This is a Specifications document (work order SPC) for a federal construction project. NAVFAC Pacific Work Order No. 1696746 is for the Battle Staff Training Facility (J-875) at U.S. Naval Supply Activity Marine Corps Base Camp Blaz, Guam, prepared under JFY 2022 funding. The project involves constructing a two-story reinforced concrete Battle Staff Training Facility with integrated support systems for the Third Marine Expeditionary Brigade, including utilities, site improvements, emergency generator, access roads, and parking. The facility is designed to meet seismic and environmental requirements per Unified Facilities Criteria applicable to Guam's conditions. The specification encompasses comprehensive design and construction requirements across 34 divisions covering site conditions, demolition, structural systems (concrete, masonry, metals, wood), thermal protection, openings, finishes, specialties, furnishings, fire suppression, plumbing, HVAC, integrated automation, electrical, communications, safety systems, earthwork, exterior improvements, and utilities. Contract execution requires payment through an Earned Value Report derived from a cost-loaded Network Analysis Schedule, with cost breakdowns separating primary facility work (within 5 feet of exterior) from supporting facilities (site work beyond 5 feet). Contractors must coordinate with Navy Base Operations Support Contractor for utility outages with minimum 30-day notice and establish funding through PAY.GOV prior to service provision. Personnel access requires DBIDS credentialing or one-day passes, security clearance processing, and advance submission of personnel lists. Work is restricted to regular hours (7:30 a.m. to 4:00 p.m., Monday-Friday, excluding holidays) unless approved otherwise. The project includes 468 contract drawings and approximately 33 major specification sections detailing all construction trades and systems. Approved submittals require Government classification ("G"), and monthly invoicing includes multiple supporting documents including earned value reports, safety evaluations, certified payrolls, and waste disposal reports.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC PACIFIC
WORK ORDER NO:
1696746
SPECIFICATIONS
For
J-875 GOJ – BATTLE STAFF TRAINING FACILITY
At the
US NAVSUPPACT MARINE CORPS BASE CAMP BLAZ, GUAM
PREPARED BY: ASMD LLC
Architectural: Architects Hawaii Ltd.
Geotechnical: Environmental Science Corporation
Civil: Stanley Consultants, Inc.
Landscape: Belt Collins Hawaii
Structural/ATFP: Stanley Consultants, Inc.
Fire Protection: Coffman Engineers, Inc.
Mechanical: Stanley Consultants, Inc.
Electrical: Stanley Consultants, Inc.
Telecommunications: Stanley Consultants, Inc.
Cybersecurity: Shearer & Associates
Audio-Visual/Acoustical: Censeo
Environmental: Duenas-Camacho & Associates Inc.
Sustainability: AMEL Technologies, Inc.
Elevator: Elevator Consulting Services. Inc.
Submitted By: _______________________________ Date: ____________
Myles M. Michibata
APPROVED BY:
For Commander, NAVFAC Pacific: ________________________________________________
Mr. Evan A Mizue, P.E.
Date: _______________________
3/12/2026 evan.mizue Text Box
10 APRIL 2026
evan.mizue Text Box evan.mizue Text Box
JFY 2022 PROJECT J-875, BATTLE STAFF TRAINING FACILITY 1696746
U.S. NAVSUPPACT MCB CAMP BLAZ, GUAM
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24, CHG 1: 05/25 SUMMARY OF WORK
01 14 00 11/22, CHG 5: 05/25 WORK RESTRICTIONS
01 20 00 11/20, CHG 5: 02/25 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 5: 02/25 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 08/23, CHG 1: 02/24 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
(eCMS)
01 32 17.00 20 05/25 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21, CHG 1: 08/25 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 13.02 34 01/25 FACILITY-RELATED CONTROL SYSTEMS
(FRCS) PROCUREMENT FOR NAVY
01 35 26 05/24, CHG 1: 05/25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 3: 08/25 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 3: 08/24 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22, CHG 2: 08/25 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 12/23 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL
CONTROLS MCBCB EV
01 57 19.03 20 04/21 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL
CONTROLS Munitions Response Explosives Safety Submission (MRESS) Guam Construction Support
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23, CHG 2: 11/25 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 91 00.15 05/23, CHG 3: 08/24 BUILDING COMMISSIONING
01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 56 13.16 02/25 CLAY WASTE CONTAINMENT
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 10: 08/25 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
BELOW GRADE CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 05/25 UNIT MASONRY
PROJECT TABLE OF CONTENTS Page 1
DIVISION 05 - METALS
05 05 20 05/22, CHG 1: 08/24 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 50 13 08/24, CHG 1: 08/25 MISCELLANEOUS METAL FABRICATIONS
05 51 33 08/24 METAL LADDERS
05 52 00 08/23 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 08/24 FINISH CARPENTRY
06 41 16.00 10 08/25 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 53 08/25 ELASTOMERIC SHEET WATERPROOFING
07 21 13 08/23, CHG 1: 08/25 BOARD AND BLOCK INSULATION
07 21 16 08/23, CHG 1: 08/25 MINERAL FIBER BLANKET INSULATION
07 24 00 08/23 EXTERIOR INSULATION AND FINISH SYSTEMS
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 56 00 08/09 FLUID-APPLIED ROOFING SYSTEM
07 60 00 08/23, CHG 1: 05/25 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20, CHG 1: 08/25 STEEL DOORS AND FRAMES
08 11 16 05/17, CHG 2: 11/18 ALUMINUM DOORS, FRAMES, AND WINDOW WALL
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS
08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 22 00 08/24 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/24, CHG 1: 05/25 GYPSUM BOARD
09 30 10 08/20 CERAMIC TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 11/24 RESILIENT FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 68 00 11/24 CARPETING
09 69 13 11/24 RIGID GRID ACCESS FLOORING
09 84 20 08/16, CHG 1: 08/18 ACOUSTICAL WALL PANELS
09 90 00 02/21 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 14 53 02/15, CHG 1: 05/17 TRAFFIC SIGNAGE
PROJECT TABLE OF CONTENTS Page 2
10 21 13 08/20 TOILET COMPARTMENTS
10 22 13 08/24 WIRE MESH PARTITIONS
10 22 39 08/20 FOLDING PANEL PARTITIONS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 99 00 04/06 MISCELLANEOUS BUILDING SPECIALTIES
DIVISION 12 - FURNISHINGS
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 24 13 08/20 ROLLER WINDOW SHADES
12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES
12 93 00 08/17, CHG 1: 08/18 SITE FURNISHINGS
DIVISION 13 - SPECIAL CONSTRUCTION
13 48 73 05/25 SEISMIC CONTROL FOR NONSTRUCTURAL
COMPONENTS
DIVISION 14 - CONVEYING EQUIPMENT
14 24 23 05/16 HYDRAULIC PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
DIVISION 22 - PLUMBING
22 00 00 05/24, CHG 1: 11/24 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00 11/25 BASIC MECHANICAL MATERIALS AND METHODS
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 02/25 SEISMIC BRACING FOR MECHANICAL SYSTEMS
23 05 93 05/25 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 08/24 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 08 00 05/23, CHG 1: 08/24 COMMISSIONING OF MECHANICAL[ AND
PLUMBING] SYSTEMS
23 09 00 08/24, CHG 1: 08/25 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 08/24 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 30 00 02/25 HVAC AIR DISTRIBUTION
23 64 10 05/25 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 11/25 CHILLED, CHILLED-HOT, AND CONDENSER
WATER PIPING SYSTEMS
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11 08/24 CYBERSECURITY FOR FACILITY-RELATED
PROJECT TABLE OF CONTENTS Page 3
CONTROL SYSTEMS
25 08 10 05/21 UTILITY MONITORING AND CONTROL SYSTEM
TESTING
25 08 11.00 20 11/20 RISK MANAGEMENT FRAMEWORK FOR
FACILITY-RELATED CONTROL SYSTEMS
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 48 11/23 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 12 19.10 05/19, CHG 1: 11/19 THREE-PHASE, LIQUID-FILLED PAD-MOUNTED
TRANSFORMERS
26 20 00 05/25, CHG 1: 08/25 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 28 01.00 10 08/21 COORDINATED POWER SYSTEM PROTECTION
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15 05/24 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 05/25 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 41 00 11/21 AUDIO-VISUAL SYSTEMS
27 51 16 05/20, CHG 1: 05/22 PUBLIC ADDRESS SYSTEMS
27 51 20 10/22 TWO-WAY COMMUNICATION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
31 31 16.19 08/22 TERMITE CONTROL BARRIERS
31 62 00 03/24 CEMENT DEEP SOIL MIXING
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 CHG 1: 11/24 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
PROJECT TABLE OF CONTENTS Page 4
32 11 20 05/22 BASE COURSE FOR RIGID PAVING
32 11 23 05/22 GRADED CRUSHED AGGREGATE BASE COURSE
FOR FLEXIBLE PAVING
32 12 13 05/24 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 17 23.16 11/24 ROAD AND PARKING LOT PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK AND
ORNAMENTAL) AND GATES
32 84 24 08/11, CHG 1: 05/17 TEMPORARY IRRIGATION SPRINKLER SYSTEMS
32 92 19 08/17, CHG 1: 08/21 SEEDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 11 00 02/18, CHG 1: 02/22 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 52 40 05/25 FUEL SYSTEMS PIPING (NON-HYDRANT)
33 56 10 05/25 FACTORY-FABRICATED FUEL STORAGE TANKS
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 6
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/24
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET
NO.
DRAWING
NO.
NAVFAC
DRAWING NO.
SHEET TITLE
1 G-001 17321759 COVER SHEET
2 G-002 17321760 LIST OF SHEETS
3 G-003 17321761 LIST OF SHEETS
4 G-004 17321762 LIST OF SHEETS
5 G-005 17321763 BUILDING CODE SUMMARY
6 G-101 17321764 CODE COMPLIANCE SITE PLAN
7 G-102 17321765 1ST FLOOR PLAN - LIFE SAFETY
8 G-103 17321766 2ND FLOOR PLAN - LIFE SAFETY
9 G-104 17321767 UTILITY BUILDING AND PAVILION - LIFE SAFETY
10 V-101 17321772 TOPOGRAPHIC SURVEY
11 B-001 17321774 SOIL BORING LOCATION MAP AND BORING LOGS-1
12 B-002 17321775 BORING LOGS-2
13 B-003 17321776 BORING LOGS-3
14 B-004 17321777 BORING LOGS-4
15 C-001 17321780 CIVIL ABBREVIATIONS AND SYMBOLS
16 C-002 17321781 CIVIL NOTES - PAGE 1
17 C-003 17321782 CIVIL NOTES - PAGE 2
18 C-101 17321783 CIVIL HAUL - ACCESS ROUTE
19 C-102 17321784 CIVIL BEDROCK DETERMINATION MAP
DOCUMENT 00 01 15 Page 1
20 CD100 17321785 CIVIL DEMOLITION PLAN
21 CS100 17321786 CIVIL SITE PLAN
22 CS101 17321787 CIVIL SITE LOCATION PLAN
23 CS501 17321788 CIVIL - DETAILS - SHEET 1
24 CS502 17321789 CIVIL - DETAILS - SHEET 2
25 CS503 17321790 CIVIL - DETAILS - SHEET 3
26 CS504 17321791 CIVIL - DETAILS - SHEET 4
27 CS505 17321792 CIVIL - DETAILS - SHEET 5
28 CG100 17321793 CIVIL GRADING PLAN
29 CG100B 17321794 CIVIL GRADING PLAN - BID OPTIONS 1 AND 2
30 CG101 17321795 CIVIL LID STORMWATER DESIGN
31 CG200 17321796 CIVIL GRADING PROFILES
32 CG201 17321797 CIVIL LID PROFILES
33 CG501 17321798 CIVIL GRADING - DETAILS - SHEET 1
34 CG502 17321799 CIVIL GRADING - DETAILS - SHEET 2
35 CG503 17321800 CIVIL GRADING - DETAILS - SHEET 3
36 CP100 17321801 CIVIL PAVING PLAN
37 CP501 17321802 CIVIL PAVING - DETAILS - SHEET 1
38 CP502 17321803 CIVIL PAVING - DETAILS - SHEET 2
39 CP503 17321804 CIVIL PAVING - DETAILS - SHEET 3
40 CP504 17321805 CIVIL PAVING - DETAILS - SHEET 4
41 CP505 17321806 CIVIL PAVING - DETAILS - SHEET 5
42 CU100 17321807 CIVIL UTILITY PLAN
43 CU200 17321808 CIVIL UTILITY PROFILES - SHEET 1
44 CU201 17321809 CIVIL UTILITY PROFILES - SHEET 2
45 CU202 17321810 CIVIL UTILITY PROFILES - SHEET 3
46 CU501 17321811 CIVIL UTILITY - DETAILS - SHEET 1
47 CU502 17321812 CIVIL UTILITY - DETAILS - SHEET 2
DOCUMENT 00 01 15 Page 2
48 CU503 17321813 CIVIL UTILITY - DETAILS - SHEET 3
49 CU504 17321814 CIVIL UTILITY - DETAILS - SHEET 4
50 CU505 17321815 CIVIL UTILITY - DETAILS - SHEET 5
51 LP101 17321828 LANDSCAPE PLAN
52 LP501 17321829 PLANTING DETAILS
53 LP502 17321830 SITE FURNISHING DETAILS
54 LP601 17321831 PLANT MATERIAL SCHEDULE AND NOTES
55 S-001 17321836 STRUCTURAL NOTES AND LEGEND - SHEET 1
56 S-002 17321837 STRUCTURAL NOTES AND LEGEND - SHEET 2
57 SS101 17321838 ENCLOSURE FOUNDATION PLAN
58 SS102 17321839 ENCLOSURE SLAB PLAN
59 SS103 17321840 ENCLOSURE ROOF FRAMING PLAN
60 SS110 17321841 PAVILION FOUNDATION / SLAB PLAN
61 SS111 17321842 PAVILION ROOF PLAN
62 SS301 17321843 STRUCTURAL SECTIONS
63 SS310 17321844 STRUCTURAL SECTIONS
64 SS601 17321845 STRUCTURAL SCHEDULES
65 SS610 17321846 STRUCTURAL SCHEDULES
66 SB101 17321847 COMPREHENSIVE FOUNDATION PLAN
67 SB102 17321848 FOUNDATION PLAN - AREA 'A'
68 SB103 17321849 FOUNDATION PLAN - AREA 'B'
69 SB104 17321850 COMPREHENSIVE SLAB PLAN (EL. 0'-0", UNO)
70 SB105 17321851 SLAB PLAN - AREA 'A' (EL. 0'-0", UNO)
71 SB106 17321852 SLAB PLAN - AREA 'B' (EL. 0'-0", UNO)
72 SB401 17321853 MECHANICAL ENCLOSURE FOUNDATION / SLAB PLAN
73 SB402 17321854 CANOPY FOUNDATION / SLAB PLAN
74 SB403 17321855 ELEVATOR PIT ENLARGED PLAN
75 SB501 17321856 STRUCTURAL FOUNDATION / SLAB DETAILS - SHEET 1
DOCUMENT 00 01 15 Page 3
76 SB502 17321857 STRUCTURAL FOUNDATION / SLAB DETAILS - SHEET 2
77 SB503 17321858 STRUCTURAL FOUNDATION / SLAB DETAILS - SHEET 3
78 SF101 17321859 COMPREHENSIVE SECOND FLOOR FRAMING PLAN (EL.
14'-0", UNO)
79 SF102 17321860 SECOND FLOOR FRAMING PLAN - AREA 'A' (EL. 14'-0",
UNO)
80 SF103 17321861 SECOND FLOOR FRAMING PLAN - AREA 'A' (EL. 16'-0",
UNO)
81 SF104 17321862 SECOND FLOOR FRAMING PLAN - AREA 'B' (EL. 14'-0",
UNO)
82 SF105 17321863 SECOND FLOOR FRAMING PLAN - AREA 'B' (EL. 16'-0",
UNO)
83 SF106 17321864 COMPREHENSIVE ROOF FRAMING PLAN (ABOVE EL. 42'-0")
84 SF107 17321865 ROOF FRAMING PLAN - AREA 'A' (ABOVE EL. 42'-0")
85 SF108 17321866 ROOF FRAMING PLAN - AREA 'B' (ABOVE EL. 42'-0")
86 SF301 17321867 STRUCTURAL SECTIONS - SHEET 1
87 SF302 17321868 STRUCTURAL SECTIONS - SHEET 2
88 SF401 17321869 MECHANICAL ENCLOSURE FRAMING PLAN
89 SF402 17321870 CANOPY ROOF FRAMING PLAN
90 SF501 17321871 STRUCTURAL FLOOR FRAMING DETAILS - SHEET 1
91 SF502 17321872 STRUCTURAL FLOOR FRAMING DETAILS - SHEET 2
92 SF503 17321873 STRUCTURAL ROOF FRAMING DETAILS
93 SF504 17321874 STRUCTURAL CONCRETE STAIR DETAILS
94 SF505 17321875 STRUCTURAL FRAMING DETAILS
95 SJ601 17321876 STRUCTURAL SCHEDULES
96 SK501 17321877 TYPICAL REINFORCING DETAILS
97 SK502 17321878 TYPICAL FOUNDATION DETAILS
98 SK503 17321879 TYPICAL SLAB-ON-GRADE DETAILS - SHEET 1
99 SK504 17321880 TYPICAL SLAB-ON-GRADE DETAILS - SHEET 2
100 SK505 17321881 TYPICAL SHEAR WALL DETAILS
101 SK506 17321882 CONCRETE COLUMN DETAILS
102 SK507 17321883 CONCRETE BEAM DETAILS
103 SK508 17321884 TYPICAL CONCRETE ELEVATED SLAB DETAILS
DOCUMENT 00 01 15 Page 4
104 A-001 17321900 ARCHITECTURAL NOTES AND SYMBOLS
105 AS101 17321901 ARCHITECTURAL SITE PLAN AND OPTION ITEMS
106 AS102 17321902 CHILLER ENCLOSURE PLAN, EXTERIOR ELEVATIONS, AND
SECTION
107 AS103 17321903 TRANSFORMER ENCLOSURE PLAN, EXTERIOR ELEVATIONS,
AND SECTION
108 AS104 17321904 TRASH ENCLOSURE PLAN, EXTERIOR ELEVATIONS, AND
SECTIONS
109 AS105 17321905 SITE SIGNAGE
110 AS106 17321906 BUILDING SIGNAGE
111 AS107 17321907 GENERATOR AND FUEL TANK ENCLOSURE PLAN AND ROOF
PLAN, OPTION ITEM #2
112 AS108 17321908 GENERATOR AND FUEL TANK ENCLOSURE ELEVATIONS,
OPTION ITEM #2
113 AS109 17321909 GENERATOR AND FUEL TANK ENCLOSURE SECTIONS,
OPTION ITEM #2
114 AS110 17321910 PAVILION PLANS, ELEVATIONS, AND SECTIONS, OPTION
ITEM #1
115 AS111 17321911 SITE DETAILS
116 A-101 17321912 OVERALL FIRST FLOOR PLAN
117 A-102 17321913 ENLARGED FLOOR PLAN - 1A
118 A-103 17321914 ENLARGED FLOOR PLAN - 1B & OPTION ITEM #2
119 A-104 17321915 OVERALL SECOND FLOOR PLAN
120 A-105 17321916 ENLARGED FLOOR PLAN - 2A
121 A-106 17321917 ENLARGED FLOOR PLAN - 2B
122 A-111 17321918 OVERALL FIRST FLOOR REFLECTED CEILING PLAN
123 A-112 17321919 ENLARGED REFLECTED CEILING PLAN - 1A
124 A-113 17321920 ENLARGED REFLECTED CEILING PLAN - 1B & OPTION ITEM
#2
125 A-114 17321921 OVERALL SECOND FLOOR REFLECTED CEILING PLAN
126 A-115 17321922 ENLARGED REFLECTED CEILING PLAN - 2A
127 A-116 17321923 ENLARGED REFLECTED CEILING PLAN - 2B
128 A-120 17321924 ROOF PLAN
129 A-201 17321925 EXTERIOR ELEVATIONS - NORTH AND EAST & OPTION ITEM
#2
130 A-202 17321926 EXTERIOR ELEVATIONS - SOUTH AND WEST & OPTION ITEM
#2
131 A-203 17321927 DETAILED EXTERIOR ELEVATIONS
DOCUMENT 00 01 15 Page 5
132 A-301 17321928 BUILDING SECTIONS
133 A-310 17321929 WALL SECTIONS
134 A-311 17321930 WALL SECTIONS
135 A-401 17321931 INTERIOR ELEVATIONS
136 A-402 17321932 INTERIOR ELEVATIONS
137 A-403 17321933 INTERIOR ELEVATIONS
138 A-404 17321934 INTERIOR ELEVATIONS
139 A-405 17321935 INTERIOR ELEVATIONS
140 A-411 17321936 DETAILED RESTROOM PLANS AND INTERIOR ELEVATIONS
141 A-412 17321937 DETAILED RESTROOM PLANS AND INTERIOR ELEVATIONS
142 A-413 17321938 DETAILED ELEVATOR PLANS AND SECTION
143 A-414 17321939 DETAILED STAIR A PLANS AND SECTION
144 A-415 17321940 DETAILED STAIR B PLANS AND SECTION
145 A-416 17321941 DETAILED STAIR C PLANS AND SECTION
146 A-501 17321942 TYPICAL MOUNTING HEIGHTS
147 A-502 17321943 PARTITION TYPES
148 A-503 17321944 PARTITION TYPES
149 A-504 17321945 COLUMN DETAILS
150 A-601 17321946 DOOR AND OPERABLE PARTITION SCHEDULES
151 A-602 17321947 DOOR, WINDOW, LOUVER TYPES AND SCHEDULES & OPTION
ITEM #2
152 A-603 17321948 OPERABLE PARTITION DETAILS
153 A-604 17321949 DOOR DETAILS
154 A-605 17321950 DOOR DETAILS
155 A-606 17321951 DOOR DETAILS
156 A-607 17321952 GATE DETAILS
157 A-608 17321953 WINDOW DETAILS
158 A-609 17321954 WINDOW DETAILS
159 A-610 17321955 INTERIOR COLOR MATERIAL SCHEDULE
DOCUMENT 00 01 15 Page 6
160 A-611 17321956 EXTERIOR COLOR MATERIAL SCHEDULE
161 A-612 17321957 ROOM FINISH SCHEDULE
162 A-613 17321958 ROOM FINISH SCHEDULE
163 A-614 17321959 ENLARGED SIGNAGE FLOOR PLAN - 1A
164 A-615 17321960 ENLARGED SIGNAGE FLOOR PLAN - 1B
165 A-616 17321961 ENLARGED SIGNAGE FLOOR PLAN - 2A
166 A-617 17321962 ENLARGED SIGNAGE FLOOR PLAN - 2B
167 A-618 17321963 SIGNAGE SCHEDULE
168 A-619 17321964 TYPICAL SIGNAGE DETAILS
169 A-701 17321965 CEILING DETAILS
170 A-710 17321966 CASEWORK DETAILS
171 A-720 17321967 RAILING DETAILS
172 A-730 17321968 MISCELLANEOUS INTERIOR DETAILS
173 A-731 17321969 MISCELLANEOUS INTERIOR DETAILS
174 A-740 17321970 ROOF DETAILS
175 A-750 17321971 MISCELLANEOUS EXTERIOR DETAILS
176 A-801 17321972 ENLARGED RAF FLOOR PLAN - 1A
177 A-802 17321973 ENLARGED RAF FLOOR PLAN - 1B
178 A-803 17321974 ENLARGED RAF FLOOR PLAN - 2A
179 A-804 17321975 ENLARGED RAF FLOOR PLAN - 2B
180 A-901 17321976 AIR BARRIER DIAGRAM - FLOOR PLANS
181 A-902 17321977 AIR BARRIER DIAGRAM - SECTIONS
182 A-903 17321978 AIR BARRIER DETAILS
183 AI101 17321979 ENLARGED FLOOR FINISH PLAN - 1A
184 AI102 17321980 ENLARGED FLOOR FINISH PLAN - 1B
185 AI103 17321981 ENLARGED FLOOR FINISH PLAN - 2A
186 AI104 17321982 ENLARGED FLOOR FINISH PLAN - 2B
187 I-801 17321997 OVERALL FIRST FLOOR FF&E PLAN
DOCUMENT 00 01 15 Page 7
188 I-802 17321998 OVERALL SECOND FLOOR FF&E PLAN
189 I-803 17321999 FF&E SCHEDULE
190 I-804 17322000 ENLARGED FF&E FLOOR PLAN - 1A
191 I-805 17322001 ENLARGED FF&E FLOOR PLAN - 1B
192 I-806 17322002 ENLARGED FF&E FLOOR PLAN - 1C
193 I-807 17322003 ENLARGED FF&E FLOOR PLAN - 1D
194 I-808 17322004 ENLARGED FF&E FLOOR PLAN - 1E
195 I-809 17322005 ENLARGED FF&E FLOOR PLAN - 1F
196 I-810 17322006 ENLARGED FF&E FLOOR PLAN - 2A
197 I-811 17322007 ENLARGED FF&E FLOOR PLAN - 2B
198 I-812 17322008 ENLARGED FF&E FLOOR PLAN - 2C
199 I-813 17322009 ENLARGED FF&E FLOOR PLAN - 2D
200 I-814 17322010 ENLARGED FF&E FLOOR PLAN - 2E
201 I-815 17322011 ENLARGED FF&E FLOOR PLAN - 2F
202 I-816 17322012 TYPICAL MOUNTING HEIGHTS - FF&E
203 F-001 17322023 FIRE PROTECTION NOTES, SYMBOLS AND ABBREVIATIONS
204 FX401 17322024 ENLARGED FLOOR PLAN 1A - FIRE SPRINKLER
205 FX402 17322025 ENLARGED FLOOR PLAN 1B - FIRE SPRINKLER
206 FX403 17322026 ENLARGED FLOOR PLAN 2A - FIRE SPRINKLER
207 FX404 17322027 ENLARGED FLOOR PLAN 2B - FIRE SPRINKLER
208 FX405 17322028 ENLARGED UTILITY BUILDING FLOOR PLAN - FIRE
SPRINKLER
209 FX501 17322029 FIRE SPRINKLER DETAILS
210 FA401 17322030 ENLARGED FLOOR PLAN 1A - FIRE ALARM-MASS
NOTIFICATION SYSTEM
211 FA402 17322031 ENLARGED FLOOR PLAN 1B - FIRE ALARM-MASS
NOTIFICATION SYSTEM
212 FA403 17322032 ENLARGED FLOOR PLAN 2A - FIRE ALARM-MASS
NOTIFICATION SYSTEM
213 FA404 17322033 ENLARGED FLOOR PLAN 2B - FIRE ALARM-MASS
NOTIFICATION SYSTEM
214 FA405 17322034 ENLARGED UTILITY BUILDING FLOOR PLAN - FIRE
ALARM-MASS NOTIFICATION SYSTEM
215 FA501 17322035 FIRE ALARM-MASS NOTIFICATION SYSTEM DETAILS
DOCUMENT 00 01 15 Page 8
216 FA601 17322036 FIRE ALARM-MASS NOTIFICATION SYSTEM - SEQUENCE OF
OPERATIONS
217 FA602 17322037 FIRE ALARM-MASS NOTIFICATION SYSTEM - RISER DIAGRAM
218 P-001 17322048 PLUMBING LEGEND, ABBREVIATIONS AND NOTES
219 PL100 17322049 COMPOSITE PLUMBING PLAN - BELOW FIRST FLOOR
220 PL101 17322050 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'A'
221 PL102 17322051 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'B'
222 PL103 17322052 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'C'
223 PL104 17322053 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'D'
224 PL105 17322054 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'E'
225 PL106 17322055 PLUMBING PLAN - BELOW FIRST FLOOR - AREA 'F'
226 PL110 17322056 COMPOSITE PLUMBING PLAN - FIRST FLOOR
227 PL111 17322057 PLUMBING PLAN - FIRST FLOOR - AREA 'A'
228 PL112 17322058 PLUMBING PLAN - FIRST FLOOR - AREA 'B'
229 PL113 17322059 PLUMBING PLAN - FIRST FLOOR - AREA 'C'
230 PL114 17322060 PLUMBING PLAN - FIRST FLOOR - AREA 'D'
231 PL115 17322061 PLUMBING PLAN - FIRST FLOOR - AREA 'E'
232 PL116 17322062 PLUMBING PLAN - FIRST FLOOR - AREA 'F'
233 PL120 17322063 COMPOSITE PLUMBING PLAN - SECOND FLOOR
234 PL121 17322064 PLUMBING PLAN - SECOND FLOOR - AREA 'A'
235 PL122 17322065 PLUMBING PLAN - SECOND FLOOR - AREA 'B'
236 PL123 17322066 PLUMBING PLAN - SECOND FLOOR - AREA 'C'
237 PL124 17322067 PLUMBING PLAN - SECOND FLOOR - AREA 'D'
238 PL125 17322068 PLUMBING PLAN - SECOND FLOOR - AREA 'E'
239 PL126 17322069 PLUMBING PLAN - SECOND FLOOR - AREA 'F'
240 PL140 17322070 COMPOSITE PLUMBING PLAN - ROOF
241 PL400 17322071 ENLARGED PLUMBING PLANS - SHEET 1
242 PL401 17322072 ENLARGED PLUMBING PLANS - SHEET 2
243 PL500 17322073 PLUMBING DETAILS - SHEET 1
DOCUMENT 00 01 15 Page 9
244 PL501 17322074 PLUMBING DETAILS - SHEET 2
245 PL600 17322075 PLUMBING SCHEDULES - SHEET 1
246 PL601 17322076 PLUMBING SCHEDULES - SHEET 2
247 PL901 17322077 PLUMBING ISOMETRICS - OVERALL
248 PL902 17322078 PLUMBING ISOMETRICS - FIRST FLOOR BATHROOM
249 PL903 17322079 PLUMBING ISOMETRICS - SECOND FLOOR BATHROOM
250 PL905 17322080 PLUMBING ISOMETRICS - ENLARGED VIEW
251 PL906 17322081 PLUMBING ISOMETRICS - SPECIAL SYSTEMS
252 M-001 17322092 MECHANICAL LEGEND, ABBREVIATIONS AND NOTES
253 MH100 17322093 COMPOSITE HVAC DUCT PLAN - FIRST FLOOR
254 MH101 17322094 HVAC DUCT PLAN - FIRST FLOOR - AREA 'A'
255 MH102 17322095 HVAC DUCT PLAN - FIRST FLOOR - AREA 'B'
256 MH103 17322096 HVAC DUCT PLAN - FIRST FLOOR - AREA 'C'
257 MH104 17322097 HVAC DUCT PLAN - FIRST FLOOR - AREA 'D'
258 MH105 17322098 HVAC DUCT PLAN - FIRST FLOOR - AREA 'E'
259 MH106 17322099 HVAC DUCT PLAN - FIRST FLOOR - AREA 'F'
260 MH110 17322100 COMPOSITE HVAC DUCT PLAN - SECOND FLOOR
261 MH111 17322101 HVAC DUCT PLAN - SECOND FLOOR - AREA 'A'
262 MH112 17322102 HVAC DUCT PLAN - SECOND FLOOR - AREA 'B'
263 MH113 17322103 HVAC DUCT PLAN - SECOND FLOOR - AREA 'C'
264 MH114 17322104 HVAC DUCT PLAN - SECOND FLOOR - AREA 'D'
265 MH115 17322105 HVAC DUCT PLAN - SECOND FLOOR - AREA 'E'
266 MH116 17322106 HVAC DUCT PLAN - SECOND FLOOR - AREA 'F'
267 MH127 17322107 GENERATOR/TANK MECHANICAL PLAN
268 MH300 17322108 MECHANICAL SECTIONS - SHEET 1
269 MH301 17322109 MECHANICAL SECTIONS - SHEET 2
270 MH400 17322110 ENLARGED FLOOR PLAN - SHEET 1
271 MH501 17322111 HVAC DETAILS - SHEET 1
DOCUMENT 00 01 15 Page 10
272 MH502 17322112 HVAC DETAILS - SHEET 2
273 MH503 17322113 HVAC DETAILS - SHEET 3
274 MH504 17322114 HVAC DETAILS - SHEET 4
275 MH505 17322115 HVAC DETAILS - SHEET 5
276 MH506 17322116 HVAC DETAILS - SHEET 6
277 MH507 17322117 HVAC DETAILS - SHEET 7
278 MH508 17322118 HVAC DETAILS - SHEET 8
279 MH509 17322119 HVAC DETAILS - SHEET 9
280 MH510 17322120 HVAC DETAILS - SHEET 10
281 MH511 17322121 FUEL OIL SYSTEM DETAILS - SHEET 1
282 MH512 17322122 FUEL OIL SYSTEM DETAILS - SHEET 2
283 MH513 17322123 FUEL OIL SYSTEM DETAILS - SHEET 3
284 MH514 17322124 FUEL OIL SYSTEM DETAILS - SHEET 4
285 MH600 17322125 HVAC SCHEMATICS - SHEET 1
286 MH601 17322126 HVAC SCHEMATICS - SHEET 2
287 MH602 17322127 HVAC SCHEMATICS - SHEET 3
288 MH603 17322128 HVAC SCHEMATICS - SHEET 4
289 MH700 17322129 MECHANICAL SCHEDULES - SHEET 1
290 MH701 17322130 MECHANICAL SCHEDULES - SHEET 2
291 MH702 17322131 MECHANICAL SCHEDULES - SHEET 3
292 MH703 17322132 MECHANICAL SCHEDULES - SHEET 4
293 MH704 17322133 MECHANICAL SCHEDULES - SHEET 5
294 MH800 17322134 MECHANICAL CONTROLS
295 MH900 17322135 HVAC ISOMETRICS - SHEET 1
296 MH901 17322136 HVAC ISOMETRICS - SHEET 2
297 MP100 17322137 COMPOSITE HVAC PIPING PLAN - FIRST FLOOR
298 MP101 17322138 HVAC PIPING PLAN - FIRST FLOOR - AREA 'A'
299 MP102 17322139 HVAC PIPING PLAN - FIRST FLOOR - AREA 'B'
DOCUMENT 00 01 15 Page 11
300 MP103 17322140 HVAC PIPING PLAN - FIRST FLOOR - AREA 'C'
301 MP104 17322141 HVAC PIPING PLAN - FIRST FLOOR - AREA 'D'
302 MP105 17322142 HVAC PIPING PLAN - FIRST FLOOR - AREA 'E'
303 MP106 17322143 HVAC PIPING PLAN - FIRST FLOOR - AREA 'F'
304 MP107 17322144 HVAC PIPING PLAN - FIRST FLOOR - MECHANICAL
ENCLOSURE
305 MP110 17322145 COMPOSITE HVAC PIPING PLAN - SECOND FLOOR
306 MP111 17322146 HVAC PIPING PLAN - SECOND FLOOR - AREA 'A'
307 MP112 17322147 HVAC PIPING PLAN - SECOND FLOOR - AREA 'B'
308 MP113 17322148 HVAC PIPING PLAN - SECOND FLOOR - AREA 'C'
309 MP114 17322149 HVAC PIPING PLAN - SECOND FLOOR - AREA 'D'
310 MP115 17322150 HVAC PIPING PLAN - SECOND FLOOR - AREA 'E'
311 MP116 17322151 HVAC PIPING PLAN - SECOND FLOOR - AREA 'F'
312 MP400 17322152 ENLARGED FLOOR PLAN - SHEET 1
313 E-001 17322168 ELECTRICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND
NOTES
314 E-002 17322169 ONE-LINE AND THREE LINE DIAGRAM LEGEND
315 ES100 17322170 ELECTRICAL SITE PLAN
316 ES100B 17322171 ELECTRICAL SITE PLAN - BID OPTIONS 1 & 2
317 EG101 17322172 OVERALL GROUNDING PLAN
318 EG102 17322173 ENLARGED GROUNDING PLAN AREA A
319 EG103 17322174 ENLARGED GROUNDING PLAN AREA B
320 EG104 17322175 OVERALL LIGHTNING PROTECTION PLAN
321 EG105 17322176 ENLARGED LIGHTNING PROTECTION PLAN AREA A
322 EG106 17322177 ENLARGED LIGHTNING PROTECTION PLAN AREA B
323 EG107 17322178 GENERATOR & PAVILION BUILDINGS - GROUNDING AND
LIGHTNING PROTECTION PLANS
324 EG401 17322179 ENLARGED GROUNDING PLAN - MECHANICAL ENCLOSURE
325 EL101 17322180 OVERALL LIGHTING PLAN - FIRST FLOOR
326 EL102 17322181 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1A
327 EL103 17322182 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1B
DOCUMENT 00 01 15 Page 12
328 EL104 17322183 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1C
329 EL105 17322184 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1D
330 EL106 17322185 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1E
331 EL107 17322186 ENLARGED LIGHTING PLAN - FIRST FLOOR AREA 1F
332 EL108 17322187 OVERALL LIGHTING PLAN - SECOND FLOOR
333 EL109 17322188 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2A
334 EL110 17322189 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2B
335 EL111 17322190 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2C
336 EL112 17322191 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2D
337 EL113 17322192 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2E
338 EL114 17322193 ENLARGED LIGHTING PLAN - SECOND FLOOR AREA 2F
339 EL122 17322194 GENERATOR BUILDING - LIGHTING PLAN - BID OPTION #2
340 EL123 17322195 PAVILION - LIGHTING PLAN - BID OPTION #1
341 EL301 17322196 LIGHTING SECTIONS - SHEET 1
342 EL302 17322197 LIGHTING SECTIONS - SHEET 2
343 EL401 17322198 ENLARGED LIGHTING PLANS
344 EL501 17322199 LIGHTING DETAILS - SHEET 1
345 EL502 17322200 LIGHTING DETAILS - SHEET 2
346 EL503 17322201 LIGHTING DETAILS - SHEET 3
347 EL504 17322202 LIGHTING DETAILS - SHEET 4
348 EL505 17322203 LIGHTING DETAILS - SHEET 5
349 EL601 17322204 LIGHTING CONTROL SCHEDULE
350 EL602 17322205 SITE LIGHTING DIAGRAM
351 EL701 17322206 LIGHT FIXTURE SCHEDULE - SHEET 1
352 EL702 17322207 LIGHT FIXTURE SCHEDULE - SHEET 2
353 EP101 17322208 OVERALL POWER PLAN - FIRST FLOOR
354 EP102 17322209 ENLARGED POWER PLAN - FIRST FLOOR AREA 1A
355 EP103 17322210 ENLARGED POWER PLAN - FIRST FLOOR AREA 1B
DOCUMENT 00 01 15 Page 13
356 EP104 17322211 ENLARGED POWER PLAN - FIRST FLOOR AREA 1C
357 EP105 17322212 ENLARGED POWER PLAN - FIRST FLOOR AREA 1D
358 EP106 17322213 ENLARGED POWER PLAN - FIRST FLOOR AREA 1E
359 EP107 17322214 ENLARGED POWER PLAN - FIRST FLOOR AREA 1F
360 EP108 17322215 OVERALL POWER PLAN - SECOND FLOOR
361 EP109 17322216 ENLARGED POWER PLAN - SECOND FLOOR AREA 2A
362 EP110 17322217 ENLARGED POWER PLAN - SECOND FLOOR AREA 2B
363 EP111 17322218 ENLARGED POWER PLAN - SECOND FLOOR AREA 2C
364 EP112 17322219 ENLARGED POWER PLAN - SECOND FLOOR AREA 2D
365 EP113 17322220 ENLARGED POWER PLAN - SECOND FLOOR AREA 2E
366 EP114 17322221 ENLARGED POWER PLAN - SECOND FLOOR AREA 2F
367 EP122 17322222 GENERATOR BUILDING - POWER PLAN
368 EP123 17322223 PAVILION - POWER PLAN - OPTION ITEM #1
369 EP401 17322224 ENLARGED POWER PLAN - MECHANICAL ENCLOSURE
370 EP402 17322225 ENLARGED POWER PLAN - BASE BID ELECTRICAL ROOMS
371 EP403 17322226 ENLARGED POWER PLAN - BID OPTION #2 ELECTRICAL
ROOMS
372 EP404 17322227 ENLARGED POWER PLAN - MECHANICAL ROOM 119
373 EP405 17322228 ENLARGED POWER PLAN - MECHANICAL ROOM 217
374 EP501 17322229 ELECTRICAL DETAILS - SHEET 1
375 EP502 17322230 ELECTRICAL DETAILS - SHEET 2
376 EP503 17322231 ELECTRICAL DETAILS - SHEET 3
377 EP504 17322232 ELECTRICAL DETAILS - SHEET 4
378 EP505 17322233 ELECTRICAL DETAILS - SHEET 5
379 EP506 17322234 ELECTRICAL DETAILS - SHEET 6
380 EP601 17322235 ELECTRICAL ONELINE DIAGRAM - BASE BID SHEET 1
381 EP602 17322236 ELECTRICAL ONELINE DIAGRAM - BASE BID SHEET 2
382 EP603 17322237 ELECTRICAL ONELINE DIAGRAM - BID OPTION 2 SHEET 3
383 EP604 17322238 ELECTRICAL ONELINE DIAGRAM - BID OPTION 2 SHEET 4
DOCUMENT 00 01 15 Page 14
384 EP701 17322239 PANELBOARD SCHEDULES - SHEET 1
385 EP702 17322240 PANELBOARD SCHEDULES - SHEET 2
386 EP703 17322241 PANELBOARD SCHEDULES - SHEET 3
387 EP704 17322242 PANELBOARD SCHEDULES - SHEET 4
388 EP705 17322243 PANELBOARD SCHEDULES - SHEET 5
389 EP706 17322244 PANELBOARD SCHEDULES - SHEET 6
390 EP707 17322245 PANELBOARD SCHEDULES - SHEET 7
391 EP708 17322246 PANELBOARD SCHEDULES - SHEET 8
392 EP709 17322247 PANELBOARD SCHEDULES - SHEET 9
393 EP710 17322248 PANELBOARD SCHEDULES - SHEET 10
394 EP720 17322249 CABLE SCHEDULE
395 T-001 17322265 TELECOMMUNICATIONS LEGEND
396 TS100 17322266 TELECOM OVERALL SITE PLAN
397 TS101 17322267 TELECOM SITE PLAN
398 TS501 17322268 TELECOM SITE DETAILS - SHEET 1
399 TS502 17322269 TELECOM SITE DETAILS - SHEET 2
400 TS503 17322270 TELECOM SITE DETAILS - SHEET 3
401 TN101 17322271 COMPOSITE PLAN - TELECOMMUNICATIONS - FIRST FLOOR
402 TN102 17322272 PARTIAL PLAN - TELECOMMUNICATIONS - FIRST FLOOR -
AREA 'A'
403 TN103 17322273 PARTIAL PLAN - TELECOMMUNICATIONS - FIRST FLOOR -
AREA 'B'
404 TN104 17322274 COMPOSITE PLAN - TELECOMMUNICATIONS - SECOND FLOOR
405 TN105 17322275 PARTIAL PLAN - TELECOMMUNICATIONS - SECOND FLOOR -
AREA 'A'
406 TN106 17322276 PARTIAL PLAN - TELECOMMUNICATIONS - SECOND FLOOR -
AREA 'B'
407 TN110 17322277 CABLE TRAY PLAN - FIRST FLOOR
408 TN111 17322278 CABLE TRAY PLAN - SECOND FLOOR
409 TN300 17322279 TELECOM CABINET ELEVATION GTR 1 RM 121A
410 TN301 17322280 TELECOM CABINET ELEVATION GTR 1T RM 121B
411 TN302 17322281 TELECOM CABINET ELEVATION GTR 2 RM 229A
DOCUMENT 00 01 15 Page 15
412 TN303 17322282 TELECOM CABINET ELEVATION GTR 2T RM 229B
413 TN401 17322283 ENLARGED FIRST FLOOR GTR PLAN
414 TN402 17322284 ENLARGED SECOND FLOOR GTR PLAN
415 TN500 17322285 TELECOMMUNICATIONS DETAILS - SHEET 1
416 TN501 17322286 TELECOMMUNICATIONS DETAILS - SHEET 2
417 TN502 17322287 TELECOMMUNICATIONS DETAILS - SHEET 3
418 TN503 17322288 TELECOMMUNICATIONS DETAILS - SHEET 4
419 TN504 17322289 TELECOMMUNICATIONS DETAILS - SHEET 5
420 TN505 17322290 TELECOMMUNICATIONS DETAILS - SHEET 6
421 TN506 17322291 TELECOMMUNICATIONS DETAILS - SHEET 7
422 TN507 17322292 TELECOMMUNICATIONS DETAILS - SHEET 8
423 TN601 17322293 TELECOM BACKBONE RISER DIAGRAM
424 TN602 17322294 TELECOM RISER DIAGRAMS - SHEET 1
425 TN603 17322295 TELECOM RISER DIAGRAMS - SHEET 2
426 TN604 17322296 TELECOM RISER DIAGRAMS - SHEET 3
427 TY101 17322297 SPECIAL SYSTEMS - FIRST FLOOR - AREA 'A'
428 TY102 17322298 SPECIAL SYSTEM - FIRST FLOOR - AREA 'B'
429 TY103 17322299 SPECIAL SYSTEMS - SECOND FLOOR - AREA 'A'
430 TY104 17322300 SPECIAL SYSTEMS - SECOND FLOOR - AREA 'B'
431 TY501 17322301 SPECIAL SYSTEMS DETAILS - SHEET 1
432 TY502 17322302 SPECIAL SYSTEMS DETAILS - SHEET 2
433 TT-001 17322318 GENERAL NOTES, ABBREVIATIONS & SYMBOLS LEGEND
434 TT-101 17322319 1ST FLOOR TWO-WAY COMMUNICATION PLAN
435 TT-102 17322320 2ND FLOOR TWO-WAY COMMUNICATION PLAN
436 TT-501 17322321 TWO-WAY COMMUNICATIONS DETAILS & DIAGRAM
437 TT-502 17322322 TWO-WAY COMMUNICATIONS SEQUENCE OF OPERATIONS
MATRIX
438 TA001 17322326 AV SYSTEMS GENERAL NOTES
439 TA002 17322327 AV SYSTEMS SYMBOLS, LEGEND, AND ABBREVIATIONS
DOCUMENT 00 01 15 Page 16
440 TA101 17322328 OVERALL AV FIRST FLOOR PLAN
441 TA102 17322329 PARTIAL AV FIRST FLOOR PLAN - A
442 TA103 17322330 PARTIAL AV FIRST FLOOR PLAN - B
443 TA104 17322331 PARTIAL AV FIRST FLOOR CABLE TRAY PLAN - A
444 TA105 17322332 PARTIAL AV FIRST FLOOR CABLE TRAY PLAN - B
445 TA106 17322333 OVERALL AV SECOND FLOOR PLAN
446 TA107 17322334 PARTIAL AV SECOND FLOOR PLAN - A
447 TA108 17322335 PARTIAL AV SECOND FLOOR PLAN - B
448 TA109 17322336 PARTIAL AV SECOND FLOOR CABLE TRAY PLAN - A
449 TA110 17322337 PARTIAL AV SECOND FLOOR CABLE TRAY PLAN - B
450 TA401 17322338 AV INTERIOR ELEVATIONS
451 TA402 17322339 AV INTERIOR ELEVATIONS
452 TA403 17322340 AV INTERIOR ELEVATIONS
453 TA404 17322341 AV INTERIOR ELEVATIONS
454 TA405 17322342 ENLARGED AV PLANS & INTERIOR ELEVATIONS
455 TA406 17322343 ENLARGED AV PLANS & INTERIOR ELEVATIONS
456 TA407 17322344 ENLARGED AV PLANS & INTERIOR ELEVATIONS
457 TA408 17322345 ENLARGED AV PLANS
458 TA409 17322346 ENLARGED AV PLANS
459 TA410 17322347 AV INTERIOR ELEVATIONS & SECTIONS
460 TA501 17322348 AV INFRASTRUCTURE DETAILS
461 TA502 17322349 AV INFRASTRUCTURE DETAILS
462 TA503 17322350 AV INFRASTRUCTURE DETAILS
463 TA504 17322351 AV INFRASTRUCTURE DETAILS
464 TA601 17322352 AV SYSTEMS SCHEDULES
465 TA701 17322353 AV INFRASTRUCTURE RISER DIAGRAMS
466 TA702 17322354 AV INFRASTRUCTURE RISER DIAGRAMS
467 TA703 17322355 AV INFRASTRUCTURE RISER DIAGRAMS
DOCUMENT 00 01 15 Page 17
468 TA704 17322356 AV INFRASTRUCTURE RISER DIAGRAMS
-- End of Document --
DOCUMENT 00 01 15 Page 18
SECTION 01 11 00
SUMMARY OF WORK
02/24, CHG 1: 05/25
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes constructing a two-story Battle Staff Training Facility (BSTF) building for the Third Marine Expeditionary Brigade (3d MEB) Marine Air-Ground Task Force (MAGTF) at Marine Corps Base (MCB) Camp Blaz, Guam, consisting of reinforced concrete foundation, exterior walls and flooring, windows, roofing, mechanical, electrical, emergency power and information systems appropriate to Guam's seismic and environmental conditions and designed to meet applicable Unified Facilities Criteria (UFC). Support facilities include utilities, site improvements, emergency generator, access roads, parking, and incidental related work.
1.1.2 Location
The work is located at the Marine Corps Base Camp Blaz, Finegayan, Guam, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Contact Contracting Officer prior to excavating, to mark utilities, and to verify existing utility locations indicated on Contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with dual frequency Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
SECTION 01 11 00 Page 1
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer at least 30 calendar days prior to starting excavation work.
1.3.2 Utility Locations
Provide a third party, independent, private utility locating company to positively identify underground utilities in the work area in addition to any station locating service and coordinated with the station utility department.
1.4 COMPUTER/TELECOMMUNICATION/ACCESS CONTROL/IDS COORDINATION REQUIREMENTS
1.4.1 Computer/Telecommunication/Access Control/IDS Contractor Access
Allow the Computer/Telecommunication/Access Control/IDS Contractor access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections. Coordinate efforts with the Computer/Telecommunication/Access Control/IDS Contractor to facilitate joint use of building spaces during the final phases of construction. After the Contracting Officer has facilitated coordination meetings between the two contractors, within one week, incorporate the effort of additional coordination with the Computer/Telecommunication/Access Control/IDS Contractor into the construction schedule to demonstrate a plan for maintaining the contract duration.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 5: 05/25
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 State
"State" when used in reference to states of the United States also includes the Territory of Guam.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
Personnel List
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.
c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an
SECTION 01 14 00 Page 1 emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.4.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/Operations-and-Management/Base-Support/DBIDS/ .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.4.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
SECTION 01 14 00 Page 2
1.4.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.4.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.4.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period, between 7:30 a.m. and 4:00 p.m., Monday through Friday, excluding Government holidays.
1.4.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 30 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.4.4 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: Do not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will
SECTION 01 14 00 Page 3 operate the control devices as required for normal conduct of the work. Notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's Sanitary Sewer Connection Permit 2 weeks prior to connection and in accordance with Section 33 30 00 SANITARY SEWERAGE.
f. Contractor must apply for a utility outage request as described herein. Outages must be coordinated with the Base Operating Services Contractor (BOSC) and NAVFAC Marianas Public Works Department (PW) Utilities Management (UM). Use the BOSC Utility Outage/Connection/Service form to apply (refer to PWUC BP, Appendix 4). Utility (Electric, Water & Sewer) outages, de-energization, or energization support shall be coordinated with the BOSC Service Support Center. Cost related to utility service outages/connections shall be paid by the Contractor to the BOSC. Comply with PWUC-BP Appendix 4, provided at the end of this section.
1.5 SECURITY REQUIREMENTS
1.5.1 Personnel List
Submit for approval, at least 21 days prior to the desired date of entry, an original alphabetical list of personnel who require entry into Government property to perform work on the project. Furnish for each person:
a. Name
b. Date and place of birth
c. Citizenship
d. Home address
e. Social Security number
f. Current pass expiration date
g. Naturalization or Alien Registration number
h. Passport number, place of issue, and expiration date
i. Guam Police clearance report for last six months
The request for personnel passes must be accompanied with the following certification:
"I hereby certify that all personnel on this list are either born U.S.
citizens, naturalized U.S. citizens with the naturalization number shown, or legal aliens with the alien registration number indicated or Temporary Non-Immigrant with the Temporary Non-Immigrant ID card number shown."
Signature/Firm Name
SECTION 01 14 00 Page 4
1.5.1.1 Citizenship Requirements
Aliens will not be admitted to the work site without approval. Clearance for aliens may require approximately 20 workdays for approval.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00 Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 14 00 Page 6
NAVFACMAR PWUC-BP
10 January 2024
This PWUC-BP supersedes previous versions. A - 4
Appendix 4
BOSC UTILITY SERVICES
INSTRUCTION GUIDE;
FORM - UTILITY OUTAGE /
CONNECTION / SERVICE REQUEST
This page intentionally left blank.
BOSC Utility Services Instruction Guide
Requesting and Paying for Work Directly Through DZSP 21
Printed document may be obsolete - validate before use
RCCM-I-0001 Rev. 1 Effective: 04/01/2021
Printed Date:4/15/2021
The procedure for contractors to schedule and pay for utility services from the Navy Base Operations
Support Contractor are as follows:
1. For Project(s) connecting to or needing/consuming any Navy Utility Commodities (e.g. water, power, etc.), coordination with respective NAVFAC Marianas FEAD, ROICC, or MCAG Project
Construction Management /Construction Management Engineer (CM/CME) is required to establish a Line of Funding for consumption usage through PAY.GOV
a. NOTE: No Utility Connection or Service will be provided until funding for Commodity consumption is in place.
2. Submit completed Utility Outage Request Form (UOR) and Customer Payment Information
Sheet (CPI) to Regional Call Center Marianas (RCCM) via e-mail at dzsp21RCCM@dzsp21.com with required documents:
a. Completed customer Payment Information Sheet for deposit
Forms of Payment Accepted: Government Purchase Cards or Credit Cards
b. Drawings/sketches and other required documents for the supporting Annexes
•NOTE: A minimum deposit of $1,000.00 is required for each Utility Outage Request.
This deposit goes towards DZSP 21 labor hours for the assessment of the outage. This amount does not include any costs associated with utilities consumption or meters.