Electrical Distribution Testing SOW final.docx

DOCX document 55 KB Posted

Attached to
36-Month Electrical Distribution Testing
Solicitation number
36C24727Q0044
Issued by

About this file

This is a Statement of Work (SOW) for electrical distribution system inspection, testing, maintenance, calibration, and infrared scanning services at three Atlanta VA Health Care System locations: Joseph Maxwell Cleland Atlanta VA Medical Center, Fort McPherson VA Clinic, and Trinka-Davis Veterans Village Clinic.

The contractor must complete all field testing, inspection, calibration, maintenance, and infrared scanning within 240 calendar days after Notice to Proceed, with the consolidated final testing and maintenance report due within 30 calendar days thereafter, not to exceed 270 calendar days total. Work includes visual and mechanical inspection, de-energized electrical testing (requiring outages coordinated through the VA), energized infrared thermographic surveys, and maintenance of low-voltage and specified medium-voltage electrical distribution equipment per ANSI/NETA MTS standards and applicable codes. The contractor must be either a NETA Accredited Company or demonstrate equivalent qualifications through certified technicians, documented quality assurance programs, calibrated instruments, five years of relevant experience, and conforming procedures. Infrared thermography must be performed by personnel holding current Level II or higher certification. All on-site personnel must be qualified persons under NFPA 70E and complete VA site-specific safety orientation. The scope includes switchgear, panelboards, transformers, circuit breakers, automatic transfer switches, motor control centers, and isolated power systems as listed in Attachments A, B, and C; it excludes repairs, equipment modifications, engine-generator maintenance (except output and main breakers), internal UPS service, utility-owned equipment, individual device testing unless listed as separate assets, and temporary power provision. The contractor must submit deliverables including safety plans, qualifications documentation, work schedule and phasing plan, rolling 30-day outage look-ahead, daily field reports, per-segment Engineering Service Reports within 10 business days of each segment completion, and a comprehensive final report with test data, infrared images, deficiency logs, and laboratory results in searchable PDF format plus native spreadsheet files and two hard copies. Work is performed at multiple sites sequentially or concurrently at the contractor's discretion, primarily outside normal hours (evenings, weekends, and Federal holidays) to minimize patient care disruption, with all such hours included in pricing. The first VA-directed outage cancellation after crew mobilization is at no additional charge; subsequent cancellations are compensable only when authorized in advance by the Contracting Officer. The contractor warrants workmanship for one year from Government acceptance and must reperform any deficient work at no cost.

View the file

Other files

File Type Posted
Final - AF Label List.xlsx XLSX spreadsheet
final remote - gen device eval.pdf PDF
Attachment B - Fort McPherson Equipment Schedule - REV19.1.xlsx XLSX spreadsheet
Drawing List.pdf PDF
GHTA-AG-1.pdf PDF
final main site - util input report.pdf PDF
NHSB-BG-1.pdf PDF
20200603 - Final Combined pdfs.pdf PDF
final main site - util device eval.pdf PDF
final main site - util bus eval.pdf PDF
Existing-Recommended Breaker Settings - Final.xlsx XLSX spreadsheet
GHSB-C3-1.pdf PDF
final remote - gen results report.pdf PDF
NHSB-CB-1.pdf PDF
final main site - gen bus eval.pdf PDF
Equipment Condition Assessment Sheets.xlsx XLSX spreadsheet
GHTA-CB-1.pdf PDF
final remote - gen input report.pdf PDF
final remote - util results report.pdf PDF
Questions and Answers.docx DOCX document
Attachment C - Trinka-Davis Equipment Schedule - REV19.1.xlsx XLSX spreadsheet
Switchboard C.pdf PDF
Attachment D - Equipment and Test Matrix - REV19.1.docx DOCX document
final remote - util bus eval.pdf PDF
7.6 Facility Condition Assessment - Final Submission.xlsx XLSX spreadsheet
NHSB-C3-2.pdf PDF
final main site - gen device eval.pdf PDF
GHSB-AG-1.pdf PDF
Electrical Directive 1028 D 2020-02-24.pdf PDF
GHTA-CB-2.pdf PDF
final remote - util device eval.pdf PDF
ArcFlash - Atlanta Main Site Final.xls XLS spreadsheet
Attachment A - Main Campus Equipment Schedule - REV19.1.xlsx XLSX spreadsheet
ArcFlash - Atlanta Remote Sites Final.xls XLS spreadsheet
final remote - gen bus eval.pdf PDF
NSHB-CB-2.pdf PDF
NHSB-C3-1 Fast Transfer.pdf PDF
36C24727Q0044 0002.pdf PDF
7.7 Building System Assessment_Atlanta.xlsx XLSX spreadsheet
NHSB-C3-1.pdf PDF
Wage Determination 2015-4471.docx DOCX document
final main site - gen input report.pdf PDF
Switchgear ED.pdf PDF
final main site - gen results report.pdf PDF
final remote - util input report.pdf PDF
Atlanta VA Main Campus 2022 IR Report.pdf PDF
final main site - util results report.pdf PDF
36C24727Q0044 0001.pdf PDF
36C24727Q0044_1 36-Month Electrical Distribution Testing.docx DOCX document
Attachment D - Equipment and Test Matrix - REV19.docx DOCX document
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Electrical Distribution System Inspection, Testing, Maintenance, Calibration, and Infrared Scanning Atlanta VA Health Care System (Station 508) Joseph Maxwell Cleland Atlanta VA Medical Center • Fort McPherson VA Clinic • Trinka-Davis Veterans Village Clinic Table of Contents

1.0 Background3
2.0 Objective3
3.0 Scope of Work3
3.1 Order of Precedence and Conflict Resolution3
4.0 Place of Performance4
5.0 Period of Performance and Schedule4
6.0 Applicable Standards4
7.0 Contractor Qualifications5
7.1 Organizational Qualification (Alternative Paths)5
7.2 Mandatory Requirements Applicable to Either Path5
8.0 Government-Furnished Information6
9.0 Equipment Covered and Scope6
10.0 Specific Tasks: Testing, Calibration, Maintenance, and Infrared6
10.1 Required Maintenance Level by Asset Class7
10.2 Infrared Thermographic Survey Requirements8
10.3 Fort McPherson Site-Specific Equipment8
10.4 Trinka-Davis Site-Specific Equipment9
11.0 Protective-Device Settings9
12.0 Outage Planning, Coordination, and Access9
12.1 Government Inability to Provide Planned Outages10
13.0 Temporary Power10
14.0 When an Outage Cannot Be Obtained11
14.1 Deferred-Testing Register11
14.2 Closeout of Deferred Testing11
14.3 Acceptance11
15.0 Retesting12
15.1 Separately Ordered Retesting12
15.2 No-Cost Reperformance12
16.0 Field Documentation12
17.0 Reporting12
18.0 Deliverables13
19.0 Contract Administration14
19.1 Contracting Officer (CO)14
19.2 Contracting Officer's Representative (COR)14
19.3 Contractor Responsibilities14
19.4 Key Personnel14
19.5 Submittals14
19.6 Kickoff and Notice to Proceed14
19.7 Invoicing14
20.0 Inspection and Acceptance14
21.0 Warranty15
22.0 Safety and Hospital Operational Controls15
23.0 Site Access, Security, Badging, and Conduct15
23.1 Identity Verification, Vetting, and Unescorted Access15
23.2 Parking, Staging, and Conduct16
24.0 Privacy and Information Security16
25.0 Hours of Work16
26.0 Exclusions16
27.0 Definitions and Acronyms17
28.0 Attachments18

1.0 Background

The Atlanta VA Health Care System operates VA-owned electrical power distribution equipment serving occupied healthcare facilities at the Main Campus, Fort McPherson VA Clinic, and Trinka-Davis Veterans Village Clinic. Applicable VA facility electrical power systems policy, including VHA Directive 1028, Facility Electrical Power Systems, or formally issued successor, requires recurring inspection, testing, maintenance, calibration, and documentation of facility electrical power system equipment on a 3-year maintenance interval. This Statement of Work (SOW) defines the services required to complete the current inspection, testing, calibration, maintenance, and infrared scanning cycle for the equipment listed in Attachments A, B, and C.

2.0 Objective

The contractor shall perform inspection, testing, adjustment, calibration, preventive maintenance, and infrared thermographic scanning of the electrical distribution equipment listed in Attachments A, B, and C, in accordance with this SOW and the applicable standards, and shall document the results and report deficiencies to the VA.

3.0 Scope of Work

The work includes the labor, supervision, materials, tools, calibrated test equipment, and reporting necessary to inspect, test, adjust, calibrate, maintain, and infrared-scan the low-voltage and specified medium-voltage electrical distribution equipment at the three sites, as listed in the attached equipment schedules. The work is a nonpersonal service. It is testing and maintenance, not repair or construction.

The equipment schedules in Attachments A, B, and C define the equipment. Attachment D, the Equipment and Test Matrix, states the test method applicable to each asset class.

3.1 Order of Precedence and Conflict Resolution

In the event of a conflict or apparent inconsistency among the documents governing this work, the following order of precedence applies:

1. Applicable law, regulation, and the terms and conditions of the resulting contract, including all solicitation clauses incorporated by reference or in full text.

1. This SOW, which governs the general scope of work, performance requirements, and contract administration.

1. Attachments A, B, and C, which govern asset identity, asset location, and quantities.

1. Attachment D, which governs the test method for each asset class only to the extent it is consistent with this SOW. Attachment D does not add an asset, add a quantity, or expand the scope.

1. The cited consensus standards and the equipment manufacturers' maintenance and testing instructions, as applicable to the equipment serviced.

The contractor shall raise any conflict, ambiguity, or apparent discrepancy in writing to the Contracting Officer before performing the affected work. Only the Contracting Officer may direct a change to the requirement. Performance of work based on the contractor's own resolution of a conflict is at the contractor's risk.

4.0 Place of Performance

Site
Address
Equipment schedule
Main Campus, Joseph Maxwell Cleland Atlanta VAMC
1670 Clairmont Road, Decatur, GA 30033
Attachment A
Fort McPherson VA Clinic (Buildings 125, 128, 129, 130, and 131)
1701 Hardee Ave SW, Atlanta, GA 30310
Attachment B
Trinka-Davis Veterans Village Clinic
180 Martin Drive, Carrollton, GA 30117
Attachment C

5.0 Period of Performance and Schedule

The contractor shall not begin on-site work until the Contracting Officer issues a Notice to Proceed (NTP). The contractor shall complete all field testing, inspection, calibration, maintenance, and infrared scanning at all three sites within 240 calendar days after NTP. This is the contractual completion deadline for field work.

The consolidated final testing and maintenance report is due within 30 calendar days after completion of all field testing, and in no case later than 270 calendar days after NTP. Per-segment Engineering Service Reports are due as stated in Section 18.0. The period of performance of the contract extends through Government acceptance of the final report and closeout.

This is a single, non-recurring performance action. There are no option periods, option quantities exercised as separate performance periods, and no option-year renewals. Separately ordered work described in Sections 15.0 and 16.0 is ordered by the Contracting Officer within this action.

The contractor is responsible for the crewing and sequencing needed to meet the completion deadline and may perform the three sites sequentially, concurrently, or in any combination, using one or more crews. The Government does not require simultaneous performance at the three sites. Because the equipment is in occupied healthcare facilities, outage availability rather than labor hours is expected to govern the sequence of work.

Within 14 calendar days after NTP, the contractor shall submit a proposed work schedule and phasing plan showing the planned sequence of sites, the number of crews, and requested outage windows, with all field work completed within the 240-calendar-day period and de-energized testing sequenced to minimize impact on patient care. The phasing plan establishes planned interim milestones for coordination and acceptance only. Acceptance of the phasing plan by the COR does not change, extend, or shorten the contractual completion deadline, and does not constitute a change to the contract. Only the Contracting Officer may adjust the completion deadline, by modification.

6.0 Applicable Standards

The contractor shall perform the work in accordance with the following, in the edition adopted by the VA and the authority having jurisdiction (AHJ) as of the solicitation date, and with the equipment manufacturers' maintenance and testing instructions:

1. ANSI/NETA Standard for Maintenance Testing Specifications for Electrical Power Equipment and Systems (ANSI/NETA MTS). This is the primary test-method basis.

1. VHA Directive 1028, Facility Electrical Power Systems, or formally issued successor. Directive 1028 remains applicable until it is recertified or rescinded.

1. NFPA 70, National Electrical Code.

1. NFPA 70B, Standard for Electrical Equipment Maintenance.

1. NFPA 70E, Standard for Electrical Safety in the Workplace.

1. NFPA 99, Health Care Facilities Code, and NFPA 110, Standard for Emergency and Standby Power Systems, as applicable to the equipment serviced.

1. OSHA, 29 CFR 1910 (General Industry), including Subpart S (Electrical).

1. The Joint Commission Environment of Care standards for utility and electrical systems, as applicable.

1. Infrared thermographic testing shall be performed by personnel holding current Level II (or higher) infrared thermography certification from a nationally recognized certification program, using written procedures consistent with the current ANSI/NETA MTS.

Where a cited standard conflicts with this SOW, or with another cited standard, the contractor shall request clarification from the Contracting Officer before performing the affected work, and the order of precedence in Section 3.1 applies.

7.0 Contractor Qualifications

The contractor, including any subcontractor personnel performing specialized testing, shall possess the licenses, certifications, training, and qualifications required for the specific work each entity performs. The prime contractor remains fully responsible for all subcontractor work.

7.1 Organizational Qualification (Alternative Paths)

The organization performing the electrical testing shall satisfy one of the following two alternative paths. Personnel-level qualifications do not satisfy this organizational requirement.

1. Path 1: Be a NETA Accredited Company; or

1. Path 2: Demonstrate a documented objective equivalent by providing all of the following: on-site testing technicians certified as electrical testing technicians at a level appropriate to the work, with crew leaders at the senior level; a documented quality-assurance program; test instruments calibrated within the previous 12 months with dated calibration labels; at least five years of experience performing inspection, testing, and maintenance of low-voltage and medium-voltage electrical power distribution equipment of the types included in this SOW, in healthcare, industrial, or comparable commercial facilities; and written testing procedures that conform to the current ANSI/NETA MTS.

7.2 Mandatory Requirements Applicable to Either Path

The following requirements apply regardless of which organizational qualification path in Section 7.1 is used, and are in addition to that path:

1. Personnel performing testing of the medium-voltage main distribution transformer at Trinka-Davis shall be qualified for that voltage class and equipment type, including the liquid-filled transformer and insulating-liquid tests specified in Section 10.4. This personnel qualification does not substitute for the organizational qualification required by Section 7.1.

1. Infrared thermography shall be performed by a thermographer holding current Level II (or higher) infrared thermography certification from a nationally recognized certification program.

1. All on-site personnel performing or supervising electrical work shall be qualified persons as defined in NFPA 70E.

1. All test instruments used shall carry current calibration, calibrated within the previous 12 months, with dated calibration labels and traceable calibration records available on request.

1. All on-site personnel shall complete VA site-specific safety orientation before work begins.

8.0 Government-Furnished Information

Attachments A, B, C, and D are issued with the solicitation. For reference, and to the extent available, the VA will also provide one-line diagrams, riser information, and any existing electrical distribution condition assessment at or before the kickoff meeting. Reference drawings are provided for planning and are not warranted for accuracy. The contractor shall report any discrepancy between field conditions and the reference materials as part of its documentation.

9.0 Equipment Covered Scope

Attachments A, B, and C are the controlling equipment lists. The scope is the equipment listed in those attachments. Field verification confirms nameplate data, exact locations, and any discrepancies; it does not change the scope. Where field verification identifies a quantity discrepancy, or the Contracting Officer directs a change.

10.0 Specific Tasks: Testing, Calibration, Maintenance, and Infrared

1. Perform maintenance testing, inspection, adjustment, and calibration of each listed asset in accordance with the current ANSI/NETA MTS and the manufacturers' instructions. Components of an assembly shall be tested in their final connected condition.

1. The scope for each scheduled assembly consists of visual and mechanical inspection, the assembly-level electrical tests expressly identified for that asset class in Section 10.1, and the infrared survey required by Section 10.2. Panelboard, switchboard, switchgear, and unit-substation main and branch devices are inspected, and their connections are checked, as part of the listed assembly.

1. Individual device testing is not included in the scope. Primary-injection time-current testing, secondary-injection or trip-unit testing, calibration, and functional testing of separately testable low-voltage power circuit breakers, electronic trip units, and protective relays are excluded from the work unless the individual device is expressly listed as an asset in Attachment A, B, or C.. Nothing in this SOW, in Section 10.1, or in Attachment D requires injection testing, trip-unit testing, or relay calibration of branch devices within a scheduled assembly as part of the work.

1. For automatic transfer switches listed in the attachments, perform controller and functional verification, inspect and check main and neutral connections, verify timing, and include each switch in the infrared survey. Any test that actually transfers facility load between the normal and emergency sources shall be performed only when approved through the outage plan and coordinated with the COR, so that no unplanned emergency-power transfer occurs during patient care.

1. For generator output and main breakers listed in the attachments, perform visual and mechanical inspection, connection checks, trip verification, and infrared survey. Engine-generator maintenance is not part of this work (Section 27.0).

1. Perform inspection, cleaning, measurement, testing, and calibration at the level required for each asset class in the maintenance-level table in Section 10.1.

1. Perform an infrared thermographic survey of the listed equipment in accordance with Section 10.2.

1. After servicing each asset, apply a durable adhesive test label bearing, at a minimum, the contractor name, the test date, the technician identification, and the result. The COR may approve reasonable variations in label format that contain these minimum elements.

1. Immediately report any deficiency the contractor deems critical or catastrophic to the COR and the Chief, Engineering Service. Record other defective or worn conditions in the daily field report and the deficiency log.

1. The contractor shall not change protective-device settings except as provided in Section 11.0.

10.1 Required Maintenance Level by Asset Class

The table below states the required level of work by asset class for assets listed in Attachments A, B, and C. Attachment D states the test method for each asset class. Where the table and Attachment D differ, the order of precedence in Section 3.1 applies and the contractor shall request clarification from the Contracting Officer before performing the affected work. Neither this table nor Attachment D adds an asset to the scope or expands scope beyond the assemblies and devices listed in Attachments A, B, and C.

The rows for low-voltage power circuit breakers, molded-case and insulated-case breakers with electronic trip units, and protective relays state the test method that applies when the individual device is listed as an asset in Attachment A, B, or C. Those rows do not place individual device testing in the scope (Section 10.0, item c).

De-energized electrical tests require an outage; the contractor shall schedule outages under Section 12.0. Where a listed asset cannot be de-energized within the period of performance, Section 14.0 applies. The contractor shall not omit a required test on its own determination; any exception must be approved in writing by the COR and documented.

Asset class
Energized IR
Visual / mechanical
De-energized electrical tests (require outage)
LV switchgear, switchboards, main distribution panels, unit substations
Yes, under load
Yes
Insulation resistance; contact resistance on main and tie devices; connection-torque verification
Distribution panelboards
Yes, under load
Yes
Insulation resistance and connection-torque verification on de-energized panels
Dry-type transformers
Yes, under load
Yes
Insulation resistance; turns ratio
Medium-voltage main distribution transformer (Trinka-Davis, 750 kVA, liquid-filled)
Yes, under load
Yes
Insulation resistance; turns ratio; winding resistance; power or dissipation factor; insulating-liquid dielectric breakdown and dissolved gas analysis
LV power circuit breakers (drawout), individually listed or ordered
Yes
Yes
Primary-injection time-current testing; contact resistance; insulation resistance
Molded-case or insulated-case breakers with electronic trip units, individually listed or ordered
Yes
Yes
Secondary-injection or trip-unit testing per ANSI/NETA MTS
Protective relays, individually listed or ordered
Not applicable
Yes
Calibration or functional test; record as-found and as-left settings
Motor control centers, where listed in Attachments A, B, or C
Yes, under load
Yes
Insulation resistance; connection-torque verification
Automatic transfer switches
Yes, under load
Yes
Controller and functional verification; contact and connection check; timing; transfer test coordinated through the outage plan (Section 12.0), not performed unplanned during patient care
Generator output and main breakers
Yes
Yes
Connection check; trip verification
Safety-switch and service disconnects
Yes, under load
Yes
Contact and connection check; mechanical operation
Isolated power systems, where listed in Attachments A, B, or C
Yes
Yes
Line isolation monitor function verification; insulation testing per NFPA 99

10.2 Infrared Thermographic Survey Requirements

1. Survey equipment under normal or representative load. Record the load condition, for example percent of rated or measured current, for each surveyed section.

1. For each finding, provide a thermal image and a corresponding visible-light image, tied to the equipment asset identifier and location, with a severity classification, the probable cause, and a recommended corrective action.

1. Energized cover or panel removal for infrared access shall follow NFPA 70E and VA energized-work controls (Section 23.0). Where infrared inspection windows are installed, document their use.

1. Equipment that cannot be surveyed under load, or that is inaccessible, shall be listed and reported so the VA can schedule a follow-up survey.

10.3 Fort McPherson Site-Specific Equipment

Fort McPherson comprises five VA-owned buildings: 125, 128, 129, 130, and 131. All electrical distribution equipment listed for those buildings in Attachment B is in scope and is tested per the maintenance-level table in Section 10.1. In addition:

1. Fire-pump controller and motor (Building 125): electrical inspection and testing only, coordinated with the facility fire-protection program. The scope for this asset is limited to visual and mechanical inspection, infrared survey underload, connection checks, and insulation-resistance testing of the controller and motor circuit. Fire-pump flow testing, pump performance testing, mechanical fire-pump service, and fire-protection system certification are not included.

1. Uninterruptible power supply (UPS) (Building 125): external connection inspection and infrared survey only. Internal UPS service, including batteries, power electronics, and firmware, is not included.

10.4 Trinka-Davis Site-Specific Equipment

The medium-voltage main distribution transformer listed in Attachment C for Trinka-Davis Veterans Village Clinic is treated as VA-owned or VA-maintained equipment and is included in the scope, notwithstanding the general exclusion of utility-owned equipment in Section 27.0, item d. It is a liquid-filled (mineral-oil) pad-mounted transformer rated 750 kVA, 12,470GrdY/7,200 volts primary to 480Y/277 volts secondary. Ratings shall be confirmed against the nameplate during field verification and any discrepancy reported under Section 8.0.

The contractor shall perform the following on this transformer, in accordance with the applicable ANSI/NETA MTS provisions for liquid-filled transformers: visual and mechanical inspection; insulation-resistance tests (winding-to-winding and winding-to-ground); turns-ratio test at all tap positions; winding-resistance test; power-factor or dissipation-factor test of the insulation system; insulating-liquid sample testing, including dielectric breakdown voltage and dissolved gas analysis; and an infrared survey under load.

The following boundaries apply to this asset:

1. Sampling and laboratory work: the contractor furnishes sampling equipment, containers, and normal test consumables; draws the insulating-liquid samples; and provides laboratory analysis with the results, laboratory identification, test methods, and interpretation included in the reports required by Sections 17.0 and 18.0.

1. Government-furnished records: the VA will provide available ownership, maintenance, and environmental records for this transformer to the extent they exist. The contractor shall not assume the condition or regulatory status of the insulating liquid and shall handle all samples in accordance with applicable Federal, State, and local requirements.

1. Suspected contamination or release: the contractor shall immediately stop affected work and notify the COR and the Chief, Engineering Service, of any suspected contamination, leak, or release, and shall not disturb the affected area further without VA direction.

1. Waste disposal: the contractor is responsible for lawful disposal of the sample volumes and normal test consumables it generates. Disposal, remediation, or handling of any other material, including bulk insulating liquid or contaminated media, is outside the scope and requires Contracting Officer direction before the contractor performs it.

1. Switching and energization: the VA controls all switching and re-energization of this equipment through the approved outage plan (Section 12.0). The contractor shall not operate VA switching devices except as authorized in the approved outage plan.

11.0 Protective-Device Settings

The contractor shall record as-found and as-left protective-device settings as maintenance documentation. The contractor shall not develop coordination recommendations and shall not change settings unless the VA directs a specific change in writing. A VA-directed change to protective-device settings is outside the scope and outside the price in the price schedule; it requires a separately negotiated bilateral modification to the contract before the contractor performs the change.

12.0 Outage Planning, Coordination, and Access

1. Outages are requested and approved through the Atlanta VA Health Care System Utility Outage Request process. The contractor shall submit the current Utility Outage Request form to Engineering Service at least 15 working days before the requested outage date. Outages are approved at the discretion of the Chief Engineer or other authorized VA authority. The VA retains final control over the timing of outages that affect patient care.

1. The COR coordinates outage scheduling between the contractor and Engineering Service and facilitates site access. The COR does not approve scope or price, does not authorize additional work, and does not unilaterally grant outages.

1. The contractor shall provide Engineering Service a rolling 30-day look-ahead of anticipated outages, updated as the schedule develops, so that affected service lines can be coordinated before the individual outage requests are submitted. The look-ahead is for planning and does not replace the outage-request requirement in item a.

1. The work is expected to require multiple outage windows at each site. Pricing includes all work performed outside normal hours, including evenings, weekends, and Federal holidays, as necessary to complete the required testing without disrupting patient care.

1. Mobilization and cancellation: a VA-directed cancellation or delay of an approved outage that is communicated after the contractor crew has arrived on site, or after it has departed for the site on a COR-confirmed schedule, is a mobilization event. The first such event per site is absorbed at no additional charge. Each additional VA-directed cancellation after mobilization is a remobilization, compensable under the remobilization line item in the price schedule only when authorized in advance by the Contracting Officer. Delays, cancellations, and return trips caused by the contractor, and ordinary rescheduling of outage windows within the approved phasing plan, are cost and are not compensable. Standby time within an approved outage window is included in the price.

1. The contractor shall coordinate site access, escort, and staging with the COR and shall not create life-safety or infection-control impacts (Section 23.0).

12.1 Government Inability to Provide Planned Outages

Where the VA is unable to provide an outage that was timely requested and reflected in the approved phasing plan, the following process applies:

1. The contractor shall notify the COR in writing promptly, and in no case later than 10 calendar days after the contractor knows or should know that a planned outage will not be provided, identifying the affected assets, the requested and denied dates, and the schedule effect; the contractor and the COR shall then jointly pursue reasonable mitigation, including rescheduling within the period of performance, resequencing sites, regrouping outage windows, performing the energized portion of the work where permitted, and recording the asset in the deferred-testing register under Section 14.0.

1. Where mitigation does not resolve the effect, the COR shall refer the matter to the Contracting Officer with the documentation. The Contracting Officer alone determines any adjustment to the completion deadline and any entitlement to compensation, in accordance with the terms and conditions of the contract; only the Contracting Officer may grant a schedule extension or authorize additional compensation, and a denied or delayed outage does not by itself authorize the contractor to perform additional work or entitle the contractor to additional compensation. Failure by the contractor to submit timely written notice and supporting documentation may be considered in determining entitlement, to the extent the lack of notice prejudices the Government.

13.0 Temporary Power

Where an outage requires temporary or backup power, the VA will furnish or separately arrange it. Contractor-furnished temporary power is not part of the scope. The contractor is not required to furnish temporary power and shall not include temporary power generation or distribution in its price. The contractor shall coordinate any temporary-power need with the COR during outage planning.

14.0 When an Outage Cannot Be Obtained

If a required outage for a listed asset cannot be obtained within the period of performance, the contractor shall perform the energized (visual and infrared) portion for that asset and shall record the asset in a deferred-testing register.

14.1 Deferred-Testing Register

The contractor shall maintain and submit to the COR a register listing each affected asset, its location, the specific de-energized tests not performed, the reason the outage could not be obtained, the outage requests submitted, and the proposed reschedule date. The register is updated as items are cleared and is submitted with each Engineering Service Report.

14.2 Closeout of Deferred Testing

Any de-energized testing still open in the deferred-testing register as the completion deadline approaches shall be dispositioned before closeout. No later than 30 calendar days before the 240-calendar-day completion deadline, or earlier if it becomes apparent that a required outage cannot be obtained, the contractor and the COR shall review the register and, for each open item, either schedule completion before that deadline or refer it to the Contracting Officer for disposition.

14.3 Acceptance

Before field work begins, the contractor shall submit, and the COR shall review and approve, a schedule of values allocating price across the major equipment groups and between the energized and de-energized portions of the work. If the solicitation prescribes a schedule-of-values template or allocation framework, the contractor shall use it. If the solicitation does not prescribe one, the schedule of values shall at a minimum identify, each major equipment group; the count of listed assets in that group; the allocated dollar amount for the energized (visual, mechanical, and infrared) portion; the allocated dollar amount for the de-energized portion; the allocated amount for reporting and closeout; and a total that reconciles exactly to the price.

15.0 Retesting

15.1 Separately Ordered Retesting

Retesting of equipment after the VA or another party performs corrective action, where the original testing was complete and correct, is separately ordered work.

15.2 No-Cost Reperformance

Retesting or completion of work that is required because of contractor error, incomplete testing, or inadequate or missing documentation is not a paid item. The contractor shall reperform or complete that work, including any return trips, at no additional cost to the Government, and such reperformance does not count against any separately ordered retesting quantity.

16.0 Field Documentation

1. Record, for each asset: identification and nameplate data, location, test methods and instruments used with model and serial numbers, test data with as-found and as-left values and settings, pass or fail results, and deficiencies with recommended corrective action.

1. Maintain a deficiency log throughout performance and report discrepancies between field conditions and the reference drawings and attachments.

17.0 Reporting

1. Engineering Service Report (ESR), per work segment: for each completed building, area, or outage grouping agreed with the COR, submit an ESR within 10 business days of completing that segment, documenting the information in Section 17.0 and the current deferred-testing register.

1. Consolidated final testing and maintenance report: submit within 30 calendar days after completion of all field testing, and no later than 270 calendar days after NTP.

1. Daily field reports during performance, and immediate notice of any critical or catastrophic deficiency.

The consolidated final report shall contain, at a minimum: an executive summary; the equipment inventory as tested, cross-referenced to the asset identifiers in Attachments A, B, and C; nameplate data; the test data required by Section 17.0 with as-found and as-left settings; the infrared survey results with paired thermal and visible-light images, load conditions, and severity classifications; the deficiency log with recommended corrective actions and priorities; the deferred-testing register with its final disposition; insulating-liquid laboratory results for the Trinka-Davis transformer; and instrument calibration records covering the performance period.

Reports shall be delivered electronically as searchable Portable Document Format (PDF) files, plus the tabular test data, deficiency log, and deferred-testing register in native editable spreadsheet format. Two hard copies of the consolidated final report shall also be provided. The COR may approve reasonable variations in report format and organization that satisfy these minimum content and format requirements.

18.0 Deliverables

Deliverable
Content
Due
Site-specific safety plan
Energized-work procedures, lockout/tagout (LOTO) procedures, hazard analysis, and personal protective equipment plan
Before on-site work begins
Qualifications and calibration submittal
Organizational qualification under Section 7.1, key personnel qualifications and certifications, thermographer certification, and instrument calibration records
Before on-site work begins
Schedule of values
Allocation price across major equipment groups and between the energized and de-energized portions of the work, per Section 14.3
Before field work begins, with or before the phasing plan
Work schedule and phasing plan
Planned sequence of sites, number of crews, requested outage windows, planned interim milestones
Within 14 calendar days after NTP
Rolling outage look-ahead
30-day look-ahead of anticipated outages
Before the first outage request, updated at least monthly
Utility Outage Request forms
Completed VA outage request for each planned outage
At least 15 working days before each requested outage
Daily field report
Work performed, assets serviced, deficiencies, areas affected
Each work day
Critical deficiency notice
Immediate notice to the COR and Chief, Engineering Service
Upon discovery
Deferred-testing register
Assets with de-energized testing not performed, reason, outage requests, proposed reschedule dates
With each ESR, and at closeout review under Section 14.2
Engineering Service Report (ESR)
Per-segment test data, settings, deficiencies, recommendations
Within 10 business days of segment completion
Final testing and maintenance report
Consolidated content required by Section 18.0, in searchable PDF with native tabular data and two hard copies
Within 30 calendar days after all field testing, and no later than 270 calendar days after NTP

19.0 Contract Administration

19.1 Contracting Officer (CO)

The Contracting Officer is the only person authorized to award, modify, or terminate this contract, to change the scope, to authorize additions or deletions, to adjust the schedule, or to obligate Government funds.

19.2 Contracting Officer's Representative (COR)

The Contracting Officer will designate a COR in writing after award. The COR is the primary point of contact for technical coordination, outage coordination, review of deliverables, and inspection of work. The COR cannot change the scope, price, schedule, or terms of the contract.

19.3 Contractor Responsibilities

The contractor is responsible for the means and methods of performance, the safety and conduct of its personnel and subcontractors, protection of Government property, and the quality of the work. The contractor shall designate a single point of contact for the VA.

19.4 Key Personnel

The contractor shall designate a project supervisor and a lead testing technician as key personnel. Key personnel shall not be substituted without prior written notice to the COR and replacement personnel of equal or better qualifications.

19.5 Submittals

The contractor shall provide the submittals and deliverables listed in Section 19.0 at the times stated in that table. The COR-approved schedule of values is the basis for acceptance under Sections 14.3 and 20.7.

19.6 Kickoff and Notice to Proceed

The contractor shall not begin on-site work until the Contracting Officer issues a Notice to Proceed and a kickoff meeting is held or waived in writing. At or before kickoff, the contractor shall confirm key personnel, the safety plan, and the proposed schedule and outage approach.

19.7 Invoicing

The contractor shall submit invoices electronically in accordance with the invoices and payment clauses of the contract, including VAAR 852.232-72, Electronic Submission of Payment Requests, referencing the contract and CLIN, the period covered, the deliverables or milestones accepted with COR acceptance dates, and a description of the services provided. Acceptance is based on the COR-approved schedule of values (Sections 14.3 and 19.0); the amount allocated to deferred de-energized testing is withheld until that testing is performed and accepted, or until the Contracting Officer modifies the requirement. Payment is tied to VA acceptance of the associated deliverables.

20.0 Inspection and Acceptance

The Government will inspect and accept the work through the COR. Work under CLIN 0001 will be considered complete and acceptable when all of the following conditions are met:

1. The required inspection, testing, calibration, maintenance, and infrared survey have been performed on the listed equipment, consistent with Section 10.0 and the maintenance-level table in Section 10.1.

1. Test labels have been applied to serviced equipment and contain the minimum elements required by Section 10.0, item h.

1. The per-segment ESRs and the consolidated final report have been submitted and accepted, with complete and legible test data, as-found and as-left settings, deficiency log, and infrared findings, in the formats required by Section 18.0.

1. Deficiencies attributable to the contractor's work, including missing or unreadable data or labels, have been corrected at no additional cost.

1. Any required de-energized testing that could not be completed has been dispositioned under Section 14.0.

The COR will perform a final review of the documentation and a walk-through of the serviced areas, and will document acceptance in writing. Acceptance is governed by Section 14.3. The Government reserves the right to witness any test.

21.0 Warranty

The contractor shall warrant the workmanship of the testing, calibration, and maintenance services for one year from the date of Government acceptance. If, during that period, work is found to have been performed incorrectly or not in accordance with the applicable standards and this SOW, the contractor shall reperform the affected work at no additional cost. This warranty applies to the services performed and does not obligate the contractor to warrant the continued operation of VA-owned equipment that the contractor did not repair, replace, or recondition. This provision states a minimum workmanship warranty and does not limit, waive, or supersede any inspection, warranty, or remedy clause included in the contract; where this provision and a contract clause differ, the clause governs.

22.0 Safety and Hospital Operational Controls

1. Perform all work in accordance with NFPA 70E and OSHA 29 CFR 1910, using qualified persons, energized-work controls, lockout/tagout, and appropriate personal protective equipment.

1. Coordinate infection control risk assessment (ICRA) and interim life-safety measures (ILSM) with the VA before affecting occupied areas.

1. Protect patients, staff, visitors, and Government property, and maintain egress and life-safety systems during the work.

23.0 Site Access, Security, Badging, and Conduct

Contractor personnel shall comply with all VA facility access and security requirements at all three sites.

23.1 Identity Verification, and Unescorted Access

This work requires contractor personnel to move throughout occupied clinical, administrative, and utility spaces to reach the equipment listed in Attachments A, B, and C. The contractor shall perform with personnel authorized for unescorted access. Continuous VA escort is not available, and personnel who are not authorized for unescorted access must be escorted in occupied areas.

23.2 Parking, Staging, and Conduct

1. Check in and out at Engineering Service at the start and end of each work period.

1. Do not block fire lanes, loading areas, emergency exits, or patient and visitor parking. Coordinate staging and parking with the COR.

1. The Atlanta VA Health Care System is a tobacco-free campus. Comply with all campus tobacco restrictions.

1. Photography is permitted only as necessary to document equipment conditions and completed work. Do not photograph patients, staff, visitors, or protected information.

24.0 Privacy and Information Security

Performance of this work does not require contractor access to VA information systems or to VA sensitive information, other than the administrative processes required by the contract. Submission of invoices through the Government's authorized electronic invoicing system, are administrative contract processes. This process does not authorizes access to any other VA information system, network, or data.

Contractor personnel shall not access VA information systems, networks, or sensitive information unless separately authorized in writing by the Contracting Officer in accordance with the applicable contract clauses and VA policy.

25.0 Hours of Work

Normal hours are Monday through Friday, 7:00 a.m. to 4:30 p.m., excluding Federal holidays. Because this equipment serves occupied facilities, much of the work will be performed outside normal hours, including evenings, weekends, and Federal holidays, as coordinated with the COR and approved through the outage process. Work performed outside normal hours is included in the price (Section 12.0, item d).

26.0 Exclusions

The following are not included in this contract:

1. Repair, replacement, rewiring, breaker upgrades, equipment modifications, and reconditioning of deficient equipment.

1. Engine-generator maintenance, including NFPA 110 generator operational testing, engine maintenance, fuel-system work, and generator preventive maintenance. Only the generator output and main breakers and the transfer switches listed in the attachments are in scope.

1. Internal UPS service; fire-pump flow testing, pump performance testing, mechanical fire-pump service, and fire-protection system certification.

1. Utility-owned equipment. Only VA-owned or VA-maintained equipment listed in the attachments is included. The Trinka-Davis medium-voltage main distribution transformer identified in Section 10.4 is treated as VA-owned or VA-maintained and is included in the scope notwithstanding this exclusion.

1. Individual device testing is excluded from the scope under Section 10.0, item c.

1. Any arc-flash incident-energy study, short-circuit study, protective-device coordination study, one-line diagram development, or arc-flash labeling. No study-level engineering or labeling is included. The infrared and testing tasks in this SOW do not include or require an arc-flash or coordination study. That engineering-study work is performed under a separate action and is not part of this contract.

1. Contractor-furnished temporary power (Section 13.0).

1. Environmental remediation, and disposal of material other than the sample volumes and normal test consumables addressed in Section 10.4.

27.0 Definitions and Acronyms

Term
Definition or meaning
AHJ
Authority having jurisdiction.
ANSI
American National Standards Institute.
ATS
Automatic transfer switch.
CLIN
Contract line item number.
CO
Contracting Officer.
COR
Contracting Officer's Representative.
DGA
Dissolved gas analysis of insulating liquid.
ESR
Engineering Service Report.
FAR
Federal Acquisition Regulation.
ICRA
Infection control risk assessment.
ILSM
Interim life-safety measures.
IR
Infrared.
kVA
Kilovolt-ampere.
LOTO
Lockout/tagout.
LV
Low voltage.
MDP
Main distribution panel.
MTS
Maintenance Testing Specifications (ANSI/NETA).
MV
Medium voltage.
NETA
InterNational Electrical Testing Association.
NFPA
National Fire Protection Association.
NTP
Notice to Proceed.
OSHA
Occupational Safety and Health Administration.
PDF
Portable Document Format.
PIV
Personal Identity Verification credential.
PPE
Personal protective equipment.
Primary-injection testing
Testing a circuit breaker by injecting current through its primary conductors.
Qualified person
A person with demonstrated skills and knowledge of the construction and operation of electrical equipment who has received safety training to identify and reduce the associated hazards.
Secondary-injection testing
Testing an electronic trip unit or relay by injecting a signal at the trip unit or relay input rather than through the primary conductors.
SOW
Statement of Work.
UPS
Uninterruptible power supply.
VAAR
Department of Veterans Affairs Acquisition Regulation.
VAMC
VA Medical Center.
VHA
Veterans Health Administration.

28.0 Attachments

The following attachments are issued with, and form a part of, the solicitation. Each is the current solicitation attachment as issued, and any revision or date shown on the attachment itself controls that attachment.

Attachment
Title and content
Revision / date
A
Equipment Schedule, Main Campus, Joseph Maxwell Cleland Atlanta VA Medical Center (Decatur, GA)
Current solicitation attachment as issued
B
Equipment Schedule, Fort McPherson VA Clinic (Atlanta, GA), Buildings 125, 128, 129, 130, and 131
Current solicitation attachment as issued
C
Equipment Schedule, Trinka-Davis Veterans Village Clinic (Carrollton, GA)
Current solicitation attachment as issued
D
Equipment and Test Matrix, by asset class, with test method, outage requirement, and infrared requirement
Current solicitation attachment as issued

Attachments A, B, and C govern asset identity and quantities. Attachment D governs test method only to the extent consistent with this SOW and does not add an asset or expand the scope (Section 3.1).

Records Management and Contract Security:

Procedures and VA Handbook 6500.6 Contract Security. Both can be found at: https://www.va.gov/vapubs/search_action.cfm?dType=2 **Note: This link is the complete list of VA Handbooks and are in sequential order. **Instructions for accessing VA Handbooks at link listed above: Click on link above and once it is opened, please scroll down on the left side until you get to VA Handbook 6300.1. Once there, go to the PDF Format Column and click on PDF. VA Handbook 6300.1 will then ask you to open or save the document.

Please follow the same instructions listed above for accessing VA Handbook 6500.6.

All contractor employees working on this requirement are required to complete mandatory annual training entitled, “VA Privacy and Information Security Awareness” and “HIPPA Training” prior to providing service for each year of the contract with copies sent to the COR for each and available for audit as requested. The course numbers are VA10203 and VA 10176. You must select that you are a contractor. Contractor employees are to self-enroll into TMS via the link: https://www.tms.va.gov/learning/user/SelfRegistrationUserSelection.do A VA employee will escort the contractor when contractor is required to enter/work in sensitive areas.

Identifications, smoking and VA Regulations:

The Contractor's FSE shall wear visible identification always while on the premises of the Atlanta VA Health Care System. Contractor shall contact the Contracting Officer’s Representative (COR) upon contract award, to receive instructions on how to obtain a VA Identification Badge during the performance of this contract. Atlanta VA Health Care System is a smoke-free campus which includes both tobacco and e-cigarettes; tickets can be issued by Police Services. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court. Photography or Video on medical center premises is strictly prohibited. Additionally, pursuant to 38 CFR 1.218(b) (23) Use of recording devices of any kind to record patients or employees is strictly prohibited.

VA Notice of Limitations on Subcontracting - Certificate of Compliance: To be eligible for evaluation and consideration for award, offerors must return the entire Limitations on Subcontracting Certificate of Compliance clause containing a fully completed certification at the time offers are due or the offer will be rejected and not forwarded for evaluation. In addition to completing the offeror ‘fill-in’ requirements for this clause, offerors must insert the offeror’s name in the brackets. Electronic signatures are not acceptable.