WWYK263009_65 Design Analysis_Part5.pdf
PDF 4 MB Posted
- Solicitation number
- W912BV25S0014
About this file
This is a 65% design analysis document reviewing several technical aspects of the Bomber Agile Common Hangar (BACH) project at Tinker Air Force Base. The document contains civil engineering drawings, architectural plans, mechanical/plumbing designs, electrical/communications specifications, and sustainability requirements for a 4-dock hangar facility.
The document details specific design elements including pavement specifications for the towway and hangar access areas, utility connections for water/sewer/fire systems, interior space allocations for maintenance shops and administrative areas, HVAC systems utilizing air-cooled chillers and dedicated outside air systems, and sustainability features targeting 30% energy cost savings over ASHRAE baselines. Key infrastructure components include a 75-foot wide towway, storm drainage systems, electrical and communications infrastructure, and life safety systems. The design incorporates requirements from multiple UFC specifications and includes detailed Dr. Checks comments addressing technical clarifications for civil, architectural, mechanical and electrical systems. The facility includes both hangar bays for aircraft maintenance as well as supporting administrative and shop spaces across approximately 197,000 square feet.
View the file
Other files
Show 40 more
Latest 50 of 95 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Civil – Pavement Design
• PCASE Version 7.0.6
Shoulder Towway, Hangar Access Apron, Hangar Floor Airfield Access PC C
Load - 10,000-lb single wheel Load - Heavy Loading Criteria Load – KC-46A Traffic**
Traffic Area - N/A Traffic Area - Type C Traffic Area – N/A
Subgrade CBR - 2* Subgrade K-value - 49 pci* Subgrade K-value - 49 pci*
*CBR and K-value utilized from KC-46A Kitting Facility **KC-46A Traffic Included (B1200, M978, P-23, Various Trucks)
Civil - Utility Plan
• 1 – Connection point for the Sanitary Sewer to the existing
MH.
• 2 – Connection point for the Fire Water to the existing Fire Water Main west of Douglas
• 3 – Connection for the Domestic Water to the existing Water Main west of Douglas
• 4 – Connection for the Domestic Water to the existing Water Main south of SE 59th
Architectural Design Review
Architecture – Project Requirements
Lunch Break Reconvene at 1200hrs
Interior Design Review
Interior – Design Review LO Stor 127
22 Pallet storage 96" x 48" x 120" 1 Marker board 1 Display board Finishes epoxy floor, painted walls, and open to structure ceiling.
PMD 128
18 Task chairs and cubicles 4 Lateral filing cabinets 1 Display board 1 Marker board 1 Printer Finishes epoxy floor, painted walls, and open to structure ceiling.
Dock Office 119 5 Task chairs and cubicles 2 Lateral files 1 Marker board 1 Printer Finishes LVT floor, painted walls, and ACT ceiling.
Hangar 22 Lockers 1 Task chair and desk 2 Televisions Finishes epoxy floor, painted walls, and open to structure ceiling.
Break Room 125
32 Chairs and 16 tables 2 Commercial Refrigerators 2 Food vending machines 2 Beverage vending machines 1 Coffee maker and 4 microwaves 2 Televisions 2 Trash cans 2 Recycling bins 1 Reverse Osmosis machine and 1 water and ice dispenser Finishes LVT flooring, painted walls with graphics, and ACT ceiling with decorative ceiling element.
Well 124
1 Side table 1 Reclining chair 1 Under counter refrigerator Finishes LVT flooring, painted walls, and ACT ceiling.
Hangar 1 Work bench 1 Movable marker board
DLA/IPV 026
5 Pallet storage 96" x 24" x 96" 20 Shelving units 48" x 18" x 84" Finishes epoxy flooring, painted walls, and open to structure ceiling.
Composite 025 9 Shelving units 48" x 18" x 84" 2 Pallet storage 96" x 24" x 96" 4 Pallet storage 48" x 18" x 84" Finishes epoxy flooring, painted walls, and open to structure ceiling.
Hangar 22 Lockers 1 Task chair and 1 desk 2 Televisions
Break Room 021
24 Chairs and 12 tables 2 Commercial Refrigerators 2 Food vending machines 2 Beverage vending machines 1 Coffee maker and 4 microwaves 2 Televisions 2 Trash cans 2 Recycling bins 1 Reverse Osmosis machine and 1 water and ice dispenser Finishes LVT flooring, painted walls with graphics, and ACT ceiling with decorative ceiling element.
Well 021A 1 Side table 1 Reclining chair 1 Under counter refrigerator Finishes LVT flooring, painted walls, and ACT ceiling.
Dock Office 012
8 Task chairs and 8 cubicles 1 Printer 2 Lateral files 1 Marker board Finishes are LVT flooring, painted walls, and ACT ceiling.
PSC 107
12 Task chairs and 12 cubicles 1 Printer 1 Shredder 1 Bulletin Board 1 Marker board 10 Lateral files Finishes LVT flooring, painted walls, and ACT ceiling.
Dock Office 108 4 Task chairs and 4 cubicles 1 Printer 3 Lateral files 1 Marker board
Tool Crib 104
1 High density shelving 11 carriages at 24" D with 2 static shelves at 12" D
21 Shelving 48" x 18" x 84" 1 Metal Table 2 Marker board 5 Pallet storage 96" x 48" x 120" 12 Vidmar 12 drawer cabinet 3 Vidmar 10 drawer cabinet 1 Vidmar 19 drawer cabinet 4 Tool Storage 36" x 36" x 72" 3 Task chairs and 3 cubicles 1 Shredder and 1 Printer 1 Display Board 4 Lateral files Finishes epoxy flooring, painted walls, and open to structure ceiling.
Hazmat Stor 102
9 Flammable Cabinets 7 Oil Tank Barrels 2 Oil Stand Waste Stream 1 Oil Can Stand 1 Freezer Ultralow Finishes epoxy flooring, painted walls, and open to structure ceiling.
FOM Storage 101
6 Task chairs and 6 cubicles 1 Printer and 1 shredder 2 Mobile work bench 6 Pallet storage 96" x 48" x 120" Finishes epoxy flooring, painted walls, and open to structure ceiling.
Dock Office 008
5 Task chairs and 5 cubicles 1 Marker board and 1 display board 1 Printer 2 Lateral files Finishes LVT flooring, painted walls, and ACT ceiling.
Sheet Metal 006 1 Grizzly Disc Sander 1 Small break 1 Drill press 1 Shrinker stretcher 1 Rotex punch machine 1 Band saw 1 Rack for sheet metal 1 Locked cabinet 1 4' Box and pan brake 1 Plate roll 1 Accur press brake die rack 1 Shearing Machine 1 Hand brake 1 Sheet brake 1 Bead blaster barrel 1 Pressure blast cabinet
Tire (Open) Shop 005
6 Charging stations for tugs and 6 tugs 1 GTX floor sweeper Finishes epoxy flooring, painted walls, and open to structure ceiling.
Landing Gear Shop 003 2 Metal bins 2 Landing gear bench 2 Work table with cutout for PVC pipe 1 Nitrogen inflation machine - Branick 1 Refrigerated air dryer - Champion 1 Air compressor – Hydorvane HR07 1 Work table with 3 drawer file 1 Lab workbench, white with 3 drawer and cabinet
Private Offices
L-Shaped desk, task chair, two guest chairs, and a marker board.
Open Offices
Cubicles, task chairs, lateral files, marker boards, and printers.
Conference Rooms
Conference table with power, task chairs around table, side chairs, and presentation wall with marker boards and television.
Training Room
Training tables, task chairs, instructor desk, and presentation wall with marker boards and television.
Mechanical/Plumbing Design Review
HVAC – Design Review
Criteria The following is an incomplete list but includes the major criteria affecting the design. A more complete list is included in the 35% DA
USACE ECB 2023-08 Electrification, Decarbonization, and Executive order (E.O.) 14057., 22 June 2023 UFC 4-211-01 Aircraft Maintenance Hangars, Change 3, 20 Apr 2021 UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems, with Change 8 Jul 2021
Design Conditions The HVAC systems for the Bomber Agile Common Hangar (BACH) at Tinker AFB will be designed to provide required occupant comfort while minimizing energy consumption. The buildings and equipment will be designed to exceed ASHRAE 90.1-2019 standards in accordance with UFC 1-200-02.
Design Temperatures
Inside Design Conditions: Typical Office or Shops: 78°Fdb, 55°Fdp max cooling, 68°F Heating (capacity for 70°F) Hangar: Ventilation only cooling, 55°F Heating (capacity for 70°F)
Outside Design: Per ASHRAE 2021 Fundamentals Climate Data, 1% Cooling, 1% Dehumidification, 99% Heating)
Load Calculations: Heat gain and loss calculations have been performed using the Carrier HAP 6.11 computer software.
Equipment Loading: 1.5 W/sf for open office spaces, 200W for each computer workstation, 100W for each desk and instructor positions in classrooms, Comm Rooms and Server Room - 6000 Btuh heat load per rack.
Ventilation: Per ASHRAE 62.1-2022 and UFC 4-211-01
Mechanical – Design Review
Typical Air Handling Units
Central station AHU’s will be 100% recirculating (no outside air), have chilled water-cooling coils sized for 30% propylene glycol, VAV fans with VFD’s for duct static pressure control, 4” MERV 8 prefilters and 4” MERV 13 final filters. Construction will be minimum 3-inch-thick insulated walls suitable for indoor installation. These AHU’s will deliver 55°Fdb air to VAV air terminal units equipped with electric resistance reheat coils. The VAV terminal units will modulate the quantity and final temperature of the supply air to maintain zone temperature.
Typical Dedicated Outside Air Systems
DOAS will deliver tempered (70°Fdb, 52°Fdp) 100% outside air directly to each space. Dew point will vary to meet latent loads. Additionally, the DOAS units will exhaust air from various spaces including restrooms and shop areas. The exhaust air and outside air will pass through a crossflow plate energy recovery system (ERV) to exchange energy between the exhaust and outside air streams. Each DOAS will have both exhaust and outside air flow rate monitors for building pressurization control.
Makeup Air Units
MAU’s will deliver supply air for ventilation and heating as well as exhaust air from the space. These units will have electric resistance pre- and heating coils, MERV 8 outside air filters, MERV 13 final filters, supply and exhaust fans, and a cross flow heat exchanger. These units are heating and ventilating only with no cooling. The outside air will bypass the heat exchanger in the summer.
Air-Cooled Chilled Water Plant
The air-cooled chilled water plant will consist of a single variable speed air cooled chiller with redundant primary and secondary pumps. Primary pumps will be constant volume. Secondary pumps will be variable flow and controlled through VFD’s to maintain a differential pressure setpoint in the chilled water distribution system. The chilled water will be 30% propylene glycol to prevent freezing.
Ductless Split-System Heat Pumps: Ductless split-system heat pumps will be used to provide temperature control for dedicated spaces such as fire alarm rooms, data rooms, and comm rooms that require conditioning during unoccupied periods.
Unit Heaters: Electric resistance unit heaters will be used to heat smaller heated only spaces such as mechanical and electrical rooms.
Cabinet Heaters: Electric resistance cabinet heaters or electric resistance convectors will be used for vestibules and other spaces that require supplemental heat.
Plumbing – Design Review
Design Criteria The following is an incomplete list but includes the major criteria affecting the design. A more complete list is included in the 35% DA
USACE ECB 2023-08 Electrification, Decarbonization, and Executive order (E.O.) 14057., 22 June 2023 UFC 4-211-01 Aircraft Maintenance Hangars, Change 3, 20 Apr 2021 UFC 3-420-01 Plumbing Systems, 01 April 2021 UFC 3-420-02 Compressed Air Systems, 08 November 2022
Design Conditions Domestic Water Pressure: 50 psi minimum per OCWUT contract requirements Domestic Water Quality: 12 grains per gallon hardness
Domestic Water Supply Equipment
A triplex variable speed domestic water booster pump will be provided, with each pump sized for 40% of the full demand load. The outlet pressure will be set to 75 psi.
A duplex progressive flow water softener will be provided for the hot water supply. Each tank will be sized for 100% of the full demand load at a maximum of 15 psi pressure loss thru the equipment.
Domestic hot water will be generated with two water source heat pump water heaters. Each water heater will be sized for 70% of the full demand load of the facility. A 250 gallon storage tank will also be provided. Hot water will be generated at 140°F and reduced to 120°F for distribution.
Compressed Air Equipment
Two rotary screw type air compressors will be provided, one to serve the north half of the facility and one to serve the south half of the facility. Each air compressor will include an air cooled aftercooler, refrigerated dryer, and filters. A 400 gallon reciever will be provided at each air compressor.
Plumbing Fixtures
All plumbing fixtures will be manual operation. Water closets and urinals will be wall hung, flush valve type fixtures. Lavatories will be wall mount vitreous china or intetral with countertop, depending on location. Work sinks will be stainless steel.
Electrical/Communications Design Review
Electrical – Design Review
• Complete documentation of existing parking lot lighting design
• Complete documentation of existing fence lighting
• Complete documentation of existing power stands
Electrical – Design Review
• Site Lighting, TAFB Electrical Standard – “Any lighting fixtures mounted over 30 feet high require special review by 72ABW/CENMP.”
• FAA obstruction lighting with respect to BASE BRL line(s) and 1 to 100 transitional surface (4043’ to edge of runway 36, 3225’ to end of runway 31)
• Recommend breakout session for electrical discussion of Power Stands and routing of cables to hangar bay docks
Communications Design Overview
• Design Criteria − NFPA 70, National Electrical Code (NEC) 2023
− NFPA 72, National Fire Alarm and Signaling Code 2016
− UFC 3-580-01, Telecommunications Building Cabling Systems Planning and Design 2016
− ANSIA/TIA/EIA 568-C, Series of Telecommunication Standards
− ANSIA/TIA/EIA 569-B, Commercial Building Telecommunications Cabling Standard
− ANSIA/TIA/EIA 607, Generic Telecommunications Grounding and Bonding(Earthing) for Customer Premises
• Design Criteria (cont.)
− NECA/NEMA 105, Standard for Installing Metal Cable Tray Systems (ANSI)
− NECA/FOA 301, Installing and Testing Fiber Optic Cables 2016
− NECA/BICSI 568, Installing Commercial Building Telecommunications Cabling
− BICSI TDMM 14TH EDITION
− NECA 607, Standard for Telecommunications Bonding and Grounding Planning and Installation Methods for Commercial Buildings
− 72 ABW/SC COMM.RM-STANDARD V3.2
− UFC 4-021-02 (Security ESS), AFI 31-101 NFPA 731 (Physical Security), and
UFC 4-010-05 (SCIF/SAPF)
• Design Items − Service Entrance: New service entrance with fiber optic and copper cables run through new utility duct from central utility plant (CUP) building.
− Telecom Rooms: Comm 114, Comm 014, Comm 204.
− Network: NIPRNet, SIPRNet, JIWCS: Identify devices in each category, log and report to cybersecurity.
− Access Control / Intrusion Detection: Provide rough-in facilities for installation of access control and/or IDS systems.
− Paging: No separate paging system for the hanger.
• In Accordance With UFC and Base V3.2 Technology Space Requirements:
− Standard 2 rack comm rooms will be sufficient.
− Sized at 1.1% of area served, min 10’x8’, at 10,000 sq/ft 10’x11’
− Dedicated power for each rack from an independent panel within the room.
− The electrical panel in the room is only for Comms requirements in the room.
− Independent HVAC for the Comm room.
• Comments regarding secure storage and future use:
− Apply ICD 705.
− Place X10 in main entrance and controlled by B21?
− Requirements for physical and TEMPEST should be factored in.
• Z ducts
• Inspection ports
• Man bars
• Dielectric breaks and grounding
• (2) 4” conduit for B21 circuits
• conduit for ACS and IDS pulls
− SAPWA requirements.
− Standard MOB facility guide.
Life Safety/Fire Protection Design Review
Life Safety / Fire Protection – Design Review
• Life Safety o Fire Resistance-Rated Construction oOccupant Loads / Egress
• Fire Protection oWet Pipe Suppression – TAFB Fire Water
▪ Two Riser Rooms
▪ No Fire Pump / Tank oHydrants – OCWUT
• Fire Alarm / Mass Notification o Two-Sided System
Structural Design Review
Structural – Design Review
• Structural Overview − Substructure
• Drilled Piers
• Grade Beams Supporting Perimeter Walls
• Mat Foundation – Equipment, Storm Shelters, & Hangar Door Tracks
− Superstructure
• Hangar Bay
• 3” decking on Steel Beams / Trusses / Columns
• Horizontal & Diagonal Diaphragm Bracing at Top & Bottom Chords
• Wall System: Insulated Metal Wall Panel with Steel Girts
• Lateral System: Vertical Steel Bracing
• Admin / Shop Areas
• Structurally Isolated by Bldg. Expansion Joints
• Roof: 1 ½” decking on Steel Joists / Beams / Girders / Columns, and Precast Concrete
• 2nd Floor: 5 ½” total concrete deck thickness on Composite Steel Beams / Columns / CMU
• Lateral System: Insulated Precast Concrete Panels (E-W), Steel vert. Bracing & CMU Shear Walls (N-S)
• Structural – Overhead Items − Bridge Cranes
• (1) 5 Ton @ center of hangar in N-S direction
− Monorails
• 2 Ton aligned w/fuselage
− Fall Protection
• Single track aligned w/engine pods
• Dual track aligned w/wings
• Single track aligned w/tail
− Support for: Power Reels, HVLS Fans, Ductwork, Lighting, Draft Curtains, Fire Protection
− Stair Access to Roof & Catwalk
− Catwalk
• Structural – Special Items − Emergency Shelter
• at Break Rooms
• Designed per ICC 500
• Risk Category IV
− Shop Requirements
• Bridge Crane in Landing Gear Shop
Cost Estimate Review
Cost Estimate – Review
Construction Schedule Review
Construction Schedule Review
Sustainability & Guiding Principles Review
Sustainability and Guiding Principles Overview
Tracking and compliance:
Additional Requirements
GBI DOD GPC
NC Survey/
Scoping Checklist
Air Force Sustainability Requirements
Scoresheet
HPSB Checklist/Design Analysis + Third Party Validation + Other Federal Requirements
Six Guiding Principles
1. EMPLOY INTEGRATED DESIGN PRINCIPLES
• Integrated Design
• Commissioning
2. OPTIMIZE ENERGY PERFORMANCE
• Energy Efficiency
• Onsite Renewable Energy
• Metering
3. PROTECT AND CONSERVE WATER
• Indoor Water Use
• Outdoor Water Use
• Alternative Water
• Stormwater Management
4. ENHANCE INDOOR ENVIRONMENTAL
QUALITY
•Ventilation and Thermal Comfort
•Daylighting and Lighting Controls
• Indoor Air Quality
•Occupant Health and Wellness
5. REDUCE ENVIRONMENTAL IMPACTS OF
MATERIALS
•Material Content and Performance
•Waste Diversion and Materials Management
6. ASSESS AND CONSIDER CLIMATE CHANGE
RISKS
•Address Climate Change Risks
GBI Guiding Principles Validation
Employ Integrated Design Principles
INTEGRATED DESIGN
COMMISSIONING
• Regular inter-disciplinary meetings to ensure synergy
• Passive Design Strategies Included:
− Sunshades are located on the east and west façade to mitigate heat gain
− Daylighting maximized to the greatest extent possible
• Cx agent will be engaged at 65% to verify system design requirements are met
Optimize Energy Performance
ENERGY EFFICIENCY
ONSITE RENEWABLE ENERGY
METERING
• Per LCCA design will achieve 30% energy cost savings from ASHRAE 90.1-2019 Appendix G baseline
• Efficient equipment specified to meet Energy Star, FEMP-designated
• Proposed solar array would net 29.4% energy consumption reduction, pending final approval
• 30% Solar Hot Water evaluated but not LCCE
• Metering will measure total energy, mechanical systems, and lighting systems
• Advanced Digital Metering will communicate usage data
Protect and Conserve Water
INDOOR/OUTDOOR WATER USE
• WaterSense® compliant fixtures have been specified − Lavatory faucets: 0.50 gpm, Water closets: 1.28 gpf, Urinals: 0.125 gpf, Showers: 1.5 gpm
• Metered at building-level, sub-meters are being considered
• The site will include no landscaping, requiring no outdoor irrigation
STORMWATER MANAGEMENT
• Drainage routed to detention basin which will discharge into the existing grassy swale that drains into Soldier Creek
• Reduction in stormwater volume not achievable due to minimal soil infiltration and removal of some areas of swales
ALTERNATIVE WATER
• Rain collection system for flushing was evaluated but not LCCE
Enhance Indoor Environmental Quality
VENTILATION AND THERMAL COMFORT
DAYLIGHTING AND LIGHTING CONTROLS
• Ventilation systems will control and remove pollutants from indoor air
• Thermal comfort strategies effectively address temperature, humidity, air movement
• Work areas, break rooms and other gathering areas along exterior walls will incorporate daylighting
• Lighting in daylit areas will be zoned and dimmable to maximize efficiency
INDOOR AIR QUALITY
• Building envelope will minimize moisture intrusion into interior
• Moisture-resistant materials will be used in places prone to moisture
• Low VOC / Low-Emitting materials will be specified
• Construction will abide by approved Air Quality Management Plan − Includes stipulations for air filtration, site clean-up, material protection
• Tobacco smoking prohibited within 50 feet of building
OCCUPANT HEALTH AND WELLNESS
• Multiple paths and stairwells promote walking
• Interior design package will enhance user experience − Timeless blue-gray colorway
− Cohesive furnishings
− Instill pride among users
• Wellness rooms will be provided on first floor
• Open office configurations with views add to occupant satisfaction
Reduce Environmental Impacts of Materials
MATERIAL CONTENT AND PERFORMANCE
• Recycled content – specified to meet or exceed EPA CPG − Where feasible: finish materials, supplementary cementitious materials
• Biologically-based – specified to meet USDA Bio-Preferred program − Where feasible: finish materials analyzed
• Ozone-Depleting/Global Warming – according to SNAP guidelines − No sodium hexafluoride, ozone depleting/global warming substances, or gaseous fire suppression systems will be installed in project
WASTE DIVERSION AND MATERIAL MANAGEMENT
• Recyclables will be collected and stored in designated areas − Accessible/visible locations in breakrooms and workstations, encourage recycling
− Streams will include paper, cardboard, glass, plastics, and metals
• During construction, a minimum of 60% of waste will be diverted
Assess and Consider Climate Change Risks
CLIMATE CHANGE RISKS
• Climate change risks, according to Oklahoma City Sustainability Plan − Increased temperatures – drier, hotter summers bringing drought/wildfires
− Increased rainfall events – increased flooding in low-lying areas
• Natural hazard assessment for Oklahoma State identified the following:
− Extreme heat, drought, wildfires
− Severe storms, high winds, tornadoes, flooding
− Area to the north of project lies in FEMA 100-year floodplain
Assess and Consider Climate Change Risks
ADDRESS CLIMATE CHANGE RISKS
• Storm shelters are included in design
• Designed passive systems (thermal envelope, solar, daylighting) minimize reliance on grid
• Building designed to withstand snow, fire, high winds
• Proposed PV array will help reduce contribution to climate change
• Efficient plumbing fixtures will protect regional water resources
Life-Cycle Cost Analysis (LCCA)
• Requirement − ASHRAE 90.1-2019 Appendix G Performance Rating Method
• New construction should achieve at least 30% energy cost savings over an ASHRAE 90.1-2019 Appendix G baseline while also being Life Cycle Cost Effective (LCCE)
− UFC -1-200-02
• Commercial buildings to meet the requirements of ASHRAE 90.1-2019 Appendix G and be LCCE
− Electrification - Executive Order 14057
• Military construction projects should incorporate all-electric technologies such as space conditioning, water heating, cooking, and laundry
• Process − LCCA software - Building Life-Cycle Costing (BLCC)
− A 40-year life expectancy for comparing system alternatives
− Design alternates are deemed LCCE if they had a net present value less than the base case
− Energy modeling software used - OpenStudio 3.3 (EnergyPlus 9.6) and the Parametric Analysis Tool
(PAT) 3.3.
− Several alternates were bundled together for the recommended design
• Alternates Evaluated − Envelope options were analyzed for both admin and hangar areas
• Increased Roof Insulation
• Increased Wall Insulation
• Increased Window and overhead door performance
− Reduced lighting power
− Rainwater harvesting
− 30% water consumption by solar hot water
− On-site renewable energy
− All-electrical mechanical system alternates
• Mechanical Alternates Evaluated
• Alternate 1 o Admin
➢ Air cooled chiller, VAV w/electric reheat, DOAS o Hangar
➢ MAU with electric resistance, ERV
• Alternate 2 o Admin
➢ Packaged RTU heat pump, w/ DOAS heat pump, electric resistance reheat (ERV) o Hangar
➢ MAU with heat pump heating (electric resistance backup)
• Alternate 3 o Admin
➢ VRF heat recovery with DOAS heat pump and w/ ERV o Hangar
➢ MAU heat pump (Daikin Aurora) (electric resistance backup)
• Recommendations − Envelope
• Roof o Admin
➢ 6-inch polyiso above deck, U-0.025 (R-40 c.i.)
o Hangar
➢ 6-inch polyiso, U-0.025 (R-38 c.i.)
• Wall o Admin & Hangar (Lower walls)
➢ 3-inch rigid insulation, U-0.061 (R-20 c.i.)
o Hangar (Upper walls)
➢ 1-inch insulated metal panel, U-0.044 (R-25 + R-6 c.i.)
• Fenestration
➢ Aluminum storefront 1-inch, tinted/tempered low-e, double pane, U-0.25 (COG), SHGC-
0.25, VT-0.275
• Overhead Door
➢ R-9 Alpine IMB-V9, 1-inch polyurethane (max U-0.11)
• Recommendations − Electrical
• Interior Lighting Power Density (LPD) o Admin – 0.54 W/sf o Hangar – 0.64 W/sf
• Renewable Energy o Rooftop PV
➢ 420 kW-DC PV array
➢ 594,575 kWh annual energy production
− Plumbing
• Service Hot Water o Water source heat pump − Mechanical Alternate 1 o Admin
➢ Air-cooled chiller, VAV with electric reheat, DOAS o Hangar
➢ MAU with electric resistance, ERV
• Summary − All electric Energy Efficiency Measures (EEMs) were analyzed for both energy cost savings and LCCE
− EEMs analyzed included: envelope, electrical, lighting, service hot water, HVAC, and onsite renewable energy improvements
− Bundle for 30% energy cost savings: The results of the analysis include recommendations for bundling
EEMs together for a design that meets 30% energy cost savings
Summary/Hot Wash
Adjourn for the Day Reconvene at 0800 Tomorrow
Review Day 1 Topics – Day 2 Objectives
Agenda
0730 0800 0830 0900 0930 1000 1030 1100 1130 1200 1230 1300 1330 1400 1430 1500 1530 1600
Tuesday, February 13 Base Access
Virtual Meeting
Setup and
Preparation
Project Team
Introductions and
Opening Remarks
35% Design
Review Goals and Objectives
(DD 1391)
Sustainability
& Guiding
Principles
Summarize /
Hot Wash
Adjourn for the
Day
Wednesday, February 14
Virtual Meeting
Setup and
Preparation
Reconvene /
Review Day 1 /
Day 2 objectives
Risk
Register
Review and
Update
Review
Action
Items
Project
Schedule
& Next Steps
Summarize/
Closing
Remarks
Adjourn for the
Day
Project Review
Cost Estimate
Construction Schedule
Project Review
Civil/Site
Architectural
Lunch Break
Lunch Break
Project Review
Interior Design
Mechanical/Plumbing
Electrical/Communications
Life Safety/Fire Protection
Structural
Dr. Checks Comments Review Dr. Checks Comments Review
Dr Checks Comments Review
Civil – Comment 10621968
• Existing Towway Widened to 75’
• Comment 10621968 suggests to investigate straightening towway
• Response: Replacing the existing PCC was discussed but instructed to keep in place. Not included in 1391 and currently out of scope.
Civil – Comment 10621978
Response: Proposed C/L is consistent with the C/L location in the Final Bomber Planning doc. The image from the Final Bomber Planning Doc shows the centerline 150' east of the ACH. Proposed C/L is 150' east of the ACH with a full strength towway width of 75'
Civil – Comment 10621982
Is it possible to add and additional row of POV parking along the south side of both the new lot and the existing lot? See Attachment.
It may be possible to add the additional row of POV parking. We will know once the survey and easements are completed and shown. We will either add the spaces or explain why parking can't expand south for the next submittal.
Civil – Comment 10641038
Clarification: Will Douglas or SE 59th be bored for water or sewer? Applicable specs may be needed. The Sanitary Sewer Force Main Piping may be needed, unless it's included in the Packaged Utility Wastewater Pumping Station.
Current plans do not require a specific method but do require that if trenched, the contractor must provide coordination/traffic control. We can require all crossings to be bored if that is the preferred method. Will include specification for Sanitary Sewer Force Main Piping. Currently showing Sanitary Sewer connection into the existing system north of our site, not across Douglas.
Please refer to construction limits on GC111. The connection information to the existing system will be better defined in the next submittal.
Civil – Comment 10641490
Do these markings comply with UFC 3-260-04 Para 6-1 and 6-2? Towway centerlines should be 6" wide yellow. At the end of the arc as the line enters into the hangar the line should be 6" wide white. Remove the non-reflective black background paint.
All aircraft are to be towed to the ACH and within the future B-21 campus. Paragraph 6-1 and 6-2 refer to taxilane and taxiway markings for powered aircraft, which does not apply to this project site. Towway markings per 6-5.9 of UFC 3-260-04 are to be white as shown on plans.
The black border is recommended per the UFC on light-colored pavements (PCC), especially with white markings.
Civil – Comment 10641512
Comment: Show new pavement for AGE parking that will be demolished by the project between B2301 and south of B2300
Civil – Comment 10641515
Existing utilities need to be removed under the towway in addition to the 18" and 24" culvert crossings being installed. Due to the size of the culverts, boring and jacking as an installation method will be costly. In future submittals restrictions can be provided on the phasing plans to expedite the construction work in these areas to limit the effects on towway operations.
Require that both storm drain crossings of towway be bored instead of trenched.
Civil – Comment 10641518
Comment: Verify sufficient room on ramp to turn B-52 into crabbed position and push it into the hangar on the east side
Civil – Comment 10641520
Comment: Show dimensions of modified keel section of existing east-west towway and new north-south towway
Civil – Comment 10641534/35, 10641568, 10643456
10641534/35 Show B-52 crabbed wheel lines into hangar as well as centerlines.
Please provide operational pavement markings for B-52 crab movements. These are not covered in the UFC.
10641568 Add additional personnel gate at existing personnel gate due to increased personnel flow.
Will discuss at the review meeting for confirmation to add additional personnel gate and to verify no other infrastructure will be required (additional guards or lighting).
10643456 DA. Civil 2.3.8. Airfield aprons, taxiways pavements to use 5-year storm event for analysis as indicated in UFC 3-201-01, 3-1.2.1. Please verify, confirm and adjust as necessary.
Per paragraph 3-1.2 of UFC 3-201-01, this project is using the facility storm drainage requirements of 10-year not the airfield minimum of 5-year due to this project being located within a building campus and not within the Aircraft Operations Area. Typically, an airfield is a pond and culvert system where this facility is fully reliant on the storm sewer network to project the buildings.
Civil – Comment 10643458
10643458 Is there a master drainage plan for the whole campus?
I would think these were discussed during the campus development and design charrette.
Although the reference guide of OKC drainage manual is a good start, the governing drainage criteria should follow UFCs unless this campus has been decided to follow OKC drainage criteria.
There is a master drainage plan in the final bomber campus plan. Storm sewer infrastructure included in this project is designed to accommodate the future bomber campus to the south of the ACH. As discussed during the charrette detention will be designed only for this project as the B-21 infrastructure project to include the perimeter road and detention area has not been completed. UFC 3-201-01 paragraph 3-1 states to use the storm drainage criteria listed in the UFC or local regulatory agency; whichever is more stringent. The local OKC drainage manual and guidance will govern design parameters.
Thanks for the masterplan info.
But I was not able to locate such info. I was able to locate the drainage maps starting on PDF page 881, but these don't seem to be for all the campus and was some of the off-site on the south.
UFC 3-201-01 paragraph 3-1, "local criteria" applies only when the local criteria agency has jurisdiction over the installation. I don't believe OKC has jurisdiction over the stormsewer improvements on base or will have once the new campus is complete. Base typically operates and maintains all stormsewer infrastructure on base unless this has changed recently.
File details come from the government source that posted it. Updated .