09260 Gypsum Wallboard.pdf
PDF 121 KB Posted
- Attached to
- Renovate 20 Apartments in Parkridge - Phase 2
- Solicitation number
- US.245854
- Issued by
- Northampton County, Pennsylvania
About this file
This is a technical specification document for gypsum wallboard installation work associated with the Bethlehem Housing Authority's apartment renovation project at Parkridge family development in Pennsylvania. The specification details the complete gypsum drywall system requirements, including material standards, installation procedures, and finishing work for 20 apartments undergoing Phase 2 renovation. Sealed bids are due electronically through PennBid by Thursday, October 22, 2026 at 11:00 AM. The specification requires contractors to submit within 15 calendar days of contract execution a material list, manufacturer specifications, and recommended installation procedures for approval. All work must comply with Federal Specification SS-L-30D for gypsum wallboard, with specific requirements for wallboard type, thickness, and fire-retardant materials in designated areas such as common apartment partition walls, second floor ceilings, and walls between kitchens in adjacent apartments.
The specification establishes detailed execution standards for wallboard installation, fastening methods, and multi-coat drywall finishing work. Contractors must use skilled, experienced workmen familiar with specified requirements and maintain minimum temperature conditions of 55 degrees Fahrenheit for 24 hours prior to and during joint treatment and compound finishing. The three-coat finishing method requires minimum drying time of 24 hours between coats, with specific spread widths for each coat stage and final feathering to 12 inches wide. A satisfactory Bid Bond of 10% of the bid amount is required with submission, and the successful bidder must furnish Performance and Payment Bonds. Contract documents are available on PennBid, with inquiries directed to Scott Speshok at 610-483-0322, and the Bethlehem Housing Authority reserves the right to reject any or all bids or waive irregularities.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 09260
GYPSUM WALLBOARD SYSTEM
SUMMARY:
Provide gypsum drywall and accessories where shown on the drawings, as specified herein, and as needed for a complete and proper installation.
Documents affecting work of this section include, but are not limited to, General Conditions, Supplementary Conditions, Drawings, and these Technical Specifications.
SUBMITTALS:
Comply with the pertinent provisions of the General Requirements.
Within 15 calendar days after the executed contract has been received by the contractor, submit the following:
Material list of items proposed to be used under this section.
Manufacturer’s specifications and other data needed to prove compliance with the specified requirements.
Manufacturers recommend installation procedures which, when approved by the Owner, will become the basis for accepting or rejecting actual installation procedures used on the work.
QUALITY ASSURANCE:
Use an adequate number of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this section.
DELIVERY, STORAGE AND HANDLING:
Comply with the pertinent provisions of the General Requirements.
09260-1
GYPSUM WALLBOARD:
GENERAL MATERIAL:
Provide gypsum wallboard complying with Fed Spec SS-L-30D, in 48” widths and in such lengths as will result in a minimum of joints. Provide regular wallboard, type III, grade R, class 1, ½” or 5/8” thick, or as may be shown otherwise on the drawings.
Provide type III fire retardant wallboard, grade X, class 1, 5/8” thick as shown on the drawings or, at all common apartment partition walls dividing apartments within one building structure, all second floor ceilings, and all walls where kitchens of one apartment share walls with an adjacent apartment. Patch all voids in existing masonry walls dividing apartments prior to installing new gypsum wallboard.
EXECUTION:
Install gypsum wallboard with the separate boards in moderate contact but not forced into place.
At internal and external corners, conceal the cut edges of the boards by overlapping covered edges of the abutting boards.
Stagger the boards so that the corners of any four boards will not meet at a common point except in vertical corners.
Install wallboard to studs at right angles to the furring or framing members.
Make end joints, where required, over framing or furring members.
Corner bead is to be installed at all outside corner locations. Provide angle shapes with wings not less than 7/8” wide and perforated for nailing and joint treatment.
09260-2
For fastening wallboard in place on metal studs and metal channels, use flat-head screws, shouldered, specially designed for use with power driven tools, not less than 1” long, with self-taping threads and self-drilling points.
For fastening wallboard in place to wood studs, use 1-1/4” type “W” bulge-head screws, complying with ASTM C514 and of the length required by governmental agencies having jurisdiction.
Drive the specified type screws using a clutch-controlled power screwdriver or drill, spacing screws at 16” on center.
Where a double layer of wallboard is specified stagger all joints of varying layers.
DRYWALL FINISHWORK:
Inspect all areas to be joint treated, verifying that the gypsum wallboard fits snugly against supporting framework.
In areas where joint treatment and compound finishing will be performed, maintain a temperature of not less than 55 degrees for 24 hours prior to commencing treatment, and until joint and finishing compounds have completely dried.
Apply joint treatment and finishing compound by machine or hand tool, using thin uniform layers.
Spread the compound not less than 3” wide at the joints, center the reinforcing tape in the joint, and embed the tape into the compound. Then spread a thin layer of the compound over the tape and fastener heads.
Following proper drying of the taping process, apply a second coat of embedding compound to the joints and fastener heads, spreading in a thin uniform coat, not less than 6” wide at joints and feather edge.
Always allow a minimum drying time of 24 hours between coats and sand compound to a smooth finish prior to applying the next coat.
After embedding compound is thoroughly dry and has been completely sanded, apply a coat of finishing compound to the joints and fastener heads.
Feather the finishing compound to not less than 12” wide.
09260-3
When thoroughly dry, sand to obtain a uniformly smooth surface. Avoid scuffing the paper surfaces of the wallboard. Repeat the three coat method of finish work at all corner bead locations.
FINISHING MATERIAL: Tape and compound to be as recommended for use by the manufacturer to the gypsum wallboard approved for use on this project.
“Trim Tex” #9010 tear away “L” bead, or approved equal, shall be used at the drywall edge at the heating convectors.
END OF SECTION