This file contains erosion control plan drawings and technical details for the Bomber Agile Common Hangar project at Tinker Air Force Base, OK, issued by the US Army Corps of Engineers Tulsa District as part of solicitation WWYK263009 at 65% design stage.

The drawings show detailed erosion control measures including silt fence installations, sediment log check dams, stabilized construction entrance specifications, and rip-rap outlet protection details. Key features include specific requirements for silt fence placement 10 feet outside grading limits, phased landscaping requirements, protection measures for drainage structures, and detailed specifications for erosion control features like wattle inlet protection and grouted rip-rap outlets. The drawings contain precise technical specifications, dimensions, and installation requirements for each erosion control measure, along with general notes regarding contractor responsibilities for implementation and maintenance of these environmental protection features during construction.

View the file

Other files

File Type Posted
WWYK263009_65 Design Analysis_Part12_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part1.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part6.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part1.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part3.pdf PDF
WWYK263009_65 Drawings_Volume 2_Part5.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part2.pdf PDF
WWYK263009_65_NG-LCCA_BLCC_Summary Report.pdf PDF
WWYK263009_65 Design Analysis_Part24.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part7.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part4_Part3.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part1.pdf PDF
WWYK263009_65 Design Analysis_Part17.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part3.pdf PDF
WWYK263009_65 Design Analysis_Part10.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part8.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part1.pdf PDF
WWYK263009_65_NG_energy model results.pdf PDF
Bomber Agile Common Hangar Industry Forum Presentation.pdf PDF
WWYK263009_65 Drawings_Volume 2_Part6.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part4_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part7.pdf PDF
WWYK263009_65 Design Analysis_Part21.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part4_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part23.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part3.pdf PDF
WWYK263009_65 Design Analysis_Part20.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part26.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part5.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part27.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part5.pdf PDF
WWYK263009_65 Design Analysis_Part15.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part3.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part9.pdf PDF
WWYK263009_65 Design Analysis_Part9.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part1.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part5.pdf PDF
WWYK263009_65_NG-LCCA_BLCC results.pdf PDF
Show 40 more

Latest 50 of 95 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W W

W W

W W

W W

W W

W W

W W

W W

W W

W G

G G

G G

G G

G G

G G

G

GGGGGGGGGGG

F

SF

SF

SF

SFSF

OHE OHE OHE OHE

OHE OHE OHEOHE OHE OHE

FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC FOC

E E

E

EE

OHE OHE

OHE

MW

T

HH

HH

W W W W

SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SAN SANW W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W WWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW

WWWWWWWWWWWWWWWWWWWWWWWWWWW

W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W

E

EEEEEEEEE

E EEEEEEEEE

E E

E

HH

HH

HH

.0

.0

1281.0

.0

.0

1281.0

1281.0

1281.0

.0

1282.0

1282.0

1282.0

.0

1283.0

.0

1283.0

1283.0

1283.0

1283.0

.0

1284.0

1284.0

1284.0

1284.0

1284.0

1285.0

1286.0

1286.0 1286.0

1287.0

.0

1284.0

.0

.0

.0

.0

1285.0

1285.0

.0

.0

.0

1286.0

.0

.0

1287.0

1287.0

.0

1288.0

.0

1289.0

1289.0 1289.0

1290.0

1290.0

1291.0

1291.0

1292.0 1292.0

1293.0

1293.0

SF

SF

SF

SF

SF

SF

SF

SF

SF

SF

SF

.0

.0

.0

.0

1284.0

1285.0

.0

1286.0

SF

SF

SF

SF

FR

FR

UD

FR

U D

UD UD

.0

.0

.0

.0

.0

.0

.0

1290.0

SF

SF

SF

SF

SF

SF

0+

1+

2+

3+

4+

5+

6+

7+

0+

1+

2+

3+

4+

5+

6+

7+

AN

RP

M

EL

I

I R Y

N G

E S I

D

NOT FOR

CONSTRUCTION

US Army Corps of Engineers

SHEET OF

SHEET ID

U S

A R

M Y

C O

R

PS

O F

EN

G

IN

EE

R S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

" X

2"

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

M

AR

K D

ES

C

R

IP

TI

O

N

D

AT

E D

AT

E

M

AR

K D

ES

C

R

IP

TI

O

N

A

B

C

D

E

F

G

H

J

2 3 4 5 6 7 8 9 10 11 12

KEYPLAN

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

K

TU

LS

A

D

IS

TR

IC

T

E

. 8 1S

T

ST

R

EE

T

TU

LS

A, O K

7-

EN

G

IN

EE

R

IN

G

C O

N

ST

R U

C

TI

O N

D

IV

IS

IO

N

EN

G

IN

EE

R

IN

G

B R

AN

C

H

P.

B

U H

LE

R

A.

G

U

LA

N

S.

N

AL

L

M . R

U N

D E

N O

VE

M

BE

R

0, D

ES

IG

N

BO

M

BE

R

A G

IL

E

C O

M M

O N

H

AN

G

AR

W W

YK

Mead and Hunt, Inc.

2440 Deming Way

Middleton, WI 53562 phone: 608-273-6380 meadhunt.com

D

ES

IG

N

/2 0/

W

2B V-

-D

-0

W

2B V-

-D

-0

50' 100'0

ER

O

SI

O

N C

O N

TR

O

L

PL

AN

CG103

MATCH LINE - SHEET CG101 MATCH LINE - SHEET CG102

ASPHALT POV PARKING

LOT (150 SPACES)

SE 59TH STREET

GENERAL NOTES:

1. CONTRACTOR SHALL INSTALL SILT FENCE PRIOR TO

BEGINNING ANY EXCAVATION OR GRADING WORK.

SILT FENCE SHALL BE INSTALLED 10' OUTSIDE THE

LIMITS OF GRADING OR AS INDICATED.

2. CONTRACTOR SHALL PHASE LANDSCAPING IN

ORDER TO PROVIDE PERMANENT VEGETATIVE

COVER PRIOR TO SUBSEQUENT PHASES. THIS WILL

REQUIRE THE CONTRACTOR TO WATER THE

LANDSCAPED AREAS IN ORDER TO ESTABLISH

VEGETATIVE COVER.

3. PRIOR TO OPENING PAVEMENTS CLOSED DURING

CONSTRUCTION, ALL EROSION CONTROL ITEMS ARE

TO BE REMOVED WITH THE LANDSCAPED AREAS

WELL ESTABLISHED PER SPECIFICATIONS.

4. PROTECT ALL NEW DRAINAGE STRUCTURES AFTER

PLACEMENT.

5. SEDIMENT/EROSION CONTROL FEATURE TO BE

INSTALLED BEFORE EACH PHASE AND REMOVED

AFTER PERMANENT MEASURES ARE IN PLACE AND

PRIOR TO COMMENCING TO THE NEXT PHASE.

LEGEND

SILT FENCE

(SEE SHEET CG501 FOR DETAIL)

GRADING LIMITS

STORM PIPE

MANHOLE

CATCH BASIN

INLET PROTECTION

(SEE SHEET CG501 FOR DETAIL)

SEDIMENT LOG CHECK DAM

(SEE SHEET CG501 FOR DETAIL)

STABILIZED CONSTRUCTION ENTRANCE

(SEE SHEET CG502 FOR DETAIL)

GROUTED RIP-RAP OULET PROTECTION

(SEE SHEET CG502 FOR DETAIL)

EROSION MAT

FLOW DIRECTION

PROPOSED CONTOUR

EXISTING CONTOUR

SF

SD

CB

D

GROUTED RIP-RAP

OUTLET PROTECTION

GEOTEXTILE

10' - 0" (TYP)

2'

0"

5'

0" M

IN

. P

O

ST

S 3'

0"

FL

O

W

WOVEN WIRE ENDS

GEOTEXTILE

FL

O

W

GROUND LINE

FLOW

1.

5'

M

IN

ANCHOR THROUGH

NETTING WITHOUT

DAMAGE (TYP.)

WATTLES 12"

WATTLE

12"

WOOD STAKE

TOP OF FILL

THE ELEVATION AT THE BOTTOM OF THE

DISTANT END OF THE "J-HOOK" A SHOULD BE

THE SAME AS THE LOWEST POINT ALONG

THE TOP OF SILT FENCE B .

A

B

A

B

NOTE:

1. EL. A = EL. B TO MAXIMIZE STORAGE.

FLOW

ANGLE AND LENGTH OF

"J-HOOK" WILL VARY

20" WATTLE USED TO

RELEASE WATER IF NECESSARY

A

B

* SILT FENCE SHOULD BE LOCATED

AWAY FROM THE TOE OF THE SLOPE

TO PROVIDE SUFFICIENT SPACE TO

ALLOW A BROAD, FLAT AREA FOR

SEDIMENT ACCUMULATION AND

MAINTENANCE ACTIVITIES. THE ENDS

OF THE SILT FENCE SHOULD BE TURNED

UP GRADIENT TO MAXIMIZE STORAGE.

SILT FENCE

NOTES:

1. CONTRACTOR SHALL IMPLEMENT BEST STORMWATER MANAGEMENT PRACTICES AS DETAILED PER THE OKLAHOMA DEPARTMENT OF

TRANSPORTATION ROADSIDE DEVELOPMENT STORMWATER MANAGEMENT PROGRAM. LAND DISTURBANCE & SWPPP PERMIT MUST BE

APPROVED AND DELIVERED TO THE CONTRACTING OFFICER PRIOR TO ANY SITE DISTURBANCE.

2. CONTRACTOR SHALL MAINTAIN AND INSPECT EROSION CONTROL MEASURES AS DETAILED IN THE CONTRACTOR SUPPLIED AND

APPROVED STORMWATER POLLUTION PREVENTION PLAN.

3. SPOIL AREAS, DUMPING AREAS AND BURN AREAS TO BE OFF GOVERNMENT PROPERTY.

4. UTILITIES REQUIRED FOR CONSTRUCTION TO BE INSTALLED AND MAINTAINED BY CONTRACTOR AT CONTRACTOR'S EXPENSE.

5. SLOPE STABILIZATION METHODS ARE AS FOLLOWS:

LESS THAN 3H:1V SEED AND MULCH

GREATER THAN 3H:1V, LESS THAN 2V:1H TURF REINFORCEMENT MATTING

GREATER THAN 2H: 1V SODDING

NOTES:

1. SILT FENCES SHALL BE USED IN AREAS WHERE FLOW IS NOT SEVERE.

2. ANCHOR AND INSTALL SILT FENCE PER DETAILS SHOWN ON THIS SHEET.

3. SILT FENCES ARE TEMPORARY SEDIMENT CONTROL ITEMS THAT SHALL BE ERECTED OPPOSITE ERODIBLE AREAS SUCH AS NEWLY GRADED FILL SLOPES AND

ADJACENT TO STREAMS AND CHANNELS.

4. SILT FENCE SHOULD BE PLACED PER LOCATIONS SHOWN ON SHEETS CG101 - CG103.

5. IF THE DEPOSITS BECOME GREATER THAN 1/2 THE HEIGHT SILT FENCE, THE CONTRACTOR SHALL REMOVE THE SILT OR INSTALL A BACKUP SILT FENCE BEHIND

THE SILT FENCE AT HIS OPTION.

6. WHEREVER POSSIBLE, SILT FENCE SHALL BE CONSTRUCTED ACROSS A LEVEL AREA IN THE SHAPE OF A SMILE. THIS AIDS IN PONDING OF RUNOFF AND

FACILITATES SEDIMENTATION.

7. THE CONTRACTOR MAY ELECT TO USE EITHER METHOD I OR METHOD II.

8. METHOD II INSTALLATION SHALL BE ACCOMPLISHED USING AN IMPLEMENT THAT IS MANUFACTURED FOR THE APPLICATION AND PROVIDES A CONFIGURATION

MEETING THE REQUIREMENTS OF THE DETAIL.

9. WIRE SHALL BE MINIMUM OF 32" IN WIDTH AND SHALL HAVE A MINIMUM OF 6 LINE WIRES WITH 12" STAY SPACING.

10. GEOTEXTILE FABRIC MEETING THE TYPE II MATERIAL REQUIREMENTS AND INSTALLED ACCORDING TO SPECIFICATION MAY BE USED WITHOUT WIRE FENCE.

11. SILT FENCE AND ALL OTHER EROSION CONTROL ITEMS ARE REQUIRED TO BE REMOVED PRIOR TO OPENING OF THE AIRFIELD PAVEMENTS. ALL SEEDED AREAS

TO HAVE THE CONTRACTING OFFICER'S APPROVAL ON SUBSTANTIAL GROWTH PRIOR TO REMOVAL.

RING FASTENERS (TOP ONLY) AT

APPROXIMATELY 2' - 0" O.C.

BURY WOVEN WIRE

FENCE APPROX. 6"

TRENCH (APPROX. 6" X 6")

BACKFILL ON TOP OF

GEOTEXTILE WITH SOIL

POST

GROUND LINE

WOVEN WIRE

COVERED WITH

GEOTEXTILE

GROUND

LINE

STUDDED METAL "T" POST

OR FUNCTIONALLY EQUAL

FLOW

POST

FLOW

GROUND LINE

8" MIN. WIRE &

FABRIC

STOP GEOTEXTILE HERE

MECHANICAL INSTALLATION

TOE OF SLOPE

TOP OF FILL

BYPASS

FLOW

175' M

AX

EMBANKMENT

FLOW

FLOW

200' M

AXTOE OF SLOPE

2' - 0" WIRE OVERLAP AT POST (USE

3-FASTENERS MIN.)

1' - 0" OVERLAP (USE

TWO FASTENERS

MIN.)

WOVEN WIRE ENDS

WOVEN WIRE

POST

METHOD I

SIDE VIEW

METHOD II

PLAN VIEW

ELEVATION VIEW

SECTION A-A

15' INSIDE DIA.

DROP INLET

SURFACE FLOW DIRECTION(TYPICAL)

NOT TO SCALE

REQUIRED LAPPING 1

CG501 CG101

NOT TO SCALE

"J-HOOK" SILT FENCE APPLICATION 3

CG501 CG101

NOT TO SCALE

SILT FENCE SECTION AT TOE OF FILL 4

CG501 CG101

NOT TO SCALE

SEDIMENT LOG CHECK DAM 6

CG501 CG101

NOT TO SCALE

"SMILE-CONFIGURATION" SILT FENCE APPLICATION2

CG501 CG101

NOT TO SCALE

WATTLE DROP INLET PROTECTION 5

CG501 CG101

45°

2" x 2" STAKE

2" x 2" WOOD STAKE

FLOW

D

IT

C H

B O

TT

O

M

PLAN VIEW

SEDIMENT LOG

MAXIMUM

STRENGTH/RETENTION

VOLUME AT 45°

NOTES:

1. ANCHOR AND INSTALL PER SEDIMENT LOG DETAIL ON THIS SHEET AND AS

DIRECTED BY COR IN THE FIELD.

2. A "W" SHAPE MAY BE USED FOR WIDER DITCHES.

3. IF MULTIPLE SEDIMENT LOGS ARE NEEDED, LOGS SHALL BE OFFSET TO THE

UP FLOW SIDE OF THE RUN TO ENSURE NO WATER PENETRATES

ATTEMPTED EROSION CONTROL MEASURE. EXTRA CARE SHALL BE USED

TO ENSURE STABILITY OF LOGS.

POINT X (TOP OF SEDIMINT FIBER LOG)

POST AT TOE OF SLOPE (EACH SIDE)

POINT Y (BOTTOM OF FENCE)

POINT Y (BOTTOM OF SEDIMENT LOG)

SLOPE

SLOPE

POINT Y

POINT X

DITCH

BOTTOM

GROUND

SECTION A-A

ELEVATION OF POINT X SHALL BE BELOW THE ELEVATION OF POINT Y.

AN

RP

M

E L I

I R Y

N G

ES

I

D

NOT FOR

CONSTRUCTION

US Army Corps of Engineers

SHEET OF

SHEET ID

U S

A R

M Y

C O

R

PS

O F

EN

G

IN

EE

R S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

" X

2"

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

M

AR

K D

ES

C

R

IP

TI

O

N

D

AT

E D

AT

E

M

AR

K D

ES

C

R

IP

TI

O

N

A

B

C

D

E

F

G

H

J

2 3 4 5 6 7 8 9 10 11 12

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

K

TU

LS

A

D

IS

TR

IC

T

E

. 8 1S

T

ST

R

EE

T

TU

LS

A, O K

7-

EN

G

IN

EE

R

IN

G

C O

N

ST

R U

C

TI

O N

D

IV

IS

IO

N

EN

G

IN

EE

R

IN

G

B R

AN

C

H

P.

B

U H

LE

R

A.

G

U

LA

N

S.

N

AL

L

M . R

U N

D E

N O

VE

M

BE

R

0, D

ES

IG

N

BO

M

BE

R

A G

IL

E

C O

M M

O N

H

AN

G

AR

W W

YK

Mead and Hunt, Inc.

2440 Deming Way

Middleton, WI 53562 phone: 608-273-6380 meadhunt.com

D

ES

IG

N

/2 0/

W

2B V-

-D

-0

W

2B V-

-D

-0

ER

O

SI

O N

C O

N

TR

O L

D

ET

AI

LS

CG501

APPROACH LENGTH

50' STD.

SL

O

PE

T

O D

R

AI

N (0

.1 F

T/ F

T M

IN

TEMPORARY PIPE

(AS REQUIRED)

EXISTING

EDGE OF PAVEMENT

' W

ID

TH

M

IN

SECTION A-A

30' MIN.

AGGREGATE

SLOPE TO DRAIN (0.1 FT./FT. MIN.)

AGGREGATE

TRANSITION DETAIL

4" MIN.

APPROACH LENGTH

(AS REQUIRED)

PLAN

12" MIN.

EXISTING

GROUND

1. A STABILIZED CONSTRUCTION ENTRANCE SHALL BE CONSTRUCTED AT POINTS OF

EGRESS FROM UNSTABILIZED AREAS OF THE PROJECT TO PUBLIC ROADS WHERE

OFFSITE TRACKING OF MUD COULD OCCUR. TRAFFIC FROM UNSTABILIZED

AREAS OF THE PROJECT SHALL BE DIRECTED THRU THE STABILIZED ENTRANCE.

BARRIERS, FLAGGING, OR OTHER POSITIVE MEANS SHALL BE USED AS REQUIRED

TO LIMIT AND DIRECT VEHICULAR EGRESS ACROSS THE STABILIZED ENTRANCE.

2. THE CONTRACTOR MAY PROPOSE AN ALTERNATIVE TECHNIQUE TO MINIMIZE

OFFSITE TRACKING OF SEDIMENT. THE ALTERNATIVE MUST BE REVIEWED

AND APPROVED BY THE CONTRACTING OFFICER PRIOR TO IT'S USE.

3. ALL MATERIALS SPILLED, DROPPED, OR TRACKED ONTO PUBLIC ROADS

(INCLUDING THE STABILIZED CONSTRUCTION ENTRANCE AGGREGATE AND

CONSTRUCTION MUD) SHALL BE REMOVED DAILY, OR MORE FREQUENTLY

IF SO DIRECTED BY THE COR. REMOVE FOREIGN OBJECT DEBRIS IMMEDIATELY

FROM ANY ACTIVE AIRFIELD PAVEMENTS OR PUBLIC ROAD.

4. STABILIZER AGGREGATE SHALL BE 1.5-INCH TO 3.5-INCH DIAMETER STONE.

5. THE STABILIZED CONSTRUCTION ENTRANCE SHALL BE MAINTAINED IN A CONDITION

THAT WILL ALLOW IT TO PERFORM IT'S FUNCTION TO PREVENT OFFSITE TRACKING,

THE STABILIZED CONSTRUCTION ENTRANCE SHALL BE RINSED WHEN NECESSARY

TO MOVE ACCUMULATED MUD DOWNWARD THRU THE STONE. ADDITIONAL STABILIZATION

OF THE VEHICULAR ROUTE LEADING TO THE STABILIZED ENTRANCE MAY BE

REQUIRED TO LIMIT THE MUD TRACKED.

6. THE NOMINAL SIZE OF A STANDARD STABILIZED CONSTRUCTION ENTRANCE

IS 30' X 50' UNLESS OTHERWISE SHOWN IN THE EROSION CONTROL PLAN

AGGREGATE

12" MIN.

COMPACTED FILL

EXISTING OR TEMPORARY

SIDEDRAIN PIPE

EDGE OF

TRAVELWAY

FILTER BLANKET

(GEOTEXTILE)

A

FILTER BLANKET(GEOTEXTILE) FILTER BLANKET

(GEOTEXTILE)

NOTES:

EX

IS

T.

D

IT

C

H

EX

IS

T.

D

IT

C H

NOT TO SCALE

STABILIZED CONSTRUCTION ENTRANCE 1

CG502 CG101

NOT TO SCALE

DITCH CROSSING DETAIL 2

CG502 CG101

A

3 x Do

La

La + Do

1. RIP-RAP SHALL MEET THE REQUIREMENTS OF ODOT STANDARD SPECIFICATION FOR

CONSTRUCTION, SECTION 601 FOR TYPE IV RIP RAP.

2. GROUT RIP-RAP PER ODOT STANDARD SPECIFICATIONS FOR CONSTRUCTION WITH GROUT

CONFORMING TO SPECIFICATION SECTION 31 00 00 EARTHWORK.

ROCK OUTLET PROTECTION

NOTES:

Do = OUTLET PIPE DIAMETER

La = 24" PIPE - 12 FT, 30" PIPE - 14 FT, 36" PIPE - 16 FT, 42" PIPE - 18 FT, 48" PIPE - 25 FT, 54" PIPE - 30 FT

NOT TO SCALE

RIP-RAP OUTLET PROTECTION 3

CG502 CG101

AN

RP

M

E L I

I R Y

N G

ES

I

D

NOT FOR

CONSTRUCTION

US Army Corps of Engineers

SHEET OF

SHEET ID

U S

A R

M Y

C O

R

PS

O F

EN

G

IN

EE

R S

D R

AW

N

B Y:

D

ES

IG

N

ED

B

Y:

SU

BM

IT

TE

D B

Y:

SI

ZE

C H

EC

KE

D B

Y:

" X

2"

IS

SU

E D

AT

E:

C O

N

TR

AC

T

N O

SO

LI

C

IT

AT

IO

N N

O

M

AR

K D

ES

C

R

IP

TI

O

N

D

AT

E D

AT

E

M

AR

K D

ES

C

R

IP

TI

O

N

A

B

C

D

E

F

G

H

J

2 3 4 5 6 7 8 9 10 11 12

TI

N

KE

R

A

IR

F O

R C

E

BA

SE

, O

K

TU

LS

A

D

IS

TR

IC

T

E

. 8 1S

T

ST

R

EE

T

TU

LS

A, O K

7-

EN

G

IN

EE

R

IN

G

C O

N

ST

R U

C

TI

O N

D

IV

IS

IO

N

EN

G

IN

EE

R

IN

G

B R

AN

C

H

P.

B

U H

LE

R

A.

G

U

LA

N

S.

N

AL

L

M . R

U N

D E

N O

VE

M

BE

R

0, D

ES

IG

N

BO

M

BE

R

A G

IL

E

C O

M M

O N

H

AN

G

AR

W W

YK

Mead and Hunt, Inc.

2440 Deming Way

Middleton, WI 53562 phone: 608-273-6380 meadhunt.com

D

ES

IG

N

/2 0/

W

2B V-

-D

-0

W

2B V-

-D

-0

ER

O

SI

O N

C O

N

TR

O L

D

ET

AI

LS

CG502

V1_50 CIVIL
Sheets and Views
CG103 EROSION CONTROL PLAN
CG501 EROSION CONTROL DETAILS
CG502 EROSION CONTROL DETAILS

File details come from the government source that posted it. Updated .