W50S9F21B00010004.pdf

PDF 157 KB Posted

Attached to
F-35 Alter Hangar 406 Federal contract opportunity
Solicitation number
W50S9F-21-B-0001
Issued by
Department of the Army National Guard

About this file

This solicitation package describes a federal contract opportunity to alter an F-35 aircraft hangar at Dane County Regional Airport - Truax Field in Madison, Wisconsin. The project scope includes demolishing 19,913 square feet of hangar shop space and reconfiguring the area for F-35 aircraft maintenance operations, including lavatories, offices, break rooms, and repair shops. An additional 19,803 square feet of hangar space will be modified to accommodate F-35 aircraft, with modifications to fire suppression, aircraft power and air systems, and lightning protection. Mechanical, plumbing, electrical, and communications systems work is also included. The solicitation will result in a single construction contract and includes two options related to fire protection and runoff storage. The bid due date is March 8, 2021. The contract is designated for the Department of the Army National Guard and adherence to F-35 requirements is necessary.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 Alter Hangar 406, newest first.
File Type Posted
Abstract of Offers with Hubzone Preference.pdf PDF
SF1419 Abstract of Offers - No Hubzone Preference.pdf PDF
W50S9F21B00010007.pdf PDF
W50S9F21B00010006.pdf PDF
406 Questions and Answers_142-143.pdf PDF
23 07 00_Add04.pdf PDF
406 Questions and Answers_113-141.pdf PDF
F-102_Add03.pdf PDF
T-001 Add03.pdf PDF
E-101_Add03.pdf PDF
32 13 14.13_Add03.pdf PDF
21 13 18.00 10_Add03.pdf PDF
F-001_Add03.pdf PDF
C-141_Add02.pdf PDF
G-011_Add02.pdf PDF
AD101_Add02.pdf PDF
C-101_Add02.pdf PDF
E-501_Add02.pdf PDF
SD111_Add02.pdf PDF
A-201_Add02.pdf PDF
10 28 13_Add02.pdf PDF
A-311_Add02.pdf PDF
406 Questions and Answers_26-112.pdf PDF
G-001_Add02.pdf PDF
E-101_Add02.pdf PDF
01 50 00_Add02.pdf PDF
12 21 00_Add02.pdf PDF
10 14 00.20_Add02.pdf PDF
05 40 00_Add02.pdf PDF
01 78 00_Add02.pdf PDF
Asbestos and Lead Inspection.pdf PDF
Repair Roofs 406 Warranty Cert.pdf PDF
A-401_Add02.pdf PDF
04 20 00_Add02.pdf PDF
W50S9F21B00010003.pdf PDF
10 22 39_Add01.R1.pdf PDF
A-131_Add01.R1.pdf PDF
C-121_Add01.R1.pdf PDF
W50S9F21B00010002.pdf PDF
B.07.406 Site Visit Sign In 22Feb21.pdf PDF
B.07.406 Site Visit Sign In 19Feb21.pdf PDF
Pre-Bid Slides - F-35 406.pptx PPTX presentation
W50S9F21B00010001.pdf PDF
W50S9F-21-B-0001.pdf PDF
ATTACHMENT 6-Justification and Approval Monaco.pdf PDF
ATTACHMENT 8-406 Submittal Log.xlsx XLSX spreadsheet
ATTACHMENT 9-SFS Form 12.xls XLS spreadsheet
ATTACHMENT 10-PRE-BID CONFERENCE AND SITE VISIT INSTRUCTIONS.pdf PDF
ATTACHMENT 1-Truax F-35 B406 XGFG182008 Specs Vol 1 of 2 Dated 31 July 2020.pdf PDF
ATTACHMENT 5-Justification and Approval Andover.pdf PDF
Show all 50

F-35 Alter Hangar 406 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

XGFG182008

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to make changes to several plans and specifications and to addAsbestos And Lead Pre-Renovation Inspection, dated October 8, 2019 and Existing Roof Warranty. See the next page for details.

The due date remains unchanged of 15 March 2021.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Mar-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W50S9F21B0001

X 9B. DATED (SEE ITEM 11)

04-Feb-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Mar-2021

CODE

USPFO WI 115 MISSION SUPPORT CONTRACTING

3110 MITCHELL ST BLDG 500

MADISON WI 53704-2591

W50S9F 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W50S9F21B0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0004 CHANGES

Amendment 0004 consists of changes to the specifications and drawings listed below. Revised specifications and drawings are also provided with this amendment.

Changes to specifications:

A. Specification TOC

1. Replace Specification Table of Contents (TOC) with Revised Specification TOC.

B. Section 01 11 00

1. Replace Section 01 11 00 with revised Section 01 11 00 that includes the changes below:

a. Add to the end of the paragraph in 1.2.1: “The project will be constructed in a single phase.”

b. Add as the first paragraph under 1.6: “Government to remove all non-real property items from the facility prior construction. Contractor to remove all remaining equipment, furniture, etc., made obsolete or no longer wanted by the Government. Offer to the Government before salvaging or disposing of existing equipment, furniture, etc. Remaining items designated by the Contracting Officer to be salvaged remain the property of the Government.”

C. Section 01 14 00

1. Replace Section 01 14 00 with revised Section 01 14 00 that includes changes below:

a. Add as the first line in paragraph 1.2.4: “The building will not be occupied during construction.”

b. Add paragraph 1.2.6 Airfield Safety.

D. Section 01 45 00.00 10

1. Add as a new section for Quality Control.

E. Section 01 50 00

1. Replace Section 01 50 00 with revised Section 01 50 00 that includes the changes below:

a. Add paragraph under 3.5.6 Maintenance of Storage Area: “b. Snow Removal: The Contractor is responsible for removing all snow and ice within the boundaries of the construction site, including material storage and prep areas and contractor parking. Coordinate with the COR for location to pile removed snow.”

F. Section 01 78 00

1. Replace Section 01 78 00 with revised Section 01 78 00 that includes the changes below:

a. Under 3.1 As-Built Drawings, add as the first paragraph: “Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as- builts throughout construction as red-lined hard copies on site and red-lined PDF files. Submit As-Built Drawings in PDF format 30 days prior to Beneficial Occupancy Date (BOD).”

G. Section 02 83 00

1. Replace Section 02 83 00 with revised Section 02 83 00 that includes the changes below:

a. Revise paragraph 1.2.5 Certified Industrial Hygienist (CIH) to delete the last sentence of the text paragraph.

b. Delete paragraph 1.2.6 Child-Occupied Facility.

c. Renumber paragraphs 1.2.7 through 1.2.21 to 1.2.6 through 1.2.20 accordingly.

d. Revise current paragraph 1.2.8 (new paragraph 1.2.7) Competent Person (CP) to read: “As used in this section, refers to a person employed by the Contractor or the Lead- based Paint remediation subcontractor who is trained in the recognition and control of lead, cadmium and chromium hazards in accordance with current federal, State, and local regulations and has the authority to take prompt corrective actions to control the lead, cadmium and chromium hazard. The Contractor or Lead-based Paint remediation subcontractor may provide more than one CP as required to supervise and monitor the work. The CP must be a Certified Industrial Hygienist (CIH) certified by the American Board of Industrial Hygiene or a Certified Safety Professional (CSP) certified by the Board of Certified Safety Professionals or a licensed lead-based paint abatement Supervisor/Project Designer in the State of Wisconsin.”

H. Section 04 20 00

1. Replace section 04 20 00 with revised Section 04 20 00 that includes changes below.

a. Under 2.2.2.2.5 Unit Types add: “d. Thin Block Units: Provide Split Face finish, nominal 1 inch thick by 16 inches long by 8 inches high units.”

I. Section 05 40 00

1. Add section 05 40 00 to the specifications.

J. Section 10 14 00.20

1. Replace Section 10 14 00.20 with revised Section 10 14 00.20 that includes the changes below.

a. Part 2.2 delete requirement for radiused corners.

K. Section 10 28 13

1. Replace Section 10 28 13 with revised Section 10 28 13 that include the changes below.

a. Revise paragraph 2.2.8 to eliminate Towel Bar and change to Clothes/Robe Hook.

b. Revise paragraph 2.2.10 to read “Provide Floor-Standing Waste Receptacle with Open Top (21 Gallon)

L. Section 12 21 00

1. Replace Section 12 21 00 with revised Section 12 21 00 that includes the changes below:

a. Revise paragraph 1.1 Summary, replace “Window Treatment Placement Schedule” with “drawings”

Changes to plans:

A. Drawing G-001:

1. Replace sheet G-001 with revised Sheet G-001 that changes Drawing F-505 FIRE ALARM DETAILS to F-502 FIRE ALARM DETAILS in the Sheet Index. Note that the correct sheets are included in the set, only the Sheet Index was incorrect.

2. Add G-011 PROJECT WORKSITE AND OPERATION PLAN to the Sheet Index.

B. Drawing G-011:

1. Add Sheet G-011 PROJECT WORKSITE AND OPERATIONS PLAN to the drawing set.

C. Drawing AD101:

1. Replace Sheet AD101 with revised Sheet AD101 with information added about hazardous material locations for abatement.

2. Revise Demolition Plan General Notes #11 to clarify removals.

D. Drawing A-101:

1. Replace Sheet A101 with Revised Sheet A-101 with added Keyed Note 4.134. adding in window treatment locations.

E. Drawing A-201:

1. Replace Sheet A-201 with revised Sheet A-201 that has revised Keyed Note 4.213 "EXISTING

HANGAR DOOR TO REMAIN, REVIEW DOOR WITH GOVERNMENT PRIOR TO FINISHING,

CLEAN PATCH AND REPAIR ANY EXISTING HOLES OR DAMAGE NOTED, REPAIR TO

MATCH EXISTING PRIOR TO APPLYING NEW PAINT FINISH TO MATCH.”

2. Edit Keyed Note 4.202 to read: “SPLIT FACE THIN BLOCK VENEER (SEE SPECS).”

F. Drawing A-301:

1. Replace A-301 with revised A-301. Revised Section 4/A-301, Added Keyed Note 4.133 “PROVIDE

HEAVY ANGLE TRAVEL STOP WELDED TO WEB, MATCH EXISTING STOPS FOR

THICKNESS AND DIMENSIONS. LOCATION NOTED IS APPROXIMATE, CONTRACTOR TO

VERIFY FINAL LOCATION, COORDINATE WITH NEW HOIST CARRIAGE SELECTED TO

ENSURE PROPER CLEARANCES.”

G. Drawing A-311:

1. Replace A-311 with revised A-311 with revised details 1, 3, and 7 revising wall material notes.

H. Drawing A-401:

1. Replace A-401 with revised A-401 with revised details 7 and 10 providing mirror dimensions.

I. Drawing A-501:

1. Replace A-501 with revised A-501, revised details 1, 2, 12, 13, and 14, clarifying wall materials.

J. Drawing A-601:

1. Replace A-601 with revised A-601, with updated door and hardware schedule and added frame type.

K. Drawing A-801:

1. Replace A-801 with revised A-801, with unused detail deleted and updated signage locations.

L. Drawing A-901:

1. Replace A-901 with revised A-901 with revised note 2.

M. Drawing E-101:

1. Revise locations for (8) grounding receptacles as shown clouded on attached sheet.

N. Drawing E-501:

1. Revise Static Grounding Receptacle detail as shown clouded on attached sheet.

O. Drawing SD111:

1. Replace Sheet SD111 with revised Sheet SD111, indicating electrical ground receptacle locations per the electrical drawings and their required avoidance of existing embedded truss arch tie plates.

Additionally, clarified these items are the only items to be cut into the existing hangar slab.

P. Drawing C101:

1. Replace Sheet C101 with revised Sheet C101, that changes “LIMESTONES” to state “QUARRIED

LIMESTONE BOULDERS WITH TOP AND BOTTOM SHAPED / SCORED TO BE SMOOTH

AND LEVEL, 36" TO 48" LONG X 24" TO 30" WIDE X 18" TO 20" TALL, 4' MAXIMUM

SPACING BETWEEN BOULDERS”.

Q. Drawing C141:

1. Replace Sheet C141 with revised Sheet C141, to indicate the length and size of the hydrant laterals located on the site.

Reports

A. Asbestos And Lead Pre-Renovation Inspection, dated October 8, 2019:

1. Attached

B. Existing Roof Warranty:

1. Attached.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .