLETE PROJECT DURATION. ALSO MAINTAIN ALL EGRESS/EXIT

DOORS OF THE FACILITY.

9. CONTRACTOR SHALL REFER TO INFECTION CONTROL DRAWINGS AND SUGGESTED LOCATION OF

CONSTRUCTION BARRIERS AND ENTRANCES.

10. CONTRACTOR SHALL NOTE ALL EXISTING PLUMBING, MECHANICAL AND ELECTRICAL SERVICES

AND SYSTEMS THAT ARE SCHEDULED TO REMAIN FULLY OPERATIONAL AND FUNCTIONAL FOR

DURATION OF SPECIFIC PHASES.

11. CONTRACTOR SHALL NOTE THAT BUILDING 50 SHALL BE OCCUPIED DURING CONSTRUCTION.

12. HOURS OF OPERATION FOR NOISE AND VIBRATION OPERATIONS ARE DURING OFF NORMAL

HOSPITAL OPERATION HOURS (6:00PM TO 6:00AM). SERVICE INTERRUPTIONS DURING OFF

NORMAL WORK HOURS AND SCHEDULED MINIMUM (2) WEEK ADVANCED NOTICE.

13. WHERE TWO OR MORE SEQUENCES MEET IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO

COORDINATE THE TRANSITION WORK BETWEEN SEQUENCES.

14. CONTRACTOR TO HAVE ALL MATERIALS AND EQUIPMENT ON SITE FOR THE COMPLETION OF ANY

WORK THAT IS DESIGNATED FOR OFF HOURS PRIOR TO THE START OF OFF HOURS WORK

15. PHASES TO BE PERFORMED IN SEQUENCE.

16. THE INTENT OF THE PHASING PLANS IS TO PROVIDE A MEANS BY WHICH THE EMERGENCY

DEPARTMENT REMAINS AVAILABLE AND FUNCTIONAL IN A LIMITED MANNER TO THE VETERANS.

17. PHASING IS SUBJECT TO THE CONTRACTORS MEANS AND METHODS, SCHEDULING AND TO

EXISTING CONDITIONS AND TIME RESTRAINTS.

18. PLEASE REFER TO EACH DISCIPLINES PHASING SHEETS FOR DISCIPLINE SPECIFIC NOTES AND

CONDITIONS WITHIN EACH PHASE. THERE ARE INSTANCES WHEN WORK WILL NEED TO BE

PERFORMED IN ACTIVE PARTS OF THE HOSPITAL TO ACCOMPLISH THE DESIRED INTENT WITHIN

THE PHASE. THIS WORK IS TO BE COMPLETED AFTER HOURS AND TO BE COORDINATED WITH

THE COR.

19. ADDITIONAL SHEETS ARE : 50-MC101, 50-MC102, 50-FX002, 50-FX003, 50-FX004, 50-P003, 50-P004, 50-P005, 50-P006, 50-P007, 50-P008, 50-MG-002 AND 50-MG004.

PHASE 3 NOTES

PHASE 4 NOTES

PHASE 5 NOTES

N 1/16" = 1'-0"

PHASE 3

A. THE INTENT OF PHASE 3 IS THAT 10 NEW EXAM ROOMS WHICH INCLUDE 2 MENTAL HEALTH

ROOMS AND NURSING SUPPORT WILL BE OPERATIONAL AT THE END OF PHASE 3.

B. IN PHASE 3 THE ED ENTRY DRIVE WILL BE IN USE

C. THE AMBULANCE ENTRY WILL BE OPEN AND WALK IN ED PATIENTS WILL UTILIZE THE NEW ED

ENTRANCE AND DROP-OFF CONSTRUCTED IN PHASE 1.

D. USERS WILL IDENTIFY ROOMS CONSTRUCTED IN PHASE 2 TO BE USED AS MENTAL HEALTH

ROOMS IN PHASE 3

E. PHASE 3 TO INCLUDE THE CONSTRUCTION OF THE CONNECTING CORRIDOR BETWEEN PHASE 1

CONSTRUCTION AND THE RENOVATED PHASE 3 CONSTRUCTION VIA A NEW CORRIDOR THROUGH

TOILET ROOM # 163,164 AND ROOM # 133.

A. PHASE 4 WILL ADD 4 EXAM ROOMS, A THROUGH CORRIDOR ACCESSING THE NEW PHYSICIAN

COLLABORATION ROOM.

B. PHASE 4 WILL REQUIRE A TEMPORARY STAFF AREA TO MONITOR THE NEW ISOLATION ROOMS

AND AMBULANCE ENTRANCE. ACCESS TO IMAGING WILL NEED TO BE MAINTAINED.

C. ONE OF THE LARGER EXAM ROOMS CONSTRUCTED DURING PHASE 3 WILL BE USED FOR TRAUMA

D. WALK IN AND AMBULANCE ACCESS WILL REMAIN UNCHANGED FROM PREVIOUS PHASE

A. THE INTENT OF PHASE 5 IS TO CONSTRUCT THE ED PROCEDURE ROOMS AND BOTH CT AND

RADIOGRAPHIC ROOMS AND WOMENS TOILET ROOM. PROVISIONS WILL BE MADE TO

TEMPORARILY USE ONE OR MORE OF THE NEWLY CONSTRUCTED EXAM ROOMS FOR ACUTE

PATIENTS. THE SOUTH END OF THE NURSE STATION ADJACENT TO THE AMBULANCE ENTRY WILL

BE CONSTRUCTED WITH CONSTRUCTION OF THE REMAINING NORTH-SOUTH CORRIDOR

FRONTING THE PROCEDURE ROOMS

B. WALK IN AND AMBULANCE ACCESS WILL REMAIN UNCHANGED FROM THE PREVIOUS PHASE

C. PHASE 5A - FINISHED FLOOR IN COORIDOR TO BE DONE AFTER HOURS

PHASING LEGEND

N 1/16" = 1'-0"

PHASE 5

Revisions: Date:

BID SET 05/01/2023

ADDENDUM 1 04/30/2024

-RFI #12

Sheets
50-GC102 - GENERAL - PHASING PLANS

File details come from the government source that posted it. Updated .