This is a Specification document (Section 01 30 00 Administrative Requirements and Section 01 45 00 Quality Control) for JFY 2022 Project J-875, the Battle Staff Training Facility at U.S. Naval Base Camp Blaz, Guam, a design-bid-build construction project involving a two-story reinforced concrete facility with mechanical, electrical, and emergency power systems designed to meet seismic and environmental criteria for Guam.
The specifications establish comprehensive administrative and quality control requirements for the contractor. Key administrative requirements include: mobilization within 30 calendar days after GEPA NPDES permit issuance; a Workforce Housing Logistics and Material Management Plan addressing medical, housing, food, material management, safety, and transportation for temporary resident workers; a project superintendent with minimum 10 years construction experience and 5 years as superintendent on similar projects; mandatory formal partnering sessions within 45 days of notice to proceed with third-party independent facilitators at contractor expense; preconstruction meetings within 35 calendar days of notice to proceed; monthly Building Information Modeling coordination meetings; and facility turnover planning meetings ("Red Zone Meetings") beginning at 75 percent project completion. The contractor must maintain appropriate insurance per FAR 28.307-2 and comply with Guam law, including workers' compensation waiver provisions for non-U.S. residents.
Quality control requirements mandate establishment of a Contractor Quality Control Program with a Quality Control Manager possessing a Bachelor's degree in engineering or architecture, current professional engineer registration, and minimum 10 years construction experience with 2 years as QC Manager, plus completion of CQM for Contractors course certification within 90 days of award. The QC Manager must maintain physical presence on-site at all times and implement three phases of control (Preparatory, Initial, and Follow-up) for each Definable Feature of Work. Specific QC specialists are required for concrete inspection (ACI-certified), exterior finish systems, fireproofing, elevators, mechanical systems, electrical systems, telecommunications, and landscape work. A Fire Protection Quality Control Specialist with Fire Protection Engineering P.E. licensure and 5 years experience is mandatory. Testing laboratories must be accredited per ASTM standards (ASTM E329, C1077, D3666, D3740, E543). Daily Contractor Quality Control Reports and monthly testing summaries must be submitted to the Contracting Officer, along with monthly BIM model submissions meeting USACE Minimum Modeling Matrix requirements. Completion inspections include punch-out, pre-final, and final acceptance inspections with Government participation. All deficiencies must be corrected and concurred by the Contracting Officer prior to final acceptance.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JFY 2022 PROJECT J-875, BATTLE STAFF TRAINING FACILITY
U.S. NAVSUPPACT MCB CAMP BLAZ, GUAM
1696746
PROJECT TABLE OF CONTENTS Page 1
(04/27/26)
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24, CHG 1: 05/25 SUMMARY OF WORK
01 14 00 11/22, CHG 5: 05/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 05/25 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21, CHG 1: 08/25 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 13.02 34 01/25 FACILITY-RELATED CONTROL SYSTEMS
(FRCS) PROCUREMENT FOR NAVY
01 35 26 05/24, CHG 1: 05/25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 3: 08/25 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22, CHG 2: 08/25 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 12/23 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL
CONTROLS MCBCB EV
01 57 19.03 21 07/31/25 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL
CONTROL Secretary of the Navy (SECNAV) Explosive Safety Risk Acceptance Within Joint Region Marianas
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23, CHG 2: 11/25 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 56 13.16 02/25 CLAY WASTE CONTAINMENT
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
BELOW GRADE CONSTRUCTION
DIVISION 04 – MASONRY
04 20 00 05/25 UNIT MASONRY
1696746
PROJECT TABLE OF CONTENTS Page 2
DIVISION 05 - METALS
05 05 20 05/22, CHG 1: 08/24 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS
05 51 33 08/24 METAL LADDERS
05 52 00 08/23 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 08/24 FINISH CARPENTRY
06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 53 08/25 ELASTOMERIC SHEET WATERPROOFING
07 21 13 08/23, CHG 1: 08/25 BOARD AND BLOCK INSULATION
07 21 16 08/23, CHG 1: 08/25 MINERAL FIBER BLANKET INSULATION
07 24 00 08/23 EXTERIOR INSULATION AND FINISH SYSTEMS
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 56 00 08/09 FLUID-APPLIED ROOFING SYSTEM
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20, CHG 1: 08/25 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS, FRAMES, AND WINDOW WALL
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS
08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 22 00 08/24 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/24, CHG 1: 05/25 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 11/24 RESILIENT FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 68 00 11/24 CARPETING
09 69 13 11/24 RIGID GRID ACCESS FLOORING
09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
1696746
PROJECT TABLE OF CONTENTS Page 3
10 21 13 08/20 TOILET COMPARTMENTS
10 22 13 08/24 WIRE MESH PARTITIONS
10 22 39 08/20 FOLDING PANEL PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 99 00 04/06 MISCELLANEOUS BUILDING SPECIALTIES
DIVISION 12 - FURNISHINGS
12 00 01.00
12 24 13
20 02/23
08/20
FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
ROLLER WINDOW SHADES
12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES
12 93 00 08/17, CHG 1: 08/18 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 05/25 SEISMIC CONTROL FOR NONSTRUCTURAL
COMPONENTS
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 05/16 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 05/24, CHG 1: 11/24 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 02/25 SEISMIC BRACING FOR MECHANICAL SYSTEMS
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL AND
PLUMBING SYSTEMS
23 09 00 08/24, CHG 1: 08/25 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 08/24 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 64 10 05/25 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 11/25 CHILLED, CHILLED-HOT, AND CONDENSER
WATER PIPING SYSTEMS
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 08/24 CYBERSECURITY FOR FACILITY-RELATED
1696746
PROJECT TABLE OF CONTENTS Page 4
CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 08 11.00 20 11/20 RISK MANAGEMENT FRAMEWORK FOR
FACILITY-RELATED CONTROL SYSTEMS
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 20 00 05/25, CHG 1: 08/25 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15 05/24 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 05/25 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 41 00 11/21 AUDIO-VISUAL SYSTEMS
27 51 16 05/20, CHG 1: 05/22 PUBLIC ADDRESS SYSTEMS
27 51 20 10/22 TWO-WAY COMMUNICATION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
31 31 16.19 08/22 TERMITE CONTROL BARRIERS
31 62 00 03/24 CEMENT DEEP SOIL MIXING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 CHG 1: 11/24 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
1696746
PROJECT TABLE OF CONTENTS Page 5
32 11 20 05/22 BASE COURSE FOR RIGID PAVING
32 11 23 05/22 GRADED CRUSHED AGGREGATE BASE COURSE
FOR FLEXIBLE PAVING
32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23.16 11/24 ROAD AND PARKING LOT PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK AND
ORNAMENTAL) AND GATES
32 84 24 08/11, CHG 1: 05/17 TEMPORARY IRRIGATION SPRINKLER SYSTEMS
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 52 40 05/25 FUEL SYSTEMS PIPING (NON-HYDRANT)
33 56 10 05/25 FACTORY-FABRICATED FUEL STORAGE TANKS
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
JFY 2022 PROJECT J-875, BATTLE STAFF TRAINING FACILITY 1696746
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
11/20, CHG 5: 02/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map
Progress and Completion Pictures
1.3 CONTRACTOR WORKFORCE HOUSING LOGISTICS AND MATERIAL MANAGEMENT
REQUIREMENTS
a. For the purposes of this specification, the term, "temporary resident worker" means all workers except the following:
(1) Permanent residents of Guam
(2) Managers and supervisors (U.S. citizens or resident aliens)
b. For the purpose of this specification, the term, "worksites" means locations at Finegayan, Naval Base, and Andersen Air Force Base.
c. For the purpose of this specification, the term, "peak hours" for traffic means 6:30 a.m. to 8:30 a.m. and 3:30 p.m. to 6:00 p.m.
d. Workforce Housing Logistics and Material Management (WHL&MM) Plan: The WHL&MM Plan shall address the requirements for Medical, Housing, Food, Material Management, Safety & Security, and Transportation set forth in this specification section. Approval of the WHL&MM Plan is required prior to the start of construction. The Contracting Officer reserves the right to require changes in the WHL&MM Plan and operations as necessary. Maintain the WHL&MM Plan and submit any changes for Contracting Officer review.
SECTION 01 30 00 Page 1
1.3.1 Medical
Assure that staffing, personnel assignment and other human resources practices result in development and maintenance of a healthy Contractor and Subcontractor workforce employed in the performance of this contract in accordance with all statutes and regulations of the U.S Federal Government or the GovGuam in effect on the date of award of this contract or thereafter promulgated by the aforementioned governmental authorities.
Perform health care activities in accordance with 10 G.C.A. §§ 84 - 96 - Guam Public Health Act, 25 G.A.R. § 6 - Guam Board of Nurse Examiners, 25 G.A.R. § 11 - Guam Board of Medical Examiners, 26 G.A.R. §§ 4401, et seq., Health Certificate Regulations, and 26 G.A.R. §§ 6200, et seq., Ambulance and Emergency Medical Technician.
1.3.1.1 Medical Quality Control Manager (MQCM)
Medical QC Manager qualifications:
A licensed physician from a state or territory in the U.S. with either an Internal Medicine or Family Practic background or credentials. Also have occupational health or public health experience. Submit a copy of the medical license to the Contracting Officer for approval.
1.4 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.5 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.
Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.
Include a date designator in file names. Photographs provided are for unrestricted use by the Government.
1.6 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by Guam law.
1.7 SUPERVISION
1.7.1 Superintendent Qualifications
Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on
SECTION 01 30 00 Page 2 projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.7.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.
1.7.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.7.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time or excess costs or damages by the Contractor.
1.8 CYBERSECURITY OF CONTROL SYSTEMS
Discuss Cybersecurity of building control system requirements and submittals as required for Section 25 05 11 CYBERSECURITY FOR
FACILITY-RELATED CONTROL SYSTEMS.
1.9 CANTONMENT COORDINATION MEETINGS WITH OTHER PRIME CONTRACTORS
All Prime Contractors executing Government contract construction efforts within the Camp Blaz cantonment area will ensure that they have appropriate representation at coordination meetings facilitated by the Government every two weeks. Where the level of activity dictates, the Contracting Officer may adjust the frequency of the meeting.
1.10 PRECONSTRUCTION MEETING CONFERENCE
Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after notice to proceed , but prior to commencement of any work at the
SECTION 01 30 00 Page 3 site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.
1.10.1 Attendees
Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.
1.11 MONTHLY BIM COORDINATION MEETING
The Contractor shall participate in monthly coordination meetings with the Contracting Officer and other Government representatives, as applicable.
The Contractor shall be responsible for preparing the agenda in coordination with the Contracting Officer, distributing the agenda, conducting the meeting, preparing the meeting minutes, distributing the minutes, and tracking action items. The Contractor’s superintendent, project manager, and QC Manager shall attend each meeting. A “virtual walk through” of the model shall be performed demonstrating model development progress and likeness to the actual field conditions. Typical topics shall consist of, but be limited to, the following: review of the previous month’s modeling efforts & progress; forecast of the following month’s modeling efforts & progress; concerns, and/or issues.
1.12 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:
1.12.1 Red Zone Checklist
a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.
b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.
1.12.2 Meetings
a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will establish the frequency of the meetings, SECTION 01 30 00 Page 4 which is expected to increase as the project completion draws nearer.
At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.
c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.
e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.
Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.
1.13 WAIVER FOR WORKER'S COMPENSATION
In addition to FAR 52.228-4 Workers' Compensation and War-Hazard Insurance Overseas, the Secretary of Labor has granted a waiver. The waiver does not apply to employees who are hired in the United States, or who are residents, or citizens of the United States.
1.14 PARTNERING
To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record (DOR) (regardless of whether the contract is a design-build or a design-bid-build) are required to participate in the Partnering process.
1.14.1 Facilitated (Formal) Partnering
a. Within 45 calendar days after notice to proceed and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.
b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering .
c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.
Partnering session may take place concurrently with the
SECTION 01 30 00 Page 5
Pre-Construction Post-Award Kickoff Meeting.
d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant
- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.
e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.
f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.
Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.
1.15 MOBILIZATION
Mobilize to the jobsite within 30 calendar days after GEPA NPDES Permit is obtained. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 30 00 Page 6
SECTION 01 45 00
QUALITY CONTROL
08/23, CHG 3: 08/25
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C1077 (2025a) Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
ASTM D3666 (2016) Standard Specification for Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials
ASTM D3740 (2019) Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM E90 (2023) Standard Test Method for Laboratory Measurement of Airborne Sound Transmission Loss of Building Partitions and Elements
ASTM E329 (2025a) Standard Specification for Agencies Engaged in Construction Inspection, Testing, or Special Inspection
ASTM E543 (2021) Standard Specification for Agencies Performing Non-Destructive Testing
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Occupational Health (SOH) Requirements
1.2 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Pricing Schedule item.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES.
SECTION 01 45 00 Page 1
SD-01 Preconstruction Submittals
Contractor Quality Control (CQC) Plan ; G
SD-06 Test Reports
Verification Statement
SD-07 Certificates
Certificate Of Readiness ; G
1.4 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product that complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and must be keyed to the proposed design and construction sequence. The Quality Control Manager, Superintendent, Site Safety and Health Officer (SSHO), and all on-site supervisors are responsible for the quality of work and are subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the Contract. The Quality Control Manager must maintain a physical presence at the work site at all times and is the primary individual responsible for all quality control.
1.5 QUALITY CONTROL (QC) PROGRAM REQUIREMENTS
Establish and maintain a QC program as described in this section. This QC program is a key element in meeting the objectives of the Commissioning Process (Cx). The QC program consists of a QC Organization, QC Plan, QC Plan Meeting(s), a Coordination and Mutual Understanding Meeting, QC meetings, three phases of control, submittal review and approval, testing, completion inspections, QC certifications, independent Special Inspections in accordance with Section 01 45 35 SPECIAL INSPECTIONS, and documentation necessary to provide materials, equipment, workmanship, fabrication, construction and operations that comply with the requirements of this Contract. The QC program must cover on-site and off-site work and be keyed to the work sequence. No construction work or testing may be performed unless the QC Manager is on the work site. The QC Manager must report to an officer of the firm and not be subordinate to the Project Superintendent or the Project Manager. The QC Manager, Project Superintendent and Project Manager must work together effectively.
Although the QC Manager is the primary individual responsible for quality control, all individuals will be held responsible for the quality of work on the job.
1.5.1 Meetings
1.5.1.1 Quality Control Plan Meeting
Prior to submission of the QC Plan, the Contractor may request a meeting with the Contracting Officer to discuss the QC Plan requirements of this Contract.
The purpose of this meeting is to develop a mutual understanding of the QC Plan requirements prior to plan development and submission and to agree on the Contractor's list of Definable Feature of Work (DFOW).
SECTION 01 45 00 Page 2
1.5.1.2 Coordination and Mutual Understanding Meeting
After the Preconstruction Conference, Post Award Conference, before start of design or construction, and prior to acceptance by the Government of the CQC Plan, meet with the Contracting Officer and discuss the Contractor's quality control system. During the meeting, a mutual understanding of the system details must be developed, including the forms for recording the CQC operations, design activities, control activities, testing, administration of the system for both onsite and offsite work, and the interrelationship of Contractor's Management and control with the Government's Quality Assurance. Minutes of the meeting will be prepared by the QC Manager and signed by the Contractor , the Architect/Engineer (A/E), and the Government. Provide a copy of the signed minutes to all attendees and incorporate into the relevant QC Plan. At a minimum the Coordination and Mutual Understanding Meeting must be repeated when a new QC Manager is appointed. There can be other occasions when subsequent conferences will be called by either party to reconfirm mutual understandings or address deficiencies in the CQC system or procedures which can require corrective action by the Contractor.
1.5.1.2.1 Purpose
The purpose of this meeting is to develop a mutual understanding of the QC details, including documentation, administration for on-site and off-site work, design intent, Cx in accordance with Section 01 91 00.15 BUILDING COMMISSIONING, environmental requirements and procedures, coordination of activities to be performed, Special Inspections, and the coordination of the Contractor's management, production, and QC personnel. At the meeting, the Contractor must explain in detail how three phases of control will be implemented for each DFOW, as well as how each DFOW will be affected by each management plan or requirement as listed below:
a. Waste Management Plan.
b. Procedures for noise and acoustics management.
c. Environmental Protection Plan.
d. Environmental regulatory requirements.
e. Cx Plan requirements in accordance with Section 01 91 00.15 BUILDING
COMMISSIONING.
f. Special Inspections.
g. Indoor Air Quality (IAQ) Management Plan.
1.5.1.2.2 Coordination of Activities
Coordinate activities included in various sections to assure efficient and orderly installation of each component. Coordinate operations included under different sections that are dependent on each other for proper installation and operation. Schedule construction operations with consideration for indoor air quality as specified in the IAQ Management Plan. Coordinate Special Inspections.
SECTION 01 45 00 Page 3
1.5.1.2.3 Attendees
As a minimum, the Contractor's personnel required to attend include an officer of the firm, the Project Manager, Project Superintendent, QC Manager, Alternate QC Manager, QC Specialists, Special Inspector of Record, Commissioning Provider (CxC), Environmental Manager, and subcontractor representatives. Each subcontractor who will be assigned QC responsibilities must have a principal of the firm at the meeting.
1.5.1.3 Quality Control (QC) Meetings
After the start of construction, conduct weekly QC meetings led by the QC Manager at the work site with the Project Superintendent, the QC Specialists, the Special Inspector of Record, CxC, and the other personnel as necessary. The QC Manager is to prepare the minutes of the meeting and provide a copy to the Contracting Officer within 2 working days after the meeting. The Contracting Officer may attend these meetings. As a minimum, accomplish the following at each meeting:
a. Review the minutes of the previous meeting.
b. Review the schedule and the status of work and deficiencies/rework.
Review the most current approved schedule (in accordance with schedule specification) and the status of work and deficiencies/rework.
c. Review the status of submittals and Request For Information (RFIs).
d. Review the work to be accomplished in the next 3 weeks as defined by the schedule section paragraph WEEKLY LOOK AHEAD in Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS) and all quality control documentation required for that work.
e. Review Testing Plan and Log including status of tests performed since last QC Meeting.
f. Resolve QC and production problems. Discuss status of pending change orders.
g. Address items that may require revising the QC Plan.
h. Review Accident Prevention Plan (APP) and effectiveness of the safety program.
i. Review environmental requirements and procedures.
j. Review Environmental Management Plan.
k. Review Waste Management Plan.
l. Review the status of training completion.
m. Review Cx Plan and progress. Review Issues Log and resolution.
n. Review IAQ Management Plan.
SECTION 01 45 00 Page 4
1.5.2 Contractor Quality Control (CQC) Plan
Submit no later than 30 days after Contract Award , the CQC Plan proposed to implement the requirements FAR 52.246-12 Inspection of Construction.
Design and Construction will be permitted to begin only after acceptance of the CQC Plan and other Contract requirements Design work is not permitted to start prior to approval of a Design Quality Control Plan.
1.5.2.1 Content of Contractor Quality Control (CQC) Plan
Provide a CQC Plan, prior to start of construction that includes a table of contents, with major sections identified, pages numbered sequentially, and that documents the proposed methods and responsibilities for accomplishing quality control during the construction of the project. The CQC Plan must at a minimum include the following sections:
a. A description of the quality control organization and acknowledgment that the CQC staff will implement the three phase control system for all aspects of the work specified.
b. An organizational chart showing the quality control organization with individual names and job titles and lines of authority up to an executive of the company at the home office.
c. NAMES AND QUALIFICATIONS: Names and qualifications, in resume format, (including position titles and durations for qualifying experiences) for each person in the QC organization. Include the Construction Quality Management (CQM) for Contractors course certifications for the QC personnel as required by the paragraph CONSTRUCTION QUALITY
MANAGEMENT TRAINING.
d. DUTIES, RESPONSIBILITY AND AUTHORITY OF QC PERSONNEL: Duties, responsibilities, and authorities of each person in the QC organization.
e. OUTSIDE ORGANIZATIONS: A listing of outside organizations, such as architectural and consulting engineering firms, that will be employed by the Contractor and a description of the services these firms will provide.
f. APPOINTMENT LETTERS: Letters signed by an officer of the firm appointing the QC Manager and Alternate QC Manager, Design Quality Control Manager, CxC, and stating that they are responsible for implementing and managing the QC program as described in this Contract. Include in this letter the responsibility of the QC Manager and Alternate QC Manager to implement and manage the three phases of control, and their authority to stop work that is not in compliance with the Contract. Letters of direction are to be issued by the QC Manager to all other QC Specialists or quality control representatives outlining their duties, authorities, and responsibilities. Include copies of the letters in the QC Plan.
g. SUBMITTAL PROCEDURES AND INITIAL SUBMITTAL REGISTER: Procedures for reviewing, approving, scheduling, and managing submittals, including those of subcontractors, designers of record, consultants, architect-engineers (AE), offsite fabricators, suppliers, and purchasing agents. Provide the name(s) of the person(s) in the QC organization authorized to review and certify submittals prior to approval. Provide the initial submittal of the Submittal Register as
SECTION 01 45 00 Page 5 specified in Section 01 33 00 SUBMITTAL PROCEDURES.
h. TESTING LABORATORY INFORMATION: Testing laboratory information required by the paragraph ACCREDITATION REQUIREMENTS, as applicable.
i. TESTING PLAN AND LOG: A Testing Plan and Log that includes the tests required, associated feature of work required, referenced by the specification paragraph number requiring the test, the frequency, and the person responsible for each test.
j. Procedures to complete design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected. This phase is performed prior to beginning work on each definable feature of work, after all required plans, documents, materials are approved, and after copies are at the work site.
k. Reporting procedures, including proposed reporting formats.
l. Procedures for submitting and reviewing design changes/variations prior to submission to the Contracting Officer.
m. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task that is separate and distinct from other tasks and has control requirements and work crews unique to that task. A DFOW is identified by different trades or disciplines, or it is work by the same trade in a different environment. A DFOW is by definition any item or activity on the construction schedule, and the schedule specification provides direction regarding how the DFOWs are to be structured. Include in the list of DFOWs for all activities on the Construction Schedule.
Provide separate DFOWs in the Network Analysis Schedule for each design development stage and submittal package. Although each section of the specifications can generally be considered as a definable feature of work, there are frequently more than one definable features under a particular section. Identify the specification section number and schedule activity ID for each DFOW listed. The DFOW list will be reviewed in coordination with the construction schedule and agreed upon during the Coordination and Mutual Understanding Meeting.
n. PROCEDURES FOR PERFORMING AND TRACKING THE THREE PHASES OF CONTROL:
Identify procedures used to ensure the three phases of control to manage the quality on this project. For each Definable Feature of Work (DFOW), a Preparatory and Initial phase checklist will be filled out during the Preparatory and Initial phase meetings. Conduct the Preparatory and Initial Phases and meetings with a view towards obtaining quality construction by planning ahead and identifying potential problems for each DFOW.
o. Coordinate scheduled work with Special Inspections required by Section 01 45 35 SPECIAL INSPECTIONS, the Statement of Special Inspections and the Special Inspections Project Manual. Where the applicable code issued by the International Code Council (ICC) calls for inspections by the Building Official, the Contractor must include the inspections in the Quality Control Plan and must perform the inspections required by the applicable ICC. The Contractor must perform these inspections using independent qualified inspectors. Include the Special Inspections Project Manual requirements in the QC Plan.
p. PROCEDURES FOR COMPLETION INSPECTION: Procedures for identifying and
SECTION 01 45 00 Page 6 documenting the completion inspection process. Include in these procedures the responsible party for punch out inspection, pre-final inspection, and final acceptance inspection.
q. TRAINING PROCEDURES AND TRAINING LOG: Procedures for coordinating and documenting the training of personnel required by the Contract.
r. ORGANIZATION AND PERSONNEL CERTIFICATIONS LOG: Procedures for coordinating, tracking and documenting all certifications required for entities such as subcontractors, testing laboratories, suppliers, and personnel. The QC Manager will ensure that certifications are current, appropriate for the work being performed, and will not lapse during any period of the Contract that the work is being performed.
1.5.3 Preliminary Construction Work Authorized Prior to Acceptance
The only construction work that is authorized to proceed prior to the acceptance of the QC Plan is mobilization of storage and office trailers, temporary utilities, and surveying with specific prior approval of the Contracting Officer.
1.5.4 Notification of Changes
Notify the Contracting Officer, in writing, of any proposed changes in the QC Plan or changes to the QC organization personnel. Proposed changes are subject to acceptance by the Contracting Officer.
1.5.5 Special Inspections
Perform all required Special Inspections per Section 01 45 35 SPECIAL INSPECTIONS, the statement of Special Inspections and the Schedule of Special Inspections.
1.6 QUALITY CONTROL (QC) ORGANIZATION
1.6.1 Quality Control (QC) Manager
1.6.1.1 Duties
Provide a QC Manager at the work site to implement and manage the QC program The only duties and responsibilities of the QC Manager are to manage and implement the QC program on this Contract. The QC Manager must attend the partnering meetings, QC Plan Meetings, Coordination and Mutual Understanding Meeting, conduct the QC meetings, perform the three phases of control except for those phases of control designated to be performed by QC Specialists, perform submittal review and approval, ensure testing is performed and provide QC certifications and documentation required in this Contract. The QC Manager is responsible for managing and coordinating the three phases of control and documentation performed by the QC Specialists, testing laboratory personnel and any other inspection and testing personnel required by this Contract. The QC Manager is the manager of all QC activities. The QC manager is responsible for notifying the Special Inspector of activities which require their review. The QC manager is responsible for coordinating the Special Inspection activities, see paragraph CONTRACTOR'S QUALITY CONTROL (QC) MANAGER, in Section 01 45 35 SPECIAL INSPECTIONS. The QC manager is responsible for the quality control for Sound Rated perimeter construction.
SECTION 01 45 00 Page 7
1.6.1.2 Qualifications
The QC Manager must possess at least a Bachelor's degree in engineering, architecture, or construction management, with a current professional engineer registration and a minimum of 10 years construction experience as a Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. The individual must have at least 2 years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability.
The QC Manager and all members of the QC organization must be capable of reading, writing, and conversing fluently in the English language.
1.6.1.3 Construction Quality Management Training
In addition to the above experience and education requirements, the QC Manager Alternate QC Manager, Superintendent, QC Specialist, and DQCM must have completed the CQM for Contractors course. If the QC Manager does not have a current certification, obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Systems Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class.
The Construction Quality Management Training certificate expires after 5 years. If the QC Manager's certificate has expired, retake the course to remain current.
1.6.2 Organizational Changes
Maintain the QC staff with personnel as required by the specification section at all times. When it is necessary to make changes to the QC staff, revise the CQC Plan to reflect the changes and submit the changes to the Contracting Officer for acceptance.
1.6.3 Alternate Quality Control (QC) Manager Duties and Qualifications
Designate an alternate for the QC Manager at the work site to serve in the event of the designated QC Manager's absence. The period of absence may not exceed 2 weeks at one time, and not more than 30 workdays during a calendar year. The qualification requirements for the Alternate QC Manager must be the same as for the QC Manager.
1.6.4 Commissioning
Commissioning (Cx) is a systematic, quality-focused process for delivery of a project focusing on verifying and documenting all commissioned systems and assemblies are installed, tested, and operating as they were planned and designed to meet the project requirements. The Quality Control requirements outlined in this specification section are key in supporting the objectives of the Cx process, specifically coordinating testing, documenting, and verifying proper system operation. Properly executed the Quality Control support of Cx ensures timely execution of necessary tasks to deliver the fully commissioned and operating systems in coordination with the overall construction and project schedule.
SECTION 01 45 00 Page 8
Provide Cx in addition to the quality control requirements of this section and not as a substitute for quality control requirements. The QC Manager is responsible for carrying out the three phases of control while ensuring the functional performance and integrated systems tests are coordinated with the Cx provider as required for each system to be commissioned.
1.6.4.1 Certificate of Readiness
The QC Manager must issue a Certificate of Readiness for Government approval for each system to be commissioned. Schedule Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. The Certificate of Readiness certifies that all required inspections have been completed and deficiencies that were identified through any prior review, inspection, or test activity have been corrected before the start of Functional Performance Tests. Refer to Cx requirements in Section 01 91 00.15 BUILDING COMMISSIONING for a list of systems to be commissioned and detailed requirements for the Cx provider.
1.6.5 Quality Control (QC) Specialists
Provide a separate QC Specialist at the work site for each of the areas as listed in the Matrix listed below, who must assist and report to the QC Manager and who may perform production related duties but must be allowed sufficient time to perform their assigned quality control duties. These individuals or specialized technical companies are employees of the Prime or subcontractor including Designer of Record (DOR) . QC Specialists must be physically present at the work site with frequency as indicated in the Experience Matrix below, to participate in the QC Meetings, perform the three phases of control, including participation in Preparatory and Initial Phase meetings, and to perform and document Follow-up inspections as an extension of the QC Manager for each definable feature of work in their area of responsibility. QC Specialist must assist and be present for training events, and Critical System Acceptance inspections by the Government. Qualification, experience, Area of Responsibility, and frequency of QC surveillance are provided in Matrix listed herein.
Qualification/Experience In Area of Responsibility
Area of Responsibility Frequency
CQC personnel shall be certified by ACI as a Concrete Construction Special Inspector.
Inspection of Cast-in-Place Concrete operations. See Section 03 30 00 , 1.6.7.a.
Continuous.
Exterior Finish System Exterior Finish System Inspector with 3-year minimum manufacturer's inspection experience.
Inspection of EFS installation.
As specified in Section
07 24 00 EXTERIOR FINISH
SYSTEMS.
SECTION 01 45 00 Page 9
Qualification/Experience In Area of Responsibility
Area of Responsibility Frequency
Fireproofing Manufacturer's Technical Representative with 5-year minimum in responsible position comparable to that required by this Project and pre-qualified by manufacturers of fireproofing and firesafing products.
Inspection of Fireproofing and Firesafing systems as per Division 07 Thermal and Moisture Protection.
sections of specifications Division 07 Thermal and Moisture Protection:
Periodic Inspections to confirm substrate preparation and installations, and as required by IBC 1704.11.
Elevator Specialist and Elevator Inspector with qualifications as required by Section 14 24 23
HYDRAULIC ELEVATORS.
Field Quality Control for Hydraulic Passenger Elevators as per Section 14 24 23 .
As specified intechnical sections of specifications Division 14 Conveying Equipment: Inspections required during progress of work as specified in Section 14 24 23 .
U.S. Registered P.E., Fire Protection.
See requirements in 1.5.7. See requirements in 1.5.7.
Registered Mechanical Engineer with 5-year minimum in responsible position comparable to that required for this Project.
Inspection of items in Division 23 Heating, Ventilating, and Air Conditioning.
As specified in technical sections of specifications Division 23 Heating, Ventilating, and Air Conditioning: Periodic inspections required during progress of work.
Registered Electrical Engineer with 5-year minimum in responsible position comparable to that required for this Project.
Inspection of items in Division 26 Electrical.
As specified in technical sections of specifications Division 26 Electrical:
Periodic inspections when specified equipment is being installed.
U.S. Licensed Electrical Engineer (PE) with 5 years minimum experience in electrical engineering
Electrical installation of lightning protection and grounding system, primary (medium voltage) electrical system, uninterruptible power supply (UPS) system, and emergency back-up generator system.
Minimum 3 times a week during installation and full time during testing.
Electrical Inspector, International Conference of Building Officials (ICBO)/ 5 years minimum.
Building electrical systems and all other electrical systems not listed above for Licensed Electrical Engineer (PE).
Minimum 1 time a week during installation and full-time during testing.
SECTION 01 45 00 Page 10
Qualification/Experience In Area of Responsibility
Area of Responsibility Frequency
BICSI…
This is the start of the file's text. The full file is on GovTribe.