AD101_Add02.pdf
PDF 1 MB Posted
- Attached to
- F-35 Alter Hangar 406 Federal contract opportunity
- Solicitation number
- W50S9F-21-B-0001
- Issued by
- Department of the Army National Guard
About this file
This document provides details for an invitation for bid for alteration services at an F-35 aircraft hangar. Work includes demolishing 19,913 square feet of hangar shop space and modifying 19,803 square feet of hangar space to accommodate F-35 aircraft. Demolition and new construction services are required, along with mechanical, plumbing, electrical, technology, communications, and security systems installation. Strict adherence to construction plans and specifications is necessary to ensure F-35 requirements are met. Asbestos removal and options for additional work are also included. Interested contractors must register in SAM and attend a mandatory pre-bid conference on February 16, 2021. Bids are due on March 8, 2021 and award will be made to the responsive and responsible lowest bidder. The contract duration is 365 days with a budget between $10-25 million. The solicitation and specifications are available at beta.SAM.gov.
View the file
Other files for this federal contract opportunity
Show all 50
F-35 Alter Hangar 406 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REF. REF.
UP
DEMOLITION PLAN GENERAL NOTES:
1. THE GENERAL CONTRACTOR SHALL VERIFY ALL BUILDING AND SITE
CONDITIONS AND REPORT ANY DISCREPANCIES TO THE COR
BEFORE PROCEEDING WITH ANY SCHEDULED DEMOLITION WORK.
2. THE GENERAL CONTRACTOR SHALL COORDINATE ARCHITECTURAL,
STRUCTURAL, CIVIL, MECHANICAL, ELECTRICAL, TECHNOLOGY, AND
PLUMBING WORK AND ALL SUBCONTRACTORS FOR DEMOLITION AND
REPAIR WORK.
3. IT IS THE INTENT OF THESE DRAWINGS TO INDICATE THE REMOVAL OF ALL
ITEMS WHICH INTERFERE WITH THE FINAL CONSTRUCTION AS SHOWN ON
THE FLOOR PLANS, ELEVATIONS, DETAILS, AND SCHEDULES. ALL FLOOR
FINISHES, BASE, ACOUSTICAL CEILINGS, ABANDONED FURNITURE, WINDOW
TREATMENTS,SHELVING, SIGNAGE, AND ROOFING MATERIALS SHALL BE
DEMOLISHED IN THEIR ENTIRETY.
4. REMOVE ALL ITEMS OF DEMOLITION WORK FROM THE PROJECT DAILY AND
DISPOSE OF PROPERLY.
5. EXISTING CONCRETE AND STEEL STRUCTURE TO REMAIN, TYP. PROTECT
COLUMNS, PILASTERS, BEAMS, AND SLABS.
6. THE EXISTING MECHANICAL, ELECTRICAL,TECHNOLOGY, AND PLUMBING
ITEMS AND/OR SYSTEMS, AND GAS, WATER AND ELECTRICAL METERS ARE
GENERALLY INTENDED TO REMAIN. WHERE WORK CONFLICTS WITH NEW
WORK, DEMOLITION OR REROUTING OF EXISTING INFRASTRUCTURE SHALL
BE REQUIRED. REF: MEP FOR ALL ITEMS TO BE REUSED TYP. ALL ITEMS TO
BE DEMOLISHED SHALL BE REMOVED IN THEIR ENTIRETY, BACK TO THE
ORIGINAL SOURCE. SURROUNDING MATERIALS WHICH ARE DISTURBED OR
DEMOLISHED THAT ARE SCHEDULED TO REMAIN SHALL BE PATCHED WITH
LIKE SURROUNDING MATERIALS, TYPICAL.
7. DEMOLISH CONCRETE FLOOR SLABS AS REQUIRED TO INSTALL NEW
EQUIPMENT, UNDERGROUND CONDUIT, PLUMBING SYSTEMS, AND FLOOR
DRAINS, REF: STRUCTURAL, EQUIPMENT, ELECTRICAL, PLUMBING
DEMOLITION, AND PLUMBING DRAWINGS.
8. PROTECT EXISTING SURFACES TO REMAIN DURING DEMOLITION AND
CONSTRUCTION.
9. REPAIR OR REPLACE ANY EXISTING CONSTRUCTION (WINDOWS, WALLS,
DOORS, CEILINGS, FLOORS, ETC.) TO REMAIN WHICH ARE DAMAGED DURING
CONSTRUCTION. REPLACEMENT MATERIAL SHALL MATCH IN KIND.
10. ASBESTOS ABATEMENT LOCATIONS ARE PRESENTED ON AD-101 AS A
CONVENIENCE TO CONTRACTOR. CONTRACTOR REMAINS RESPONSIBLE FOR
ABATEMENT OF MATERIALS PRESENTED IN THE REPORT. THE REPORT STATES
THERE COULD BE OTHER HAZMAT IN AREAS THAT WERE INACCESSIBLE FOR
INVESTIGATION. IF OTHER LOCATIONS NOT INCLUDED IN THE REPORT ARE
FOUND, REPORT THE FINDINGS TO THE CONTRACTING OFFICER.
11. GENERAL CONTRACTOR TO REMOVE ALL EXISTING EQUIPMENT, FURNITURE,
ETC. MADE ABOSLETE OR NO LONGER WANTED BY THE GOVERNMENT.
VERIFY WITH GOVERNMENT BEFORE SALVAGING OR DISPOSING OF EXISTING
EQUIPMENT, FURNITURE, ETC.
A
B
C
D
E
F
G
DP
R0 R2 R4 R6 R8 10 L8 L6 L4 L2 L0 LDPR1 R3 R5 R7 R9 L9 L7 L5 L3 L1
4.0014.001
4.011
4.010
4.012
4.006
OPERATION
DEBRIEF
ROOM
MECHANICAL
LOCKER
4.008
4.008
4.011
4.010
4.002
4.013
4.013
4.001
4.014 4.014 4.014 4.014 4.014
4.0104.010
4.008
4.001
4.0094.009 4.009
4.009
4.001
4.008
4.009
4.013
4.003
4.003
4.003
4.001
4.001
4.001
4.001
4.010 4.001
4.014
4.001
4.007
4.001
4.002
4.002
4.002
4.010
4.001
4.010
4.010
4.001
4.0044.004
4.001
4.0054.005
4.001 4.0104.001
TYP
4.001
4.001
4.001
4.001
4.001
4.001
4.010
4.001
4.007
4.009
4.0094.009
4.0104.010
TYP
TYPTYP
TYP
TYP
TYP
TYP
4.018
4.019
4.020 4.0204.0204.020
4.020
4.001 4.0184.001
4.018 4.018
4.018 4.008
4.018
4.022
4.018
4.008
4.018
4.018
4.001
4.011
4.008
4.008
4.018
4.001
4.011
4.011
4.001 4.0014.011
4.023
003001
003 003 001
006006
DEMOLITION LEGEND:
EXISTING CONSTRUCTION TO REMAIN
EXISTING CONSTRUCTION TO BE DEMOLISHED, TYP
(U.N.O.)
EXISTING DOOR TO REMAIN
DOOR, FRAME, AND HARDWARE TO BE
DEMOLISHED COMPLETELY, TYP (U.N.O.)
xxx
ASBESTOS ABATEMENT REPORT MATERIAL
CODE
SHEET NO.:
SHEET CONTENTS
DO NOT SCALE DRAWINGS
M&H NO.:
DATE:
DESIGNED BY:
DRAWN BY:
CHECKED BY:
ISSUED
© Copyright This document, or any portion thereof, shall not be duplicated, disclosed, or used on any other project or extension of this project except by written agreement with Mead & Hunt, Inc. Mead & Hunt shall not be responsible for any unauthorized use of, or alteration to these documents.
Mead & Hunt, Inc.
2440 Deming Way
Middleton, WI 53562 phone: 608-273-6380 meadhunt.com
/3
/2
:0
:1
P M
C R e v it L o c a l\
-1
.0
-A
-C e n tr a l-p jc
.r v t
T R
U A
X F
IE
L D
A N
G B
M A
D
IS
O N
W
I
F -3
A L T
E R
B U
IL
D
IN
G
AD101
FIRST FLOOR
DEMOLITION PLAN
XGFG182008ANG NO.:
3141300-190289.01
BAE
SZK
July 31, 2020
PJC
KEYED NOTES
4.012 REMOVE GYPSUM BOARD AND FURRING.
4.013 DEMO FLOOR IN AREAS TO RECEIVE NEW PLUMBING. SEE PLUMBING
PLANS.
4.014 DEMO EXISTING DOOR RAMPS.
4.018 REMOVE 8" CMU AND PRECAST SILL.
4.019 DEMOLISH AND REMOVE SHELTER AND CANOPY IN ITS ENTIRETY,
CONCRETE PAD TO REMAIN.
4.020 DEMO FLOORS FOR NEW WORK (SEE STRUCTURAL).
4.022 REMOVE CONCRETE LOWER LINTEL AND 12" CMU ABOVE
4.023 EXISTING OVERHEAD BRIDGE CRANE TO REMAIN.
KEYED NOTES
4.001 REMOVE PORTION OF WALL FOR NEW DOOR OR WINDOW OPENING,
COORDINATE WITH FLOOR PLAN FOR NEW OPENING REQUIREMENTS,
LOCATION AND SIZE. COORDINATE WITH STRUCTURAL SHEET S-221 FOR
ADDITIONAL WALL REMOVAL PER MASONRY WALL ELEVATIONS.
4.002 REMOVE COUNTERTOP, CASE WORK AND SINK. SEE PLUMBING FOR
CAPPING OR DEMOLITION OF PIPING.
4.003 REMOVE EXISTING PLUMBING FIXTURES. COMPLETELY CAP DEMOLISHED
PIPING. REF - PLUMBING, TYPICAL.
4.005 REMOVE STORAGE AND MEZZANINE AREA AND RELATED COMPONENTS
COMPLETE. FINAL DISPOSITION TO GOVERNMENT.
4.006 REMOVE AND SALVAGE LOCKERS AND TURN OVER TO GOVERNMENT.
4.007 ALTER PORTION OF CROSS BRACING. REF - STRUCTURAL.
4.008 REMOVE WINDOW, FRAME AND FLASHING, COMPLETE.
4.009 REMOVE EXISTING DOOR, FRAME, AND HARDWARE FOR REPLACEMENT IN
SAME LOCATION.
4.010 REMOVE EXISTING EIFS AND INSULATION BACK TO EXISTING CMU
STRUCTURE AROUND ENTIRE PERIMETER OF HANGAR. PREP AND PREPARE
SURFACE FOR NEW EIFS AND SPLIT BLOCK SIDING INSTALLATION.
4.011 REMOVE SCUPPER BOX AND DOWNSPOUT.
PLAN
NORTH
TRUE
NORTH
1/8" = 1'-0"1
DEMOLITION FLOOR PLANEXTERIOR CANOPY IMAGES
MEZZANINE IMAGES
07/31/20 TYPE B3 FINAL
2 03/03/21 ADDENDUM - 02
Hazardous Material Abatement Requirements Note: Material Code in parentheses after the note corresponds to Asbestos and Lead Pre-Renovation Inspection report by Environmental Management Consulting, Inc, October 8, 2019.
001 Existing door assumed to have asbestos containing material. Remove and dispose of in accordance with ACM abatement requirements. (MFD)
002 Abate Black and Yellow Carpet adhesive in room for asbestos containing material. (MCMLK)
003 Abate Gray and White Floor Tile and adhesive in room for asbestos containing material. (MF12YW)
004 Flooring may extend under gypsum and stud partition walls.
005 Abate Brown and Tan Floor Tile and adhesive (including door step) for asbestos containing material. (MF12NT)
006 Abate wall paneling black adhesive for asbestos containing materials.
Material is on back side of the wall paneling and furring strips in noted locations. The adhesive is adhered to various substrates including wood studs, drywall and concrete block, depending on the wall. (MPM(1))
007 Abate black adhesive on blue foam rigid insulation for asbestos containing material. Adhesive applied to exterior walls of rooms noted. (MPM(2))
008 Abate lead-based paint (cream colored paint) on CMU walls in room.
009 Abate lead-based paint (lime colored paint) on CMU walls in room.
010 Abate lead-based paint (White/green colored paint) on CMU walls in hangar bay.
011 Abate lead-based paint in maroon/gray floor striping on floor in hangar bay.
012 Abate lead-based paint (white paint) on metal door frame.
013 Abate lead-based paint (beige/green colored paint) on CMU walls in room.
014 Abate lead-based paint (red colored paint) on CMU walls in room.
| Sheets |
| AD101 - FIRST FLOOR DEMOLITION PLAN |
File details come from the government source that posted it. Updated .