01 78 00_Add02.pdf

PDF 26 KB Posted

Attached to
F-35 Alter Hangar 406 Federal contract opportunity
Solicitation number
W50S9F-21-B-0001
Issued by
Department of the Army National Guard

About this file

This solicitation package describes requirements for a federal construction contract to alter an F-35 aircraft hangar at Truax Field in Madison, Wisconsin. The project scope includes demolishing 19,913 square feet of hangar shop space and modifying 19,803 square feet of hangar space to accommodate F-35 aircraft. Specific requirements include high expansion foam fire suppression system modifications, aircraft make-up power and air systems, and lightning protection work. Mechanical, plumbing, electrical, and communications systems are also included. The contract value is estimated between $10-25 million. The solicitation will include two options related to fire protection runoff storage and perimeter trench infill. Interested parties must register in SAM and attend an optional pre-bid conference on February 16, 2021. Bids are due by March 8, 2021 and award will be made to the responsive and responsible lowest bidder.

View the file

Other files for this federal contract opportunity

Other files attached to F-35 Alter Hangar 406, newest first.
File Type Posted
C-102_Add03.pdf PDF
C-101_Add03.pdf PDF
Specs TOC_Add03.pdf PDF
01 50 00_Add03.pdf PDF
W50S9F21B00010005.pdf PDF
C-121_Add03.pdf PDF
C-504_Add03.pdf PDF
34 71 13.19_Add03.pdf PDF
01 45 00.00 10_Add03.pdf PDF
22 31 00_Add03.pdf PDF
T-121 Add03.pdf PDF
Specs TOC_ Add02.pdf PDF
A-301_Add02.pdf PDF
A-901_Add02.pdf PDF
A-801_Add02.pdf PDF
A-101_Add02.pdf PDF
01 45 00.00 10_Add02.pdf PDF
Asbestos and Lead Inspection.pdf PDF
Repair Roofs 406 Warranty Cert.pdf PDF
A-401_Add02.pdf PDF
04 20 00_Add02.pdf PDF
A-501_Add02.pdf PDF
A-601_Add02.pdf PDF
02 83 00_Add02.pdf PDF
01 14 00_Add02.pdf PDF
01 11 00_Add02.pdf PDF
406 Questions and Answers_1-25.pdf PDF
Specs TOC_Add01.R1.pdf PDF
07 24 00_Add01.R1.pdf PDF
09 67 23.13_Add01.R1.pdf PDF
32 92 19_Add01.R1.pdf PDF
A-201_Add01.R1.pdf PDF
C-101_Add01.R1.pdf PDF
Geotechnical Report_Add01.R1.pdf PDF
07 27 26_Add01.R1.pdf PDF
W50S9F21B00010003.pdf PDF
10 22 39_Add01.R1.pdf PDF
B.07.406 Site Visit Sign In 19Feb21.pdf PDF
B.07.406 Site Visit Sign In 22Feb21.pdf PDF
Pre-Bid Slides - F-35 406.pptx PPTX presentation
406 Site Visit Sign In.pdf PDF
ATTACHMENT 2-Truax F-35 B406 XGFG182008 Specs Vol 2 of 2 Dated 31 July 2020.pdf PDF
ATTACHMENT 3-Truax F35 B406 XGFG182008 Plans Dated 31 July 2020.pdf PDF
ATTACHMENT 7-Justification and Approval Best Lock.pdf PDF
ATTACHMENT 4-Justification and Approval Advantor.pdf PDF
W50S9F-21-B-0001.pdf PDF
ATTACHMENT 6-Justification and Approval Monaco.pdf PDF
ATTACHMENT 8-406 Submittal Log.xlsx XLSX spreadsheet
ATTACHMENT 9-SFS Form 12.xls XLS spreadsheet
ATTACHMENT 10-PRE-BID CONFERENCE AND SITE VISIT INSTRUCTIONS.pdf PDF
Show all 50

F-35 Alter Hangar 406 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRUAX FIELD ANGB - F-35: ALTER BLDG 406 Addendum 2

XGFG182008 03 MAR 2021

SECTION 01 78 00

CLOSEOUT SUBMITTALS

05/19

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 As-Built Drawings

As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site. These files serve as the basis for the creation of the record drawings.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Warranty Management Plan

Spare Parts Data

SD-08 Manufacturer's Instructions

Posted Instructions

SD-10 Operation and Maintenance Data

Operation and Maintenance Manuals; G

SD-11 Closeout Submittals

As-Built Drawings; G

As-Built Record of Equipment and Materials

Certification of EPA Designated Items; G

1.3 SPARE PARTS DATA

Submit electronic copies of the Spare Parts Data list.

a. Indicate manufacturer's name, part number, and stock level required for

SECTION 01 78 00 Page 1 test and balance, pre-commissioning, maintenance and repair activities. List those items that may be standard to the normal maintenance of the system.

1.4 WARRANTY MANAGEMENT

1.4.1 Warranty Management Plan

Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Submit warranty information, made available during the construction phase, to the Contracting Officer for approval prior to each monthly pay estimate.

Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a joint 4 month and 9 month warranty inspection, measured from time of acceptance; with the Contractor, Contracting Officer and the Customer Representative. The warranty management plan must include, but is not limited to, the following:

a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.

b. For each warranty, the name, address, telephone number, and e-mail of each of the guarantor's representatives nearest to the project location.

c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.

d. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:

(1) Name of item.

(2) Model and serial numbers.

(3) Location where installed.

(4) Name and phone numbers of manufacturers or suppliers.

(5) Names, addresses and telephone numbers of sources of spare parts.

(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.

(7) Cross-reference to warranty certificates as applicable.

(8) Starting point and duration of warranty period.

(9) Summary of maintenance procedures required to continue the warranty in force.

(10) Cross-reference to specific pertinent Operation and Maintenance manuals.

(11) Organization, names and phone numbers of persons to call for

SECTION 01 78 00 Page 2 warranty service.

(12) Typical response time and repair time expected for various warranted equipment.

e. The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.

f. Procedure and status of tagging of equipment covered by warranties longer than one year.

g. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.

1.4.2 Performance Bond

The Performance Bond must remain effective throughout the construction and warranty period .

a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.

c. Following oral or written notification of required construction warranty repair work, respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

1.4.3 Pre-Warranty Conference

Prior to contract completion, and at a time designated by the Contracting Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. At this meeting, establish and review communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contact must be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other portions of this provision.

SECTION 01 78 00 Page 3

PART 2 PRODUCTS

2.1 CERTIFICATION OF EPA DESIGNATED ITEMS

Submit the Certification of EPA Designated Items as required by FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items and FAR 52-223-17 Affirmative Procurement of EPA designated items in Service and Construction Contracts.. Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and certification.

The certification will read as follows and be signed and dated by the Contractor.

Record each product used in the project that has a requirement or option of containing recycled content in accordance with SECTION 01 33 29 SUSTAINABILITY REPORTING, noting total price, total value of post-industrial recycled content, total value of post-consumer recycled content, exemptions (1, 2, 3, or 4, as indicated), and comments. Recycled content values may be determined by weight or volume percent, but must be consistent throughout.

PART 3 EXECUTION

3.1 AS-BUILT DRAWINGS

Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files.

Submit As-Built Drawings in PDF format 30 days prior to Beneficial Occupancy Date (BOD).

3.1.1 Markup Guidelines

Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.

Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:

a. Use base colors of red, green, and blue. Color code for changes as follows:

(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.

(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.

(3) Additions (Green) - Added items, lettering in notes and leaders.

b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.

c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.

d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.

SECTION 01 78 00 Page 4

691jjb Highlight

e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.

f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.

g. For deletions, cross out all features, data and captions that relate to that revision.

h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.

i. Indicate one of the following when attaching a print or sketch to a markup print:

1) Add an entire drawing to contract drawings

2) Change the contract drawing to show

3) Provided for reference only to further detail the initial design.

j. Incorporate all shop and fabrication drawings into the markup drawings.

3.1.2 As-Built Drawings Content

Show on the as-built drawings, but not limited to, the following information:

a. The actual location, kinds and sizes of all sub-surface utility lines.

In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.

b. The location and dimensions of any changes within the building structure.

c. Layout and schematic drawings of electrical circuits and piping.

d. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.

e. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.

f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.

SECTION 01 78 00 Page 5

g. Changes or Revisions which result from the final inspection.

h. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.

i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.

j. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.

k. Changes in location of equipment and architectural features.

l. Modifications.

m. Actual location of anchors, construction and control joints, etc., in concrete.

n. Unusual or uncharted obstructions that are encountered in the contract work area during construction.

o. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.

3.2 OPERATION AND MAINTENANCE MANUALS

Provide project operation and maintenance manuals as specified in Section 01 78 23 OPERATION AND MAINTENANCE MANUALS DATA. Provide electronic copies of the Operation and Maintenance Manual files. Submit to the Contracting Officer for approval within 14 calendar days of the Beneficial Occupancy Date (BOD). Update and resubmit files for final approval at BOD.

3.3 CLEANUP

Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances;

polish transparent and glossy surfaces; vacuum carpeted and soft surfaces.

Clean equipment and fixtures to a sanitary condition. Replace filters of operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas.

Remove waste and surplus materials, rubbish and construction facilities from the site..

-- End of Section --