This is a technical specifications document for fiberglass wall panel installation associated with the Bethlehem Housing Authority's apartment renovation project at Parkridge in Pennsylvania. The specification details the requirements for providing and installing semi-rigid fiberglass wall panels (Glassboard-P Fiberglass Panel with Surfaseal manufactured by Kemlite Company or Owner-approved equivalent) throughout 20 apartments in Phase 2 of the renovation. Sealed bids are due electronically through PennBid on Thursday, October 22, 2026 at 11:00 AM. Contractors must submit product data within 15 days of contract award, including manufacturer's recommended installation procedures, material lists, and 18" X 18" samples demonstrating color, pattern, and specified grade. The contract requires proper quality assurance through skilled, experienced workmen trained in the specified installation methods.
Installation requirements include comprehensive surface preparation (ensuring walls are dry, flat, dust-free, and grease-free, with leveling plaster applied to concrete block as needed), application of non-flammable construction adhesive using a notched trowel with complete panel coverage, and installation of matching vinyl molding and trim at all joints and edges per manufacturer recommendations. All gaps at joints and cutouts must be 1/8" or less, with material grain patterns running in the same direction across all panels in a given space. A 10% bid bond secured by a Treasury-approved surety company is required, and the successful bidder must provide performance and payment bonds. Questions should be directed to Scott Speshok at 610-483-0322, with contract documents available on the PennBid website.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 10260
FIBERGLASS WALL PANELS
SUMMARY:
Provide semi-rigid fiberglass wall panels where shown on the drawings, as specified herein, and as needed for a complete and proper installation.
Documents affecting work of this section include, but are not necessarily limited to, General Conditions Supplementary Conditions, Drawings, and these specifications.
SUBMITTALS:
Comply with the pertinent provisions of the General Requirements.
Submit product data within 15 days of award of contract to the contractor.
Submit product data and material list of items to be provided under this section. Supply sufficient technical data to demonstrate compliance with the specified requirements.
Provide manufacturer’s recommended installation procedures which, when approved by the Owner, will be incorporated into these Specifications and contract documents.
Provide samples of each item proposed for use under this section. Provide 18” X 18” sample for color, pattern and specified grade.
QUALITY ASSURANCE:
Use adequate number of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and methods needed for the proper performance of work covered under this section.
DELIVERY, STORAGE, AND HANDLING:
Comply with pertinent provision of the General Requirements.
10260-1
MATERIAL:
Fiberglass Wall Panel: Where indicated on the drawings, provide Glassboard-P Fiberglass Panel with Surfaseal as manufactured by Kemlite Company, or Owner approved equal. Color: as selected by the Owner.
OTHER MATERIALS:
Provide non-flammable construction adhesive No. 265 recommended by the manufacturer of the approved wall panel.
Place matching vinyl molding, divider strips, corner trim and end caps on all joints and visible edges as recommended by the manufacturer.
Provide other materials, not specifically described but required for a complete and proper installation, as selected by the Contractor subject to approval of the Owner.
EXECUTION:
Surface Conditions: Examine all areas and conditions under which work of this section will be performed. Promptly correct all conditions detrimental to timely and proper completion of the work. Do not proceed until all unsatisfactory conditions are corrected.
Walls must be dry and free from dust, dirt, and grease. Wall surface shall be flat.
Remove high spots and fill in low spots. Concrete block may require a leveling plaster coat.
PREPARATION:
Wood:
Make the surface completely smooth; set nail heads and fill with water-proof filler, sanding smooth with the adjacent surfaces; and verify proper moisture content.
10260-2
Gypsum Wallboard and Plaster:
Over gypsum wallboard, apply a uniform release coat of material recommended by the manufacturer of the approved adhesive.
Dust the surface thoroughly and remove all loose material.
Verify proper moisture content.
INSTALLATION:
Spread adhesive material over the entire back of panel using notched trowel (1/4” X ¼” X ¾”). Be sure panel is well covered all the way to the edge.
As soon as adhesive is spread over the entire panel and before it “skins over”, set panel into position and press against wall. Apply adequate pressure to make full contact between wall and panel.
Apply fasteners as recommended by the manufacturer.
Ensure all gaps at joints and edges of cutouts are 1/8” or less.
Verify material grain pattern runs in same direction for all panels installed in one space, room, or area.
To achieve moisture-resistant application, apply “Kemlite Silicone Sealant 255” during installation of the panels. Follow manufacturer’s recommended steps for installation.
Install the approved molding at all joints, corners and ends of wall panels; using adhesive recommended for the purpose by the manufacturer of the molding. Install molding true to line, using full-length stock to the maximum practicable, cutting horizontal joints to form tight hairline cracks and mitering corners.
10260-3
ADJUSTMENTS AND CLEANING:
As the work progresses, clean the surplus adhesive from the wall panel surfaces and adjacent surfaces.
Visually inspect to verify that installed wall panel is secure, smooth, clean, without bulges, and with no gaps or overlaps.
Inspect all seams, verifying that precise match has been achieved, and correcting miss-match of color and/or pattern as necessary to secure approval of installation by the Owner.
END OF SECTION