Questions and Answers.docx
DOCX document 26 KB Posted
- Attached to
- 36-Month Electrical Distribution Testing
- Solicitation number
- 36C24727Q0044
About this file
This is a Questions and Answers document for federal contract solicitation 36C24727Q0044, a 36-month electrical distribution testing effort for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7. The contractor will perform inspection, testing, adjustment, calibration, preventive maintenance, and infrared thermographic scanning of electrical distribution equipment across three VA sites: Decatur Main Campus, Fort McPherson, and Trinka Davis, with all three sites treated as a single job. The period of performance is 240 calendar days from receipt of Notice to Proceed, and the project represents a single, non-recurring performance effort.
The base scope of work includes visual inspection, cleaning, mechanical inspection, torque verification, electrical testing (insulation resistance, contact resistance, ground fault system testing, protective relay testing, circuit breaker trip testing, continuity testing, and grounding system testing), circuit breaker maintenance, grounding system inspection, documentation, and one round of infrared thermographic inspection under normal load conditions per VHA Directive 1028 requirements. All corrective work, repairs, component replacements, and remediation of identified deficiencies are explicitly excluded from the base scope. De-energized electrical testing is required for all assets that the VA can de-energize, with ground fault testing required for circuit breakers rated 1000A and above equipped with ground fault protection. Secondary injection testing and protective relay calibration are excluded from base work. All work requiring equipment outages shall be performed during scheduled weekend shutdowns, with contractors anticipating three separate outage schedules for the three sites. The contractor must provide comprehensive reports documenting all equipment tested, test results, deficiencies identified, and corrective action recommendations. Previous test documents and existing equipment lists are available from the VA, and offerors must demonstrate relevant experience with electrical distribution system testing and maintenance.
View the file
Other files
Show 40 more
Latest 50 of 53 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions – Electrical Distribution Equipment Maintenance and Testing
1. Scope of Work The SOW indicates that the scope consists of inspection, testing, adjustment, calibration, preventive maintenance, and infrared thermographic scanning of the electrical distribution equipment listed in Attachments A, B, and C for the Decatur Main Campus, Fort McPherson, and Trinka Davis sites.
Please confirm that all of the above activities are required and shall be included in the base scope of work. All 3 sites are 1 job.
2. Project Schedule The Solicitation states that the period of performance shall be 240 calendar days from receipt of Notice to Proceed (NTP) and that this is a single, non-recurring performance effort.
Please advise the anticipated NTP date and planned project start date. Award date to completion date.
3. Electrical Testing We understand that testing will be performed on the electrical equipment identified in Attachment A in accordance with applicable NFPA 70B maintenance practices.
Upon completion of testing, we will provide a comprehensive report documenting:
· Equipment tested
· Test results
· Deficiencies identified
· Recommendations for corrective actions, where applicable
Please confirm that any corrective work, repairs, replacement of components, or remediation of deficiencies identified during testing are excluded from the base scope. This is correct.
4. Preventive Maintenance Activities Our understanding is that preventive maintenance may include some or all of the following activities, as applicable to the equipment being maintained:
a) Visual Inspection - Inspection for signs of overheating, contamination, moisture intrusion, corrosion, or physical damage.
b) Cleaning - Removal of dust, debris, and contaminants from accessible equipment surfaces and compartments.
c) Mechanical Inspection - Verification of proper operation of mechanical mechanisms, interlocks, and moving components.
d) Torque Verification - Inspection and re-torquing of accessible power and control connections in accordance with manufacturer specifications.
e) Electrical Testing - Depending upon equipment type and project requirements, testing may include:
· Insulation Resistance (Megger) Testing
· Contact Resistance (Ducter) Testing
· Ground Fault System Testing
· Protective Relay Testing
· Circuit Breaker Trip Testing
· Primary Injection Testing
· Secondary Injection Testing
· Continuity Testing
· Grounding System Testing
f) Circuit Breaker Maintenance - Inspection, exercising, and operational verification of circuit breakers.
g) Grounding System Inspection - Inspection and verification of grounding conductors and grounding connections.
h) Documentation and Reporting
· Documentation of all inspection findings and test results.
· Identification of deficiencies and recommended corrective actions.
· Submission of a final maintenance report.
Please confirm which of the above preventive maintenance activities are required under the base scope.
Per VHA Directive 1028 pg 16: “6) Electrical equipment (including, but not limited to switchgears, switchboards, distribution panels, motor control centers, and all related components) is inspected, tested, maintained, or calibrated every 36 months, and all work must be documented.”
5. Outage Requirements Please confirm that all work requiring equipment outages shall be performed during scheduled weekend shutdowns (Saturday and Sunday). Additionally, please advise whether any weekday outages will be permitted. Yes.
6. Infrared Thermographic Inspections: The SOW requires infrared thermographic scanning.
Please clarify:
· How many rounds of infrared inspections are required. 1
· The required interval between each inspection cycle.
· The anticipated date for the first inspection cycle.
· Whether scans are required under normal load conditions and if minimum loading criteria apply.
Per VHA Directive 1028 pg 1617
7. Adjustment and Calibration Requirements: The SOW includes equipment adjustment and calibration activities.
Please note that adjustment and calibration of protective devices can only be properly performed when current Power System Coordination and Arc Flash Studies are available for reference.
However, Page 21 of 69 of the Solicitation indicates that the Coordination Study and Arc Flash Study are excluded from the scope.
Please clarify:
· Whether a current Coordination Study and Arc Flash Study will be provided by the Owner. No
· Whether we are expected to perform device adjustments and calibration based on existing study information. No
· Whether preparation of a new Coordination Study and Arc Flash Study is intended to be added to the scope. No
If new studies are required, we will require: No
· Latest single-line diagrams for all three sites.
· Equipment schedules.
· Detailed bill of materials (BOM).
· Equipment submittals and shop drawings.
· Existing protection settings, if available.
· Cable lengths, material type, number of conductors, utility data, gen set data.
8. Injection Testing and Protective Device Verification: Page 10 of 69 of the Solicitation states that:
"Primary-injection time-current testing, secondary-injection or trip-unit testing, calibration, and functional testing of separately testable low-voltage power circuit breakers, electronic trip units, and protective relays are excluded from the base work."
The Solicitation further states that:
"Nothing in this SOW, in Section 10.1, or in Attachment D requires injection testing, trip-unit testing, or relay calibration of branch devices within a scheduled assembly as part of the base work."
Please review and confirm this requirement.
Note that verification of the proper operation and trip functionality of electronic trip units and protective relays typically requires, at a minimum, secondary injection testing. Excluding injection testing may limit the ability to fully validate protective device performance and coordination.
Please advise whether secondary injection testing is to remain excluded from the scope. Yes.
9. Ground Fault Testing Per NFPA 70B and NETA maintenance practices, circuit breakers equipped with Ground Fault (GF) protection are commonly tested to verify proper operation of the ground-fault sensing and tripping functions.
Our understanding is that existing low-voltage circuit breakers rated 1000A and above, equipped with ground-fault protection, should undergo on-site secondary injection and ground-fault performance testing.
Please confirm whether ground-fault testing is required and identify any minimum breaker ratings or specific equipment exclusions that may apply. Yes, ground-fault testing is required. See attached equipment list.
10. Documents required – please provide the following documents:
· complete as-built drawings/submittal packages for all equipment included in the testing, inspection, and preventive maintenance (PM) scope.
· current and complete single-line diagrams for each of the three project sites, reflecting all existing electrical distribution equipment and system configurations.
See attached previous test
11.The Technical Capability evaluation criteria reference experience related to “automatic door maintenance,” while the SOW is for electrical distribution system inspection, testing, maintenance, calibration, and infrared scanning. Please confirm that the references to “automatic door maintenance” are inadvertent, and that offerors should instead demonstrate relevant experience with electrical distribution system testing and maintenance. We just need electrical distribution system experience.
12. Please confirm the anticipated execution plan for the three sites.
Specifically, will the Contractor be able to mobilize once and perform the testing consecutively across all three sites, or should multiple mobilizations be anticipated based on separate outage schedules for each site? Should anticipate three separate outage schedules.
13. Could you please provide information about the project’s previous maintenance history, including the year when the most recent maintenance was performed? See attachments.
14. Please confirm whether there are any costs or fees associated with scheduled outages, and if so, whether these costs will be borne by the VA or the Contractor None known cost.
15. SOW Section 10.1 and Attachment D require de-energized electrical testing (insulation resistance, contact resistance, connection-torque verification, and turns ratio) that depends on outages, but the solicitation does not identify which listed assets the VA expects to be able to de-energize. To price the work accurately, please clarify the following:
· Can the VA identify any assets in Attachments A, B, or C that it already knows cannot be de-energized during the period of performance, or that can be de-energized only under limited conditions, such as critical-branch, life-safety, or operating-room equipment? All assets are to be de-energized.
· For distribution panelboards, Attachment D calls for insulation resistance and connection-torque verification "on de-energized panels." Does this mean these tests are required only on panels for which the VA provides an outage, with panels that remain energized receiving visual/mechanical inspection and infrared only? Yes.