This document is a Statement of Bid Items for a temperature controls remediation project at the Department of Veterans Affairs Medical Center in Cincinnati, Ohio. The solicitation includes five bid items with progressive complexity and integration options for temperature control systems. Bid Item 1 is the base bid for complete remediation work, which includes electrical work and must be completed within 730 calendar days after receiving the Notice to Proceed. Subsequent bid items (2-5) offer alternative configurations by selectively removing integration requirements for Automated Logic Routers and Metasys Routers with the new Tridium system, allowing flexibility in system integration and potential cost adjustments based on available funding. The government intends to award the contract on Bid Item 1, but may select alternative bid items if funding constraints exist, with a predetermined priority order for bid item selection.
View the file
Other files for this federal contract opportunity
Show all 50
Z2DA--Remediate Temperature Controls 539-21-108 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF BID ITEM(S)
A. BID ITEM 1, BASE BID ALL WORK: Work shall include all labor, materials, equipment and supervision required to complete the project REMEDIATE TEMPERATURE CONTROLS in the Hospital, at the
Department of Veterans Affairs Medical Center, 3200 Vine Street, Cincinnati, Ohio. Work includes electrical work, as described on the technical specifications and drawings.
It is the intent of the Government that award will be made on BID ITEM 1 (BASE BID); however, should the bids exceed the funds available, award may be made on BID ITEM 2, 3, 4 or 5 in that order of priority, based on available funding. Bidders should bid on each item listed.
All phases of work including close out documents shall be complete within 730 calendar days after receipt of
Notice to Proceed.
Total Bid Item No. 1: $_________________________ (Lump Sum)
B. BID ITEM 2: All work in BID ITEM 1, BASE BID, except DELETE all labor and materials associated with integrating Automated Logic Routers into the new Tridium system thru JACEs. In lieu of using JACEs, the Automated Logic Routers shall be integrated via over IP.
All phases of work including close out documents shall be complete within 730 calendar days after receipt of
Total Bid Item No. 2: $_________________________ (Lump Sum)
C. BID ITEM 3: All work in BID ITEM 2, except DELETE all labor and materials associated with integrating Metasys Routers into the new Tridium system thru JACEs. In lieu of using JACEs, the
Metasys Routers shall be integrated via over IP.
All phases of work including close out documents shall be complete within 730 calendar days after receipt of
Total Bid Item No. 3: $_________________________ (Lump Sum)
D. BID ITEM 4: All work in BID ITEM 3, except DELETE all labor and materials associated with integrating
Automated Logic Routers into the new Tridium system. ALC system shall stand-alone under this alternate.
All phases of work including close out documents shall be complete within 730 calendar days after receipt of
Total Bid Item No. 4: $_________________________ (Lump Sum)
E. BID ITEM 5: All work in BID ITEM 4, except DELETE all labor and materials associated with integrating Metasys Routers into the new Tridium system. Metasys system shall stand alone under this alternate.
All phases of work including close out documents shall be complete within 730 calendar days after receipt of Notice to Proceed.
Total Bid Item No. 5: $_________________________ (Lump Sum)