This file contains design review meeting minutes from multiple meetings held between July-September 2024 regarding the Bomber Agile Common Hangar (BACH) project at Tinker Air Force Base. Key discussion items focused on revisions to electrical and mechanical systems after switching from all-electric to gas-powered utilities, floor plan changes, and interior design requirements.

The meetings addressed specific design elements including: utility corridor configurations, sidewalk layouts, floor plan modifications for secure areas and tool crib storage, mechanical system changes for gas-fired heating units, updates to electrical distribution systems and panel sizes, and coordination of fire protection requirements. Notable decisions included approval of changing Room 214 to a command suite, confirmation of manual flush valves, revised scheduling of the 65% design review to January 2025, and coordination requirements for ICD 705 compliant areas. The minutes also document ongoing action items related to equipment lists, trash enclosure locations, and construction security plan development. A civil plan drawing showing pavement joint layouts and utility relocations was included.

View the file

Other files

File Type Posted
WWYK263009_65 Design Analysis_Part12_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part1.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part6.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part1.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part3.pdf PDF
WWYK263009_65 Drawings_Volume 2_Part5.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part2.pdf PDF
WWYK263009_65_NG-LCCA_BLCC_Summary Report.pdf PDF
WWYK263009_65 Design Analysis_Part24.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part7.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part4_Part3.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part1.pdf PDF
WWYK263009_65 Design Analysis_Part17.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part3.pdf PDF
WWYK263009_65 Design Analysis_Part10.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part8.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part1.pdf PDF
WWYK263009_65_NG_energy model results.pdf PDF
Bomber Agile Common Hangar Industry Forum Presentation.pdf PDF
WWYK263009_65 Drawings_Volume 2_Part6.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part4_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part4_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part7.pdf PDF
WWYK263009_65 Design Analysis_Part21.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part6_Part4_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part23.pdf PDF
WWYK263009_65 Design Analysis_Part22_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part2.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part3.pdf PDF
WWYK263009_65 Design Analysis_Part20.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part2.pdf PDF
WWYK263009_65 Design Analysis_Part26.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part5.pdf PDF
WWYK263009_65 Design Analysis_Part19_Part4.pdf PDF
WWYK263009_65 Design Analysis_Part27.pdf PDF
WWYK263009_65 Design Analysis_Part18_Part5.pdf PDF
WWYK263009_65 Design Analysis_Part15.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part3.pdf PDF
WWYK263009_65 Design Analysis Part 28_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part9.pdf PDF
WWYK263009_65 Design Analysis_Part9.pdf PDF
WWYK263009_65 Design Analysis_Part12_Part4.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part7_Part1.pdf PDF
WWYK263009_65 Drawings_Volume 1_Part1_Part5.pdf PDF
WWYK263009_65_NG-LCCA_BLCC results.pdf PDF
Show 40 more

Latest 50 of 95 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Civil – Comment 10643470, 10643473

10643470 Site plan. Will sidewalk or walkway be provided from the POV to the Hangar? Or is intended to use the existing sidewalk that goes to MROTC.

This project will provide a sidewalk along the northern boundary of the POV parking lot to the personnel gate. There are currently no new sidewalks being provided from the personnel gate to the hangar.

10643473 Utility corridor. Arch plan shows a 20' wide corridor.

Consider a wider utility corridor path and provide a preliminary utility trench configuration showing all the possible utilities for this campus. KC-46A utility corridor has become a congested corridor due to poor planning and narrow width.

Please, provide direction from Base CE (Matt DeToy).

Civil – Comment 10643481, 10643507, 10643520

10643481 The utility plan is lacking or missing other utilities such as industrial waste, breathing air, telecom, power, fuels and fuel pits(if applicable), dedicated fire mains(if applicable), etc.

The current design does not include industrial waste, breathing air, or fuel lines serving this hanger from off site. The site telecom and power information will be shown in the electrical/communications site drawings. A dedicated fire main will be shown in the next submittal running from the existing fire main west of Douglas, parallel to the domestic water line, to feed into the north and south sides of the proposed hangar.

10643520 Indicate if there will be designated dumpster areas for this hangar?

Government to provide direction regarding any necessary dumpster areas.

10643507 DA. Pavement design. Please confirm or indicate what's the pavement design life. Unless I overlooked it.

The standard traffic pattern utilized by the Air Force is based on 20-year life. Will add to the DA.

Thank you. Please ensure this is clear for airfields and and site roads as applicable. FYSA. Site roads require a 25-design life if applicable.

Architecture/Security - Comment 10641007 10641007 Attached are my initial findings in looking at the room to be built/provisioned for future SAP use by us. Mr. Liles is communicating with B52 stakeholder to ensure they have absolutely no need to utilize this space to store/process/discuss collateral or SAP. So far he is hearing they do not need the room at that level; however, is confirming they have no intended use for that space until we take over the facility later down the road. In provisioning the room for us, ICD 705 needs to be applied and the issues noted in the attached/below need to be remedied. With that, we need to understand from Mr. Akin how he would want the room protected between when build is complete and we take ownership and plan to bring that room up to SAP level. I would think if B52 is not going to use the room, an X10 should be placed on the main entrance and controlled by us until later but that is AO PSO call. At a minimum, security requirements for physical and TEMPEST need to be factored in now (z ducts, inspection ports, man bars, dielectric breaks/grounding, conduit in place for ACS/IDS pulls later) so the room does not need to be torn apart and reworked.

Our next concern is that none of the SAPWA requirements for the Hangar bays have been planned in to provision it for that level of work for us later. Mr. Taber has stated it will need to be able to go up to SAP levels in future when we take ownership. We believe we should build to the standard JT has outlined for MOB facilities now with the exception of installing IDS/ACS, secure locks, etc. We strongly urge we consider planning in the following:

- Z ducts with manbars, flex ducts or grounding, and inspection ports on the secure side

- Dielectric breaks or grounding for electric conduit/water piping

- If metal fiber trays run through the space, they need to be looked at closer. i.e. they should not penetrate secure boundary and should be grounded

- Roof hatch assemblies with no external hardware that can be secured on the inside with conduit available to tie them into the IDS later

- Conduit in place for future IDS to include adding BMS's at the perimeter doors (main entrance, emergency egress, hangar doors, roll up doors, etc)

- ID location for IDS/ACS panels contained within the SAPWA boundary

- Sound attenuation is not as concerning here where we need to rework walls understanding the SOP JT has laid out for the MOBS when it comes to discussion in the bays

Architecture/Security - Comment 10641007 (Cont.)

10641007 ICD 705 will be applied with concerns mentioned above. An X-10 will be considered and confirmed with AO PSO.

For future SAPWA requirements, design will consider all construction techniques mentioned above.

Architecture/Security – Comment 10641007 (Cont.)

Please, confirm this room is to be designed to ICD 705 version 1.5.1, 26 July 2021. Also, confirm TEMPEST is a requirement.

Previous direction was that it was not required and therefore has not been designed as such.

Please, provide AO PSO contact, so we can coordinate design submittal reviews with them.

Comment refers to SAP and SAPWA. Please, confirm that we are to design to DoDM 52.05.07- B3 April 23, 2015, change 3 12/08/2023.

Is RF Shielding required?

*MOB facility guide.

Architecture – Comment 10641499

10641499 Make sure storage (such as lockers and or desk drawers) inside the hangar bay are above 18" AFF to maintain the Class 1 Div 2 rating.

Talking with our FPE, NFPA 70 requirements for Class 1 Div 2 rating is to have no powered devices less than 18" AFF in the hangar bay which could provide enough exposed energy to ignite an explosive concentration of vapor. The interior designer will specify lockers that do not have power and that meet NFPA 286 Class A rating. She also noted that the desks at the hangar bay currently do not have storage below 18" AFF. Any power requirements will be coordinated with the electrical engineer.

Architecture – Comment 10621987, 10641542 10621987 Kind of confusing when overlaying the outlines of the future campus. In particular, what are the lines just across the towway across Douglas?

10641542 Recommend to remove future facilities from this plan as they appear incomplete and confusing.

Please, provide direction as to what you would like us to show with regards to future planning. (This can be a separate civil sheet used for internal planning purposes only – Not For Construction.)

Architecture – Comment 10621990 106219990 Request we find a way to get the Dock Office rm 108 moved to the North so they have a window onto the hangar bay. See attachment for options.

The design team can make the attached revision work. We will discuss further at the review conference to get concurrence from all reviewers.

Architecture – Comment 10621990 (Cont.)

106219990 Request we find a way to get the Dock Office rm 108 moved to the North so they have a window onto the hangar bay. See attachment for options.

The design team can make the attached revision work. We will discuss further at the review conference to get concurrence from all reviewers.

Architecture – Comment 10621999 10621999 Request we take the Stairwell 10' above the roof eave and provide a 4' door onto the roof. See attachment for reference.

The design team should be able to accommodate this request. We will discuss further at the review conference to seek consensus amongst all reviewers.

Architecture – Comment 10641545, 10641548 10641545 The amount of brick looks excessive. In the KC-46A campus we usually have a wainscot up to about 4' AFF.

The wall construction is different since we opted for precast concrete sandwich panels for speed of construction and durability.

10641548 The color of brick does not seem to match the intent of "Creech Brown" standards because of too much red.

TAFB Facility Standards for District C (closest district to our project) lists Garnet by Acme as a basis of design for exterior brick. This is not available as a thin brick, but selection chosen is close to this color and complements it. At the charrette, it was discussed that this was a new campus and that they were open to a new color palette.

Garnet Acme

TAFB Facility Standard Districts Map

Architecture – Comment 10641548 (Cont.)

Exterior Finishes

BRK-1, BRK-2 – Thin Brick Veneer

MV – Thin Masonry Veneer

AL-1 – Aluminum, PVDF Finish (Aluminum Entrances, Window

Frames, Ext. Trim)

RF-1 – Prefinished Standing Seam Metal Roof

MWP – Prefinished Metal Wall Panel

Architecture – Comment 10641587

10641587 Consider devoting rm 119 to vault storage if square footage becomes available.

Room is currently allocated for Dock office with 6 workstations. Please, advise.

Architecture/MEP – Comment 10641589, 10641590, 10641595

10641589 Request hangar door controls be located 6' min from end of door to eliminate pinch point issues.

Please, advise as to where you'd like the controls located. Electrical will show power accordingly and note controls by hangar door manufacturer.

10641590 Ensure operator pinch/crush point does not exist at hangar door pocket. If so, second wall mounted control will be required.

Hangar door controls will be coordinated with the electrical engineer. Electrical will show power accordingly and note controls by hangar door manufacturer.

10641595 Request floor drains under eye wash stations.

UFC 4-211-01 3-5.5.1 states to not install floor drains adjacent to emergency shower eye wash stations for Air Force hangars.

Architecture – Comment 10641606 10641606 Request (8) AGE 16" square portal locations in hangar door. Request interior lockable door to meet ATFP req.

Portals will be provided as requested.

*Do you have a preferred manufacturer that you'd like for us to design around?

Architecture/Structure – Comment 10641524 10641524 Show minimum distance of 6 ft. between hangar door and door pocket Post S4 to prevent a pinch point between hangar door operator, walking with the opening hangar door and Post S4. Typical of 4 locations in the hangar. Submitted by Jum Lennarson.

If the pocket grows to incorporate the additional requested space, this has an impact on the coordinates provided by the base CE (Matt Detoy) set point for all hangars in the future. *Limited opportunities to grow hangar (1'-4"). Possibility to eliminate corridor at Area B only, travel distances not met in Area C/D with this approach. Please, advise.

Architecture/Structure – Comment 10643381 10643381 General Comment: Wall sections show architectural precast concrete panels with thin brick veneer. Please ensure that the thin brick is mechanically attached to the panel and not adhered when the specification is created. Adhered thin brick is susceptible to detaching in the frequent freeze-thaw cycles in Oklahoma.

We plan to integrally cast the thin brick into the concrete panel. Our BOD thin brick conforms with ASTM and PCI standards. PCI Architectural Precast Concrete manual states:

With thin-brick units, no metal ties or weeps are required to attach them to the concrete because adequate bond is achieved. In general, clay products that are cast integrally with the concrete have bond strengths exceeding that obtained when laying units in the conventional manner. Thin bricks conforming to PCI standard have lower water absorption than conventional brick. In addition, thin brick is less susceptible than conventional brick to freeze-thaw issues, spalling, and efflorescence.

Lunch Break Reconvene at 1200hrs

Structural – Comment 10641764 10641764 Provide verification that all connections from the host building to the storm shelter are designed to the ultimate failure of the connection, per ICC 500-2020, section 304.9. This includes foundation elements, such as grade beams and slab-on-grade. Recommend to disconnect the storm shelter foundation elements from the host building. Recommend providing an additional adjacent pier and grade beam system at the boundary between the host and storm shelter buildings.

The storm shelters are currently detailed to be completely isolated from the host building. The foundation shown for the shelters is a soil supported mat foundation. Once the geotech report is received, we will either confirm the use of the mat foundation or utilize grade beams and piers that are isolated from the host building.

The submitted foundation drawings do not appear to currently indicate a separate foundation from the host building. Clarify the response.

Mechanical

10634850 Mechanical Design Analysis Sec. 6.3.2. pg 73

Instead of MERV 8, use MERV 13 for pre-filters in order to adequately protect (and extend) the life of the equipment.

Comment provided by Sara Sayler.

Evaluation: Check and Resolve

Typically at Tinker AFB, we have been requested to use MERV 8 prefilters followed by MERV 13 final filters. Although labeled as final filters, they come right after the pre-filters and before any coils or fans. These should not be confused with clean room type final filters that are located after the fan. Please confirm MERV 8 prefilter are not desired to extend the life of the MERV 13 filters.

10641572 Mechanical Design Analysis Sect 6.3.2

What level of filtering is accomplished on incoming air for the DOAS? Requesting capable of filtering fumes, jet fuel, and gaseous contaminants. Southwest of this hangar will be the primary engine runs spots. Common issue with existing hangars near run spots is the HVAC system pulls in fumes taking hours to dissipate. Submitted by Dustin Baker.

Evaluation: Check and Resolve

Carbon filters can be installed in the outside air stream of the DOAS units. However, these filters are fairly expensive to install as well as very expensive to maintain. They require frequence maintenance with either regeneration or replacement. Please confirm this is the direction the Government wishes to take and also confirm whether gas-phase filters should be installed on all OA intakes including hangar bay ventilation units.

10641604 Mechanical Plans M-100

Request (2) AGE 8" insulated ducts with connectors per dock at dock wall location as shown on provided layout, 35% ACH Layout - PDM Requirements - Delsigne - 6 Feb 2024.

(2) exterior connection points per dock for AGE. Submitted by D.Delsigne

Evaluation: Check and Resolve

Please provide criteria for the ducts, pressure class, amount of insulation, end connections.

10641607 Architectural Plans A-101

Request (2) 3" aircraft supply air (not building compressed air) pipe with connectors at N.3-4 and D.8-7 wall locations as shown on provided layout, 35% ACH Layout - PDM Requirements - Delsigne - 6 Feb 2024. (1) exterior connection point per dock for AGE.

Submitted by D.Delsigne

Evaluation: Check and Resolve

Pipe and connectors will be provided as requested; however, we need to know what the service is (flow and pressure) and/or the type of pipe and fittings. Also, will need to know what connector are needed.

10643000 Mechanical Plans

Document Reference: M-100s Add installed bottom of duct heights,VAV numbering helps to match room numbers,HVLS fans are light at nose of plane. Submitted By: Eric Slater.

Evaluation: Check and Resolve

1. BOD elevation will be added at a future submittal. Probably after the 65% stage.

2. VAV's do not correspond to room numbers and it would be confusing to have VAV boxes numbered after a room it is located in when it serves another room or if two VAV's serve the same room.

3. Agree, but the aircraft is not being ventilated. The fans are to increase the circulation within the space to minimize dead spots. We are trying not to blow down directly on the AC. Please advise if more HVLS fans are desired.

10643099 Mechanical Plans

Document Reference: M-schedules

I believe UFC only allows up to 6 row coils. Submitted By: Eric Slater

Evaluation: Check and Resolve

I cannot find the requirement stated, please furnish the reference since it is generally desired to have an 8 row coil to maintain a decent chilled water delta T.

10644163 Mechanical Specifications 23 25 00

UFGS 23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS may not be deleted from the specifications. Water treatment is required per para K. WATER TREATMENT on page 18 of the TAFB Base Mechanical Standard. Submitted By: Joe Marcano

Evaluation: Check and Resolve

Typically in the past at Tinker, we have used the Water Treatment requirements listed in Section 23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems since it addresses chilled water and condenser water only. It has the same requirements as 23 25 00 for chilled water without all the requirements for different boilers and cooling tower systems. We feel using the same section for piping and water treatment makes for a cleaner set of specs; however, if the Government feels a separate spec section if desired, please advise.

General / Life Safety – Comment 10641585

10641585 Remove RM 104A, 104B, 104C, and 104D labels; assign square footage to RM 104.

Remove RM 102A and add SF to 102.

Non-Concurred Those are architectural model features. The occupant loads associated with those areas are collectively calculated under area #33, except 104C which is an office calculated accordingly.

Fire Protection / Life Safety – Comment 10641623

10641623 Perpendicular PPE to hangar door should continue until they intersect the hangar door hazard warning area lines. No other PPE lines is required next to hangar door. PPE Lines to be yellow.

Life Safety – Comment 10643326

10643326 SECTION 9 - LIFE SAFETY - FIRE PROTECTION, 9.1 GENERAL PARAMETERS: SF is listed as 176, 230 SF. I don't see any correlation between that number and the Program Area Comparison table starting on page 58 of the PDF. Please clarify if the 176,230 is representing a Net area or Gross area and correct if necessary.

Concurred* The calculation of building area for the IBC is the footprint area of the structure measured to the inside face of the exterior walls (generally). The Program Area in the indicated table is the total area of multiple floors and not compared to the IBC area in Section 9.

Electrical

• Comment 10643384

• Building configuration naturally divides loads into north and south groups

• UFC 3-550-01, 2500 kVA limit for padmounted transformer

• Comment 10641616 Relocate ceiling electric/air to locations shown

• Comment 10641611 Relocate power centers to locations shown

• Comment 10641614 Added (1) 208V, 40A receptacle to wing power stations

• Comment 10641593 separate eye wash stations and power racks

Electrical – Design Review

Electrical – Design Review

• Comment 10641622

• Add (3) Tugs

• Add (3) Scissor Lifts

• 10637953, purpose of so many switched receptacles

• 10640901 – Storm shelter power Will coordinate with mechanical design for storm shelter ventilation loads and include 26 33 53 as required.

• 10640909, Underground Electrical and Cathodic protection.

Base standard specifies PVC and PVC coated GRC

• 10640911 – Section 7.1 does not list the TAFB Electrical Standard.

Will list TAFB Electrical Standard 2023 in next DA submittal.

• 10641051,2,3,4,6 – Lift Station design

• Generator or generator connection

• 480V, 3-phase service with sunshade and disconnect switch

• LED lighting

• PVC coated rigid conduit underground

• 120v receptacle within cord length of sump pit

• 10641553, How are power cables routed across aisle from wall to aircraft?

• 10641553, Provide elevations for Nose and Wing Power Centers.

• 10641603, Provide additional aircraft ground points

Interior Design – Comment 10641564, 10641575

10641564 Add E-Tools Carousels to list of GFGI equipment items, determine locations for carousels, and coordinate with dedicated electrical circuits for power and LAN drops for the carousels.

More information needed about E-Tools Carousels such as manufacturer, model number, count, and desired location.

10641575 Room 107 is meant to be office space. Please add desk and standard print station to area. Move SS-4 to rooms 104, 025, and 026

Workstations have been added, please advise to the number of workstations and approved layout changes to room 104, 025,and 026.

Interior Design – Comment 10641576, 10641586

10641576 Workstations were added, please note one EQ-15 was lost to keep circulation advise on whether it is needed.

Workstations were added, please note one EQ-15 was lost to keep circulation advise on whether it is needed.

10641586 Add 2 workstation desks to RM 206 with power/data supply to support.

Please advise on 'workstations' this room is used as a training room.

Customer DA – Comment 10634840

10634840 This specifies no natural gas service is being provided. I realize there is an electrification requirement, but should we reconsider gas service for resiliency and/or future use purposes?

EO 14057 requires electrification of buildings but does not specify if that would include connections for future usage. Adding a natural gas connection for potential future usage would be an additional cost that may not ever be used.

Cost Engineering – Comment 10643606

10643606 The design analysis (page 6 of the .pdf) states the following: "The current DD 1391 provides a Programmed Amount (PA) of $282,000,000 which includes a 5.0% construction contingency and 6.5% for Corps of Engineer Supervision, Inspection and Administration. The contract Scope of Work requires that any construction cost estimate base bid that exceeds 80% of the PA have bid options."

The CCL from the DD 1391 is is $251,551,000, so where is the requirement stated above coming from?

The DD1391 PA is $282M as stated.

Section 2.5 of our Scope of Work identifies the ECCL for this project as $239,700,000.

Section 5.14 of our Scope of Work directs us to define recommendations /solutions if that cost is exceeded.

As $239.7M is not 80% of $282M, that will be corrected in the DA.

Cost Engineering – Comment 10644685

10644685 A design contingency of more than 15% should be added to the MII cost estimate at this point.

There are still numerous unknowns in the design that could have some significant cost impacts.

We'll capture some of these risks in the CSRA/cost certification process as well.

The cost estimate is currently carrying a 20% design contingency. If the design contingency needs to be higher than 20% please advise.

Risk Register Review & Update

Risk Register Review & Update

Review of Action Items

Action Items Review

• Example text

• Example text

• Example text

Project Schedule and Next Steps

Project Schedule

Next Steps

• Example text

• Example text

Summarize & Closing Comments

Adjourn for the Day

Thank you!!

U.S. Army Corps of

Engineers Tulsa District

THANK YOU!!

Life-Cycle Cost Analysis (LCCA)

• Required for every building. Apply where first cost is higher, but life cycle cost effectiveness is applicable to design decision.

− Prepare the LCCA in accordance with 10 CFR Part 436, Subpart A and NIST Handbook 135 Life-Cycle Costing Manual for the Federal Energy Management Program. The LCCA must be completed using the Building Life-Cycle Costing (BLCC) program.

• Identify the best design alternatives for evaluation. Select the highest efficiency building systems and features feasible.

• An LCCA is required for the following:

− Systems contributing to the energy footprint of the building including, but not limited to, HVAC, domestic hot water, and the building envelope − Renewable energy generating systems − Alternative water

Air Force Additional Requirements

• Tracking and reporting includes revising and submitting the Air Force Sustainability Requirements Scoresheet and the Design Analysis to AFCEC.CF.SustainableRpt@us.af.mil at each design submittal and when construction is complete.

• Sustainability Guidelines - Tinker Air Force Base − Tinker AFB Policy: Every project shall address the most economic and sustainable building practice to the fullest extent possible. Sustainable practices include those elements of planning, design and construction that promote the efficient use of energy and material resources, the conservation of water and the protection of land and water environments.

Agenda

• Design Kick-off & Charrette - Friday − A/E work session (0800)

− Out-brief (1000)

− Adjourn and travel (1100)

35% Review Meeting Schedule

0730 0800 0830 0900 0930 1000 1030 1100 1130 1200 1230 1300 1330 1400 1430 1500 1530 1600

Tuesday, February 13 Base Access

Virtual Meeting

Setup and

Preparation

Project Team

Introductions and

Opening Remarks

35% Design

Review Goals and Objectives

(DD 1391)

Sustainability

& Guiding

Principles

Summarize /

Hot Wash

Adjourn for the

Day

Wednesday, February 14

Virtual Meeting

Setup and

Preparation

Reconvene /

Review Day 1 /

Day 2 objectives

Risk

Register

Review and

Update

Review

Action

Items

Project

Schedule

& Next Steps

Summarize/

Closing

Remarks

Adjourn for the

Day

Project Review

Cost Estimate

Construction Schedule

Project Review

Civil/Site

Architectural

Lunch Break

Lunch Break

Project Review

Interior Design

Mechanical/Plumbing

Electrical/Communications

Life Safety/Fire Protection

Structural

Dr. Checks Comments Review Dr. Checks Comments Review

Attachment 2: 35% Design Review On-site Meeting Roster

MH+MH Joint Venture 1616 East 5th Street, Tulsa, OK 74120 The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Mead & Hunt Inc. 2440 Deming Way Madison, WI 53562 t 608.273.6380 f 608.273.6391 meadhunt.com

MEETING MINUTES

PROJECT:

Bomber Agile Common Hangar

(BACH)

PROJECT #:

WWYK263009

PREPARED BY:

Grace N. Foley

DATE PREPARED:

March 26, 2024

MEETING DATE:

March 25, 2024

MEETING LOCATION:

Microsoft Teams

SUBJECT:

Tinker VE Study Consensus Meeting

PARTICIPANTS:

Listed Below

CC:

Attendees

This confirms and records our understanding of the discussions which occurred, and the decisions reached during this meeting. Unless notified in writing within seven days of the date prepared, we will assume that the following documentation is complete and accurate.

1. The meeting began with an overview of the purpose of the meeting and presentation of the VE findings by Mike Dell’ Isola of Crawford Consulting.

2. Review Decisions on Value Alternatives – Notes on those with in depth discussion.

a. AM-01

i. Do we need catwalks? What if we just kept one?

ii. Needs to be tabled until the fuel source is determined. Decisions should be determined within 1 week of the talk with utilities. Date of decision due on Wednesday, March 27th.

iii. Louvers currently not incorporated into design.

b. AM-03

i. Would be helpful for access without dramatically impacting aesthetics.

ii. Is there enough room for a door?

iii. Concerns about water converging on door location.

iv. Needs to be tabled until utility determination finalized. Fuel source will determine size/quantity of equipment.

v. Aesthetics

1. There may be concerns with the layout of the precast and the impact on cost.

2. Is preferred look gabled look? Once the final look is determined, the components to achieve the look can be finalized.

3. Mason vs. alternative is $400K value

c. AM-06 & AM-07

i. Long term, anticipate that the towway will be straightened out

d. AM-20

i. How much space is actually required will drive the limits of the airfield pavement construction for storage.

ii. Is concrete pad considered a permanent facility? Can we replace it with a temporary facility?

e. AP-11

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

i. Metal panel system?

ii. Aesthetic benefits of admin area and shop space looking different from rest of the building.

iii. Still replicable at future bases with adjustments for local environment/aesthetics

Attendees – Those present are highlighted

1. Chris Angelucci, Crawford

2. Chris Clark, LDG

3. Dann Layou, M&H

4. Dennis Ward

5. Dustin Baker, Tinker AFB

6. Gena Mollica

7. Grace Foley, M&H, PM

8. Greg Stern

9. Thurston Hurst, USACE

10. Jim Lennarson

11. John Moore, M&H

12. Matt DeToy, Tinker AFB

13. Michael Dell’lsolo, Crawford

14. Michael Roering, Mead & Hunt

15. Michael Yielding, M&H

16. Natalie Anderson, Mead & Hunt

17. William (Clint) Rodgers, USACE

18. Rebekah Ulm, LDG

19. Rick Siler, LDG

20. Ron Rosebrook, USACE

21. Scott Nall, M&H, PM

22. Terry Helms, Mead & Hunt

23. Tim Craddock, M&H

24. Tom Linck, LDG

Attachments:

1. Decisions Table

Table 1: Decisions on Value Alternatives Alter. Mut. Potential Costs (in USD) Cons. Consensus

ID No. Alternative Title Cat. Excl. Initial Recurring (PW) Life Cycle Dec. Comments AM-00 Allow Movement zz-T zz-T AM-01 Move the make-up air units from the roof to the catwalk QLT (37,000) 399,727 362,000 FS Decision on gas vs electric heat is needed to make determinization; decision pending

AM-03 Adjust roof and parapet design on administrative space to improve roof access

QNT AP-11 99,000 - 99,000 AM May move equipment from roof or may need less equipment with gas system to allow for a pitched roof

AM-05 Reduce concrete thickness inside hangar where no keel paths will occur (UFC Waiver)

QNT 492,000 - 492,000 R UFC will not be pursued

AM-06 Replace all concrete for the existing tow way area

QLT AM-07

CE-38

(1,978,000) - (1,978,000) R This will be considered in the future when aircraft movement requirements allow the adjustment without operational impacts.

AM-09 Use asphalt pavement section in the area between the tow-way and the north side of ACH

QNT 991,000 - 991,000 R FOD risk is less with concrete and asphalt can rut in the heat

AM-11 Lower catwalk to elevation of top of hangar doors

QLT AM-18 (62,000) - (62,000) R Adds cost due to structural add

AM-12 Expand the west tow-way construction limits to 37.5' west of centerline and further south to limits of hangar construction

QLT CE-38 (1,660,000) - (1,660,000) R This can be addressed in the future

AM-14 Swap comm 114 and fire 113 room locations

QLT RU-10

FF-09

- - - R FF-09 accepted

AM-15 Reduce the size of fire room 013 QLT (33,000) - (33,000) A

AM-16 Use electric elevator and convert machine room 120 to other use

QNT (100,000) - (100,000) A

Bomber Agile Common Hangar 1

ID No. Alternative Title Cat. Excl. Initial Recurring (PW) Life Cycle Dec. Comments AM-18 Eliminate catwalks from the scope QNT AM-11 1,838,000 - 1,838,000 FS Tied to gas/electric decision AM-19 Utilize phased construction to create temporary airfield equipment storage north of proposed building

QLT (50,000) - (50,000) R Accepted AM-20

AM-20 Build permanent airfield pavement south of B2300 for use as airfield equipment storage in interim condition

QLT AM-07 (2,352,000) - (2,352,000) A

AP-00 Accommodate Personnel zz-T zz-T AP-01 Eliminate windows above the truss line in the hangar QNT 45,000 - 45,000 R The additional natural light is desired AP-02 Add glass for interior rooms QLT (23,000) - (23,000) A AP-05 Add bathroom within future secure space QLT (154,000) - (154,000) R AM-16 will provide an interior access to other building facilities

AP-09 Use walkoff carpet in lieu grid entry in the entry way

QNT 24,000 - 24,000 A

AP-11 Adjust architectural approach at entry to be more readily duplicated

QNT AM-03 444,000 - 444,000 R Preference is differing materials for the architectural approach

CE-00 Control Environment zz-T zz-T CE-02 Design to minimum space temperature QNT 39,000 1,176,286 1,215,000 R The higher temperature is desired for operations CE-03 Implement new ASHRAE 241 standards for air filtration

QNT (87,000) - (87,000) A

CE-11 Use 2x2 light fixtures in lieu of linear pendant fixtures

QNT 70,000 - 70,000 R

CE-18 Use insulated metal panel roof in lieu of metal deck with insulation and standing seam metal roof

QNT (3,845,000) - (3,845,000) R Too much cost

CE-19 Allow shop primed steel in lieu of field primed

QNT 952,000 - 952,000 A Waiver from the UFGS specification

Bomber Agile Common Hangar 2

ID No. Alternative Title Cat. Excl. Initial Recurring (PW) Life Cycle Dec. Comments CE-24 Consolidate drop inlets and drainage manholes in airfield pavement

QLT - - - A

CE-30 Use duct sock in lieu of sheet metal duct work in hangar

QNT (19,000) - (19,000) R

CE-31 Decouple the ventilation from the make-up air units

QNT (163,000) - (163,000) FS Tied to gas/electric decision

CE-33 Eliminate walls creating room Air Rooms 015A and 112

QNT FF-09

RU-01

20,000 - 20,000 AM One room adjusted under idea FF-09

CE-34 Use lower NRC rated acoustical ceiling tile

QNT 86,000 - 86,000 A Verify still meets UFC

CE-38 Allow onsite recycling of pavement areas that are being demolished

QNT AM-06

AM-12

368,000 - 368,000 A

FF-00 Facilitate Flexibility zz-T zz-T FF-08 Remove floor boxes from break rooms QNT 36,000 - 36,000 R Allows the break rooms to be multipurpose when needed

FF-09 Incorporate Corridor 109 into mechanical room to provide outside wall exposure for mechanical room

QNT AM-14

CE-33

RU-01

RU-10

33,000 - 33,000 A

RU-00 Route Utilities zz-T zz-T RU-01 Combine the compressed air stations into a single air station location

QNT CE-33

FF-09

- - - R FF-09 accepted

RU-04 Eliminate 24" storm sewer crossing of tow-way and re-route the southside drainage to the east

QNT 133,000 - 133,000 A

RU-05 Relocate pad mounted transformers to corners of the proposed building

QNT 574,000 - 574,000 A To be confirmed with electric company

RU-06 Move chiller south to column G/F QNT (2,000) - (2,000) A

Bomber Agile Common Hangar 3

ID No. Alternative Title Cat. Excl. Initial Recurring (PW) Life Cycle Dec. Comments RU-10 Increase the size of the comm room 114

QLT AM-14

FF-09

(23,000) - (23,000) R FF-09 accepted

RU-12 Use existing 30in storm sewer under existing tow way to retain pipe and pavement

QNT (77,000) - (77,000) A Design team to confirm inverts

RU-13 Adjust proposed water main layout to minimize removal of existing concrete

QNT 9,000 - 9,000 A

RU-15 Provide duct bank with spare capacity for future connections across the hangar

QLT (161,000) - (161,000) A

SL-00 Support Load zz-T zz-T

Recommended Alternatives 0 -$ -$ -$ Total Included Quantitative 0 -$ -$ -$ Total Included Qualitative 0 -$ -$ -$

Accept & Accept w/ Modification 19 (537,000)$ -$ (537,000)$ Total Accept Quantitative 14 2,298,000$ -$ 2,298,000$ Total Accept Qualtitative 5 (2,835,000)$ -$ (2,835,000)$ Further Study 3 1,638,000$ 399,727$ 2,037,000$

ALTERNATIVE CATEGORIES

QNT - Quantitative, reduces initial QLT - Qualitative, adds initial cost or has no cost impact

CONSENSUS DECISIONS

A - Accept AM - Accept w/ Modification FS - Further Study R - Reject OBE - Overcome By Events

Bomber Agile Common Hangar 4

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Scott Nall

June 7, 2024

June 4, 2024

Teams Call

Bomber Agile Common Hangar (BACH) – FF&E Discussion

Terry Helms

This confirms and records our understanding of the discussions which occurred, and the decisions reached during this meeting. Unless notified in writing within seven days of the date prepared, we will assume that the

General Notes

1. Mead & Hunt to provide a PDF format of the most current equipment plan sheets and schedules as part of the meeting minutes deliverable.

2. Users requested the eyewash stations move closer to the doors in order to free-up wall space.

Coordinate with plumbing.

3. Walk behind forklifts will likely be positioned at dock corners.

4. Compressed air drops along dock walls with large hose reels along ceilings with regulator and gage for pressure.

5. Power for stands and reels from ceiling.

Equipment Notes with No Room Specified

1. Tool Carousels, Standard Size: 2' x 2' x 7', GFGI, I quad plex and one land drop. Waiting on information for how many and where. This will need to be 18" above the floor.

a. Holds six to 8 laptops each.

b. David to provide verification that 1 cabinet per bay is appropriate.

2. Prefer eye wash and sink to be at the side of the room and not in the middle of the wall. This applies to all rooms with eye wash/sinks.

Tool Crib

1. There is a new B-52 list of equipment. Devin to send this updated list to Mead & Hunt team.

2. Several dollies and carts will go in and out of the tool crib. Devin to measure and provide measurements to the team. Prefer the dollies and carts to be on the northwest corner of this room near the north double door. Mead & Hunt to adjust layout.

3. Dustin to send layout markups for tool crib.

4. No peg board needed.

5. Charging station shelves with power below counter. Coordinate with electrical.

6. Air drops.

7. Safety harnesses will need hanging spaces.

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Mead & Hunt to identify unit for hanging items and will locate near the counter.

8. Tool counter to be an open box with a single shelf with a 4 duplex, which is the charging station.

9. High density storage is for long term storage and will house cases of equipment. Shelving configuration preferred. High density storage is to move to plan South side of room and change orientation.

10. Workstations to move to plan North side of room.

FOM Storage

1. No dividing wall between the cubicles.

2. Dustin sent an image from a CAD layout and the following notes for Rick to review.

a. Remove OHD from south face of room (left edge in image)

b. Size North OHD to 8’ (right edge in image)

c. Consume space in Haz Waste to allow for 5 desk and print station.

d. North personnel door to be a 4’ wide ‘Dutch door’ (right edge in image)

e. South personnel door to be a 4’ wide door (left edge in image

3. Dustin posted a picture to the chat.

Hazardous Storage 102 and Hazardous Waste 102A

1. From Client: Was not a category on the B-52 PDM RFI

2. Devin mentioned revising the layout to send to team.

3. Move the oil stands further South.

4. Would like more shelves along walls.

5. Oil barrels, compactor.

6. Computer power and data drops needed at counter. Coordinate with telecom and electrical.

7. Provide clear aisle straight to counter.

8. Hazmat pallet storage shelves needed. Leave bottom of shelf open.

9. The need for more shelving was expressed.

10. Move layout as sketched:

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Landing Gear Shop

1. Was not a room category on the B-52 PDM RFI sheet.

2. Plan is missing a machine with the wheels.

a. Dustin to get a cutsheet on this piece of equipment and disperse to team.

b. This machine needs power.

c. The clearance footprint is to be added to plan.

3. Column D in equipment excel document indicates the part number.

4. Fixtures for gear landing with an “X” number are bolted down to the floor.

a. #556

b. Main landing gear or holding fixture.

5. The tool crib and the hangar air drops along the walls put regulators on them just in case.

6. Need fixtures for "Gear Fixture", "Gear Holding Fixture" these are bolted to the floor. We need to know the clearance with the gear attached. Part number: X201846389.

7. Users to verify if workbench needs to be ESD type with grounding rod.

8. Add four (4) large landing gear holding fixture mounted to floor with clearances requested with dashed lines on drawings.

Hangar

1. Add a walk behind forklift parking space at each of the four docks with charging stations included.

2. Scissor lift charging station near these areas in each dock keep things consistent.

3. The main hose to fall from the ceiling.

4. Large air hose along the wall in the hangar are on the plans.

Engine Shop 004

1. This room was not on the document sent by Arch.

2. No shelving needed. Space used for general storage for rolling storage.

3. Wrenches will go in Tool Crib Pelican type cases.

4. Large portable cranes will not be in the area.

5. Will be general storage.

6. No shelving.

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Tire Shop

1. 11 tugs total in room.

2. Park tugs at a 45-degree angle for access.

3. Add parking striping on the floor (tape?)

4. If scissor lift doesn't fit in this room, it could go in dock - hangar space.

5. Move doors to the center of the walls.

6. Move personnel doors closer to plan north wall.

7. Floor sweeper.

8. Shift OH coiling doors – coordinate with architect.

Sheet Metal Shop

1. EQ-17 Shrinker stretcher needs more room. Orientation and location to be adjusted.

2. EQ-18 Sheet metal rack: the metal is fed at the end and needs to be accessible on both sides.

3. Move equipment further to the right for the equipment to clear the access area to the hangar.

4. Use an arrow on plan to show where the operator stands\works.

5. It is allowed to put the brake back-to-back.

6. Standoff space to be shown on the plans with dashed lines need striping on the floor finish.

7. Shear and brake: Plan for 10' by 5' pieces of metal to access.

8. Brake machines can be along the wall but need to be offset from the wall. Need to rope the area behind the machine. Access space to be shown with dashed lines on plan.

9. Eyewash to be moved to side of room.

10. Sanders need a vacuum.

11. Down draft table needed.

12. Hot Dimpling Machine - Mounted to the floor. Approximately: 4' x 4' x 6'H Machine. Right and left side to be open.

13. Provide verification if a rotor punch needs to be added.

14. STK means toolbox and does not need to be noted on the plan.

15. Metal work bench need. Information from the previous shop.

16. Sheet rack will be mobile.

17. Sheet metal shop should have drops along the walls.

18. Trunnion box.

19. Long sheet metal is accessed from the small end and will need to be positioned to have short end accessible and long sheet metal pulled from it.

20. Once clearances are clarified, we might need to grow this room to accommodate this function.

Coordinate.

21. L shape layout along wall for brake (hold off wall 3’ or so, Mead & Hunt to verify), zone will have to be roped off behind equipment.

22. Shift MLG saw and blades to Main landing gear shop.

23. Users to advise on Chicken leg fixture- MLG bulkhead shop aide.

24. Workbench or table might need to be added – metal top finish.

Avionics Secure Storage

1.Users to advise on when this function is needed and if this impacts design.

2. Avionics shop usually has static dissipative grounded workstations.

3. Secure grounded component storage.

4. Verify with structure that when LO storage flipped that floor slab updates were captured to accommodate the extra weight of high-density storage.

Dock office north of Tool Crib Confirmed that it does contain workstations.

PSC

Current layout to stay as is.

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

PMD Storage

1. Interiors to fix the layout move the cubes around.

2. PMD storage can move to the engine if need be.

3. Dustin to provide details about the high-density storage.

Dustin to verify if any of the cubicles need to be grounded.

Any special power and data needs?

1. The power for the stands

2. Provided some power information of 200 HZ.

3. Most special power is out in the dock.

ACTION ITEMS:

1. Team to provide drawings for FF&E review by the base,

2. Users to identify equipment that is to be bolted to the floor.

3. Users to advise on any special power, shop compressed air locations, or grounding needs.

4. Users to verify OH coiling door height clearances are sufficient. Currently, Landing Gear, Metal, Tire, Engine Shops are all 10’X10’. Corridor 007 is 18’X18’.

Scott Nall – Mason & Hanger William ‘Clint” Rodgers – USACE Christine Fernandez – Mead & Hunt Natalie Anderson – Mead & Hunt Rick Siler – Larson Design Group Rebekah Ulm – Larson Design Group Dustin Baker - 76 AMXG/MXDEO Mark Appleton – 76 AMXG/MXDEO Cote Barber – 76 AMXG/MXDEO Caleb Davis – 76 AMXG/MXDEO Ryan Inskeep – 76 AMXG/MXDEO James Lennarson - 76 AMXG/MXDEO Devin Wiegmann - 76 AMXG/MXDEO

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

July 2, 2024

June 27, 2024

Teams Call

Bomber Agile Common Hangar (BACH) – Airfield Pavements Discussion

Terry Helms

This confirms and records our understanding of the discussions which occurred, and the decisions reached during this meeting. Unless notified in writing within seven days of the date prepared, we will assume that the

General Notes – Topics of Discussion

1. The alignment of the east-west towway portion of the proposed pavement north of the proposed

BACH.

2. Size and of the proposed PCC AGE storage area.

3. Thickness\cross section of the PCC AGE storage area.

4. Alignment of the future fire station access roadway as it intersects with the BACH project pavements.

1. Pavement alignment

NW hangar location utilizes coordinate location provided from base and is oriented true north. 125’ is the distance from hangar to centerline to accommodate a 200’ wingspan aircraft and 25’ wingtip clearance. A larger aircraft (potentially C-5) could access the east side of the ACH with an offset centerline to accommodate the required wingtip clearance; moving the existing fence near marines would be required.

2. and 3. AGE parking area

20,000 SF required. Centerline of towway is 142.5’ from B2300 and also from the future de-paint hangar (285’ feet from face of hangar to face of hangar) The pavement will be 60’ clear from the de-paint hangar and be 225’x120’. The pavement keep section will extend from centerline east to account for future hangar door locations of the de-paint hangar. Mead & Hunt to provide sketches showing proposed AGE location and cross sections. Current intent is to maintain current access drive\walkway location from the access gate and POV parking, which divides the proposed AGE storage.

4.Alignment of BACH proposed pavements with future fire station The future fire station drive connection location can be flexible as long as it lines up with one of the future engine bays. Further east may be preferred. Design for 65% will be revised to eliminate the North\South storm culvert daylighting near the future drive entrance. The strengthened shoulder will be

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com rectangular and cover the length needed for the drive and the radii. BACH Sanitary force main will be shifted east to line up with the current proposed fire station parking lot. Storm structures along the north side of BACH flowing east will be sized appropriately to handle additional flows generated from the proposed fire station (oversized from what is required for current flowrate + additional BACH runoff).

ACTION ITEMS:

1. Tinker to provide A\E Team with fire station background drawing information.

2. A\E Team to provide background drawing of BACH project to USACE\Tinker to align the fire station access road w/r to the BACH project proposed pavements.

3. A\E Team to provide drawing of AGE parking area with dimensions and cross section of same for review by USACE and Tinker CE for concurrence.

Scott Nall – Mason & Hanger Matt DeToy – Tinker AFB Civil Engineering Travis Smith – Tinker AFB Civil Engineering Doug Chung – Tinker AFB Civil Engineering Patrick Buhler – Mead & Hunt Jared Lock – Mason & Hanger

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

Rebekah Ulm, AIA

July 25, 2024

July 24, 2024

Microsoft Teams

Bomber Agile Common Hangar (BACH) – Tool Crib/FOM Layout Meeting

This confirms and records our understanding of the discussions which occurred, and the decisions reached during this meeting. Unless notified in writing within seven days of the date prepared, we will assume that the

DISCUSSION ITEMS

1. Tool Crib Layout:

a. Users requested vertical rolling carousel, rather than the current stacking high density storage.

Use Kardex Megamat 180 as basis of design.

b. Large shelving units for receiving and checking out rolling carts/chests. Leave out bottom shelf of pallet racks in order to park rolling carts.

c. Users like KC-46 layout and like Vidmar flexibility of storage cabinets at corridor and tool crib.

d. Verify aisle clearance around pallet racks for pallet jack. They aren’t anticipating driving a forklift through this space.

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

e. High density storage is not preferred.

f. Vidmar cabinets to remain in the corridor on the other side of the building

g. Ceiling height in the tool crib is easily found 15' 10" to the deck

h. Concerned about the height of things for fire protection

i. Dustin to send vertical lift information

j. Vidmar cabinets in DLA and composite? - No but still reviewing the rooms

k. Completely remove high density shelving replace with carousel

l. Eliminate double door from Hazardous storage to Tool Crib. Users request that the 3’ wide door grow to a 4’ wide door by checkout counter to hazardous storage for larger items to pass through.

m. Shift workstations by posts to prevent accidental collisions with them.

n. Align windows with aisles and orient shelving vertically as shown in Dustin’s image below.

2. FOM Layout:

a. This will be used similarly to the tool crib, but for smaller piece parts of tail bins.

b. They prefer the pallet storage aisles to run horizontally in plan vs. the current vertical orientation. Request roughly 8 pallet racks.

c. Users need 4 or 5 large 4’ x 8’ metal tables on rollers to break out kits.

d. Users need 4’ wide dutch door and OH coiling door to the hangar.

e. Users would like a window to the hangar from the administrative space.

f. Storage to be arranged with one main aisle and several smaller aisles with three shelves high -see image

g. See image from Dustin below.

The Mason & Hanger Group Inc. 300 West Vine Street, Suite 1500 Lexington, KY 40507 t 859.252.9980 f 859.253.0781 masonandhanger.com

ACTION ITEMS

1. Dustin to verify if 8’ or 10’ wide OH coiling door is preferred at FOM storage. 10’ can be accommodated with current design.

2. Coordinate large storage items with structural slab.

3. Coordinate shelving height from top of shelves to structure with FPE to ensure it doesn’t interfere with fire protection.

4. Coordinate larger door with structure from hazardous storage to tool crib. Currently, a structural brace would be conflicting with the wider door.

ATTENDEES

Natalie Anderson – Mead & Hunt Dustin Baker – USAF AFMC 76 AMXG/MXDEO

Christine Fernandez – Mead & Hunt Rebekah Ulm – Larson Design Group

DEPARTMENT OF THE ARMY

U.S. ARMY CORPS OF ENGINEERS, TULSA DISTRICT

2488 E 81ST STREET

TULSA, OKLAHOMA 74137

MEETING DATE: 13 August 2024

MEETING TIME: 1400 HOURS

MEETING OBJECTIVE: BOMBER AGILE COMMON HANGER…