01500 Construction Facilities.pdf
PDF 114 KB Posted
- Attached to
- Renovate 20 Apartments in Parkridge - Phase 2
- Solicitation number
- US.245854
- Issued by
- Northampton County, Pennsylvania
About this file
This document is Section 01500 of the Technical Specifications for the Bethlehem Housing Authority's Parkridge apartment renovation project in Pennsylvania. The specifications outline the construction facilities and temporary controls required for the 20-apartment renovation work at the Parkridge family development. The contractor must provide temporary utilities including water, electricity, heating, sanitary facilities, and enclosures such as tarpaulins, barricades, and canopies. Sealed bids for this project are due electronically on the PennBid site by Thursday, October 22, 2026 at 11:00 AM. A bid bond in the amount of 10 percent of the bid amount, secured by a surety company listed in the Department of Treasury Circular #570, must accompany each submission. The successful bidder will be required to furnish and pay for satisfactory Performance and Payment Bonds.
The specifications establish detailed requirements for contractor-supplied temporary utilities and facilities throughout the construction period. The contractor shall provide all temporary water piping and supply, though the Owner will pay for water consumed during construction. For electricity, the contractor must supply temporary wiring and distribution boxes with 100-foot maximum extension cords for individual trades; if existing service is insufficient, the contractor pays for electricity used. The contractor is responsible for providing and maintaining temporary heating to maintain temperatures between 50 and 70 degrees Fahrenheit, paying all fuel costs for space heaters, and is solely liable for any damage to BHA property resulting from inadequate heat or fire. Additional contractor obligations include providing flame-proofed tarpaulins, fire extinguishers per applicable codes, fire-watchers during welding operations, temporary sanitary facilities, scaffolds, safety barricades, temporary walls and dust control measures, and temporary fencing for excavation areas. All temporary facilities must be maintained in safe condition and removed as rapidly as work progress permits or as directed by the Owner.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
SUMMARY:
This section describes construction facilities and temporary controls which may be required for this work.
Documents affecting this work include, but are not necessarily limited to, General Conditions, Supplementary Conditions, Drawings, and these complete Technical Specifications.
REQUIREMENTS:
Provide construction facilities and temporary controls needed for the work including, but not necessarily limited to:
1. Temporary utilities, such as heat, water, electricity and telephone.
2. Sanitary facilities
3. Enclosures such as tarpaulins, barricades and canopies.
4. Temporary fencing of the construction site or staging areas.
DELIVERY, STORAGE AND HANDLING:
Maintain temporary facilities and controls in proper and safe condition throughout the progress of work.
UTILITIES:
WATER: Where required, the contractor shall provide necessary temporary piping and water supply and, upon completion of the work, remove such temporary facilities. The Owner shall provide and pay for the water used in construction.
01500-1
ELECTRICITY: Where existing electric service is not available or sufficient, the contractor shall supply necessary temporary wiring and, upon completion, remove such temporary facility.
Contractor shall provide area distribution boxes so located that the individual trades may furnish and use 100-ft. maximum length extension cords to obtain power and lighting needed for work, inspection and safety.
Where existing electric service is not available or sufficient, the Contractor shall provide and pay for electricity used in construction. The Contractor shall provide wiring, connections, outlets and fixtures for 110/220V, single phase, 3-wire power; and/or any additional power or current characteristics required.
HEATING: The Contractor shall provide and maintain heat necessary for proper conduct of operations needed for work. If the existing heating system cannot provide sufficient heat while the building is under construction the contractor shall provide temporary heat as necessary.
All temporary heating following enclosure of building or work area shall be provided by space heaters until the permanent heating system is installed and operational (where applicable).
The Contractor shall pay for all fuel required for operation of all temporary space heaters required to provide adequate temporary heat for work and protection of already in-place work.
The Contractor shall be responsible for operation and maintenance of permanent heating system until completion and final acceptance of the project.
The building will be considered enclosed when it is roofed and has protection at all doorways, windows and any other openings necessary for heat retention.
A minimum of 50 degrees F. and a maximum of 70 degrees F. shall define the range of temperatures to prevail at all times. The permanent system cannot be installed until the completion of finished walls in each room. Therefore the contractor must utilize space heaters until that time.
Prior to final acceptance, the contractor shall clean the system and replace all filters and do all necessary work to the permanent heating system to assure that such system is turned over to the owner in acceptable working order and in the same condition as originally installed.
01500-2
The contractor shall be solely responsible for damage to any and all BHA property and/or material and equipment resulting from the lack of proper heat of fire during the performance of this contract.
TEMPORARY FIRE PROTECTION: The contractor and all subcontractors shall observe all provisions of the specifications relative to fire protection throughout the construction period, in accordance with provisions with this section. The contractor shall provide fire extinguishers on site as required by pertinent codes.
Tarpaulins used for temporary enclosures or for night or weather protection of masonry walls shall be flame-proofed by an approved process prior to delivery to job site and shall be reprocessed during the progression of this work as required.
Storage of flammable materials at the site shall be avoided. Materials to roofs shall be raised to roofs only in such quantities as needed for immediate use. Limited storage for flammable material inside the building and mixing of the same shall be permitted only in masonry and concrete enclosed rooms. Empty containers for such materials and oily or paint soaked rags shall be removed from the building at the close of each workday.
Welding and flame cutting equipment shall be of an approved type and shall be used only in such spaces and at such times as approved by the owner. Each contractor shall provide special fire-watchers while welding or cutting and have water and fire extinguishers available for immediate use.
Burners or torches using gasoline shall not be used on the premises.
SANITARY FACILITIES: The contractor shall provide temporary sanitary facilities in the quantity required for use and proper proportions for use by all personnel.
Maintain facilities in a sanitary condition at all times. Lock and secure facilities during non-work hours.
ENCLOSURES: The contractor shall provide and maintain, for the duration of the construction, all scaffolds, tarpaulins, canopies, warning signs, steps, platforms, bridges and other temporary construction necessary for proper completion of the work in compliance with pertinent safety regulations and to the satisfaction of the owner.
01500-3
Provide pedestrian safety at all times. All safety barricades and other necessary safety provisions must be approved by the owner and be acceptable to all agencies having jurisdiction.
The contractor shall provide and maintain, for the duration of the project, temporary walls, plastic, ventilation, and dust control measures to protect existing spaces, dividing construction and provide safe temporary egress from the building.
TEMPORARY FENCING: For projects involving excavation, the contractor shall provide and maintain, for the duration of the project, fencing of design and type needed to prevent entry to the work area by the general public.
Properly protect all excavations whether on the main building on site or off site where trenching for utilities occur. The contractor shall properly protect all excavation performed.
MAINTENANCE AND REMOVAL: Maintain temporary facilities and controls as long as needed for safe and proper completion of work. Remove such temporary facilities and controls as rapidly as progress of the work will permit, or as directed by the owner.
END OF SECTION