01700 Project Close-out.pdf

PDF 115 KB Posted

Attached to
Renovate 20 Apartments in Parkridge - Phase 2
Solicitation number
US.245854
Issued by
Northampton County, Pennsylvania

About this file

This document is a Technical Specification Section 01700 Project Close-Out for the Bethlehem Housing Authority's apartment renovation project in Pennsylvania. The specification outlines the procedures and requirements for transferring completed work from the contractor to the owner, including quality assurance measures, inspection protocols, and final acceptance criteria. The contractor must ensure all work complies with contract documents and is ready for owner inspection. Once the owner determines the work is substantially complete, a punch list of deficiencies will be generated, which the contractor must remediate before final acceptance. The owner will conduct re-inspections following contractor notification of punch list completion. Until final acceptance, the contractor remains responsible for the building or project.

Final completion requirements include submission of project record documents, operation and maintenance data, warranties and bonds, keys and keying schedules, spare parts, governmental compliance certificates (including certificates of inspection and occupancy), certificates of insurance, evidence of payment and lien releases, and contact information for subcontractors and service organizations available for emergency service on a 24/7 basis. The contractor must also submit a final accounting statement showing all previously approved adjustments to the original contract sum, including credit adjustments for deleted portions or material substitutions of lesser value, and must provide instruction to owner personnel on the proper operation and maintenance of all provided systems and equipment.

View the file

Other files

File Type Posted
02900 Landscaping.pdf PDF
16200 Electrical.pdf PDF
2-Parkridge PH 2 wage rates.pdf PDF
09670 Vinyl Composition Tile.pdf PDF
01010 General Work Requirements.pdf PDF
7-Parkridge PH 2 Addendum.pdf PDF
9-Bid table for Parkridge Phase 2.pdf PDF
06100 Rough Carpentry.pdf PDF
02210 Selective Demolition.pdf PDF
5-Parkridge PH2 IFB.pdf PDF
1-Parkridge documents to be submitted.pdf PDF
06650 Solid Polymer Fabrication.pdf PDF
15400 Plumbing.pdf PDF
05500 Metal Fabrications.pdf PDF
06240 Plastic Laminate.pdf PDF
08110 Storm Doors.pdf PDF
08200 Flush Wood Doors and Frames.pdf PDF
07920 Sealants and Caulking.pdf PDF
10300 Vinyl Coated Shelves.pdf PDF
3-Parkridge Ren. PH 2 Admin. Specs.pdf PDF
01545 Contractor Use of Premesis.pdf PDF
01500 Construction Facilities.pdf PDF
08100 Metal Doors and Frames.pdf PDF
6-Parkridge PH 2 Ren. Drawings.pdf PDF
09260 Gypsum Wallboard.pdf PDF
09650 Resilient Sheet Flooring.pdf PDF
8-Parkridge PH 2 Addendum 2.pdf PDF
09900 Painting.pdf PDF
0 Table of Contents.pdf PDF
01710 Cleaning.pdf PDF
01620 Storage and Protection.pdf PDF
12390 Kitchen Cabinetry.pdf PDF
06200 Finish Carpentry.pdf PDF
16000 Basic Electrical Requirements.pdf PDF
08541 Vinyl Windows.pdf PDF
10260 Fiberglass Wall Panels.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01700

PROJECT CLOSE-OUT

SUMMARY:

This section describes an orderly and efficient transfer of the completed work back to the owner.

Documents affecting work of this section include, but are not necessarily limited to, General Conditions, Supplementary Conditions, Contract Drawings, and these complete Technical Specifications.

QUALITY ASSURANCE:

Prior to requesting an inspection by the owner, of completed work; use adequate means to assure work is complete in accordance with the specified requirements and is ready for the requested inspection.

PROCEDURES:

Once the Owner concurs that the work is substantially complete, the work will be inspected and a list of deficiencies (Punch List) shall be generated and given to the Contractor.

The Contractor shall notify the Owner once the punch list items are completed. Within a reasonable time following notification the Owner will re-inspect the work to determine the status of completion.

Once the punch list items are completed the Owner shall accept the building or project back from the Contractor.

Until the building or project is completed and turned back to the Owner, the Contractor is responsible for the building or project.

FINAL COMPLETION:

Prepare and submit the notice required by the General Conditions.

Verify all work is complete including, but not necessarily limited to, the items shown on Contract Drawings, and listed in General Conditions and Technical Specifications.

PROJECT CLOSE -OUT

01700-1

Ensure all final cleaning is performed.

Certify that:

1.) Contract Documents have been reviewed.

2.) Work has been inspected for compliance with Contract Documents.

3.) Work has been completed in accordance with Contract Documents

4.) Equipment and systems have been tested as required, and are properly operating.

5.) All work is complete and ready for final inspection.

The owner will make an inspection to verify the state of completion.

When the Owner determines all work to all buildings included in the contract is acceptable and in accordance with the Contract Documents, he will request the contractor to make close-out submittals.

Close-out submittals include, but are not necessarily limited to:

1.) Project record documents.

2.) Operation and maintenance data for the items so listed in pertinent other sections of theses specifications, and other items when so directed by the Owner.

3.) Warranties and Bonds.

4.) Keys and keying schedule.

5.) Spare parts and material extra stock.

6.) Evidence of compliance with the requirements of governmental agencies having jurisdiction, including but not necessarily limited to:

a.) Certificates of Inspection b.) Certificates of Occupancy.

01700-2

7.) Certificates of Insurance for products and completed operations.

8.) Evidence of payment and release of liens.

9.) List of Sub-Contractors, Service Organizations, and Principle Vendors, including names, addresses and telephone numbers for emergency service at all times, including nights, weekends, and holidays.

FINAL ADJUSTMENT OF ACCOUNTS:

Submit a final statement of accounting to the Owner. Show all adjustments to the original contract sum, which were previously approved by the Owner.

Provide credit adjustments to Owner for portions of contract which may have been deleted or material substitutions approved for use which are of a lesser value than originally specified.

INSTRUCTION:

Instruct the Owner’s personnel in proper operation and maintenance of systems, equipment, and similar items which were provided as part of the work.

END OF SECTION